Delay in Construction Project Ijariie10609
Delay in Construction Project Ijariie10609
Delay in Construction Project Ijariie10609
ABSTRACT
Construction delay is a time exceeds either after the contract date or after the date that the components involved have
agreed upon for the delivery of the project. In both cases, a delay is usually a costly situation or the period of amount of
time during which something is delayed. There is various types of definition of delay are made in construction industry
such as to wait until later to do something or to take longer than expected or planned or the amount of time that you
must wait for something that is late. Delay are the major source of claim and disputes in construction industry in India.
Various delayed analysis methods have been developed, there is a lot of debate was arranged on national and
international level for how to minimize delays. This paper has intended to identify the causes of delays, the effects of
delays and methods of minimizing construction delays. This paper study has carried out based on literature review and a
questionnaire survey. The eighty-three questionnaire has been made on the basis of pilot study, which has been
distributed on various construction site. Interview has been taken on each construction sites, also take photos of any
ongoing activity on that site. Then ranked on their importance index by the data collection in India. For major factor
analysis has used to reduce all factors divided into nine groups: project, clients, consultants, contractors, designer,
equipment, labour, external and material.
Recommendation has been made for improve project management, improve cash flow by client so as to reduce payment
delays and also more some suggestions are made by top ten major factors, which has been included on report. The result
of this paper should help construction practitioners, policy makers and researchers in construction field.
Key Words:Construction Management, Causes of Delays, Effects of Delays, Construction Industry, India.
CHAPTER- 1
INTRODUCTION
1:1General
The construction industry is one of the main sectors that provide important ingredient for the development of an
economy. However, many projects experience extensive delays and thereby exceed initial time and cost estimates.
Construction delays are considered to be one of project success in term of time, cost, quality, and safety Projects are
underway around the country, and motorists are experiencing delays and detours at construction zones. And many areas
have begun building booms that are supposed to ease our Congestion woes by adding new capacity to existing roads.
But ironically, the construction projects themselves can create significant congestion and delay. The wealth of any
nation is gauged by its performance in infrastructure provision through its construction industry. The construction
industry is large, volatile, and requires tremendous capital outlays. For developing economies, road construction
constitutes a major component of the construction industry. This means that much of the national budget on
infrastructure development is channeled to road construction projects. Inflation and local government pressures were the
major causes of cost escalation in Kurdistan Region’s road construction projects. On the other hand, delayed payments,
financial processes and difficulties on the part of contractors and clients, contract modification, economic problems,
materials procurement, changes in drawings, staffing problems, equipment unavailability, poor supervision,
construction mistakes, and poor coordination on site, changes in specifications and labor disputes and strikes were
found to be the major causes of schedule delays in road construction projects. Appropriate project management
practices are thus required to curb the causes and effects of cost escalation and schedule delays in road construction
projects. The Construction delay is a universal evident reality not only in Kurdistan region however all the countries
faced this global fact.
Delay in government construction projects, especially the road sector, has had a significant impact on economic
activities in the country. Several road construction projects have littered the length and breadth of the country for which
government has commenced that has yet to be completed. Unfortunately the time line for these projects is unknown to
the citizens of the country. This has led to an increased number of uncompleted road construction projects by
government and has further compounded the woes of Kurdistan Region’s Citizens.
The cost of a construction project is one of the most important factors in the construction industry. Due to many
reasons, the total cost of a project can significantly vary from the initial estimated cost. The reasons could be changes in
scope of work, specifications, or any other contract documents. In the construction industry, variation orders are created
when changes occur. It is an official document that states the changes made into the original agreement between the
client and the contractor. When a variation order is created, it brings several negative effects to both the client and the
contractor.
The construction industry is the tool through which a society achieves its goals of urban and rural development [5]. It is
one of the sectors that provide important ingredients for the development of an economy.
The construction industry tends to fluctuate with the general economy, and it has quick response to the changes in the
economy. According to Chitkara, the construction industry in many countries accounts for 9 % of the Gross Domestic
Product (GDP). However, it is becoming more complex because of the sophistications of the construction process itself
and the large number of parties involved in the construction process
Delay has been defined severally by many researchers often times with some bias towards the central theme of their
research work. That notwithstanding, there are some definitions that explain the concept of delays with precision. There
are number of definitions for delay:
To make something happen later than expected; to cause something to be performed later than planned; or to not act
timely each of these definitions can be describe a delay to an activity of work in a schedule. On construction project s,
as well as on the projects where a schedule is being used to plan work, it is not uncommon for delays to occur
Delays generally fall into four categories. Delay is considered a major cause of construction claim. The four types of
delay namely
i. excusable delays
ii. non-excusable
iii. delays compensable delays
iv. concurrent delays
i. Excusable delays
Excusable delays are those not attributable to the contractor's actions or inactions, and typically include unforeseen
events. It's allow the contractor to obtain a time extension to complete the contract without being penalized. However,
this type of a delay normally does not entitle the contractor to any damages caused by the delay.
The examples of excusable delays to a contractor's action are differing site conditions, design problems, changes
to the work, inclement weather, and strikes. This type of clause sometimes called a "force majeure" clause, lists
excusable delays. As this list implies, when unanticipated outside 'forces delay completion of the contractor's work, the
delay is generally considered as excusable.
iv. ConcurrenDelay
Alkass said that, concurrent delays refer to delay situations when two or more delays occur at the same time or overlap
to some degree. Forexample, if an owner denies access to a project site for two weeks, and a severe storm prevents the
contractor from working on the project for one of those two weeks as well, there will be a concurrent delay of one
week. The contractor will be able to recover for delay damages for one week, as a severe storm is not a cause of delay
that is compensable and would have prevented the contractor from performing even if the owner did not deny access to
the site. However, if there two concurrent causes of delay, one of which is a relevant event, and the other is not, then the
contractor is entitle to an extension of time for the period of delay caused by the relevant event not with standing the
concurrent effect of the other event.
The literature review found that there were delays of 8 different participants (contractors, owners, consultants, and
others) in the construction industry in India, with 8 delays.
Here are 8 different reasons given:
i. The owner
The owner of the project is the party that owns, manages, and funds the project; the owner assigns either a firm or
individual representing him to overseeing the implementation of one phase or more of the phases of the project. Owner
representatives takes the responsibilities of critical decision- making on the project, and choose other parties such as
consultant and contractor to implement the project. "The owner is responsible for setting the operational criteria for the
completed Project, owner is also responsible for setting parameters on total cost, payment of costs, major milestones,
and the project completion date
Arditi et al in 1985 found that most of contractors quite slow in improving the good practices with relate to change
of times and number of projects obtained. Most of contractors also 'did not interest to take the competent technical and
management staffs. This was due to they were not aware of the potential benefits that they would be obtained. Also
there are unable to analyse the job requirement, risk management, marketing, financial control, work organization,
quality control and preparation of reasonable tender.
Imbert in 1990 studied issues related weak of organizational management found that the problems happened due to
weak of plan, instable organization, bueracracy, not relevant regulations, slow in making decision and low productivity.
According to Kirmani in 1988 turn over of staffs in company also gave an impact to the effectiveness of organizational
management in project completion. This means that construction organization need mangers not only controller but also
someone that can manage risks to the minimum.
Dlakwa and Culpin in 1990 found that delay in project completion gave a big effect to construction industry and
economy. According to Mansfield et al in 1994 lack of contract and site management can contribute to contractors'
work plan, cost control and overall project management. These were due to lack of experiences management staffs and
lack of technical staffs, low productivity, lack of short and long term financial funds and lack of experts.
Simms in 1984 found that most of construction staffs did not have sufficient knowledges in term of site
management and quality control and also do not expert in modem management practice. Modem management
techniques can improves the Process and function of sources under his/her control by change the optimum usage Of
related components which involved in the process.
Oglesby et al in 1989 found that lack of planning and lack of knowledge in project contra and also lack of record
keeping contribute to delay of project completion. Most of contractor did not familiar with the modem practice to
arrange works, plan, critical-path analysis and control technique.Contractors sometimes have resources, but due to lack
of planning will cause them fail to achieve scheduled target.
According to Oglesby et al again, construction was making the ideas in drawings and specifications into completed
structure by installing their components. To ensure that ideas being implemented effectively and satisfy the required
time and quality, so it need a proper planning. Contractor seldom prepare detail plan for their work activities.
Furthermore, they always carry out works as their previous works. They oftenly rely on verbal communication and hand
over the planning of activities to the foremen who will carry out the works. Although the works can be constructed but
very much ineffective compared to if detail planning were being prepared. Most of construction managers ignored
planning with reason that they do not have enough time.
Abdelhalim and Duff in 1991 found that normally condition of contract require detail work planning before works
can be carried out at site. However, seldom actual works being carried out as per detail work planning. This is due to
incompetent contractor's technical and management.
According to Laufer and Tucker in 1987 detail works programme only being Prepared after they were delay and
sometimes as evidence to obtain additional time to complete projects. Effective project management not only require
project objective, but more than that such as planning and effective control to achieve target. In construction time and
activity duration always relate to each other. If there were delay in any activity will effect the related activities.
v. Consultant
Consultant is the party assigned by the owner to prepare studies, designs, and documents for the project.
(Bosneneh, 2010).
The consultant role may even extends to the execution phase if some problems appears and an adjustment of the
designs needed.
vi. Designer
vii. Worker
viii. Material
ix. Equipment
x. External factors.
Category of material related to delays was identified as one of causes of delays in construction projects. Okpala and
Aniekwu in 1988 found that lack in construction materials in market always became an excuse for delay in project
completion. The insufficient COflStfllCtiOfl materials in the market were due to:
According to Fugar et al. (2010), material group delay factors were ranked the second most important factors
responsible for construction delay in Ghana. The shortage of material problem was related to the ability of client to
honour certificate. This caused of unavailability of materials on site at right time was due to the suppliers were reluctant
to supply materials on credit because contractors could only pay them once the contractor had received the payment
from the client.
Related to Manavazhia and Adhikarib survey, they found that material and equipment procurement delays in
highway projects in Nepal. Delay in the delivery of materials and equipment to construction sites is often become a
contributor to the cause of delay and make the cost overruns in construction projects. The main causes of material and
equipment procurement delays were found to be organizational weaknesses, suppliers' defaults, governmental
regulations and transportation delays.
CHAPTER– 2
LITERATURE REVIEW
2:1 General
Based on the research objectives identified in the earlier chapter, this chapter reviews the previous studies and the
research done in the field of project management by identifying the factors affecting delays in the construction industry.
It discusses the basic concepts of a project and project management, moving forward to the models for assessing a
project and carrying out the process of completing a project, thus forming a framework for the factors that cause delays
in the Indian construction industry. Most of the research work included in the literature is also based on other South
Asian countries like Malaysia, Singapore, etc and also some middle-eastern countries, as their findings also apply in the
Indian context.
The literature review highlights the research work already done in this field, explaining the key factors in detail.
This is an important element of the dissertation as it is the first step towards identifying the problems that the firms
engaged in construction activities face in India.
Scientists have analyzed many reasons for postponement in the development business.
Table 1 summarizes several reviews conducted from 1971 to 1994.
Sambasivan and Soon (2007) identify and evaluate the most significant causes of project delay in Malaysian
construction industry, which are improper planning, poor site management, inadequate experience of the contractor,
inadequate finance of the client and payments for completed work, problems related to subcontractors, material
shortage, labour supply, availability and failure of equipment, lack of communication between parties and mistakes
during the construction stage.
Al-Kharashi and Skitmore (2009) identify leading causes of construction project delay in Saudi Arabia by
conducting a questionnaire survey administered to contractors, consultants and clients. They conclude that the most
two significant causes of project delay are lack of finance to complete the work by the client and delay in progress
payments by the owner.
Haseeb et al. (2011) conduct a research on the causes of delay in large construction projects in Pakistan, where the
following factors are reported to be the most influential: natural disaster; financial and payment problems; improper
planning; poor site management; insufficient experience; shortage of materials and equipment. Doloi et al. (2012)
report the factors affecting project delays in Indian construction projects by surveying construction professionals in
India. After the factor analysis, the most influential factors of project delay were identified as follows: lack of
commitment; inefficient site management; poor site coordination; improper planning; lack of clarity in project
scope; lack of communication; and substandard contract.
J.Raj Bharath & Prof Siddesh K Pai (2013) have mentioned that recently commissioned, Bandra-worli sea
link amply demonstrates the state of project delivery system in the country. It was planned as Rs300 crore project to
be completed by 2004, but had actually cost of Rs1600 crores with the delay of five years. Ruth apolot, henry
alinaitwe & dan tindiwensi (2013) made a case study and concluded that the stakeholders in the construction
industry are advised to minimize the change in scope of work as it has the most effect on cost and time overrun and
recommended there should be change from the traditional contract type to the design-build type and improved cash
flow on the part of the client so as to reduce payment delays.
Ibrahim Mahamid (2013) conducted a survey on time performance of different types of construction projects in
Saudi Arabia to determine the causes of delay and their importance according to each of the project participants, i.e,
the owner, consultant and the contractor. Then finally he concluded that 76% of the contractors and 56% of the
consultants indicated that average of time overrun is between 10% and 30% of the original duration and also found
70% of the projects experienced time overrun in Saudi
Anu V. Thomas and J. Sudhakumar (2014) mentioned that low productivity leads to delays in construction
and reported the results of questionnaire survey made to identify the factors influencing construction labour
productivity with the project managers, site engineers, supervisors and craftsmen, in the state of Kerala, India, and
also mentioned timely availability of materials at the worksite, delayed material delivery by the supplier, strikes
called by political parties or hartals, frequent revisions of drawings/design, resulting in additional work/rework and
timely availability of drawings at the worksite as a significant impact on labour productivity. Nitin Chaphalkar and
K. C. Iyer (2014) said, in some cases disputes may raise b/w the stakeholders during the construction phase, in
which if it’s not handled properly, tend to consume time and money of the parties disputing, which leads the project
to extended stay
Ghulam Abbas Niazai and Kassim Gidado (2013) reported that contract with less than 12 months highly
contributes to delays. They concluded that two causes of delay are common between all parties, which are ‘security’
and ‘corruption’. Poor security is the most difficult challenges that stakeholders face in implementing construction
projects. It has delayed projects and increased costs. Corruption constitutes a serious threat to Afghanistan
Construction Industry improvement as it has significant effects on construction delays. There is an urgent need for
developing a legal framework for fighting corruption, whereas the current framework has been outdated and unclear.
2:2.OBJECTIVE
This is condected to identify the major causes of delays and effect of delays in construction projects industry. To
achieve this aim, the following objectives have been identified:
i. To identify the major factors that contributes to the delay in construction project.
ii. To identify the effect of delays in construction project.
iii. To find out construction-phase related factors due to which a construction project delays in delivery.
iv. Analyse and prioritise the construction-factors.
v. To give recommendations to improve the situation.
CHAPTER– 3
METHODOLOGY
In achieving these objectives, a research methodology is required. Figure .highlights the critical stages of
conducting this study. This figure comprises four essential stages of conducting the study which includes the
following:
Identify problem
Determine objective of study
Determine scope of study
Data collection
Literature review
Questionnaire
Data analysis
Result
SELECT TOPIC
IDENTIFY
PROBLEM
DETERMINE
OBJECTIVE OF STUDY
DETERMINE
SCOPE OF STUDY
DATA COLLECTION
DATA ANALYSIS
RESULT
identified for survey. Both primary and secondary methods have advantages and disadvantages. The advantages of
primary data are that it is recent and is aligned along the intended survey but it has disadvantage of being expensive.
However, secondary data is easy to get and is relatively cheap but may be out of date. This raw data was analysed
using quantitative approach. With the help of literature, various possible factors are identified. In addition, various
other factors are also added as recommended by local experts. Initially, all factors causing delay to a residential
project are identified and then they were sorted out to get only construction-related factors. Various studies and
reports were studied to get right factors which are applicable to this study. Total 26 factors are selected at last. All
these factors are arranged in a sequence according to the work done during construction phase and a questionnaire is
formed.
3:3 Questionnaires
A good questionnaire constitutes of three important facts that makes it more effective for getting response and then
analysis, i.e.
Keeping in mind all the necessary components of questionnaire finally, a Questionnaire is formed using Likert scale
in which each construction factor .
The delay in the completion of the project is due to administrative and technical matter.
The delay in the completion of the project is due to equipment and materials.
The delay in the completion of the project is due to other causes (external resource.
CHAPTER-4
DELAY ANALYSIS METHOD
4:1 Introduction
This chapter describes the results and discussion of questionnaire survey concerning time exceed from contractors,
consultants and owner viewpoints . The main aim of the current study of is to assess the causes of delay in
construction projects. This chapter focuses on describing questionnaire sample characteristics analysis.
It is divided to ten questions including information about the respondent and about the institution. The topics of
questions are:
BY the survey we got to no that Yes , the delay in the completion of the project is due to administrative and
technical matter in which a total of 14 survey was conducted which got a 9 persons who said yes and 5 said no and
got a percentage rating of 64.29% in the survey.
no
36.71%
yes
64.29%
By the survey we got to no that Yes , the delay in the completion of project is due to financial matter in which a total
of 14 survey was conducted which got a 8 person who said yes and 6 said no and got a percentage rating of 57.1% in
the survey.
NO
42.9%
YES
57.1%
By the survey we got to no that Yes , the delay in the completion of project is due to equipment and materials matter
in which a total of 14 survey was conducted which got a 6 person who said yes and 8 said no and got a percentage
rating of 42.1% in the survey.
YES
42.9%
NO
57.1%
By the survey we got to no that Yes , the delay in the completion of project is due to human resources matter in
which a total of 14 survey was conducted which got a 9 person who said yes and 5 said no and got a percentage
rating of 64.3% in the survey
NO
35.7%
YES
64.3%
By the survey we got to no that Yes , the delay in the completion of project is due to contractor matter in which a
total of 14 survey was conducted which got a 10 person who said yes and 4 said no and got a percentage rating of
71.4% in the survey
NO
28.6%
YES
71.4%
By the survey we got to no that Yes , the delay in the completion of project is due to project nature matter in which
a total of 14 survey was conducted which got a 5 person who said yes and 9 said no and got a percentage rating of
36% in the survey
YES
36%
NO
64%
By the survey we got to no that Yes , the delay in the completion of project is due to other causes matter in which a
total of 14 survey was conducted which got a 10 person who said yes and 4 said no and got a percentage rating of
71.4% in the survey
NO
28.6%
YES
71.4%
By the survey we got to no that Yes , the delay in the completion of project is due to the cost of the project is
affected by the delay matter in which a total of 12 survey was conducted which got a person who said yes and 8
said no and got a percentage rating of 85.7% in the survey
NO
14.3%
YES
85.7%
In residential redevelopment projects in Mumbai the project delay cause less profit to the builder. Because the
more the project gets delayed the builder has to give more rent to the tenants. Unless he didn't get the profit on
expected time he can't invest that money in other projects
Ultimate increase in cost..
construction cost will be increased, project duration is increased
The completion time may be shifted for number of days.
NO Factors % Rank
CHAPTER-5
5:1 Introduction
From the previous chapters, we have concluded many causes for delay in construction projects, few years ago;
most construction projects in the Mumbai were exposed to delay, so the continuation of this phenomenon affects the
progress of the construction industry, as it may expose some relevant institutions to collapse.
Thus, this chapter will present a review to the summary and conclusions of this research and recommendations,
recommendations will be presented to help in enhancing the India construction sector performance.
The construction sector is one of the most important economic sectors in India; this research discussed the
importance of studying the construction sector through the identification of gaps between theory and practice
associated with delays in the completion of construction projects. The main purpose of this study is to identify the
most important factors that delay the completion of projects, by taking a representative sample from each of the
engineering offices, the owners, and the contractors by distribution questionnaire contain 10 causes of delay to a
representative sample to know delays causes in Palestinian construction projects from the opinion of project
participant, and then analyze the results. Whenever a delay occur, its implications on the future performance of the
project can be immediately determined and corrective action can be taken to minimize any negative impact on
project performance. This research will help to discover the causes of delay in construction projects and then reduce
their effects.
The top five causes contributed to delays in India construction projects from the viewpoint of project participant
are: Referral of bids to the lowest price, incorrect and inappropriate bid pricing, lack of sufficient Cash for project
implementation (financial difficulties), Contractor failure to regulate the cash flow of the project, Irregular cash flow
for the project on owner's side, delay of due payments (according to progress), unavailability of required equipment
when demanded or delayed availability behind schedule, the kind of tenders in which the selection process to
negotiate lower prices or other criteria, the introduction of significant changes to the project by the owner after
starting the implementation phase of the project (additional work, modifications to the design), and Mistakes during
the process of implementation (intentionally or unintentionally) which require readjustment. The most impacts
expected to occur is Delay in delivery of the project, an increase in the cost, the large number of delayed projects
affect the community, Low productivity, lack of revenue, and Disputes / Trials/ prosecution.
Proposed solutions and procedures for solving and avoiding these causes. A framework to illustrate the steps
and procedures recommended for action to resolve the problem of delay and avoid or minimize them, an aide to all
parties to understand the current situation and how to solve or prevent it. Projects pass through different stages
during their life cycle can be summarized and categorized in the following four main phases, each phase involve
three main steps:
1. Planning phase divided to develop plan, Estimation required time and cost, and manage resources.
2. Design phase divided to put alternatives designs, Use of appropriate design systems, and use of monitoring and
follow-up system.
3. Contracting phase divided to work by specialist, Preparation contract documents, and available ethics and regulars.
4. Implement phase divided to use of appropriate construction systems, good manage by use control and follow-up
system, and use suitable documentation system.
This paper analysed causes of construction delays . The feedback of construction experts was obtained through
interviews and questionnaire surveys. Pie chart is calculated according to the highest values of them the top ten
delay causes of construction projects are determined.
2. Prepare (team work) with qualifications to work in the project and appoint project manager for the development of
an action plan through which to regulate , control, supervision and adjust things for the project, to avoid problems in
the implementation or problems between workers or employees, and complete project on time.
3. Develop a plan for the provision of materials, samples and machinery required on time.
4. 7- Minimizing follow the centralized decision-making and procedures with respect to projects because they hamper
the proceedings and cause delays.
B. Site management and supervision: administrative and technical staff should be assigned as soon as project is
awarded to arrange to achieve completion within specified time with the required quality, and estimated cost.
REFERENCES
[1] Abedi, M. (2011). Effects of Construction Delays on Construction Project Objectives. The First Iranian Students
Scientific Conference in Malaysia, 9 & 10 Apr 2011, UPM, Malaysia, 1–8.
[2] Aiyetan, A. O., & Smallwood, J. J. (n.d.). A linear regression modelling of the relation- ship between initial
estimated and final achieved construction time in South Africa, 39–56.
[3] Anik Gupta, S. G. (2013). Extreme Weather Events and Climate Change Impact on Construction Small Medium
Enterprises (SME‟s): Imbibing Indigenous Responses for Sustainability of SME‟s. Journal of Earth Science &
Climatic Change, 05(01), 1–7. http://doi.org/10.4172/2157-7617.1000173
[4] Construction productivity. (n.d.). Retrieved March 31, 2015, from
http://www.slideshare.net/atvisun/construction-productivity Subhav Singh, Anju Bala, Saurav Dixit and Deekshant
Varshne http://www.iaeme.com/IJCIET/index.asp 344 editor@iaeme.com
[5] Dadzie, J. (n.d.). Performance of Consultants on Government Projects in Ghana : Client and Contractor
Pespective, (2009), 256–267.
[6] Desai, M., & Bhatt, R. (2013). Critical Causes of Delay in Residential Construction Projects : Case Study of
Central Gujarat Region of India. International Journal of Engineering Trends and Technology (IJETT) - Volume 4
Issue 4, 4(April), 762–768.
[7] Dixit, S., Mandal, S. N., & Singh, S. (2017). Relationship between skill development and productivity in
construction sector: A literature review. International Journal of Civil Engineering and Technology, 8(8), 649-665.
[8] Dixit, S., Mandal, S. N., & Singh, S. (2017). Area of linkage between lean construction and sustainability in
Indian construction industry. International Journal of Civil Engineering and Technology, 8(8), 623-636.
[9] Hajela, R. (2012). Shortage of skilled workers: a paradox of the Indian economy. Skope, (111). Retrieved from
http://www.cardiff.ac.uk/socsi/research/researchcentres/skope/publications/researchpapers/WP1 11.pdf
[10] Intelligence, C. I. (2011). Timely Project Execution : A Key Challenge, (May).
[11] Keane, P. J., & Caletka, A. (2008). Delay analysis in construction contracts, 4(5), 784–788. Retrieved from
http://westminsterresearch.wmin.ac.uk/6113/
[12] Pandey, A. K., Dixit, S., Bansal, S., & Mandal, S. N. (2017). Optimize the infrastructure design of hospital
construction projects to manage hassle free services. International Journal of Civil Engineering and Technology,
8(10), 87-98.
[13] Dixit, S., Pandey, A. K., Mandal, S. N., & Bansal, S. (2017). A Study of Enabling Factors Affecting
Construction Productivity: Indian Scnerio. International Journal of Civil Engineering & Technology, 8(6), 741-758.
[14] Methods Of Minimizing Delays Construction Essay. (n.d.). Retrieved March 25, 2015, from
http://www.ukessays.com/essays/construction/methods-of-minimizing-delays-construction-essay.php