Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

Wa0008.

Download as pdf or txt
Download as pdf or txt
You are on page 1of 16

PROJECT TERMINATION /

CLOSURE

NORMAL
PREMATURE
PERPETUAL
FAILED
CHANGED PRIORITY
Project Closure

 Project Closure is a process that occurs whether a


project is successful or not
 The Aim of the Closure process is
 To cease the project at All levels with
 Minimum Administrative Dislocation
Project Closure – Reasons

 Normal – A project that ends normally is the one


that is completed as planned.
 Premature – A project may be pushed to complete
early even though the system may not include all of
the envisioned features.
 Perpetual – some projects seem to take on a “life of
their own” and are known as runaway or perpetual
projects
 Failed – Unsuccessful projects
 Changed priority – Because of financial/political/
economic reasons the organisation decides that
resources will no longer be allocated to the project.
Project Termination/ Closure

 A Project can be said to be terminated when work on


the substance of the project has ceased or slowed to
the point that further progress is no longer possible

 There are four fundamentally different ways to close


out a project: extinction, addition, integration,
and starvation.
Ways to Terminate a Project

EXTINCTION,
ADDITION,
INTEGRATION
BY STARVATION
1 - By Extinction (by decision)

 It has successfully completed its Scope that has


been accepted by the Clients
 It has failed

 It has been Superseded by extreme developments

 It no longer has sufficient Support of Senior


management.
By Extinction (by decision)

 Although the technical processes of the project are


immediately terminated there is still management
processes to be planned and executed by the PM
 Project Team members reassigned or released
 Project materials and equipment disbursed
 Preparation of final reports and reviews
2 - By Addition

 Ifthe project is a major success, it may be


terminated by making it an formal part of the
parent organization
 Project personnel, property and equipment are
often simply transferred to newly created
organizational unit within parent organization.
3 - By Integration

 Project product is integrated into operations of


client or parent company
 Project personnel, property and equipment are
reassigned /released and distributed.
 PM must plan/execute smooth integration and
termination process
 Most common mode and most complex for PM
4 - By Starvation

 A slow starvation by reducing its budget


 There could be reasons due to which senior
management does not wish to terminate an
unsuccessful or obsolete project.
 Politically dangerous to admit that one has been
supporting a failure
 Terminating a project that has not accomplished its
goals is an admission of failure
Termination Activities
Project Termination Activities

 Ensure completion of work


 Close out all work authorities and contract

 The Client
 Notify client of product completion
 Ensure delivery and installation is accomplished
 Obtained formal client acceptance

 Financial close out


 Settle outstanding accounts receivable and payable

 Termination Documentation
 Post implementation audit
 Final report
Project Termination Activities (cont.)

 Release Resources
 Release/reassign personnel as their planned activity ceases

 Distribute their resources appropriately

 Project Records
 Collate (Collect )

 Ensure delivery and installation is accomplished

 Oversee final disposition


The Final Report
Documentation

 Post Implementation Audit


 Establish the true status of the project with respect to its
planned status
 Final Report
 Should be a record of lessons learnt

 It is a commentary not an evaluation


 Recommend and justify changes to current practices
 Draw attention to practices that worked unusually well
Final Report: Some Headings

 Project Summary
 Project description, Scope, schedule, budget and quality
objectives
 Project Performance
 Compare proposal to post implementation audit

 Comment on deviations

 Administrative Performances
 Organizational Structure
 How did the structure impede and/or speed

You might also like