APM Project Fundamentals Qualification Study Guide-2020
APM Project Fundamentals Qualification Study Guide-2020
All rights reserved. No part of this publication may be reproduced, stored in a retrieval system,
or transmitted, in any form or by any means, without the express permission in writing of the
Association for Project Management. Within the UK exceptions are allowed in respect of any
fair dealing for the purposes of research or private study, or criticism or review, as permitted
under the Copyright, Designs and Patents Act, 1988, or in the case of reprographic
reproduction in accordance with the terms of the licenses issued by the Copyright Licensing
Agency. Enquiries concerning reproduction outside these terms and in other countries should
be sent to the Rights Department, Association for Project Management at the address above.
All registered trademarks are hereby acknowledged and the publisher makes no claim to these
trademarks.
1. Study planning
1.1 Using this guide
1.2 How to study
2. Study areas
2.1 Introducing projects
2.1.1 Project environment
2.1.2 Project, programme and portfolio management
2.1.3 Project roles
2.1.4 Business case
2.1.5 Project life cycles
2.1.6 Project management plan
2.2 Planning for success
2.2.1 Stakeholder engagement
2.2.2 Communication
2.2.3 Risk and issue management
2.2.4 Quality management
2.2.5 Scope management
2.3 Achieving results
2.3.1 Estimating
2.3.2 Resource scheduling and optimisation
2.3.3 Information management and reporting
2.3.4 Leadership and teamwork
3. Self-assessment
3.1 Test questions
3.2 Examination practice
Glossary
References
Index
Figures and tables
Figures
1.1.1 Illustration of PFQ learning structure
1.1.2 Pull out study guide planner
2.1.1.1 How the environment influences an organisation
2.1.2.1 Triple constraints of time, cost and quality
2.1.2.2 Projects, programmes and portfolios situated to deliver
strategic change
2.1.3.1 Example project management roles and structure
2.1.5.1 Linear project life cycle
2.1.5.2 Iterative development in dynamic, agile context
2.1.5.3 Hybrid life cycle
2.1.5.4 Extended life cycle
2.1.6.1 Different stakeholders that may need to contribute to
producing the PMP
2.2.1.1 An approach to capturing analysis of stakeholders
2.2.3.1 Risk management process and management products
2.2.4.1 Quality management as implemented within the project
2.2.5.1 Example PBS for an international conference
2.2.5.2 Example WBS structure derived directly from the PBS
2.2.5.3 Responsibility assignment matrix (RAM) showing RACI coding
2.2.5.4 Stages in a typical change control process and relationship
with configuration management
2.2.5.5 Activities involved in configuration management of an output
2.3.1.1 Estimating funnel showing factors that will influence the
accuracy of the estimate
2.3.2.1 Network created from work breakdown structure
2.3.2.2 Common dependency types
2.3.2.3 Network showing activity durations and critical path
2.3.2.4 Network and Gantt chart showing milestones
2.3.2.5 Milestone chart
2.3.2.6 Resource histogram showing the demand profile resulting from
resource allocation decisions
2.3.2.7 Resource histogram after levelling
2.3.2.8 Resource levelling and smoothing options
2.3.4.1 Factors that contribute to variance in leadership style
2.3.4.2 Stages of team development and leadership actions necessary
to reach performance
2.3.4.3 Belbin’s nine social roles
Tables
2.1.2.1 Differences between projects and BAU
Introducing APM
There are a number of ways in which you can benefit from what we
do, including:
■ membership
■ qualifications
■ chartered status
■ publications
■ events.
Our objectives
Chartered standard – We are the chartered body for the project
profession, leading the way in setting and maintaining a universally
high standard for the project profession. This includes chartership,
wider continuing professional development, qualifications and best
practice knowledge share. Our objective is to successfully position,
develop and launch the chartered standard to become the accepted
benchmark standard for project professionals.
When using this guide, think about your approach to learning in three
layers. The first layer is the main subject text; this is knowledge that
relates directly to the learning outcomes and assessment criteria.
This layer is the sufficient amount of study required to be prepared to
sit the PFQ exam. To further support your learning, you may consider
how project management influences your work and day-to-day
activity. This is where a second layer of learning may be useful. Each
subject has a ‘Think about …’ opportunity where learners can
consider projects that they may have some experience of, or where
their organisation is carrying out activity that require a project
management approach.
Sometimes during the learning of any subject, it can be difficult to
imagine just how some of the theory, techniques and processes can
actually be used in real-life practice, particularly if you are new to
project management. That’s where the third and final layer of learning
can provide some valuable insight into just how real projects deliver
what is required, actually using the very elements that you are about
to study. ‘The world of project management’ features, which
accompany some of the subject areas, provide examples of just how
projects are managed in the real world using examples drawn from
recent editions of APM’s quarterly journal, Project.
When you first view this guide, the syllabus, candidate guidance and
other available material you are planning to use, you might think that
there is a lot of different numbering systems that may not seem to be
connected. Well you are not alone. That’s probably a common first
challenge experienced by most people wanting to tackle a substantial
subject like project management. It is, however, essential that you do
get to grips with the complete structure very early on and incorporate
this into your study planning. These introductory pages will help bring
all the different components together.
The content of this learning guide will help you to accumulate the
necessary insight to demonstrate your knowledge to the required
level for this qualification. There are 15 study areas contained in the
study guide. Each study area fulfils the knowledge requirements for
one or more assessment criteria. The relationship between the study
guide, assessment criteria and learning outcomes is shown in Figure
1.1.1
You should also download the latest version of the PFQ exam sample
paper. This contains examples of questions of a similar style to those
found in the live exam. This paper will give you a feel for the actual
exam and build your familiarity with the paper prior to your exam day.
There are many benefits, therefore, in deciding early on how you are
going to schedule your studies in relation to all the other activities in
your daily life. By thinking about these aspects now you are likely to
benefit from a more enjoyable and meaningful learning experience.
This in turn will improve overall effectiveness and enable you to adopt
a more flexible approach to answering questions.
Suggested approaches
Consider the relationship between practice and theory, investigate
typical projects in your working environment, or do some online
research of projects that you hear about on your local news or in the
press. This type of research will allow you to appreciate the
connection between the theory and common practice out there in the
real world.
After completing each subject, look for opportunities where you can
apply some of the tools and techniques that you are learning. In
addition to theoretical study, application and appropriate feedback
are essential for effective learning. There are likely to be
opportunities to apply theory in your workplace, in social activities and
in the home, for example, a work-based project, a club project or a
DIY project.
The targeted time frame for study is only a suggestion and may vary
considerably depending on personal time constraints and any
previous experience of the subject matter. It is, therefore, important
to establish the feasibility of the target date you have set for taking
the exam and allow adequate study time. The key here is to be
realistic. If you dive into study to get to the exam as soon as
possible, your approach may not take into account all the other
activities that, up to this point, have gone by unnoticed and now they
too are making demands on your time. This is when you start missing
your goals, become disheartened and the plan is now in shreds. The
opposite can be just as challenging, where you purchase the guide,
don’t bother with a plan but start reading from page one expecting to
complete the guide at some point in the future. Months go by and
guess what? You still haven’t got past page 10 and you have read
page eight about 50 times!
Widely used in learning, mind maps were first developed in the late
1960s by Tony Buzan. Mind maps are now used by millions of people
around the world – from the very young to the very old – whenever
they wish to learn or use their minds more effectively. Mind maps can
be applied to most of life’s situations that involve any learning or
thinking.
If it has been some time since you last studied, you might find mind
maps helpful. An online search of ‘mind maps’ will give you more
information.
Flash cards
‘A picture paints a thousand words’ is commonly quoted to describe
the effect of using visual imagery as a substitute for lengthy text-
based information. When these images are created by learners and
placed on small cards they can act as aides-memoires to revise and
learn fundamental concepts. Learners report increased success rates
in exams when flash cards are used.
Study groups
If you work for an organisation where project management is a
common practice then the chances are that there will be others
learning project management at the same time as you. Ask those
around you if they know of anyone and discuss your course generally
with your colleagues. They may be interested in what you are doing,
so much so they may also decide to study for a project management
qualification.
Preparing and studying with others may mean that you can share
ideas, test each other and discuss some of the more practical
applications of project management within your organisation. It is
often satisfying to share areas of learning that you find more difficult
with others who may also find the same areas challenging. Together
you are able to piece together the solution and gain the satisfaction of
solving what was seen as a learning obstacle.
2 Study areas
The need for investment emerges from the aspirational plans and an
overarching purpose that transpire from the strategic intent of an
organisation. Project work encompasses strategic investments that
enable assets, structures, systems, activities and capabilities to be
formed, maintained or enhanced so that the organisational plans and
ambitions can be realised.
Learning objectives
This section introduces one of the main reasons why projects exist in
the first place. The environment is defined as the societal and/or
organisational setting of a project, programme or portfolio, also
described as the project context. By examining the project context,
stakeholders will understand how the project being considered relates
to the environment.
By the time you have studied this section you will have completed the
following:
Every project team member needs to develop the attitude that, just
as they are stakeholders, every other project stakeholder is also
important. There should be a commitment to service and the creation
of a project management environment in which every decision and
action is designed to make the stakeholder’s experience better than it
would have been had the project not been implemented. It requires a
focus on the quality of the stakeholder’s experience at every stage of
the project.
■ customers/technology;
■ industry/marketplace/intermediaries;
■ competitors/stakeholders;
■ supply sources/time;
■ internal capability/governance requirements.
The subject that you have just studied shows how the project
needs to be responsive to the driving forces of the environment
and particularly the areas that are important to stakeholders.
Traditionally, project managers have had to balance the common
areas of the environment with the commercial aspects of
delivering the project, namely the cost of delivery, the time taken
and the performance of the output of the project within the
operations of the business requiring the change to take place.
“We are building a new wharf capable of berthing the new, larger
research vessel, the Sir David Attenborough,” says Wulff. “We
needed massive rock-fill, but rather than ship it in, we opened up
a small borrow-pit nearby. That not only slashed the carbon
footprint for transport, it also minimised the risk of introducing
invasive species.”
Continued on page 12
Learning objectives
This section introduces the three layers of management involved in
delivering change to the organisation. The overall strategy is set
through the use of portfolio management and that strategy is
delivered using programme management to ensure benefits are
realised. None of this could be achieved without the delivery of each
individual project using project management.
By the time you have studied this section you will have completed the
following:
BAU, on the other hand, uses the products of the project to realise
the benefits. It is unusual for projects to deliver any benefits into the
organisation during their deployment (unless there is some form of
phased roll-out, or a delivery contractor benefits by being paid to
deliver specific phases).
Figure 2.1.2.2 Projects, programmes and portfolios situated to deliver strategic change
If you would like to read more about this example or other real-
world project examples, copies of APM’s Project journal can be
downloaded from the members’ resources area of the APM
website: apm.org.uk/project.
Learning objectives
This section introduces the key roles that are members of a typical
project organisation structure. Projects are temporary endeavours
and therefore, by definition, have a temporary structure established
by the people in the permanent organisation to manage activities and
resources to deliver specific objectives within predetermined time
frames.
By the time you have studied this section you will have completed the
following:
■ defining goals and creating vision for the operability of the project’s
outputs;
■ communicating with stakeholders to ensure that the project remains
aligned with business objectives;
■ providing feedback to the project team on task dependencies,
constraints, priorities and progress in relation to business needs;
■ establishing priorities for scope, budget and time with relation to
stakeholder requirements;
■ acting as the primary communication link between stakeholders and
teams, ensuring stakeholder buy-in, linking major decisions with
strategy and providing clear instructions and outlines of deliverables
to product developers;
■ evaluating progress, providing feedback to the team on delivery
performance and advising if continuation is feasible.
Learning objectives
This section considers the business case, which provides the
justification for undertaking a project or programme. It evaluates the
benefit, cost and risk of alternative options and provides a rationale
for the preferred solution. The very first consideration of a project by
the organisation provides the opportunity to evaluate the options that
may be available.
By the time you have studied this section you will have completed the
following:
Risks – The longer the timescale of the project the more difficult it
may be to identify the level of uncertainty and the most effective
approach. Business case risks are the most important to identify. If
they can’t be mitigated at this stage it may mean that the project is
abandoned or a less risky strategy pursued.
Options appraisal – The strength of any business case is increased
when a full range of possible options has been considered. This
shows that the organisation has not become over reliant on a single
idea, but that it has reflected on what other options may be possible
with the available funds. The do-nothing option may also be
considered. When the final business case is ultimately produced, it is
approved not only on the basis of being a good idea in itself, but also
that in relation to alternatives it was the strongest option. It is
common for options to be subject to a financial appraisal considering
relative costs in relation to time and the phasing of return value.
Options appraisal is a major part of the justification for the chosen
option to proceed.
Users – They will be key to providing the sponsor with insight about
how the output will be operated within business-as-usual. It is their
perspective that will add most value to the project and be key to
benefits realisation.
By the time you have studied this section you will have completed the
following:
There are six phases in an iterative life cycle and these are shown in
Figure 2.1.5.2. During the ‘pre-project’ phase, iterative life cycles
begin by developing a high-level vision. The ‘feasibility’ and
‘foundation’ phases ensure that the finer detail is uncovered during the
cycles of iteration. The ‘evolutionary development’ phase allows the
specification and design to run in parallel and so, fast tracks to
deployment. Iterations are thus used to progressively elaborate and
improve understanding based on client interaction with learning
between the iterations. Iterations are applied when the goals are
clear but the means of achieving them are not. The rapid deployment
of smaller, partial solutions becomes the basis for gaining fast
feedback and new insights about what needs to be done. Iterations
are often conducted through working prototypes that stakeholders
use as the basis for adaptation and improvement. The ‘deployment’
phase seeks to bring the evolving solution into operational use either
fully or using an incremental solution that delivers partial
requirements, using user experience to form the next solution
increments. The final phase, ‘post project’, identifies whether the
solution has delivered the benefits to the degree required to achieve
the business case.
Learning objectives
This section considers the output of a process of integrated planning
for a project and documents this detail in the project management
plan (PMP). At this stage the fundamental management components
of scope, schedule, cost, risk, quality and resources will be defined.
The project manager owns the PMP.
By the time you have studied this section you will have completed the
following:
Learning outcome Assessment criteria
4. Understand project 4.1 Define the term ‘deployment baseline’
management planning
4.2 State how deployment baselines differ between linear
and iterative life cycles
4.3 Outline the stakeholders of a project management plan
4.10 Explain why establishing success criteria is important
at the start, during, and at handover of a project
The project can then proceed to the deployment phase where the
deployment baseline will be used for monitoring progress and
implementing change control.
Linear life cycles treat scope and quality as the driver and calculate
the consequential consumed time and cost. Iterative projects commit
to set resources over limited periods to deliver products that are
developed over successive cycles. Many organisations use a hybrid
linear/iterative approach to projects and programmes most of the
time. The challenge is to plan in the most effective way to give the
investing organisation the best possible chance of achieving the
objectives and benefits described in the business case.
Figure 2.1.6.1 Different stakeholders that may need to contribute to producing the PMP
Where? This presents the logistics of the project location and site
conditions, and outlines any major restrictions or constraints
regarding access, or particular delivery requirements and security
protocols.
How? This is probably the most comprehensive part of the document,
and outlines the management strategy for the project. These
management plans would contain process steps, template
documents, roles and responsibilities, communication requirements
and the detailed information necessary to allow those involved in
deployment to follow the required process. Specific management
plans could exist for the following areas:
■ risk;
■ quality;
■ procurement;
■ stakeholders and communication;
■ safety;
■ scope;
■ change control procedures;
■ cost;
■ project controls;
■ information.
Learning objectives
This section considers those who ultimately will be key to the
project’s success: stakeholders. Without the effective engagement of
stakeholders there is a risk that the project will not meet its success
criteria.
By the time you have studied this section you will have completed the
following:
2.2.2 Communication
Learning objectives
This section considers how communication should be conducted if the
project is to successfully take account of stakeholders’ requirements.
There are different communication methods to be considered and
documented in a communication plan for the project.
By the time you have studied this section you will have completed the
following:
If the project requires working with virtual teams there are particular
skills needed to ensure that communication between team members
is efficient and effective, for example, the ability to include everyone
who needs to be involved on a virtual call, simultaneously.
If you would like to read more about this example or other real-
world project examples, copies of APM’s Project journal can be
downloaded from the members’ resources area of the APM
website: apm.org.uk/project.
Learning objectives
This section examines two of the most misunderstood of all the
project management processes: risk management and issue
management. Understanding risk management means that the project
can exploit the existing opportunities to further optimise the project
schedule, budget and scope. Issues are events where, in effect, the
project is caught by surprise and needs to respond. Issues may not
be avoidable but what is important is that the process applied to deal
with such eventualities creates valuable lessons learned.
By the time you have studied this section you will have completed the
following:
All projects are inherently risky because they are unique, constrained,
based on assumptions, performed by people and subject to external
influences. Risks can affect the achievement of objectives either
positively or negatively. Risk includes both opportunities and threats,
and both should be managed through the risk management process.
A key output from the initiation step is the risk management plan,
which details how risk will be managed throughout the life cycle. The
risk management plan will be an important reference for all
stakeholders who require an insight into the risk organisation and
control structure, and the specific responsibilities for risk
management. A number of appendices will also be included, such as
templates and proformas of the documents necessary to effectively
carry out the process. Part of the overall project management plan,
the risk management plan makes it quite clear how risk is going to be
tackled for the project. In many organisations it may be held as a
template in the standard project methodology, although the risk
management plan will always be specific to a particular project.
At project closure if there are any open risks remaining, the project
manager must ensure that these are communicated to those involved
in the adoption phase.
If you would like to read more about this example or other real-
world project examples, copies of APM’s Project journal can be
downloaded from the members’ resources area of the APM
website: apm.org.uk/project.
Learning objectives
This section considers the processes necessary to ensure that
outputs are delivered in accordance with requirements and have the
highest chance of being accepted at the point of final delivery. If the
project’s stakeholders are satisfied with the results of the project, the
project has met its quality criteria.
By the time you have studied this section you will have completed the
following:
As part of quality planning, test plans for quality control will have been
agreed. These include aspects such as:
There are many project scenarios where the project outputs are
highly complex and technical, and where the work to verify
conformance of outputs to specifications is extensive. Testing is well
established and understood in these scenarios. It is easy to overlook
that all projects need to deliver outputs that are fit for purpose and
therefore enable the outcomes to be achieved. Quality control applies
equally to interim or final outputs such as reports, processes,
communication materials or financial models.
Decision gates
The purpose of decision gates is to review and confirm viability of the
work across the chosen life cycle. In a linear life cycle, decision gates
are event driven, at the end of a phase of work. In the case of an
iterative life cycle, they are time bound. Many projects or
programmes adopt a hybrid life cycle with a combination of main
decision gates at the end of major phases of work, supplemented by
interim review points to reflect the iterative nature of the
development.
In all cases, the sponsor and the wider governance board are
accountable for the decision to continue the work. Reviews in
advance of decision gates ask four key questions:
Within a stand-alone project, the decision gate is dealing only with the
continued viability of that project’s business case. In programmes and
portfolios, decisions will include whether to rephase or terminate
existing, or initiate new, projects. Between decision gates, the
sponsor is accountable for ensuring authorities are in place to prevent
the team working out of compliance and at risk. Decision gates may
also be used to request relevant authorities, such as a financial or
procurement authority.
Benefit reviews
A benefit (realisation) review is carried out during benefits realisation
and is a formal review of a programme or project, typically conducted
6–12 months after handover and commissioning of the deliverables.
These reviews may be repeated throughout the operational life of the
product. This review is used to answer the question: Did we achieve
what we set out to do, in business terms and if not, what should be
done? For a construction, development or procurement project, a
review is undertaken when there has been time to demonstrate the
business benefits of a new service or building. For a major
programme of change there will be several reviews over time. A
benefits realisation review is an essential component of the benefits
management process. It checks whether benefits, including those set
out in the business case have been achieved and identifies
opportunities for further improvement.
Audit
Normally undertaken by an independent body, which may be internal
or external to the organisation but independent from the project. An
audit’s objective is to provide assurance to the sponsor that the
project is being managed using the agreed governance and process.
Audits can be undertaken by a project management office, should
one exist, and they form the foundation of assurance, providing
confidence to stakeholders that projects will achieve their objectives
and realise their benefits.
2.2.5 Scope management
Learning objectives
This section considers how the translation of requirements into
outputs for the chosen solution is achieved. There are a number of
structures used that act as communication devices that allow a
common perspective of the project to be gained by all interested
stakeholders.
By the time you have studied this section you will have completed the
following:
Figure 2.2.5.2 Example WBS structure derived directly from the PBS
At the lowest level of the WBS, work packages will exist that contain
the activities to be performed to allow estimating, scheduling and
resource assignments necessary to do the work and ultimately deliver
the output. Where the objective is well understood and has a tangible
output (e.g. in construction and engineering) it is usual to define the
scope as accurately as possible at the beginning of the life cycle.
Where the objective is less tangible, or subject to significant change,
e.g. business change or some IT systems, a more flexible or iterative
approach to scope is needed.
The work packages in the WBS are reviewed and decisions are
made about who in the project will take responsibility for carrying out
the work, supervising activity and reporting progress. The structure of
the project organisation is vitally important for the effective
performance of key activities and to support the efforts of the whole
project team. The organisation breakdown structure (OBS) describes
the structure of the project organisation required to complete the
work packages in the WBS. This is particularly useful when work will
be performed by business staff seconded to the project or by
specialist teams working on more than one project. It is also
important for individuals themselves to know where they are situated
in the structure and their reporting responsibilities.
The second point of support will be when the decision has been taken
to implement a change. Once a change has been approved, all
related documentation must be updated to reflect the change. The
configuration record relating to all affected items will be updated
accordingly. If any new changes are now being requested,
configuration management will make sure that it is the updated
version of all documentation that is released for review. The status of
all previous versions will now be shown as superseded. Working
together, these two processes ensure that deliverables meet the
required specification, any changes are beneficial changes and there
is a complete audit trail for the development of each deliverable.
Figure 2.2.5.4 shows the flow through and relationship between these
two processes.
2.3.1 Estimating
2.3.2 Resource scheduling and optimisation
2.3.3 Information management and reporting
2.3.4 Leadership and teamwork
2.3.1 Estimating
Learning objectives
This section considers how once the scope of work has been defined
a prediction of time and resources required to complete that scope
will require to be established.
By the time you have studied this section you will have completed the
following:
Analytical
When the detailed scope of the project has been defined, usually
through the formation of a work breakdown structure (WBS), detailed
estimates can be produced for labour and non-labour resources to
complete the activities in scope. This is often referred to as a bottom-
up method, in that the task of producing the estimates will be
delegated to those who are actually going to deliver the individual
pieces of work or work packages. Their individual estimates are then
summed from the bottom of the WBS to the top. For this estimating
method to be valid, the WBS needs to be representative of the work
that will eventually be carried out and so a verified WBS is essential
to the accuracy of the final estimate. Analytical estimating can only be
used to produce a cost estimate and not an estimate of duration.
Summing the estimated durations from the bottom of the WBS to the
top would not take account of work packages that will be conducted
at the same time as others.
Analogous
This method is dependent on data being available about a similar
project to the one being estimated. If the historic project was the
same size, similar complexity and the method by which the new
project is being delivered will be the same, then it is accepted that the
cost of the previous project becomes the new estimate. It is possible
to factor this estimate to take account of known variables, for
example, by adding 10 per cent to cover the known increases in
material costs. When this estimate is produced at the start of the
concept phase, it is often referred to as an order of magnitude
estimate. To carry out this type of estimate the data on previous
projects needs to be readily available. It is common that this estimate
will provide the basis for the decision to proceed with the project.
Parametric
This estimating method uses a statistical relationship between historic
data and other variables to calculate an estimate. The specifications
of each deliverable are established together with the particular
parameters that apply, for example, length of pipe, square footage of
floor space or height of wall. Applied to these parameters would be
unit rates that are either gained through experience of doing the work
previously or using rates that are produced by technical publishers as
price books or books of norms. Parametric estimating can be one of
the most accurate techniques for determining a project’s duration and
cost, provided the scope being estimated accurately represents the
expected final requirements. When applying published data, care is
required to ensure that the actual conditions of the work being
estimated are similar to the conditions that have created the norms
and take account of skill levels, lost time factors and any physical
aspects such as inclement weather.
Learning objectives
This section considers the time schedule and considers techniques
used to develop and present schedules that show when work within a
project is planned to be performed. A project schedule can reside
within a programme or portfolio schedule and have dependencies on
the completion of other projects.
By the time you have studied this section you will have completed the
following:
Once the network analysis has been completed and the network
optimised a Gantt chart is created to show the activities against a
timeline (see Figure 2.3.2.4). Milestones are entered into the
schedule as if they were an activity, but they have zero duration and
therefore act as markers, rather than having any duration in the
timeline. In this simple example, the milestones are shown as black
diamond shapes and so they can be easy to see within the detail of
the bar chart. However, if this was a more complex schedule with
many more activities, the milestones may not be as visible.
Figure 2.3.2.4 Network and Gantt chart showing milestones
Figure 2.3.2.6 Resource histogram showing the demand profile resulting from resource
allocation decisions
When all levelling options have been considered and a solution is still
unavailable, the project duration will extend but hopefully this is will be
minimised to the least possible extent.
There is, of course, a finite limit to the resource that can be put into
some tasks due to the nature of the task and the environment. For
example, a task involving data entry will be impacted very little by
additional resource, if there is only one data terminal available. If
resource really is finite, there are no more hours available from skilled
people or no more equipment available, then there is no option but to
extend durations and the overall project time to accommodate this as
shown in Figure 2.3.2.8.
■ How much risk to retain in the project and how much to share with
suppliers in the supply chain?
■ On a continuum from transactional (based solely on price and
supply) to collaborative (considering a more integrated relationship
and working together to serve parties interests), what type of
relationship is desired with different suppliers, and why?
Learning objectives
This section considers the processes for managing project data that
is essential for effective delivery of the project. All project
stakeholders rely on accurate and timely information for teams and
stakeholders to make informed decisions and fulfil their role in a cost-
efficient and effective way.
By the time you have studied this section you will have completed the
following:
Learning outcome Assessment criteria
4. Understand project 4.11 Outline the purpose and benefits of project
management planning progress reporting
The project manager will have several uses for this reported
information. Schedule status information will be reviewed and the
schedule updated. Any variances reported to the schedule for time
and cost will be noted and, if necessary, corrective action will be
taken to bring the tasks back onto the appropriate time and cost
schedule. The project manager will use information as a basis for
reporting to the sponsor and steering group and other stakeholders
as indicated by the communications plan.
Learning objectives
This section considers how leadership can enable people coming
together from different functions, disciplines and organisations to
work with a common purpose to deliver something of value to the
investing organisation.
By the time you have studied this section you will have completed the
following:
Leaders need to adapt their style and approach to the needs of the
team and the work that needs to be accomplished; this is called
Situational Leadership®. Figure 2.3.4.1 shows the factors that
influence leadership styles and the varying styles that can be adopted
in the Situational Leadership® model. There are some situations
when the leader needs to be directive, for example, to address an
issue that threatens the achievement of objectives.
Some teams are co-located in the same geographic area. Where this
is possible there are distinct benefits from the ability to share a
physical space where plans and progress can be visualised, and
close working relationships can be developed.
An important aspect of this model is that the team does not pass
through these stages naturally. Progress through each stage is
facilitated by effective leadership actions. The team leader has a key
role in helping the team move through these stages as efficiently as
possible and readdressing stages as new team members join or
others leave. The Tuckman model (Tuckman, 1977) is shown in action
in Figure 2.3.4.2 and outlines the stages as:
Forming
This is the first point of contact that team members have in this
project context. Their knowledge of the project or environmental
circumstances is very limited. Team members are naturally guarded.
At this stage the leader will ensure that they communicate clear goals
and objectives, creating an inclusive and coordinated environment.
Storming
The team now starts to understand that they will be unable to achieve
goals on their own and that cooperation is expected. It is at this stage
where individual personalities start to influence how team members
inter-react with each other. The biggest issue at this stage is conflict
created through competition and disagreements about how to achieve
project objectives. If conflict is not managed it can cause the team to
reverse back to forming, team members close down and
communication is reduced. The leader has a strong role to ensure
differences are aired and conflict is resolved in a positive way.
Norming
If conflict is resolved successfully the team start to become much
more cooperative with each other as they start to focus on the tasks
required to achieve objectives. This stage is very much felt by the
team as a need for balance; team cohesion is important but not to the
detriment of getting the work done. The leadership priority at this
stage is to provide processes, clear roles and responsibilities, and
timely feedback.
Performing
The team is now delivering the targeted performance. Creative
problem solving and motivation is at its highest level. The leader will
ensure performance is maintained by promoting openness, honesty
and the development of trusting relationships. Now that the team has
experienced achievement it is likely that this will continue; however, it
can’t be taken for granted. The team could actually revert back to
one of the earlier stages, usually in response to change, for example,
due team members leaving and new people joining, or changing the
scope of the tasks. The degree of reversal depends on the scale of
the change but also on the strength of the leader. Strong leadership
means that with even a large-scale change, the team may only revert
back to norming for a short time before returning to performing. The
opposite is also true. For example, under weak leadership a small
change can cause the team to completely collapse, returning back to
forming.
Adjourning
This was a stage that Tuckman identified several years after
developing the original four-stage model. This stage acknowledges
the efforts of the leader in preparing team members for the end of
one team and the start of a new team in the future. Providing
feedback on individual performance, liaising with functional
management and recognising achievement are just some of the
leadership tasks necessary at this stage with the aim of ensuring that
team members are transitioned effectively back into the business or
their organisation.
Figure 2.3.4.2 Stages of team development and leadership actions necessary to reach
performance
Action
The Shaper will provide the necessary drive to ensure that the team
keeps moving and does not lose focus or momentum. The
Implementer will plan a workable strategy and carry it out as
efficiently as possible. Most effectively used at the end of tasks to
polish and scrutinise the work for errors, the Completer Finisher will
subject output to the highest standards of quality control.
Social
The Resource Investigator uses their inquisitive nature to find ideas to
bring back to the team, excellent for communicating from the project
to stakeholders. The Team worker is the diplomat of the team,
helping the team to gel, using their versatility to identify the work
required and complete it on behalf of the team. The Coordinator’s
role is necessary to focus on the team’s objectives, draw out team
members and delegate work appropriately.
Thinking
When the team is faced with obstacles, needs to be highly creative
and good at solving problems in unconventional ways, the Plant
provides the necessary support to allow the team to function well in
these circumstances. The Monitor Evaluator provides a logical eye,
making impartial judgements where required, and weighs up the
team’s options in a dispassionate way. When the team requires in-
depth knowledge in key areas, the Specialist is a member of the
team who has distinct strengths in a very narrow area.
Read about…
The world of project management
Dispersed teams
Virtual working, with team members dispersed around the world,
presents a series of challenges of its own, the most obvious of
which is time difference. Finding times when everyone can talk
together can be particularly difficult. Forming emotional bonds
between team members, and avoiding miscommunication, are
other well-rehearsed issues for virtual teams.
If you would like to read more about this example or other real-
world project examples, copies of APM’s Project journal can be
downloaded from the members’ resources area of the APM
website: apm.org.uk/project.
3 Self-assessment
11 Which phase of the project life cycle will utilise the new
project and enable the acceptance and use of the benefits?
A Adoption.
B Transition.
C Deployment.
D Implementation.
2.2.2 Communication
1 Three general categories for interpretation of communication
could be described as:
A email, paper, voice.
B tactile/visual, auditory, written.
C telephone, computer, microphone.
D reception, transmission, interruption.
17 Throughout the life of the project, issues that are raised are
best recorded in the:
A quality register.
B issue register.
C change register.
D risk register.
7 When the project progresses through the life cycle, which one
of the following aspects would be expected to occur?
A The accuracy of the estimate reduces and the level of
contingency requirement increases.
B The accuracy of the estimate increases and the level of
contingency requirement reduces.
C The accuracy and level of contingency requirement both
increase.
D The accuracy and level of contingency requirement both
reduce.
A A C E F.
B A B D F.
C A C D F.
D A B E F.
A Finish to start.
B Finish to finish.
C Start to finish.
D Start to start.
5 Reports that are produced only when things are not going to
plan, are termed:
A risk reports.
B progress reports.
C exception reports.
D issue reports.
2.2.2 Communication
2.2.3 Risk and issue management
Your results
If you have gained less than 129, review each subject area.
It is likely that there are only one or two areas where you
need to do a little more work to get you ready for the
exam.
2. Exam overview
The exam is based upon the learning outcomes and assessment
criteria specified in the APM Project Fundamentals Qualification
syllabus.
The APM Project Fundamentals Qualification exam:
6. Pass mark
The pass mark is 60 per cent* of the available marks, i.e. 36 correct
questions out of 60.
Question 1
Which of the following is not a stage in an issue resolution
process?
Question 2
Which of the following are challenges for a project manager
developing and leading a project team?
Question 3
Which of the following is an activity in a typical change control
process?
a. Recommendation.
b. Justification.
c. Planning.
d. Continuous improvement.
Question 4
The purpose of quality assurance is to:
Question 5
A project manager might use a PESTLE analysis in order to:
Question 6
Which of the following are phases in an iterative project life cycle?
1) Concept.
2) Feasibility.
3) Deployment.
4) Development.
a. 3 and 4 only.
b. 1, 2 and 3.
c. 1 and 2 only.
d. 2, 3 and 4.
Question 7
Which of the following is the responsibility of a project manager?
Question 8
To develop and establish a proper communication plan within a
project, the project manager needs to consider which type of
analysis?
a. Budget.
b. Stakeholder.
c. Resource.
d. Schedule.
Question 9
Which of the following is a responsibility of the project sponsor?
Question 10
Portfolio management includes prioritising:
Question 11
Which of the following actions would not help a team leader
influence the performance of their team?
Question 13
The purpose of project progress reporting is to:
Question 14
Which of the following is the purpose of an estimating funnel?
Question 15
One advantage of virtual communications is:
a. that nonverbal signals can have an impact on discussions.
b. it’s easy to detect signs of conflict within the project team.
c. access to a wider resource pool for the project.
d. that the project team will always be co-located.
Question 16
Which technique could be used by a project manager when
resources are limited?
a. Resource aggregation.
b. Resource estimation.
c. Resource levelling.
d. Resource expansion.
Question 17
The main aim of quality management is to:
Question 18
Which of the following is a purpose of issue management?
Question 19
Product breakdown structures illustrate the required scope of
work by a hierarchical structure itemising the:
Question 20
The definition of benefits management includes which key
activities?
Question 21
Which of the following statements about scheduling is false?
Question 22
Which of the following defines the term ‘deployment baseline’?
a. Evaluation.
b. Identification.
c. Registration.
d. Justification.
Question 24
Stakeholder analysis supports effective stakeholder engagement
by:
Question 25
Which of the following is a project?
Question 26
One purpose of a typical project business case is to:
Question 27
One disadvantage of physical communication is:
Question 28
One of the benefits of developing communication plans in projects
is that this ensures:
Question 29
A project life cycle which combines approaches from the linear
and iterative life cycles is known as _________ project life cycle.
a. a hybrid.
b. an extended.
c. a reduced.
d. a combined.
Question 30
The purpose of project management is to:
Question 31
Which of the following statements refers to how scope is
managed in a linear project but not an iterative project?
Question 32
One difference between an issue and a risk is an issue:
Question 33
Communication includes:
1) exchanging information.
2) managing stakeholders.
3) confirming there is a shared understanding.
4) building relationships within your team.
a. 2 and 3 only
b. 1 and 4 only
c. 1 and 3 only
d. 2 and 4 only
Question 34
A project manager requires a team member to focus on the
team’s objectives and draw out other team members. Which of
the Belbin’s team roles is most appropriate?
a. Shaper.
b. Monitor evaluator.
c. Specialist.
d. Co-ordinator.
Question 35
An extended project life cycle can be defined as:
Question 36
One aspect of quality planning is to:
a. plan the audit of a project to provide assurance to the project
board.
b. provide confidence that a project will achieve its objectives in
the required time frame.
c. specify the acceptance criteria used to validate the outputs are
fit for purpose.
d. confirm routes for reporting to ensure effective communication.
Question 37
Which of the following is not a key element of project scope
management?
a. Define outputs.
b. Identify outputs.
c. Share outputs.
d. Control outputs.
Question 38
Which of the following is a difference between deployment
baselines in linear life cycles and iterative life cycles?
a. Linear project life cycles set the deployment baseline for the
whole project.
b. In an iterative project life cycle the scope and quality are fixed
in the deployment baseline.
c. Only deployment baselines in iterative life cycles have an
integrated baseline review.
d. Only deployment baselines in linear life cycles have an
integrated baseline review.
Question 39
Which of the following defines the term ‘risk’?
a. The potential of a situation or event to impact on the
achievement of specific objectives.
b. A problem that is now or is about to breach delegated
tolerances for work on a project or programme.
c. Scope creep within an uncontrolled project.
d. The use of estimation to determine costs, resources and
activities.
Question 40
Suppliers are stakeholders of a project management plan
because they:
Question 41
Which of the following defines the term ‘issue’?
Question 42
Which of the following define leadership?
1) Ability to establish vision and direction.
2) Developing team skills that enhance project performance.
3) Empowering and inspiring people to achieve success.
4) Ability to influence and align others towards a common
purpose.
a. 1, 2 & 4
b. 1, 2 & 3
c. 2, 3 & 4
d. 1, 3 & 4
Question 43
Which of the following are typical estimating methods?
1) Analytical.
2) Budgeting.
3) Analogous.
4) Parametric.
a. 1, 2 and 4
b. 1, 2 and 3
c. 1, 3 and 4
d. 2, 3 and 4
Question 44
Procurement strategy can be defined as the high-level approach
for securing:
a. stakeholder engagement.
b. funding for the project.
c. buy in from the project sponsor.
d. goods and services required for the project.
Question 45
Which of the following is not an output of a critical path analysis?
Question 46
A project manager would use a cost breakdown structure to
produce:
Question 47
Which of the following is the correct sequence for the stages of a
linear project life cycle?
Question 48
At which stage, in the Tuckman team development model, are
team members clear and comfortable with their roles and
responsibilities, and the project manager starts to see signs of the
team working together?
a. Storming.
b. Forming.
c. Norming.
d. Performing.
Question 49
Which of the following is a definition of project management?
Question 50
Which of the following defines quality?
Question 51
Quality control verifies that:
Question 52
The purpose of a decision gate is to decide whether:
Question 53
Establishing success criteria is important at the start of the
project, as they:
Question 54
One purpose of risk management is to:
Question 55
Which of the following is an activity in a typical risk management
process?
a. Verification.
b. Request.
c. Closure.
d. Justification.
Question 56
When an item goes through change control, which of the following
must happen as part of a robust configuration management
process?
Question 57
The purpose of a risk register is to provide a:
Question 58
Which of the following is a part of change control?
Question 59
The primary purpose of a milestone in a project is to show:
a. significant events.
b. resource constraints.
c. task dependencies.
d. critical path highlights.
Question 60
Which of the following can be adjusted during a time box?
1) Scope.
2) Resource.
3) Time.
4) Quality.
a. 1 and 2 only
b. 1 and 4 only
c. 3 and 4 only
d. 2 and 4 only
End of Questions
This glossary is made up of terms that you will find in this study guide
and is consistent with definitions outlined in the seventh edition of the
APM Body of Knowledge.
Figure 2.1.5.2 The DSDM Agile Project Framework Handbook, 2014. Reproduced with the
kind permission of the Agile Business Consortium. https://www.agilebusiness.org
Figure 2.3.4.3 Belbin Associates for the Belbin ‘Team Roles’, as defined by Dr Meredith Belbin.
Reproduced by kind permission of www.belbin.com
Index
acceptance criteria, here, here, here, here, here, here, here, here, here
accountability, here, here, here, here, here, here, here
accuracy (estimation), here, here, here
adoption, here, here, here
agile development projects, here
change control, here
life cycles, here
time boxing, here
analogous estimating, here, here, here, here, here
analytical estimating, here, here
archiving of project documentation, here, here
assumptions, here, here, here, here
audits, here, here
background/situation, here–25
baseline plans, here, here
Belbin’s team roles, here, here, here
benefit reviews, here, here
benefits management, here, here, here, here
benefits (project), here, here, here, here, here, here, here
benefits realisation, here, here, here, here, here, here, here, here, here
business case, here
in project life cycles, here
reviews, here
bottom-up estimating, here
budget, here, here, here
business analysts, here
business-as-usual, here, here, here, here
difference between a project and, here
business case
benefits realisation and, here
contents, here, here, here
contributors, here
description, here
development and production, here, here
importance of, here
and project management, here
project management plan (PMP), here
purpose of, here, here, here, here
roles in development of, here–26
strengths, here
version control, here
business value, here
change
change control, here, here, here, here
change freeze, here
change requests, here, here
uncontrolled, here
checklists, here
closure of the project, here, here, here
coaching, here
common dependencies, here
communication, here, here, here, here, here
barriers, here
categories, here
consistent, here
definition, here
effective, here
face-to-face, here
improvement, here
interpretation, here
methods, here
physical (non-verbal), here, here
and stakeholder engagement, here, here
successful, here, here
virtual, here
communication management, here
communication plan, here, here, here, here
aims, here
benefits, here, here
contents, here–43
comparative estimating. see analogous estimating
concept phase, here, here
configuration management, here, here
activities, here, here
benefits, here
outputs, here, here
use of, here
conflict, here
constraints, here
environmental, here
time, cost and quality, here
context of a project, here
continual improvement, here
continuity, here
contractors, here, here{{. see also suppliers}}
contracts, here, here, here, here
cost, here, here
allocation, here
budget, here, here, here
constraint, here
cost breakdown structure (CBS), here, here, here
status, here
critical path analysis, here, here
critical paths, here
quality, here–121
definition, here, here
standards, here
quality assurance, here, here
quality constraint, here
quality control, here, here, here
quality management, here, here, here
quality management plan, here, here, here