Site Progress Update-Phase 1

10
Dashboard

Site Progress Update-Phase 1

11
Dashboard

Site Progress Update-Phase 1

12
Dashboard

Site Progress Update-Phase 1

13
Dashboard

Site Progress Update-Phase 1

14
Dashboard

Site Progress Update-Phase 1

15
Dashboard

Site Progress Update-Phase 1

16
Dashboard-PHASE 1

NCR
NON CONFORMANCE REPORT (NCR) - CIVIL WORKS

Sr. CRC
NCR No. Document Description Location DISC Date Issued Remarks
No. Expected Date

Phase 1
Installation of False Ceiling Board without Inspection Approval of Plot 6481067 (Mock-up) Opening False Ceiling for MEP Inspection to get the
47 VLV-P1-DEC-ARC-NCR-0047 CIV 6-Sep-2023 10-Mar-2024
Suspension System and MEP Clearance 1st Floor E.V. clearence after having anew mock up at villa 38

Rectification will be done after completing the now


SOR-0043-elevated to NCR - Cistern enclosure without approval Plot 6481067 (Mock-up EV mock up (Method statement and Shopdrawing already
59 VLV-P1-DEC-ARC-NCR-0059 CIV 10-Mar-2024
of shop drawings and calculation & MV) Approved) and the structure clculation submitted on
october and still under review.

Plot 6481067 (Mock-up) The rectification will be done after completing the new
63 VLV-P1-DEC-ARC-NCR-0063 Embedded drain slot for aluminum sliding door at balcony tiles CIV 30-Sep-2023 10-Mar-2024
Mid Villa mock up.
Plot Nbr
75 VLV-P1-DEC-ARC-NCR-0075 Unapproved tile skirting material used at plot 6481077 6481077&6481078[G- CIV 5-Dec-2023 10-Mar-2024 Repair works are ongoing
01&G-02]

125 VLV-P1-DEC-HSE-NCR-0125 Unsafe & incomplete scaffolding platform with green tag Phase-1 G-27-G26-G-25 HSE 6-Feb-2024 10-Mar-2024

Phase-1 G-27-G21-G-30- G-
128 VLV-P1-DEC-HSE-NCR-0128 Unprotected & inadequately protected floor openings HSE 13-Feb-2024 10-Mar-2024
22-G23- G17

Joinery kitchen carcass perimeter lipping not comply with the Area 01, Area 02 and Area
131 VLV-P1-DEC-ARC-NCR-0131 ARC 22-Feb-2024 10-Mar-2024
approve materials 03

19
Dashboard-PHASE 1

NCR
NON CONFORMANCE REPORT (NCR) - MEP WORKS

Sr. CRC
NCR No. Document Description Location Date Issued Remarks
No. Expected Date

Phase 1

21 VLV-P1-DEC-PLU-NCR-0021 improper storage of material at site store 12-May-2023 10-Mar-2024


Installation of False Ceiling Board without WIR
50 VLV-P1-DEC-MEP-NCR-0050 Approval of Electrical & Mechanical services @plot plot 6481067 6-Sep-2023 10-Mar-2024
6481067
CONTRACTOR STARTED WIRE PULLING
51 VLV-P1-DEC-ELE-NCR-0051 WITHOUT COMPLETING CONDUIT CONNECTION PLOT 6481134 (G19) 7-Sep-2023 10-Mar-2024
& DB CONDUITING @ PLOT 6481134 (G19)
UN-APPROVED RAL COLOR & WITH OUT MIR
57 VLV-P1-DEC-ELE-NCR-0057 APPROVAL ONU INSTALLED @ PLOT 6481067( PLOT 6481067( G28) 12-Sep-2023 10-Mar-2024
G28)
CONCRETE FILLING NOT PROVIDED FOR DB
62 VLV-P1-DEC-ELE-NCR-0062 PLOT 6481067 (G01) 28-Sep-2023 10-Mar-2024
CONDUITING @ PLOT 6481067 (G01)
LIGHT FITTING & WIRING ACCESSORIES
INSTALLED AT SITE WITHOUT
67 VLV-P1-DEC-ELE-NCR-0067 PLOT 6481067 (G28) 5-Oct-2023 10-Mar-2024
WIRING,MEGGERING & MIR APPROVAL @ PLOT
6481067 (G28)
Drainage Pipes without protection-
69 VLV-P1-DEC-MEC-NCR-0069 Stones,concrete,rubbish materials inside pipe @ Plot Plot Nbr 6481124&6481071(G 33,24) 11-Oct-2023 10-Mar-2024
Nbr 6481124&6481071(G 33,24)
Improper Supports, anchoring and Threaded rod
77 VLV-P1-DEC-MEC-NCR-0077 Plot Nbr 6481077[G 01] 21-Oct-2023 10-Mar-2024
installation
Substandard of Electrical Installation at P15_008 Villa
105 VLV-P1-DEC-MEC-NCR-0105 G28-Villa 40 7-Dec-2023 10-Mar-2024
40
Wrong location of ETISALAT Box at END villa first
114 VLV-P1-DEC-ELE-NCR-0114 All end villa First floor 26-Dec-2023 10-Mar-2024
floor
BIB Tape location not as per approved drawing Back
120 VLV-P1-DEC-HSE-NCR-0130 MEP 10-Mar-2024
yard area

132 VLV-P1-DEC-MEC-NCR-0132 Blocks and rubbish inside shaft[Roof] 6481080 & 6481141[G04 & G07] MEP 10-Mar-2024

Improper sleeves installation and pipes without


133 VLV-P1-DEC-MEC-NCR-0133 6481080 & 6481141[G04 & G07] MEP 10-Mar-2024
sleeves-Roof shaft

134 VLV-P1-DEC-MEC-NCR-0134 Roof ducts without protection 6481080 & 6481141[G04 & G07] MEP 10-Mar-2024

20
Dashboard-PHASE 1

NCR

Summary of NCR - Phase 1


TYPE Civil & HSE MEP TOTAL

No. of NCR 63 74 137

Closed NCR 51 61 112

Opened NCR 6 7 13

Under Review 6 6 12
21
Dashboard-PHASE 1
Dashboard

Engineering Update
Overall Shop drawings for ARC & STR Overall Shop drawings for MEP
Item Total % Overall Shop drawings Item Total % Overall Shop drawings
Total 309 100% Total 91 100%
Planned 280 91% 9% Approved
Planned 91 100% Approved
1%
Submitted 280 91% 1% Submitted 91 100%
Rejected Rejected
Approved 276 89% Approved 91 100%
Under Review Under Review
Rejected 2 1% Rejected 0 0%
Remaining Remaining
Under Review 2 1% Under Review 0 0%
89%
Remaining 29 9% Remaining 0 0%

Overall Material Submittal for ARC & STR Overall Material Submittal for MEP
Item Total % Overall Material Submittal
Item Total %
Overall Material Submittal
Total 187 100% Total 64 100%
1%
Planned 187 100% 0%
1%
Approved
Planned 64 100% 0% Approved
Submitted 187 100% Submitted 64 100%
Rejected 0% Rejected
Approved 185 99% Approved 64 100%
Under Review Under Review
Rejected 1 1% Rejected 0 0%
Under Review 1 1% Remaining Under Review 0 0% Remaining

Remaining 0 0% 99% Remaining 0 0%


22
Dashboard-PHASE1
Dashboard

LONG LEAD ITEMS (PHASE 1)

Approval Status
Planned Date Actual Date
Total
S.N Material Description SAM LPO Date LPO No. of 1st of 1st Remarks
Date Code Delivered
No. Delivery Delivery

ELECTRICAL

1 WIRING ACCESSORIES 0091 31-Aug-23 B 29-Aug-23 12327 100% 21-Jun-23 7-Sep-23 - Completely Delivered

2 LV SWITCHGEAR 0089 21-Sep-23 B 08-Sep-23 12497 100% 1-Sep-23 - Completely Delivered

3 LIGHT FITTINGS 0110 09-Sep-23 B 26-Jul-23 52361 100% 24-Aug-23 5-Oct-23 - Completely Delivered

PLUMBING

MAT -
4 SOLAR WATER SYSTEM 03-Aug-23 B 22-Aug-23 12395 100% 30-Aug-23 - Completely Delivered
0132

5 PUMPS (WATER SUPPLY) 0042 18-May-23 B 10-Aug-23 11811 100% 18-Aug-23 - Completely Delivered

MAT -
6 SANITARYWARE 19-Apr-23 B 10-May-23 52140 80% 18-Aug-23 23-Aug-23 - Partially Delivered
0054

7 WATER TANK COVER 0111 12-Sep-23 B 17-Oct-23 54724 41% 28-Sep-23 22-Dec-23 - Partially Delivered

8 MANHOLE COVERS 0086 19-Dec-23 B 19-Jun-23 11877 75% 16-Feb-24 22-Dec-23 - Partially Delivered

HVAC

8 DX AC SYSTEM 0101 02-Oct-23 B 10-May-23 11752 100% 18-Aug-23 24-Jul-23 - Completely Delivered

9 EXTRACT FAN 0075 09-Jun-23 B 23-Aug-23 11941 100% 18-Aug-23 24-Sep-23 - Completely Delivered

10 AIR OUTLETS 0040 22-Dec-24 B 16-Aug-23 12561 75% 18-Aug-23 10-Sep-23 - Partially Delivered

CIVIL & ARC

52191
11 FLOORING TILE 0015 14-Apr-23 B 11-May-23 100% 09-Jul-23 5-Jul-23 - Completely Delivered
52451
52191
12 WALL TILE 0014 14-Apr-23 B 11-May-23 100% 09-Jul-23 5-Jul-23 - Completely Delivered
52451

13 SKIRTING 0037 12-May-23 B 23-May-23 52359 65% 09-Jul-23 22-Aug-23 - Partially Delivered

14 IRONMONGERY 0049 11-Aug-23 B 11-Sep-23 53763 93% 26-Oct-23 - Partially Delivered

15 MARBLE 0113 07-Sep-23 B 25-Aug-23 LOA#073 50% 02-Sep-23 - Partially Delivered

MARBLE
16 0077 24-Jun-23 B 31-Jul-23 53192 50% 02-Sep-23 - Partially Delivered
(CISTERN & BACKSPLASH)

17 INTERLOCK 0098 30-Aug-23 B 31-Jan-24 56649 30% 28-Sep-23 - Partially Delivered

18 TEGULA INTERLOCK 0032 18-Jan-24 B 31-Jan-24 56649 1% 28-Sep-23 - Order issued

RFI-
19 HEEL KERB 25-Sep-23 B 31-Jan-24 56649 30% 28-Sep-23 - Partially Delivered
0075

20 SIGNAGE 0128 09-Dec-23 B 11-Dec-23 56083 100% 16-Dec-23 15-Dec-23 - Completely Delivered

23
Building Permits-Phase 1

Project; DPG-0064 - Villanove PA15 - La Violeta 1


Subject; List of released Building Permits
Foundation FF HCS Structural Building
Land Roof Structure Final
Area No. Group No. Plex No. Building Permit Ref. Plot No. Group Type Structure Structure Inspection Completion
Demarcation inspection Demarcation
inspection inspection Completion Certificate
G01 P15-017 B2204661 6481077 4 Plex A Done Done Done Done Done Done
G02 P15-018 B2204645 6481078 6 Plex Done Done Done Done Done Done
G03 P15-019 B2204646 6481079 6 Plex Done Done Done Done Done Done
Area 1
G04 P15-020 B2204632 6481080 4 Plex A Done Done Done Done Done Done
G05 P15-021 B2204628 6481081 8 Plex Done Done Done Done Done Done
G06 P15-022 B2204629 6481082 8 Plex Done Done Done Done Done Done
G07 P15-081 B2204634 6481141 6 Plex Done Done Done Done Done Done
G08 P15-082 B2204655 6481142 6 Plex Done Done Done Done Done Done
G09 P15-083 B2204656 6481143 4 Plex A Done Done Done Done Done Done
G10 P15-084 B2204626 6481144 4 Plex A Done Done Done Done Done Done
G11 P15-085 B2204627 6481145 8 Plex Done Done Done Done Done Done
G12 P15-086 B2204625 6481146 6 Plex Done Done Done Done Done Done
Area 2 G13 P15-087 B2204662 6481147 4 Plex A Done Done Done Done Done Done
G14 P15-069 B2204658 6481129 8 Plex Done Done Done Done Done Done
G15 P15-070 B2102088 6481130 8 Plex Done Done Done Done Done Done
G16 P15-071 B2102085 6481131 4 Plex A Done Done Done Done Done Done
G17 P15-072 B2204647 6481132 4 Plex A Done Done Done Done Done Done
G18 P15-073 B2204648 6481133 8 Plex Done Done Done Done Done Done
G19 P15-074 B2204633 6481134 6 Plex Done Done Done Done Done Done
G20 P15-016 B2204649 6481076 4 Plex A Done Done Done Done Done Done
Area 3 G21 P15-015 B2204650 6481075 6 Plex Done Done Done Done Done Done
G22 P15-014 B2102086 6481073 6 Plex Done Done Done Done Done Done

24
Building Permits-Phase 1

Project; DPG-0064 - Villanove PA15 - La Violeta 1


Subject; List of released Building Permits
Foundation FF HCS Structural Building
Land Roof Structure Final
Area No. Group No. Plex No. Building Permit Ref. Plot No. Group Type Structure Structure Inspection Completion
Demarcation inspection Demarcation
inspection inspection Completion Certificate
G39 P15-057 B2204635 6481117 6 Plex Done Done Done Done Done
G40 P15-056 B2204636 6481116 6 Plex Done Done Done Done Done
Area 4 G41 P15-055 B2204641 6481115 6 Plex Done Done Done Done Done
G42 P15-054 B2204642 6481114 4 Plex A Done Done Done Done Done
G43 P15-058 B2204659 6481118 4 Plex A Done Done Done Done Done
G29 P15-068 B2204643 6481128 6 Plex Done Done Done Done Done Done
G30 P15-067 B2204644 6481127 6 Plex Done Done Done Done Done Done
Area 5
G32 P15-066 B2204630 6481126 4 Plex A Done Done Done Done Done Done
G31 P15-065 B2204631 6481125 4 Plex A Done Done Done Done Done Done
G23 P15-013 B2204638 6481072 8 Plex Done Done Done Done Done Done
G24 P15-012 B2204637 6481071 6 Plex Done Done Done Done Done Done
G25 P15-011 B2204651 6481070 6 Plex Done Done Done Done Done Done
Area 6
G26 P15-010 B2101843 6481069 8 Plex Done Done Done Done Done Done
G27 P15-009 B2102196 6481068 4 Plex B Done Done Done Done Done Done
G28 P15-008 B2204657 6481067 6 Plex Done Done Done Done Done Done Done
G33 P15-064 B2204639 6481124 8 Plex Done Done Done Done Done Done
G34 P15-063 B2204640 6481123 6 Plex Done Done Done Done Done Done
G35 P15-062 B2204653 6481122 4 Plex A Done Done Done Done Done Done
Area 7
G36 P15-061 B2204652 6481121 6 Plex Done Done Done Done Done Done
G37 P15-060 B2204654 6481120 4 Plex A Done Done Done Done Done Done
G38 P15-059 B2204660 6481119 4 Plex A Done Done Done Done Done Done

Count 43 43 43 43 43 43 38 1
25
Progress Photos – Phase 1
Progress Photos – Phase 1
THANK
YOU

28