Photos - Progress Layout
Photos - Progress Layout
Photos - Progress Layout
10
Dashboard
11
Dashboard
12
Dashboard
13
Dashboard
14
Dashboard
15
Dashboard
16
Dashboard-PHASE 1
NCR
NON CONFORMANCE REPORT (NCR) - CIVIL WORKS
Sr. CRC
NCR No. Document Description Location DISC Date Issued Remarks
No. Expected Date
Phase 1
Installation of False Ceiling Board without Inspection Approval of Plot 6481067 (Mock-up) Opening False Ceiling for MEP Inspection to get the
47 VLV-P1-DEC-ARC-NCR-0047 CIV 6-Sep-2023 10-Mar-2024
Suspension System and MEP Clearance 1st Floor E.V. clearence after having anew mock up at villa 38
Plot 6481067 (Mock-up) The rectification will be done after completing the new
63 VLV-P1-DEC-ARC-NCR-0063 Embedded drain slot for aluminum sliding door at balcony tiles CIV 30-Sep-2023 10-Mar-2024
Mid Villa mock up.
Plot Nbr
75 VLV-P1-DEC-ARC-NCR-0075 Unapproved tile skirting material used at plot 6481077 6481077&6481078[G- CIV 5-Dec-2023 10-Mar-2024 Repair works are ongoing
01&G-02]
125 VLV-P1-DEC-HSE-NCR-0125 Unsafe & incomplete scaffolding platform with green tag Phase-1 G-27-G26-G-25 HSE 6-Feb-2024 10-Mar-2024
Phase-1 G-27-G21-G-30- G-
128 VLV-P1-DEC-HSE-NCR-0128 Unprotected & inadequately protected floor openings HSE 13-Feb-2024 10-Mar-2024
22-G23- G17
Joinery kitchen carcass perimeter lipping not comply with the Area 01, Area 02 and Area
131 VLV-P1-DEC-ARC-NCR-0131 ARC 22-Feb-2024 10-Mar-2024
approve materials 03
19
Dashboard-PHASE 1
NCR
NON CONFORMANCE REPORT (NCR) - MEP WORKS
Sr. CRC
NCR No. Document Description Location Date Issued Remarks
No. Expected Date
Phase 1
132 VLV-P1-DEC-MEC-NCR-0132 Blocks and rubbish inside shaft[Roof] 6481080 & 6481141[G04 & G07] MEP 10-Mar-2024
134 VLV-P1-DEC-MEC-NCR-0134 Roof ducts without protection 6481080 & 6481141[G04 & G07] MEP 10-Mar-2024
20
Dashboard-PHASE 1
NCR
Opened NCR 6 7 13
Under Review 6 6 12
21
Dashboard-PHASE 1
Dashboard
Engineering Update
Overall Shop drawings for ARC & STR Overall Shop drawings for MEP
Item Total % Overall Shop drawings Item Total % Overall Shop drawings
Total 309 100% Total 91 100%
Planned 280 91% 9% Approved
Planned 91 100% Approved
1%
Submitted 280 91% 1% Submitted 91 100%
Rejected Rejected
Approved 276 89% Approved 91 100%
Under Review Under Review
Rejected 2 1% Rejected 0 0%
Remaining Remaining
Under Review 2 1% Under Review 0 0%
89%
Remaining 29 9% Remaining 0 0%
Overall Material Submittal for ARC & STR Overall Material Submittal for MEP
Item Total % Overall Material Submittal
Item Total %
Overall Material Submittal
Total 187 100% Total 64 100%
1%
Planned 187 100% 0%
1%
Approved
Planned 64 100% 0% Approved
Submitted 187 100% Submitted 64 100%
Rejected 0% Rejected
Approved 185 99% Approved 64 100%
Under Review Under Review
Rejected 1 1% Rejected 0 0%
Under Review 1 1% Remaining Under Review 0 0% Remaining
Approval Status
Planned Date Actual Date
Total
S.N Material Description SAM LPO Date LPO No. of 1st of 1st Remarks
Date Code Delivered
No. Delivery Delivery
ELECTRICAL
1 WIRING ACCESSORIES 0091 31-Aug-23 B 29-Aug-23 12327 100% 21-Jun-23 7-Sep-23 - Completely Delivered
3 LIGHT FITTINGS 0110 09-Sep-23 B 26-Jul-23 52361 100% 24-Aug-23 5-Oct-23 - Completely Delivered
PLUMBING
MAT -
4 SOLAR WATER SYSTEM 03-Aug-23 B 22-Aug-23 12395 100% 30-Aug-23 - Completely Delivered
0132
5 PUMPS (WATER SUPPLY) 0042 18-May-23 B 10-Aug-23 11811 100% 18-Aug-23 - Completely Delivered
MAT -
6 SANITARYWARE 19-Apr-23 B 10-May-23 52140 80% 18-Aug-23 23-Aug-23 - Partially Delivered
0054
7 WATER TANK COVER 0111 12-Sep-23 B 17-Oct-23 54724 41% 28-Sep-23 22-Dec-23 - Partially Delivered
8 MANHOLE COVERS 0086 19-Dec-23 B 19-Jun-23 11877 75% 16-Feb-24 22-Dec-23 - Partially Delivered
HVAC
8 DX AC SYSTEM 0101 02-Oct-23 B 10-May-23 11752 100% 18-Aug-23 24-Jul-23 - Completely Delivered
9 EXTRACT FAN 0075 09-Jun-23 B 23-Aug-23 11941 100% 18-Aug-23 24-Sep-23 - Completely Delivered
10 AIR OUTLETS 0040 22-Dec-24 B 16-Aug-23 12561 75% 18-Aug-23 10-Sep-23 - Partially Delivered
52191
11 FLOORING TILE 0015 14-Apr-23 B 11-May-23 100% 09-Jul-23 5-Jul-23 - Completely Delivered
52451
52191
12 WALL TILE 0014 14-Apr-23 B 11-May-23 100% 09-Jul-23 5-Jul-23 - Completely Delivered
52451
13 SKIRTING 0037 12-May-23 B 23-May-23 52359 65% 09-Jul-23 22-Aug-23 - Partially Delivered
MARBLE
16 0077 24-Jun-23 B 31-Jul-23 53192 50% 02-Sep-23 - Partially Delivered
(CISTERN & BACKSPLASH)
RFI-
19 HEEL KERB 25-Sep-23 B 31-Jan-24 56649 30% 28-Sep-23 - Partially Delivered
0075
20 SIGNAGE 0128 09-Dec-23 B 11-Dec-23 56083 100% 16-Dec-23 15-Dec-23 - Completely Delivered
23
Building Permits-Phase 1
24
Building Permits-Phase 1
Count 43 43 43 43 43 43 38 1
25
Progress Photos – Phase 1
Progress Photos – Phase 1
THANK
YOU
28