Jayathilaka, R.D.W.W. and Waidyasekara, K.G.A.S., 2022.

Contractual implications related to the


construction industry in pandemic situations: A review of case laws. In: Sandanayake, Y.G., Gunatilake, S.
and Waidyasekara, K.G.A.S. (eds). Proceedings of the 10th World Construction Symposium, 24-26 June
2022, Sri Lanka. [Online]. pp. 249-261. DOI: https://doi.org/10.31705/WCS.2022.21. Available from:
https://ciobwcs.com/2022-papers/

CONTRACTUAL IMPLICATIONS RELATED


TO THE CONSTRUCTION INDUSTRY IN
PANDEMIC SITUATIONS: A REVIEW OF
CASE LAWS
R.D.W.W. Jayathilaka1 and K.G.A.S. Waidyasekara2

ABSTRACT

COVID-19 catastrophe has created various complications related to the construction


industry. Conflicts arise between parties to the contract and among the majority of
stakeholders. A successful contractual implication can manage the contractual
challenges arising within construction job sites. The most common contractual
provisions for the situation are Force Majeure and Changes in Legislation clauses in
standard conditions of contracts. Sufficiency of the available remedies under the
provisions applicable to COVID-19 or any other pandemics is a current talking point in
the construction industry. Following questions are addressed to manage these
unprecedented situation-related contractual conflicts: ‘what are the contractual
challenges faced by the construction industry?’, ‘what are the most applicable
contractual provisions to a pandemic situation?’, ‘what are the pandemic-related
guidelines applicable to the construction industry?’, and ‘what are the available legal
cases to use in a pandemic situation?’ The questions were discussed by carefully
analysing existing literature referring to Case Laws. Future researchers are encouraged
to suggest appropriate strategies for contractual challenges to facilitate the construction
stakeholders to prepare them for future pandemics.

Keywords: Case Law; Contractual Challenges; Contractual Provisions; Construction


Industry; Pandemic.

1. INTRODUCTION
The world has been affected by crises such as Spanish Flu in 1918, Asian Flu in 1957,
and Hong Kong Flu in 1968 during the last century, and Severe Acute Respiratory
Syndrome - SARS in 2002, Swine flu in 2009, and Ebola in 2014 during near past
(Vithana et al., 2020). COVID-19 is the prevailing crisis, announced as a pandemic by
the World Health Organisation (WHO) and expeditious diffusion worldwide (Husien, et
al., 2021). Kiraz and Ustun (2020) stated that the world had faced a critical situation
where none could foresee its impact. The prevailing COVID-19 pandemic has been a
massive threat to the contractual performance in many industries, including the
construction sector (Niraula, et al., 2008). Apart from the high risk of infection through
droplet contamination and exposure to the virus, workers and professionals in the
construction industry are currently facing a job risk with the novel Coronavirus pandemic

1
Department of Building Economics, University of Moratuwa, Sri Lanka, jayathilakardww.21@uom.lk
2
Department of Building Economics, University of Moratuwa, Sri Lanka, anuradha@uom.lk

249
R.D.W.W. Jayathilaka and K.G.A.S. Waidyasekara

(Zheng, et al., 2021). COVID-19 outbreak reminds the researchers about the need for
creative responses to contractual challenges arising with pandemics (Pedamon and
Assileva, 2021). The construction organisations have been daunted with COVID-19 due
to the uncertainties and less awareness on contractual challenges resolution (Andres, et
al., 2020). Furthermore, Bailey et al. (2020) expressed that events such as the COVID-19
pandemic generally engage contractual provisions concerning the consequences of
unforeseen events. Evidently, the construction industry was always embroiled with
protracted and costly dispute resolution procedures (Construction Leadership Counsil
[CLC], 2020). In addition, Sierra (2021) stated that the terms time and money are related
to disputes in construction projects, and the most common conflicts are finance-related
and time-related failures.
Moreover, the author disclosed that the prevailing pandemic situation had aggravated
both these problems. The pandemic originated by COVID-19 adverts the necessity of pre-
preparation to overcome unforeseen risks and have contingency plans for managing
projects in the construction sector (Ogunnusi, et al., 2020). Therefore, it is prudent to
address the pandemic’s impact at the beginning and end of the crisis to prepare for any
future potential and learn lessons for future preparations of the construction industry
(Iqbal, et al., 2021).
This paper aims to review available most common contractual provisions related to cases
within the construction industry, globally and locally, to determine whether these
available cases can implement when parties to the contract claim their entitlements for
pandemic-related challenges. The paper is structured as follows. First, a brief introduction
to the study, followed by the research method adopted, a compressed literature synthesis,
an insight of the research methodology adopted for the study, and a discussion of findings.
Finally, the conclusion is formed based on the key research findings of the study.

2. RESEARCH METHOD
A researcher can review existing researches using several methods (Grant and Booth
2009). To achieve the aim of this research study, a comprehensive review of case laws
was conducted. Available cases in counties like United State (US), France, England and
Wales, Ghana, Singapore and China were incorporated to come up with a good review.

3. COVID-19 AND THE CONSTRUCTION INDUSTRY


Aviantara (2020) brought up the ‘pandemic’ as a critical risk factor that ought to discuss
within the construction industry. The construction industry is always linked with the other
industries directly or indirectly (Tripathi and Jha, 2018). As summarised by Iqbal, et al.
(2021), the construction industry in most countries investigates the applicable approaches
to overcome the negative impacts which may arise due to pandemics, such as the novel
Coronavirus; this is a fundamental need to obstruct an economic downturn (Zamani, et
al., 2021). Therefore, construction stakeholders should be able to answer the following
questions: what are the absolute recommended practices to make secure the construction
industry against a pandemic situation? and what are the unprecedented impacts and
consequences of the COVID-19 on the construction industry? (Porter, 2020). Husien, et
al. (2021) explained that some of the impacts by cause of COVID-19 were more wrathful
and pathetic for all construction practitioners in the construction industry. Porter (2020)

Proceedings The 10th World Construction Symposium | June 2022 250


Contractual implications related to the construction industry in pandemic situations: A review of case
laws

reported that multiple questions remain within the construction industry and the pandemic
situations, which have not been answered yet.

3.1 CONTRACTUAL CHALLENGES IN CONSTRUCTION JOB SITES


The most prominent impacts of COVID-19 are the suspension of projects, labour impact
and job loss, time overrun, cost overrun, and financial implications (Gamil and Alhagar,
2020). Husien, et al. (2021) reported that the pandemic raised many challenges at the
level of the workforce including low or halting productivity, production time and costs,
as well as disputes in contractual formulas for construction projects.
3.1.1 General Challenges with a Pandemic in Construction Job Sites
Through the existing literature, Pamidimukkala and Kermanshachi (2021) have identified
general challenges faced by the construction industry and classified them into five
categories: organisational, economic, psychological, individual, and moderating factors.
Table 1 shows the challenges under each category.
Table 1: General challenges related to COVID-19 in construction job sites

Category Challenges
Organizational • Lack of safe working environment
Factors • Challenges due to work from-home practices
• Managing a heavier workload
• Management team’s lack of leadership knowledge and skills
Economic • Reduced accessibility to updated tools and equipment needed to
Factors accomplish the tasks
• Uncertainty regarding future of workplace
• Supply chain disruptions
• Cash flow delays
Psychological • Social isolation due to teleworking
Factors • Stress and burnout
Individual • Responsibility for personal and family needs when working
Factors • Learn communication tools and overcome technical difficulties
• Feelings of not contributing enough to work
• Adjusting to new work schedules
Moderating • Effect of COVID-19 on vulnerable groups
Factors • Gender-based impacts
• Impacts on migrant workforce
Delays in permits or license, Escalations in prices, High demand of suppliers and
manufacturers, Increase of claims and disputes, Lack of funding, Less productivity in site
works, Payment delays, Project abandonment, and Suspensions or terminations of
projects are the other issues summarised by Alsharef, et al. (2021), American Society of
Civil Engineers [ASCE] (2020), and Osuizugb (2020), in addition to the general
challenges identified by Pamidimukkala and Kermanshachi (2021). On the other hand,
Zamani, et al. (2021) mentioned project duration, construction material, and human
resources are the three main factors related to project operations. According to the

Proceedings The 10th World Construction Symposium | June 2022 251


R.D.W.W. Jayathilaka and K.G.A.S. Waidyasekara

authors, project operations were delayed because COVID-19 smashed these three factors.
Although parties to the contracts needed to restart project activities, the inherent labour-
intensive nature of the construction project caused additional challenges due to the onsite
necessity of construction task delivery and the constraints on the feasibility of social
distancing on an active job site (Zheng, et al., 2021). The most common reasons for delays
in projects are that the daily working period has been shortened and the absence of
employees to the assigned work on time (Alenezi, 2020). Construction parties should
always be aware of uncertainties, incompleteness, and unforeseeable circumstances
affecting construction costs (Elhag, et al., 2005).
3.1.2 Contractual Challenges with a Pandemic in Construction Job Sites
The contractual challenges, stakeholders’ obligations, and contractual provisions may
differ from the general situation in pandemics like COVID-19 (Andres, et al., 2020).
Kabiru and Yahaya (2020) addressed the impact of COVID-19. They discovered that
professionals face legal challenges in the construction industry - e.g., contractual issues
raised to assist contractors in claiming loss and expenses and extension of time (King, et
al., 2021). Proper contract administration is one of the main challenges the construction
stakeholders face with this crisis (Niraula, et al., 2008). Legal provisions in several
contractual documents related to construction contracts may vary among countries and
from project to project (Ogunnusi et al., 2020).
The government, as the client, should revise the contract to aid the contractor to claim
losses for projects delayed due to lockdown, and the government should grant an
Extension of Time (EOT) to cover the period of projects stopping (King, et al., 2021).
Figure 1 presents the contractual challenges related to a pandemic situation in the
construction industry identified by Jayathilaka and Waidyasekara (2022) through a
systematic literature review.

Contractual
Challenges
due to
Pandemics

Figure 1: Contractual challenges due to a pandemic situation in construction industry

Proceedings The 10th World Construction Symposium | June 2022 252


Contractual implications related to the construction industry in pandemic situations: A review of case
laws

3.2 CONTRACTUAL PROVISIONS RELATED TO A PANDEMIC SITUATION IN


CONSTRUCTION INDUSTRY
There was much confusion and uncertainty about dealing with a pandemic on
construction job sites due to the absence of definite construction-related guidelines and
best practices (Budds, 2020). Although the government and health organisations have
issued guidelines to prevent the spread of the virus on job sites, there have not been many
specific guidelines for construction industry workers (Afkhamiaghda and Elwakil, 2020).
Different countries and organisations have developed guidelines and suggestions for
infection prevention (Zheng, et al., 2021), as below:
• COVID-19 - Temporary Measures Act (Singapore)
• Health and Safety Guidelines for Sri Lankan Construction Sites to be adopted
during COVID-19 outbreak (Construction Industry Development Authority -
CIDA, Sri Lanka)
• Quarantine and Prevention of Disease Act - 1897 (Health and Safety Guidelines
for Sri Lankan Construction Sites to be adopted during COVID-19 outbreak, Sri
Lanka)
• Quarantine and Prevention of Diseases Ordinance - 2020 (Sri Lanka)
• FIDIC COVID-19 Guidance Memorandum (To users of FIDIC standard forms of
works contract)
• Phase I COVID-19 construction guidelines for the safety of returning construction
workers (Washington)
• Gazette Extraordinary No. 2167/18 (COVID-19 announced as a quarantinable
disease for the existing Quarantine Regulations passed under the Ordinance in
1925 and 1960 - Sri Lanka)
• Gazette Extraordinary No. 2168/6 (Defining the proper authority and a diseased
locality - Sri Lanka)
• Gazette Extraordinary No. 2197/25 (Restriction of movement and guidelines to be
followed in public places - Sri Lanka)
Ogunnusi, et al. (2020) mentioned that the construction industry had been substantially
affected by COVID-19, and construction stakeholders have given full attention to the
standard forms of contracts to seek appropriate entitlements. Despite the contractual
challenges experienced by the construction industry due to the prevailing crisis, numerous
parties still incite construction stakeholders to rely upon the available uncertain
circumstances related to legal provisions in contractual documents (Alsharef, et al.,
2021).
In line with Bailey, et al. (2020), these provisions commonly fall into two broad
categories, ‘force majeure’, and ‘changes in law’, which is relevant and may yield a
different legal effect. Chivilo, et al. (2020) declared that, since the conditions covered
through a force majeure or excusable delay provision may vary, it should not be presumed
that any contractual language addressing excusable delays applies automatically to the
COVID-19 outbreak. Moreover, the authors reported that a careful review of the language
of any force majeure provision should be undertaken to determine whether impacts
resulting from the COVID-19 outbreak are covered as an excusable delay.
By contrast with force majeure, change in law provisions in construction and engineering
contracts may confer a right to both an extension of time for the contractor and

Proceedings The 10th World Construction Symposium | June 2022 253


R.D.W.W. Jayathilaka and K.G.A.S. Waidyasekara

compensation for the unavoidable costs incurred due to the change in the law (FIDIC,
2017).
Figure 2 compares “force majeure” and “changes in law” clauses in standard forms of
contracts.

Figure 2: Force majeure clause vs changes in law clause in standard forms of contracts

Source: Ford and Bloch (2020)

Under many forms of contract, including the FIDIC forms, a force majeure event would
typically entitle a contractor to an EOT for critical delay caused by the event, but not to
compensation for costs incurred during the period of delay, except in agreed-upon
circumstances (FIDIC, 1999).
Changes in the law/legislation clause would be more useful than the force majeure clause
in the current COVID-19 situation, where the contract can still be performed, but there is
delay and increased cost due to compliance with government regulations (Ford and Bloch,
2020). Parties to the contract should analyse the additional time and costs and contractual
provisions under force majeure and legislation changes to be aware of risk allocation
between parties (Baker, 2021).
Dealing with the force majeure clause is crucial when there is a pandemic situation, and
carefully drafted contractual provisions would ensure that parties are not liable when the
situation is out of the parties’ control (Benarroche, 2020). Furthermore, Bailey, et al.
(2020) expressed, contractually, events such as the COVID 19 pandemic generally do
engage contractual provisions concerning the consequences of unforeseen events.
Moreover, when there are more case laws available to apply for unforeseen situations, it
may help construction parties to unravel the contractual challenges quickly. Still, the issue
is the unavailability of applicable case laws related to unforeseeable circumstances
(Cartwright, et al., 2020).
Parties to the contract in construction projects should be aware of the construction
industry-related case laws, which can apply to pandemic situations for the future use of
potential contractual issues (McLennan, 2021). Therefore, this paper reviews available
most common contractual provisions addressed in few cases related to the construction
industry which can be applied to unravel contractual challenges in a pandemic situation.
Table 2 presents contractual provisions related to cases applicable to a pandemic situation
by reviewing recent past literature.

Proceedings The 10th World Construction Symposium | June 2022 254


Contractual implications related to the construction industry in pandemic situations: A review of case
laws

Table 2: Contractual cases related to a pandemic situation

Country Case
United States • JN Contemporary Art LLC vs Phillips Auctioneers
(US) • Rudolph vs United Airlines Holdings
• R & B Falcon Corp. vs American Exploration
• LLC vs Conoco Phillips
• Am. Nat. Red Cross vs Vinton Roofing Co
• SNB Farms, Inc. vs Swift & Co.
France • Lebeaupin vs Richard Crispin & Co,12 McCardie J
• General Construction Co. Ltd vs Ibrahim Cassam & Co. Ltd
England and • Fibula Air Travel Srl vs Just-US Air Srl
Wales • Entertain Video Limited and Others vs Sony DADC Europe Limited and
Others
• McCardie J in Lebeaupin vs Crispin
• Clifford Gardner vs Clydesdale Bank Limited
• Thames Valley Power Ltd vs Total Gas & Power Ltd
Ghana • Tennants (Lancashire) Ltd vs CS Wilson & Co Ltd
• Seadrill Ghana Operations Ltd vs Tullow Ghana Ltd
Singapore • Holcim Singapore Pte. Ltd vs Precise Development Pte Ltd
China • Li Ching Wing vs Xuan Yu Xiong
United States (US)
New York courts use strict interpretation for legal issues. Cartwright et al. (2020) stated
US courts rely on the express language, and only events specifically listed in the delay
clause will excuse performance as well as determine that any construction delay caused
by the COVID-19 pandemic is way beyond the “reasonable control of the parties,” and
covered with force majeure clauses. Moreover, California requires the party invoking the
clause to prove reasonable efforts to avoid the consequences of the force majeure event.
A decision given for JN Contemporary Art LLC vs Phillips Auctioneers, LLC, No. 1:20-
cv-04370-DLC in the Southern District of New York has presented the COVID-19
pandemic as a ‘natural disaster’ that is beyond the parties’ ‘reasonable control’, and thus
triggered the force majeure clause (McLennan, 2021). McLennan (2021) stated the case,
Rudolph vs United Airlines Holdings, Inc., 2021 WL 534669, related to US District
Court, provided that there must be some point where a force majeure event ends and a
schedule change or irregular operation begins. The author further mentioned that the mere
existence of a force majeure event was not sufficient, and demonstrating causation was
essential. The defendant could not rely on the force majeure clause. Moore and Cornelius
(2021) stated that Texas Supreme Court held that a force majeure event is not an excuse
for non-performance when a prior material breach has occurred. Moreover, the author
discussed that, in the construction industry context, a contractor seeking to claim a
pandemic as an “Act of God” force majeure excuse for its failure to meet a specific
turnover date would have to demonstrate that no concurrent delays existed. The following
cases suggest pandemics may fall into a “catch-all” provision:

Proceedings The 10th World Construction Symposium | June 2022 255


R.D.W.W. Jayathilaka and K.G.A.S. Waidyasekara

R & B Falcon Corp. vs American Exploration and LLC vs ConocoPhillips, in the


context of pandemic-related government regulations, the more stringent state or local
government stay-at-home orders that did not exempt construction activities could
arguably be the type of regulation constituting an excusable event under an applicable
force majeure provision (Moore and Cornelius, 2021). The case of Am. Nat. Red Cross
vs Vinton Roofing Co., 629 F. Supp. 2d 5, 9 (DDC 2009) highlighted that an act of God,
such as pandemic situations, cannot be avoided by parties before it happens or cannot be
prevented (McLennan, 2021). Huie (2020) stated that SNB Farms, Inc. vs Swift & Co.
case provides an important point when parties follow the process of seeking entitlements
during a pandemic. The parties can have their remedies when a notice is given to the other
party by mentioning the force majeure event.
Germany
The required standards are associated with the High Supreme Court Verdicts in Germany.
Haas and Markovic (2021) mentioned that if the circumstances are related to ‘force
majeure’ or ‘act of God’, when the claimant grants legal/contractual merit, entitled to get
time extensions and can grant the additional cost suffered totally or some.
France
According to Haas and Markovic (2021), Lebeaupin vs Richard Crispin & Co,12
McCardie J case referred that an epidemic could amount to an event of force majeure.
The authors mentioned that in general, if the situation is relatively uncontroversial,
whether an event of force majeure has actually arisen on a particular set of facts is a
question of fact in every case. The case of General Construction Co. Ltd vs Ibrahim
Cassam & Co. Ltd provides the following two characteristics to consider an event as a
force majeure event under the Court of Civil Appeals:
• The event must have been unforeseeable/unpredictable at the time of the
conclusion of the contract
• The event must be irresistible/Insurmountable (DLA-Piper, 2022)
DLA-Piper (2022) stated it is worth noting that epidemics outbreaks have not always been
considered as force majeure events. In 2014, the epidemic of H1N1 Flu was officially
announced and foreseen even before the implementation of health regulations but did not
constitute an event of force majeure. In addition, the author mentioned that such reasoning
could be applied perfectly to the current COVID-19 pandemic and outbreak that contains
both a natural component, which is the virus itself, as well as governmental element
(curfew) measures which make the execution of contracts even more difficult.
England and Wales
English courts have taken a cautious approach to the effect of the COVID-19 pandemic
under force majeure provisions: for example, in the High Court decision in Fibula Air
Travel Srl vs Just-US Air Srl (2020) EWHC 3048 (Comm), a party could not rely on the
pandemic to invoke a force majeure clause to escape its obligations before government
restrictions and ‘failure or delay in the performance of any obligations under the
agreement’ would continue for a period (McLennan, 2021). In the absence of express
language covering ‘pandemics’ or ‘infectious disease’, courts will be unlikely to accept
arguments that the existence of COVID-19 is sufficient to invoke a force majeure clause
(McLennan, 2021). Cheung (2020) stated even the government has failed to comply with
public procurement law under the COVID-19 pandemic pressure, the High Court in

Proceedings The 10th World Construction Symposium | June 2022 256


Contractual implications related to the construction industry in pandemic situations: A review of case
laws

London has ruled that landlords are entitled to recover rent and service charges owed to
them by tenants whose businesses were mandated to close by coronavirus restrictions.
Based on the case, Entertain Video Limited and Others vs Sony DADC Europe Limited
and Others, the Technology and Construction Court has recently considered the meaning
of a force majeure clause which could have implications for how these clauses are
interpreted within construction contracts. Fenwick (2021) stated the clause, “Neither
party shall be liable for its failure or delay, if such failure or delay is caused by
circumstances beyond the reasonable control of the party affected including but not
limited to riot, civil commotion, malicious damage, etc. as well as pandemics”. As per
the mentioned clause, the current COVID-19 pandemic comes under the force majeure
clause.
The case McCardie J in Lebeaupin vs Crispin (1920) 2 KB 714 was applied for many
situations in England. It established that the events independently happening come under
the force majeure category (Albertini, 2020). Further, Clifford Gardner vs Clydesdale
Bank Limited (2013) provides that a flu pandemic belongs to the force majeure category.
According to the case Thames Valley Power Ltd vs Total Gas & Power Ltd (2006), no
reported cases are testing the scope of the term “force majeure” in the context of some
types of standard forms of contracts (Albertini, 2020).
Saudi Arabia
The Saudi Arabian Supreme Court issued decision No. M/45/M of 08/05/1442AH (the
KSA Decision) 2020, and the decision sets out how contracts governed by Saudi law will
be impacted by COVID-19. The Saudi Arabian Supreme Court has confirmed that
COVID-19 is considered an ‘emergency event’ and will be deemed a force majeure if
certain conditions are met (McLennan, 2021).
Ghana
Some standard forms of contracts do not have the word ‘prevent’, and on behalf of that,
there may be another term (Lucy and Chambers, 2019). The case of Tennants
(Lancashire) Ltd vs CS Wilson & Co Ltd [1917] AC 495 provides the following
requirement for parties to the contract, which should be present when seeking
entitlements. “Parties shall put their full effort to minimise the impact, void, or overcome
the circumstances of force majeure.” When dealing with a pandemic, Seadrill Ghana
Operations Ltd vs Tullow Ghana Ltd [2018] EWHC 1640 case is also important because
it highlights the key importance in the context of a pandemic. In this case, the Court
emphasised that “the force majeure event must be causative to the contractual breach and
that reasonable steps to avoid the effects of force majeure event must be taken” (Lucy
and Chambers, 2019).
Singapore
Holcim Singapore Pte. Ltd vs Precise Development Pte Ltd (2011) provides that “the
force majeure event must be causative to the contractual breach and that reasonable steps
to avoid the effects of force majeure event must be taken” (Lucy and Chambers, 2019).
China
Li Ching Wing vs Xuan Yu Xiong (2004) 1 HKLRD 754 case is related to SARS
pandemic, and the Court held that even though that is an unforeseeable circumstance,

Proceedings The 10th World Construction Symposium | June 2022 257


R.D.W.W. Jayathilaka and K.G.A.S. Waidyasekara

contractual parties should fulfil their duties and obligations accordingly to have the
applicable entitlement (Hansen, 2020).

4. CONCLUSIONS
Since this is the first time most construction stakeholders face a pandemic situation like
COVID-19, many disputes have occurred, are still occurring, and may occur in future
regarding contractual provisions available in the construction industry. According to the
findings, the most common contractual provisions which are applicable to contractual
conflicts in pandemic situations available in the construction industry are ‘Force Majeure’
and ‘Changes in Legislation’ clauses. Accordingly, the Laws in terms of the Contracts
have been changed in preventive measures of the COVID-19 pandemic. Parties to the
contract should pay attention to whether they will depend on the available clauses and
terminologies related to the pandemic or adjust available provisions concerning the crisis
COVID-19. Since COVID-19 is a novel pandemic crisis, only a few cases are available
within the construction industry. Most of the cases have mentioned ‘pandemic’ as an
‘unforeseen situation beyond the reasonable control of the parties’. If more case laws are
available to apply for unforeseen situations, it may help construction parties to unravel
the contractual challenges easily; however, the issue is the unavailability of applicable
case laws related to an unforeseeable circumstance. Due to the unavailability of particular
contractual provision to ‘pandemic’ with in the standard forms of contracts, identified
cases will be provided ground for applicable contractual implications to the contractual
challenges faced by the construction industry in a pandemic situation. Further, parties to
the contract must determine whether they should include new contractual provisions
within the standard forms of contracts or use the existing provisions with minor changes.
Finally, construction stakeholders should pay attention to available legal cases to
implement when claiming their entitlements to be a success in coming contractual
challenges related to pandemic situations.

5. ACKNOWLEDGEMENTS
The authors wish to acknowledge the support from the Senate Research Committee of the
University of Moratuwa, Sri Lanka under the Grant SRC/ST/2021/01.

6. REFERENCES
Afkhamiaghda, M. and Elwakil, E., 2020. Preliminary modeling of Coronavirus (COVID-19) spread in
construction industry, Journal of Emergency Management, 18(5), pp. 1-9.
Albertini, A., 2020. COVID-19 projects & construction: The impact of the Coronavirus outbreak on
construction projects, Clyde & Co LLP. [Online] Available from:
https://doi.org/10.1016/j.tmaid.2020.101607%0Ahttps://doi.org/10.1016/j.ijsu.2020.02.034%0Ahttps:/
/onlinelibrary.wiley.com/doi/abs/10.1111/cjag.12228%0Ahttps://doi.org/10.1016/j.ssci.2020.104773
%0Ahttps://doi.org/10.1016/j.jinf.2020.04.011%0Ahttps://doi.o.
Alenezi, T.A.N., 2020. The impact of Covid-19 on construction projects in Kuwait, International Journal
of Engineering Research and General Science, 8(4), pp. 6-9.
Alsharef, A., Banerjee, S., Uddin, S.J., Albert, A. and Jaselskis, E., 2021. Early impacts of the COVID-19
pandemic on the United States construction industry. International journal of environmental research
and public health, 18(4), p.1559.
Andres, O., Rodriguez-Sastre, I. and Sevita, E., 2020. The impact of COVID-19 outbreak on international
arbitration, Anderson Global. [Online] Available from: https://global.andersen.com.

Proceedings The 10th World Construction Symposium | June 2022 258


Contractual implications related to the construction industry in pandemic situations: A review of case
laws

American Society of Civil Engineers (ASCE), 2020. COVID-19 impact and implementation survey:
Executive summary. [Online] Available from:
http://images.message.asce.org/Web/AmericanSocietyOfCivilEngineersInc/%7Be9835dea-9295-
46d7-8770-0dede6d1e907%7D_COVID3-asceV03.pdf?utm_campaign=Comm-20200612-ASCE
News
weekly%26utm_medium=email%26utm_source=Eloqua%26elqTrackId=dfa0c97ba10344a881c2386d
33f.
Aviantara, R., 2020. The ICT construction risk management in pandemic COVID-19. Trisakti University,
Jakarta, Indonesia. [Online] Available from:
https://www.academia.edu/44243479/the_ict_construction_risk_management_in_pandemic_covid_19
.
Bailey, J., Bouchardie, N. and Madalena, I., 2020. COVID-19: The current impact on construction and
engineering projects, White & Case LLp, 14 April, pp. 19-21. [Online] Available from:
https://www.whitecase.com/publications/alert/covid-19-current-impact-construction-engineering-
projects.
Baker, M., 2021. COVID-19: Impacts and responses in the construction industry, Baker McKenzie Global
COVID-19 Resource Center. [Online] Available from: https://www.bakermckenzie.com/-
/media/files/insight/publications/2021/01/covid19--impacts-and-responses-in-the-construction-
industryv2.pdf.
Benarroche, A., 2020a. Act of god: What does ‘force majeure’ mean in construction contracts ?, Levelset.
[Online] Available from: https://www.levelset.com/tag/construction-contract/.
Benarroche, A., 2020b. Coronavirus & force majeure : Are construction delays an act of god?, Levelset.
[Online] Available from: https://www.levelset.com/tag/construction-contract/ [Accessed 2 January
2022].
Budds, D., 2020. How essential is construction during the coronavirus pandemic? [Online] Available from:
https://archive.curbed.com/2020/3/30/21199753/coronavirus-covid-19-construction-industry
[Accessed 28 August 2021].
Cheung, B.M., 2020. Construction law in 2020 : key legal and industry developments. Landon. [Online]
Available from: https://www.i-law.com/ilaw/construction.htm.
Chivilo, J.P., Fonte, G.A. and Koger, G.H., 2020. A look at COVID-19 impacts on the construction
industry, Holland & Knight Alert, pp. 1-12. [Online] Available from:
https://www.hklaw.com/en/insights/publications/2020/05/a-look-at-covid19-impacts-on-the-
construction-industry.
Construction Leadership Counsil (CLC). 2020. CLC COVID-19 contractual best practice guidance, pp. 1-
19. [Online] Available from: https://www.constructionleadershipcouncil.co.uk/wp-
content/uploads/2020/06/Construction-Leadership-Council-Covid-19-Contractual-Best-Practice-
Guidance-7-May-2020.pdf.
DLA-Piper, 2022. COVID-19 and its impact on contractual performance in mauritius - Force majeure, DLA
Piper, pp. 1-7. [Online] Available from: https://larevue.squirepattonboggs.com/covid-19-impact-on-
contractual-relations-in-france-force-majeure-and-hardship.html [Accessed 14 May 2020].
Elhag, T.M.S., Boussabaine, A.H. and Ballal, T.M.A., 2005. Critical determinants of construction tendering
costs: Quantity surveyors’ standpoint, International Journal of Project Management, 23(7), pp. 538-
545.
Fenwick, E., 2021. Annual review 2020/2021 - A round up of key developments in the construction,
engineering and energy arena, European Aggregates Association. [Online] Available from:
https://uepg.eu/mediatheque/index/1.html.
FIDIC, 1999. Conditions for Contract. International Federation of Consulting Engineers. [Online]
Available from: http://site.iugaza.edu.ps/kshaath/files/2010/12/FIDIC-1999-RED-BOOK.pdf.
FIDIC, 2017. Conditions of contract for construction. 2nd ed. International Federation of Consulting
Engineers. [Online] Available from: https://www.treasury.gov.lk/api/file/7fae21c1-fb48-45c0-8d2a-
265de763bf8a.
Ford, C. and Bloch, C., 2020. Change in law clauses and force majeure in COVID-19, Squire Patton Boggs.
[Online] Available from:

Proceedings The 10th World Construction Symposium | June 2022 259


R.D.W.W. Jayathilaka and K.G.A.S. Waidyasekara

https://www.squirepattonboggs.com/en/insights/publications/2020/04/change-in-law-clauses-and-
force-majeure-in-covid-19 (Accessed: 24 April 2020).
Gamil, D.Y. and Alhagar, A., 2020. The impact of pandemic crisis on the survival of construction industry:
A case of COVID-19, Mediterranean Journal of Social Sciences, 11(4), pp. 122-128.
Grant, M.J. and Booth, A., 2009. Methodologies, Health Information and Libraries Journal, 26(2), pp. 91-
108.
Haas, O. and Markovic, P., 2021. Negative effects caused by COVID 19 on critical path of construction
projects, SHS Web of Conferences, 115(3005), pp. 1-12.
Hansen, S., 2020. Does the COVID-19 outbreak constitute a force majeure event? A pandemic impact on
construction contracts, Journal of the Civil Engineering Forum, 6(1), p. 201.
Huie, J., 2020. Managing project risk associated with the Coronavirus outbreak through force majeure
provisions, Seyfarth.
Husien, I.A., Borisovich, Z. and Naji, A.A., 2021. COVID-19: Key global impacts on the construction
industry and proposed coping strategies, In E3S Web of Conferences, pp. 1-9.
Iqbal, M., Ahmad, N., Waqas, M. and Abrar, M., 2021. COVID-19 pandemic and construction industry:
Impacts, emerging construction safety practices, and proposed crisis management. Brazilian Journal of
Operations & Production Management, 18(2), pp. 1-17.
Jayathilaka R.D.W.W. and Waidyasekara K.G.A.S., 2022. A systematic review on contractual challenges
in construction industry during a pandemic situation (COVID 19), In Proceedings of the International
Conference on Industrial Engineering and Operations Management Istanbul, Turkey, March 7-10,
2022, pp. 1-12.
Kabiru, J.M. and Yahaya, B.H., 2020. Can Covid-19 considered as force majeure event in the Nigeria
construction industry ?, International Journal of Scientific Engineering and Science, 4(6), pp. 34-39.
King, S.S., Rahman, R.A., Fauzi, M.A. and Haron, A.T., 2021, February. Mechanisms for addressing the
impact of COVID-19 on infrastructure projects. In IOP Conference Series: Earth and Environmental
Science, Vol. 682, No. 1, p. 012047, IOP Publishing.
Lucy, G. and Chambers, K., 2019. COVID-19 and force majeure:Causation. [Online] Available from:
https://uk.practicallaw.thomsonreuters.com/w-026-4918
McLennan, M., 2021. Recent COVID-19 related force majeure decisions: What do they mean for
construction contracts?, Practical Law Construction Blog. [Online] Available from:
http://constructionblog.practicallaw.com/recent-covid-19-related-force-majeure-decisions-what-do-
they-mean-for-construction-contracts/ [Accessed 18 May 2018].
Moore, M.S.C. and Cornelius, F., 2021. The force majeure doctrine and standard construction form contract
provisions: Revisiting an old contract provision during these new uncertain times, Construction Law
Journal, 17(1), pp. 1-8.
Niraula, R., Goso, T. and Kusayanagi, S., 2008. Establishing construction contract administration
education/training program for developing countries, Journal of Construction Management, JSCE, 15,
pp. 415-427.
Ogunnusi, M., Hamma-Adama, M., Salman, H. and Kouider, T., 2020. COVID-19 pandemic: The effects
and prospects in the construction industry. International Journal of Real Estate Studies, 14(Special
Issue 2).
Osuizugbo, I. C., 2020. Disruptions and responses within Nigeria construction industry amid COVID-19
threat, Covenant Journal in Research and Built Environment, 8(2), pp. 37-48.
Pamidimukkala, A. and Kermanshachi, S., 2021. Impact of COVID-19 on field and office workforce in
construction industry, Project Leadership and Society, 2, pp. 1-10.
Pedamon, C. and Assileva, V., 2021. Contractual performance in COVID-19 times : Does Anglo-French
legal history repeat itself ?, European Review of Private Law, 2, pp. 3-38.
Porter, R., 2020. 3 ways to manage the impact of COVID-19 in the construction industry. [Online] Available
from: https://exclusive.multibriefs.com/content/3-ways-to-manage-the-impact-of-covid-19-in-the-
construction-industry/business-management-services-risk-management [Accessed 28 August 2021].
Sierra, F., 2021. COVID-19: Main challenges during construction stage, Engineering, Construction and
Architectural Management, pp. 1-12.

Proceedings The 10th World Construction Symposium | June 2022 260


Tripathi, K. and Jha, K.N., 2018. Determining success factors for a construction organization: A structural
equation modeling approach, Journal of Management in Engineering, 34(1), pp. 1-15.
Vithana, N.D.I., Bandara, S. and Jayasooriya, S., 2020. Impact of COVID-19 pandemic to construction
industry in Sri Lanka, In 13th International Research Conference, General Sir John Kotelawala Defence
University, pp. 161-166. [Online] Available from:
http://www.epistemonikos.org/documents/0909a38cced04de74b97913fe0d0bb56193481f1.
Zamani, S.H., Rahman, R.A., Fauzi, M.A. and Yusof, L.M., 2021, February. Effect of COVID-19 on
building construction projects: Impact and response mechanisms. In IOP Conference Series: Earth and
Environmental Science, Vol. 682, No. 1, p. 012049, IOP Publishing.
Zheng, L., Chen, K. and Ma, L., 2021. Knowledge, attitudes, and practices toward COVID-19 among
construction industry practitioners in China, Frontiers in Public Health, 8, pp. 1-9.

Proceedings The 10th World Construction Symposium | June 2022 261