Chinese Listed Company

Stock Code: SZ 300986

Aluminium
Formwork
System
One-Stop Solution Provider to
Make Drawings Happen
COMPANY INTRODUCTION
Formwork & Scaffolding Expert Formwork & Scaffolding Expert

Company Profile
Why do I Choose GETO? GETO ① is an A-share listed company (stock code: SZ 300986) specializing in aluminium
formwork and self-climbing platform system. Its headquarters was registered in
Jiangxi and the global operation management center is based in Tsui Hang New
District, heart of the Guangdong-Hong Kong-Macao Greater Bay Area. GETO products
are sold well in over 30 countries and regions. We had set up ten domestic production
bases, and an overseas one in Malaysia. We are one of the first specially qualified
and national high-tech enterprises. With a backbone team of over 2,000 talents, we
are taking the lead in the realization of scale, specialization and intelligentization,
focusing on formwork system R&D, production, leasing, sale, renovation and
technical services, providing customers with a full range of high-quality services.
① GETO: The pronunciation of the brand name is " ".

Specialize in the Industry


Create World Famous Brand
UNITED
ROMANIA
STATES DOMINICN
REPUBLIC
ALGERIA

PAKISTAN CHINA
RUSSIA
HONG
JAMAICA Saint-Martin KONG
FR
BHUTAN
KAZAKHSTAN VIETNAM

PHILIPPINES
UNITED ARAB
PANAMA EMIRATES
INDIA
VENEZUELA
CAMBODIA

MALAYSIA
DJIBOUTI LAOS
CHILE MALDIVES

SINGAPORE AUSTRALIA

SRILANKA

ARGENTINA MAURITIUS THAILAND

NEW
ZEALAND

Guangchang Factory I Jiangmen Factory Xianning Factory Lingao Factory Tongnan Factory
Jiangxi Province, China Guangdong Province, China Hubei Province, China Hainan Province, China Chongqing Province, China

Guangchang Factory II Weifang Factory Dingxi Factory Nilai Factory Fuzhou Factory
Jiangxi Province, China Shandong Province, China Ganshu Province, China Malaysia Fujian Province, China

10 production bases

5,000,000 ㎡ total production capacity

20+ subsidiaries

Production bases VR 100+ successful projects worldwide

2 3
Formwork & Scaffolding Expert Formwork & Scaffolding Expert

CONTENTS
01
ALUMINIUM FORMWORK INTRODUCTION P5-8
Aluminium Formwork Profile
Comparison of Aluminium Formwork & Steel Formwork & Timber Formwork
Aluminium Formwork Advantages

02 ALUMINIUM FORMWORK
INTRODUCTION
GETO ALUMINIUM FORMWORK SYSTEM P9-21
GETO Aluminium Formwork Systems
System Features
Components
Accessories
Quick-deck System

03
GETO ALUMINIUM FORMWORK SYSTEM ADVANTAGES P22-26
One-stop Comprehensive Solutions
GETO-BIM Automatic Modulation Software
GETO-VR Inspection Software
Quality Assurance
Installation Instruction

04
PROJECT REFERENCES P27-43
Technical Solutions
Projects in Malaysia
Projects in Singapore
Projects in other countries in Southeast Asia
Projects in South Asia
Projects in Hongkong, China, Macao, China, Taiwan, China
Projects in GCC countries
Projects in Americas
Projects in Africa
Projects in Europe

4 5
Formwork & Scaffolding Expert Formwork & Scaffolding Expert

Aluminium Formwork Profile Comparison of Aluminium Formwork &


Aluminium formwork is a new generation of construction formwork after timber Steel Formwork & Timber Formwork
and steel formwork. Aluminium alloy profile is the main material and it is made
into formwork through machining, welding, and other processes, which is suitable Timber Aluminium
for concrete engineering. Aluminium formwork can be assembled freely according Characteristics Steel Formwork
Formwork Formwork
to different structures and sizes. Its design and application is the innovation of Material Performance
formwork technology.
Weight Heavy Light Light
Loading capacity High Low High
Waterproofness Easy to rust Easy to swell Waterproof
Corrosivity Easy to rust Corrodible Incorrodible
Tensile strength High Low High
Characteristics of Installation Process
Installation difficulty Low High Lowest
Labour intensity High High Low
Security risk High High Low
Depend on lifting
Need Need Needless
machinery or not
Aluminium Formwork Forming Effect Aluminium Formwork on Site Concrete Forming Effect
Concrete surface
Rough, clean Rough Glossy, smooth
quality
Need to plaster or not Needless Need Needless
Precision High Low High
Comparison of Cost
Amortization cost High High Low
Scrap value Middle None High
Environmental Protection
Environment friendly Yes No Yes
Generate
construction waste or None Much None
Timber Formwork Forming Effect Timber Formwork on Site not
Common formwork
30-40 times 3-5 times 150-300 times
usage times
Efficiency
10-12 days /
Efficiency 8-10 days / Floor 4-6 days / Floor
Floor
*The data above are from GETO's construction experience.

Steel Formwork Forming Effect Steel Formwork on Site

6 7
GETO ALUMINIUM
Formwork & Scaffolding Expert Formwork & Scaffolding Expert

Aluminium Formwork Advantages


Excellent Forming Effect FORMWORK SYSTEM
1. Large areas of single panels, less patchwork; What is GETO Aluminium Formwrok?
2. High precision;
3. High bearing capacity;
4. High concrete surface quality, easy to reach the quality standards of fair-faced
concrete construction that require no plastering.

Less Construction Cost


1. Reduce the integrated costs with high utilization;
2. Save labor costs due to the high erection speed;
3. Reduce heavy equipment leasing expenses such as cranes;
4. Reduce the cost of plastering and save the cost of decoration;
5. The scrap value is high.

Speed
1. Workers can carry and assemble the formwork efficiently without any equipment
due to the light weight;
2. The assembly is simple and flexible like building blocks.

Safety
1. The material of aluminium formwork has the characteristics of high strength, high
bearing capacity, and not easy to deform;
2. After the system is assembled, a whole frame is formed with high stability;
3. No need of cranes or aerial work, decreasing the risk of falling accidents.

Environment Friendly
1. The service life of aluminium formwork can reach 200-300 times, the utilization is
high;
2. The scrap aluminium formwork can be recycled, contributing to environmental
protection;
3. Reduce the construction waste.

8 9
Formwork & Scaffolding Expert Formwork & Scaffolding Expert

GETO Aluminium Formwork Systems System Features

Tie-Rod System
The forming effect of the tie-rod reinforcement system is very smooth. The tie-rod
reinforcement system is more suitable for the refurbishment project with different
structures and the project with wall thickness structures larger than 400mm.

Flat-Tie System
The formwork with the flat-tie reinforcement system is free of drilling, with the good
vertical casting effect and fewer installation accessories, reducing the installation
workload of workers, which is more in line with the use habits of overseas workers.

Statement:
*It is the normal phenomenon that the dirt spots appear on the surface of aluminium alloy formwork due to
oxidation. It will not affect the quality of the material and the concrete outcome quality.
**In order to reduce the phenomenon of oxidation of aluminium formwork can choose to powder coating
treatment on the surface of aluminium formwork, but due to the differences in actual usage on site, powder
coating aluminium formwork also exists the risk of powder coming off.

10 11
Formwork & Scaffolding Expert Formwork & Scaffolding Expert

Friction Stir Welding (FSW) Components


Technical Background WALL & COLUMN——Wall Panel Item W(WxH) Weight (kg)

Developed in 1991 in Cambridge, United Kingdom by The Welding Institute(TWI). 600 W 2400 27.54
During welding, stir welding head will move through the connection joint and turn it 500 W 2400 23.65
to the welding joint. This welding technology applies high pressure between 2 plates 400 W 2400 19.97
and welds them through the heat caused by the friction. 350 W 2400 17.93
300 W 2400 14.89

Advantages of FSW 250 W 2400 13.13


200 W 2400 11.44
Application. As a solid state process it can be REMARKS:
150 W 2400 9.35
applied to all the major aluminium alloys and
1. Without external corner at both sides
2. Without Rocker at the bottom

Bimetallic (aluminium/magnesium) welding is


125 W 2400 8.56
DESCRIPTION:

possible. [bimetallic: different metallic properties]


Wall Panel is used to support vertical structure like wall and column. Usually the 100 W 2400 7.76
bottom part is linked to Rockers with Bolt & Nut for easy dismantling while the top
is connected to Beam Joint for beam or Slab Joint with Pin & Wedge. 50 W 2400 6.18

Optimize the welding process. Avoid problems of


hot cracking, porosity, element loss, etc. common
to aluminium fusion welding processes. No
shielding gas or filler wire is required for aluminium
alloys.
WALL & COLUMN——Wall End Panel
Excellent mechanical properties. S(WxH) Weight (kg)
400 WS 2400 28.77

Reduce distortion. The absence of fusion removes much of the thermal contraction
350 WS 2400 27.01

associated with solidification and cooling, leading to significant reductions in distortion.


300 WS 2400 25.34
250 WS 2400 23.57

Workplace friendly. There is no ultraviolet or electromagnetic radiation hazards as the 200 WS 2400 18.26

absence of arc removes these hazards from the process; the process is no noisier than 150 WS 2400 19.79
a milling machine of similar power, and generates virtually zero spatter, fume and other
DESCRIPTION:
Fill up the formwork area, where standard wall panels unable to fit at the horizontal- 125 WS 2400 19.01
pollutants. end sides of the formwork system.
100 WS 2400 18.21

Reduce errors caused by manual operation. As a mechanized process, FSW does not
rely on special welding skills; indeed manual intervention is seldom required.

WALL & COLUMN——Wall Top Panel Item WT(WxH) Weight (kg)


600 WT 600 6.65
500 WT 600 5.72
400 WT 600 4.80
350 WT 600 4.32
300 WT 600 3.87
250 WT 600 3.39
200 WT 600 2.94
150 WT 600 2.47
125 WT 600 2.24
100 WT 600 2.00
DESCRIPTION:
Wall top panel is used to connect the standard wall panel to satisfy the storey. 50 WT 600 1.53

12 13
Formwork & Scaffolding Expert Formwork & Scaffolding Expert

WALL & COLUMN——External Corner Joint Item EC(H) Weight (kg) BEAM——Beam Soffit Item BSB(HxL) Weight (kg)
DESCRIPTION: REMARKS:
Used to connect wall panels at external 63.5×63.5 EC 2400 4.81 With external corner at both sides.
400 BSB 1100 8.71
corner area.
63.5×63.5 EC 600 1.21 DESCRIPTION: 300 BSB 1100 7.05
Beam soffit issued to support Beam.
250 BSB 1100 6.20
200 BSB 1100 5.39
150 BSB 1100 4.56
125 BSB 1100 4.15
WALL & COLUMN——Internal Corner Joint Item(A1+A2) IC (H) Weight (kg)
100×100 IC 2400 14.12
100×120 IC 2400 15.32
100×125 IC 2400 15.62
BEAM——Beam Prop Head Item BP(HxL) Weight (kg)
100×130 IC 2400 16.30 DESCRIPTION:
100×140 IC 2400 16.51 Panel to support beam and use to join 300 BP 300 2.51
two Beam Bottom with Pin & Wedge.
200 BP 300 1.98
100×150 IC 2400 17.12
200 BP 250 1.72
DESCRIPTION: 100×160 IC 2400 17.33
Internal corner joint is used to connect wall panel and wall end panel at internal 200 BP 200 1.47
corner. The height of IC are equal to the wall panel height. 150×150 IC 2400 20.12
150 BP 300 1.71
150 BP 200 1.26
150 BP 150 1.03

WALL & COLUMN——Rocker Item R (H+W) Weight (kg)


DESCRIPTION:
Used to connect wall panels at external 63.5 R 45 600 1.02
BEAM——Prop Head
corner area.
63.5 R 50 600 1.06 Item PH(HxL) Weight (kg)
DESCRIPTION:
Use to join the beams together (Middle 150 PH 330 1.74
beam and/or End beam), the steel props
will be placed under the prop head. 150 PH 280 1.50
150 PH 230 1.26

WALL & COLUMN——Kicker Item K(LxH) Weight (kg)


350 K 1800 12.59

BEAM——Beam Corner Joint


350 K 1200 8.50
300 K 1800 11.30 Item(A1+A2)LS(L) Weight (kg)
300 K 1200 7.62 DESCRIPTION:
100×100 LS 200 2.24
Use for internal corners usually at
DESCRIPTION: 150 K 1800 7.31 beams. Connect to other panels using 100×120 LS 200 2.57
Pin & Wedge.
Kickers are fixed on the external wall panels with kicker screws before concrete
pouring. The function of kickers is to support the external wall panels for next floor. 150 K 1200 4.92 100×125 LS 200 2.64
100×130 LS 200 2.74
100×140 LS 200 2.85
100×150 LS 200 2.99

BEAM——Beam Soffit
100×160 LS 200 3.13
Item BS(HxL) Weight (kg) 150×150 LS 200 3.70

400 BS 1100 13.35


300 BS 1100 11.69
250 BS 1100 10.84

REMARKS: 200 BS 1100 8.37


With external corner at both sides.
150 BS 1100 9.20
DESCRIPTION:
Beam soffit issued to support Beam. 125 BS 1100 8.79

14 15
Formwork & Scaffolding Expert Formwork & Scaffolding Expert

BEAM——Beam Side Panel Item B(HxL) Weight (kg) SLAB——Slab End Beam Item EB Weight (kg)
DESCRIPTION:
Use for internal corners usually 400 B 1100 8.71 150 EB 300 2.42
at beams. Connect to other
panels using Pin & Wedge. 300 B 1100 7.05 150 EB 400 3.20
200 B 1100 5.40 150 EB 500 3.97
150 B 1100 4.56 150 EB 600 4.75
100 B 1100 3.73 150 EB 700 5.53
DESCRIPTION:
Use to join the prop head and slab corner, the end beam supports the slab panels. 150 EB 800 6.31

BEAM——Beam Internal Corner Item (A1+A2) IC (H) Weight (kg)


DESCRIPTION: SLAB——Slab Corner Joint Item (A1+A2) SN (L) Weight (kg)
Internal corner joint is used to connect 100×100 IC 400 2.05
panels at internal corner. The height DESCRIPTION:
of IC are equal to the beam side panel 100×150 IC 400 2.42 The slab corner joint will 100×100 SN 1800 9.95
height. be used to connect the wall
150×150 IC 400 2.79 panel and slab panel. 100×120 SN 1800 10.79
100×100 IC 600 3.17 100×125 SN 1800 10.99
100×150 IC 600 3.77 100×130 SN 1800 11.48
150×150 IC 600 4.37 100×140 SN 1800 11.60
100×150 SN 1800 12.00
100×160 SN 1800 12.40
150×150 SN 1800 14.01

BEAM——Beam Outer Corner Item (A1+A2) LC (L1+L2) Weight (kg)


DESCRIPTION:
Use for internal corners usually at beams. Connect to 100×100 LC 400+400 4.76
other panels using Pin & Wedge.
100×150 LC 400+400 5.87
150×150 LC 400+400 7.00 SLAB——Slab Incorner Joint m (A1+A2) SC (L1+L2) Weight (kg)
DESCRIPTION:
The slab incorner joint will be used to 100×100 SC 400+400 4.76
connect the wall panel and slab panel at
the incorner position. 100×150 SC 400+400 5.87
150×150 SC 400+400 7.00

SLAB——Panel Item D(WxL) Weight (kg)


DESCRIPTION:
The slab panel will be used to support 600 D 1200 12.84
the concrete weight during concrete
pouring and casting. 450 D 1200 10.19
400 D 1200 9.34 SLAB——Slab Prop Head Item PH Weight (kg)
300 D 1200 7.29 DESCRIPTION:
Prop head to support the slab with steel 150 PH 300 2.50
200 D 1200 6.91 props.Also it will be connected with long pin
& wedge and BB bar for middle beam & end
beam.

SLAB——Slab Middle Beam Item MB Weight (kg)


DESCRIPTION:
Use to join the prop heads, the middle 150 MB 1050 8.41
beam supports the slab panels.
150 MB 900 7.16

16 17
Formwork & Scaffolding Expert Formwork & Scaffolding Expert

Accessories
BOLT,
HOLLOW SECTION Item WALLER BRACKET Item WORKING BENCH Item TIE ROD Item NUT&WASHER
Item

Weight:3.73KG/M Weight:0.58KG Weight:15KG Weight:1.7KG/M Weight:0.185KG

DESCRIPTION: DESCRIPTION: DESCRIPTION: DESCRIPTION: DESCRIPTION:


The hollow section are used to The Aluminium Waller Bracket use The working bench is used The tie rod will be used as an The set of accessories are used to
allow the horizontal straightness of to allow the horizontal straightness as the inner working embedded anchor in order to fix connect panels with panels.
wall panels and a flat wall surface of wall panels and a flat wall platform. the bracket /panels on the concrete
(especially at the bottom) after surface (especially at the bottom) surface during its installation.
concrete casting. after concrete casting.

ELEVATOR REUSABLE FLAT-TIE EMBEDDED


BRACKET Item SLAB BRACKET Item WALL BRACKET Item AND PVC SLEEVES
Item FLAT-TIE
Item

Weight:8.5KG Weight:12.5KG Weight:13KG Weight:0.158-0.711KG Weight:0.064-0.286KG

DESCRIPTION: DESCRIPTION: DESCRIPTION:


The elevator bracket is used as a The slab bracket is used as a The wall bracket is used as DESCRIPTION: DESCRIPTION:
substitute of scaffolding system, the substitute of scaffolding system, the a substitute of scaffolding The flat tie is used to joint the wall The embedded f lat-tie is one-time
working platform, slab platform working platform, slab platform system, the working panel to the opposite side's wall flat tie.
and elevator platform will be fixed and elevator platform will be fixed platform, slab platform and panel. And t he PVC sleeves will
on the concrete. on the concrete. elevator platform will be make the flat-tie reusable.
fixed on the concrete.

SLAB TRANSFER
PIN &WEDGE Item LONG PIN Item BOX
Item STEEL PROPS Item JOINT BAR Item

Weight:0.064&0.03KG Weight:0.286KG Weight:13KG Weight:11.63-17.808KG Weight:0.713KG

DESCRIPTION: DESCRIPTION: DESCRIPTION: DESCRIPTION: DESCRIPTION:


The pin and wedge will be used to The long pin is used to fix the The slab transfer box is The steel props are used to support The joint bar is used to connect
joint the panels together. middle-beam and joint bar with used to transfer panels after the slab during concrete pouring with the prop head and middle
wedge. formwork dismantlement. and casting. It will remain under the beam.
prop head until it can satisfy the
dismantling requirement.

PVC SLEEVE REUSABLE FLAT-TIE T TYPE PANEL Y TYPE PANEL


EJECTOR
Item EJECTOR
Item Item PULLER
Item HOLE HOOK Item
PULLER

Weight:1.983KG Weight:2.679KG Weight:4.86KG Weight:3.25KG Weight:0.768KG

DESCRIPTION: DESCRIPTION: DESCRIPTION: DESCRIPTION: DESCRIPTION:


The PVC sleeve ejector is used to The reusable flat-tie ejector is used The T type panel puller The Y type panel puller is used to The hole hook is used to adjust the
remove the reusable PVC sleeves . to remove the reusable flat-tie . is used to remove the remove the wall panels . position of panels.
slab panels.

18 19
Formwork & Scaffolding Expert Formwork & Scaffolding Expert

Aluminium Formwork Edge Sealing Advantages

Reinforcement System
Fast Construction. All components are light enough to erect, assembly & dismantle by
labour without heavy cranes. The 1.2m X 1.8m 36.77kg lightweight aluminium deck panels
are easy and safe to erect using a minimum of only two workers by swiveling the panel
GETO self-developed aluminium formwork edge sealing upwards from below and locking it into our quick release prop heads. Also, the standard
reinforcement system is to reinforce the connection panels are allowed to transfer by small handcart in site which is convenient for site
between panels at hole positions, The reinforcing plate construction.
and aluminium formwork are connected with riveting.
Easy & Compatible. GETO Quick-Deck Formwork System are allowed and easy to
Applicable to the 65 flat-tie system
compatible with other aluminium formwork system, timber formwork system and
Reduce the wear of pin holes
precast concrete components. As quick deck formwork panels are standard sizes and
not specifically designed for one project, they are able to be re-used repeatedly on new
Prolong the service life of aluminium formwork projects without additional design costs by 100%.

*Customers can choose to use the aluminium formwork edge Intelligent Prop Head. The special prop heads and props can be separated. And the
sealing reinforcement system according to project requirements. Applicable to the 63.5 flat-tie system props can be used in traditional aluminium formwork system. The specially designed
quick release prop head allows the panels to drop from the formed surface without
disturbing the prop. The newly developed 2-stage lowering function of the quick release
prop head prevents panels from accidentally falling during dismantling and speeds up the
formwork dismantling process.

High Quality. The concrete surface by aluminium panel will be better than other
formwork.

Quick-Deck Formwork System


Application
GETO Quick-Deck Formwork System is developed to construct large slab areas quickly, safely,
with minimal labour. It is suitable for the construction of beamless and large-area building
structures, such as carpark porch and podium. GETO Quick deck system formwork can
withstand construction loads up to 250mm thickness without the need for temporary prop.

Characteristics
Its quick installation and dismantling characteristics are realized by adjusting the height
of the adjustable props below its deck formwork, where the props are mounted up for
tightening and installation, and the dismantlement of the formwork only requires the
conduct of manual downward adjustment of the props.

Components
The system is composed of deck formworks, vertical props, quick-release prop heads, as well
as wall-edge and slab-edge prop heads.

20 21
GETO PRODUCT
Formwork & Scaffolding Expert Formwork & Scaffolding Expert

One-stop Comprehensive Solutions


QUALITY AND SERVICE
ADVANTAGES
With one-stop solutions offerings in place, GETO can help clients exclude the hiring
of multiple suppliers in one project, which consequently simplifies the on-site
coordination process and contribute to increasing effectiveness on site.

Why do I choose GETO Aluminium Formwrok? 1.Integrated Product Solutions


GETO offers one-stop package solutions for its product and service offerings. Products in
GETO's one-stop package include the podium formwork system, the basement formwork
system, the typical floor formwork system, the roofing formwork system and the self-
climbing platform.

2.Whole-chain Services
GETO's main core product packages also include the whole-chain services offerings.
Pre-sales service
We can offer pre-sale analytics and quote service.

During-sales service
We offer individualized service, drawing detailing, design and on-site engineering services,
including technical briefing, technical training and on-site instruction to ensure on-site
obstacles are cleared during use of the product.
We also provide refurbishment services for customer's formwork system. By adopting
GETO ERP Warehousing System, we simplify the recycling of customers' existing panels
and management process on-site. By refurbishment design, we maximize the turnover
rate of the aluminium formwork system. With the improvement of the exiting panel
turnover rate, the project cost will be minimized.

After-sales service
To enhance customer experience, our Customer Service Department will build and
monitor customer data to track any issues that customers might face during use of the
product.

22 23
Formwork & Scaffolding Expert Formwork & Scaffolding Expert

GETO-BIM Automatic Modulation Quality Assurance


Software
GETO independently developed it's own intellectual property GETO-BIM automatic
modulation software after 3 years R&D. The accuracy rate of GETO-BIM has reached
100%.

GETO-VR Inspection Software


GETO-VR virtual reality inspection software with special equipments makes you do
the inspection and acceptance at your home.

24 25
PROJECT
Formwork & Scaffolding Expert Formwork & Scaffolding Expert

Installation Instruction
REFERENCES

Leveling and structural Wall Panels setup Beam Panels setup Slab Panels setup
line
The site surveyor shall based on the Installation of M&E, plumbing Setup beam panels according to the Fixed the slab corner panels on the
approved construction drawings to components and steel rebar. Then construction drawing for beam soffit top of wall panels. Then the slab
ensure that the structural line and the wall panels setup process shall panels, beam support, beam side panels setup process shall be middle
level of the slab is properly set up. be the inner corner wall panels, inner panels, etc. beam, prop head, end beam, slab
wall panels, flat-tie, external wall panels, etc.
panels, pin and wedges.

Kickers setup Staircase Panels setup Installation of Inspection and


M&E,rebar acceptance
Kickers are fixed on the external wall The staircase panels setup process Installation of M&E, plumbing All the vertical panels shall be
panels with kicker screws before shall be staircase soffit length, step components , steel rebar and slab fixed in position and the external
concrete pouring. The function of panels, step angles,etc. box-out. corner should be checked. This
kickers is to support the external wall will determine if further action is
panels for next floor. required to control the deviation.

Concrete pouring Wall Panels Beam Panels Slab Panels


dismantlement dismantlement dismantlement
Concrete pouring is distributed The first wall panel will be the most Remove all pins and wedges from the After remove all pins and wedges,
evenly throughout the wall section difficult to remove out from wall. And section of beam side. Then, remove middle beam and end beam will be
before commencing to cast the slab it's forbidden to remove it violently. all the beam panels. easily removed. BTW, the prop head
areas. and steel props must not be removed
to support the floor slab.

Kickers dismantlement Flat ties & PVC sleeves Panels cleansing Transfer Panels

The wall panels are removed to Flat ties are used to ensure the wall All components shall be cleaned Transfer all panels through Slab box
disconnecting the lower kicker from thickness and fixed the wall panels. after dismantlement for a better to large open space.After that, it can
the adjacent formwork and prepared PVC sleeves are used to protect the quality in next floor. be filled with second-time concrete.
for reuse. flat tie so as to reuse it. Both of it can
be removed by special tools.

26 27
Formwork & Scaffolding Expert Formwork & Scaffolding Expert

Technical Solutions Podium and typical floors share one aluminium formwork set in one
tower
Two typical floor designs share one aluminium formwork set in one With rich experience and professional strength accumulated from the past, GETO
tower can offer one set of aluminium formwork system that could be turnover and reused
between non-typical floors and typical floors.
For a tower with two types of typical floor design, GETO's solution is to offer one set
of aluminium formwork system for reuse and turn over throughout the tower.

Residential Building, South Asia

Love River Landmark, Taiwan, China

Urban Village ii, Southeast Asia Sea Gate, Southeast Asia

28 29
Formwork & Scaffolding Expert Formwork & Scaffolding Expert

Customization for podium with large-size flat deck structure and no Skyscrapers with aluminium formwork and self-climbing platform
beams system integrated
For construction projects that consist of huge and flat structure without beams, GETO By offering integrative design of aluminium formwork system and self-climbing
will introduce them to use Quick-Deck System with 1200 x 1800mm in its formwork platform system, GETO can contribute to improving the efficacy of structural work
size to build podiums. progress for superhigh skyscrapers. Meanwhile, GETO customizes design for several
connecting points of aluminium formwork system and self-climbing platform system,
such as offering extra strengthening accessory parts and steel frame structure.

Tri-zen, South Asia

Agile Embassy Garden in KL, Malaysia

M-Arisa in KL, Malaysia

30 31
Formwork & Scaffolding Expert Formwork & Scaffolding Expert

Aluminium formwork system turnover for terrace house projects Unique design throughout the whole building
with mirror-like structure and party walls Even if buildings with unique designs have great floor height, more changes, and
Based on the project characteristics of terrace house project and the budget complex structures, including round columns, arc-shaped beams, decks with special
allocation of relevant client for the number of formwork sets, GETO proposes angles, etc, GETO can still manage to design it with zero-flaw standard by utilizing its
technical solution for aluminium formwork system turnover that takes mirror-like self-developed Intelligent Formwork Modulation System.
structure and party walls into account.

IBN Hingland City, Malaysia


Terrace House, Southeast Asia

Terrace House, Southeast Asia Office Building, Southeast Asia


32 33
Formwork & Scaffolding Expert Formwork & Scaffolding Expert

Aluminium formwork used with other formwork system The basement and typical floors of the public buildings completely
We propose solutions of aluminium formwork used with other formwork system to constructed by using aluminium formwork
our clients, such as aluminium formwork with timber, aluminium formwork with With the principle of customer-centric spirit, GETO maximized the turnover and
precast components, as to facilitate our clients in saving up construction material utilization rate of the aluminium formwork for the public buildings like station,
and labour cost, which consequently solve the pain point of our clients in bearing school, etc, by modifying the architectural drawing of the project. The basement and
high cost to procure extra set of formwork for non-typical floor construction. typical floors of the public buildings was completely constructed by using aluminium
formwork, increasing construction efficiency.

Tengah C2, Singapore

Sanying MRT Station, Taiwan, China

Inspiria Residence, Malaysia School Building, South Asia

34 35
Formwork & Scaffolding Expert Formwork & Scaffolding Expert

Projects in Malaysia Projects in Singapore

Bayu Sutera, Malaysia The Trion, Malaysia CANBERRA EC, Singapore Haus On Handy, Singapore

Lake City in KL, Malaysia Marc Residences, Malaysia Tengah Plantation C1, Singapore Toa Payoh, Singapore

D'Vine, Malaysia The Asteria, Malaysia Queen Peak, Singapore Mercedes Benz Center, Singapore

36 37
Formwork & Scaffolding Expert Formwork & Scaffolding Expert

Projects in other countries in Southeast Projects in South Asia


Asia

38 39
Formwork & Scaffolding Expert Formwork & Scaffolding Expert

Projects in Hongkong, China, Macao, Projects in GCC countries


China, Taiwan, China

Baker Circle, Hongkong, China LOHAS Park, Hongkong, China

Housing Project in Longjing Dist., Taiwan, Landmark Mansion, Taiwan, China


China

HuaYue City, Taiwan, China New City Public Housing in Section B10, T1210 Villa, Kuwait
Zone A, Macao, China

40 41
Formwork & Scaffolding Expert Formwork & Scaffolding Expert

Projects in Americas Projects in Africa

El Alamein Ultra-High Complex

Projects in Europe

42 43
GETO Group
Headquarters:
Greater Bay Area—No. 13 Heqing Road, Tsuihang New District, Zhongshan City, Guangdong Province
Southern China Production BaseⅠ:
Cuishan Lake Science and Technology Park, Kaiping, Jiangmen City ,Guangdong Province
Southern China Production BaseⅡ:
Huizhou Industrial Transfer Industrial Park, Huizhou City, Guangdong Province
Eastern China Production BaseⅠ:
Guangchang Industrial Park, Fuzhou City, Jiangxi Province
Eastern China Production BaseⅡ:
Baizhong Industrial Park, Minqing , Fuzhou City, Fujian Province
Central China Production Base:
Hi-tech Industry Development Zone, Xianning City, Hubei Province
Northern China Production Base:
China Aluminium Industrial Park, Linqu, Weifang City, Shandong Province
Southwest China Production Base:
Modern Manufacturing Industrial Park, Tongnan High-Tech District, Chongqing City
Northwest China Production Base:
The Circular Economy Park, Anding District, Dingxi City ,Gansu Province
Hainan Production Base:
Gold Medal Port Industrial Park, Lingao County, Hainan Province
ASEAN Production Base:
Negeri Sembilan, Malaysia

GETO INDIA
Regd.Off: C/703, RAAS, VU, Thakur Village, Kandivali East, Mumbai 400101
Operational Office: 8/11 Row House, Suncity Bungalows Shelter Heights, Suncity Rd, Vasai West,
Maharashtra 401202
Mobile: +91 7738091831, +91 9699173295
Email: skp@oxygreen.in; samit@geto.com.cn

Sales Hotline: 0086-760-88589004


E-mail: geto_market@geto.com.cn
www.getoformwork.com

20230501V1

You might also like