Checklists
Checklists
Checklists
Sr. Yes /
Check Points Remarks
No No
1 Is Area cordoned?
2 Is traffic diversion board displayed & alternate road explored?
3 Are Fire & Safety, Security & Admistration departments
communicated?
4 Whether soil stability is checked?
5 In case of loose soil, whether proper shoring for the excavation is
provided to prevent cave-in for side of slope.
6 While excavating whether proper slope usually 450 or suitable
benches of 0.5 m width at each 1.5 m depth is provided?
7 Whether proper footstep, slope or ladder provided for safe
access/egress of man and equipment? In case excavation trench
> 1.2 m deep, at every 7.5 mtr ladder or other means provided
for access?
Sr. Yes / No
Check Points Comments / Confirmations
No
1 Planned/Emergency Work
3 Type of Permit
Department /
SR. Emp Dt. Dt. Dt. Dt.
EMPLOYEE NAME Contractor
NO. No.
G I st II nd III rd G I st II nd III rd G I st II nd III rd G I st II nd III rd
Sr. Yes /
Check points No
Remarks
No
1 Is work carried out at more than 7 Mtr height?
Are full body harness with double latch self-locking snap
2
hook being used?
3 Is length of lifeline accepted (1.8 mtr)? Not clear
4 Has proper anchor point for the safety line been located?
Has the fall arrest equipment been visually checked for
5
damage or defects?
Is fall arrest equipment in use that will limit the free fall to 2
6 meters or less?
Plant Area:
Location
Name of Contractor : Contractor Supervisor:
Date Scaffold Serial No.
Sr. Yes /
CHECK POINTS Remarks
No No
1 Has the request for scaffolding been signed by Authorised person ?
2 Is the scaffolding area effectively barricaded during erection / usage ?
3 Are base plates provided ?
Is the ground level firm, or have proper supports been placed under the
4
structure ?
5 Is safe access to equipment for emergecy egress restricted by scaffold ?
Is there min. 300mm gap maintained between scaffolding and any small
6
bore line / cable trays / instrumentation control boxes and valves.
Are the scaffolding in plumb and level ? The bay length maintained as per
7
the maximum intended load.
Are the poles, legs or uprights of scaffolding are securely braced to
8
prevent swaying / displacement ?.
Are free standing scaffolding tower protected from toppling by guying or
9
other means ?
10 Are adequate bracings provided ?
11 Are all the scaffold tubes in good condition ?
Is there a safe and convenient means of access ? If a ladder is used, is it
12 rising atleast 1050 mm above the platform ? Are the ladder resting on firm
base. ?
Are landing platforms provided for access ladders at more than 9 meters
13
height ?
14 Are the gratings / boards placed in order without undue gaps and tied ?
15 Is every work platform fitted with hand rail, knee rail and toe guard ?
16 Are the scaffolding erected as per the load duty requested ?
Has the certificate of fitness of scaffolding been signed by scaffolding
17
competent person?
18 Are the relevant status boards (tags) attached to the scaffolding ?
19 Any deviations to above is accepted ?
20 Are excess materials cleared up and returned to the yard ?
21 Measurement - Length ____ x width ___ x Height ______ = M3 _____
Are the Steel Tubes of heavy class welded or seamless tubes of 40mm
22
nominal bore conforming to IS:1161-1963.
23 Is JSA & RA Carried out & briefed to workers engaged?
Acceptance
Scaffolding engineer Engineer (Acceptor)
Sign : Sign :
Name : Name :
NOTE : Frequency of Inspection
a) Scaffold should be inspected before first use and within every 15 days.
b) Scaffold should be inspected after alteration or repair; and
c) Scaffold should be inspected after any event likely to affect the stability of the scaffold (for
example, following strong winds or storms).
QSF- ____ -_____ 01 Rev. Date :10.11.06
Check List for Lifting Operation (>5 ton)