Duct Work Material
Duct Work Material
Duct Work Material
A. All ductwork shall be manufactured from strip mill, cold rolled sheet,
continuously hot dip galvanized. The minimum weight of zinc coating (total on
both sides) shall be 120g/m2. All ducting shall be factory machine fabricated
and fabrication at site will not be acceptable. Ducting up to 600 mm shall be
delivered in Box form and above 600 mm size duct shall be delivered in
preformed 'L' shaped in two halves.
B. The minimum gauge and thickness of sheet metal shall not be less than that
given in SMACNA or as given in the table below, whichever is more stringent.
C. Kitchen extract duct work shall be air and watertight welded construction
manufactured from 16 g black steel sheets in accordance with BS 1449, Part 1
Grade CR4 GP. Ductwork shall be painted on the outside with two coats of heat
resistant galvanic paint after manufacture. Kitchen extract ductwork passing
through accessible shafts, false ceiling voids and enclosed spaces shall be
insulated with 2” thick mineral wool insulation for personnel protection and to
avoid heat pick up by return air.
C. All air ducts, casings, plenums etc., shall be constructed of lock forming quality
prime galvanized steel sheets, which are free from blisters, slivers, pits,
imperfectly coated spots etc. No second quality sheet metal allowed.
General
All smoke management system ducts and life safety ducts which are outside of fire rated
enclosure shall be fire rated.
1. Fire rated ductwork constructed for smoke extract systems to be tested to UL
and BS476 Part 24 (1987) for two hours stability and two hours integrity and
two hour fire insulation (120/120/120) duct systems for both fire inside(Type B
test) and fire outside (Type A test) . Duct to maintain a minimum of 75% cross‐
sectional area along its whole length when tested for two hours.
3. The fire rated material used for fire rated ductwork shall be tested properties
as per the requirements of BS 476 Part 6&7, including non – combustibility, fire
propagation, Class one surface spread of flame.
4. All fire rated ductwork to be GI duct, constructed to tested standard and coated
with fire rated material. The duct to be composite fire duct manufactured to
Method 3 of BS 5588 Part 9, factory produced. The material coating shall be
applied either offsite or onsite on the ground, dried and cured prior to erection.
Once erected, to be pressure tested, if required by EMPLOYER in line with the
pressure classification of the duct being installed.
7. The fire coating to be non‐hydroscopic and have been tested with exposure to
UV and condensation cycling, with no adverse effect on the life of fire rating of
the duct for at least 30years.
8. The fire rated duct shall be connected to the fans with the use of fire rated
flexible connections. Flexible connectors shall be made of glass fabric, coated
Engineering, Procurement and Construction Page 199 of 334
of the Airport at Navi Mumbai
9. All access doors/inspection coves and test holes shall be suitably positioned in
relation to the access provided by the false ceiling or other means of
concealment supplied & fitted by the Contractor.
10. All fire rated ductwork must be manufactured and erected in line with the tested
and assessed Certification to BS476 Part 24 and ISO6944.
11. Fire rated ductwork to have passed impact test to BS5669 and Appendix A of
BS5588 Part5.
12. In addition to the above, all fire rated ductwork shall be subject to approval by
the local Fire Dept.
13. Upon part or full installation of Fire Rated Duct the local licence shall issue a
Certificate of Conformance after satisfactory inspection.
14. All openings in walls where ducts cross compartments shall be fire rated for
120 minutes Material The following fire rated system shall specifications
conformance. generally be acceptable subject to
PAER 3 – EXECUTION
3.2 CO-ORDINATION
A. Coordinate equipment location and placement details with architectural, civil,
mechanical and electrical works to prevent interferences.
B. Installation shall be done in liaison with other agencies /contractors involved in
construction of the building and related services (Building/Substation
3.3 INSTALLATION
A. Requirements of reference standards and manufacturer's instructions shall be
complied with in all respects.
B. Arrange installation of units to provide access space around equipment for
service and maintenance.
C. Units shall be installed in such a way that allows unrestrained movement of the
assembly (for vibration isolation purposes).
3.5 COMMISSIONING
Upon commissioning and final hand over of the installation, the vendor /
contractor shall submit operating Instructions, maintenance and service
manuals, part lists and all final drawings and diagrams.