IABG ICAF 2009 Concept of A320 NEF Test V3
IABG ICAF 2009 Concept of A320 NEF Test V3
IABG ICAF 2009 Concept of A320 NEF Test V3
The first full-scale fatigue test started 1973 with the A300. All following AIRBUS
aircraft A310, A320, A330/ 340, A340-600 [2], A380 [3] have been tested by IABG.
Currently, A320 is undergoing testing again in the frame of the extend service goal
(ESG) program. Thus, the A320 centre fuselage and wings will have been tested
twice (as EF2 and NEF2) in the course of 20 years. For the first time ever at test of
the A320 rear fuselage (NEF3) is currently being performed by IABG
simultaneously with the NEF2 test. While these two tests are performed in
Ottobrunn near Munich, the test of the A380 is running at the Dresden site of IABG.
Moreover, the test for the A400M is under preparation in Dresden.
ESG1 is an initial step planned to become effective in 2010 that will target a service
goal extension of 60,000FC and 120,000FH. This programme will achieve a
balanced development of structural potential and optimised maintenance activities
for the aircraft family through its analyses. The development test phase for ESG1 is
being conducted until July 2009. It will involve 120,000 simulated flights, each
characterised by operational data monitored and collected to date. Subsequent
testing through to 2011 will aim to validate ESG2’s ultimate goal of 90,000FC and
25th ICAF Symposium – Rotterdam, 27–29 May 2009
180,000FH, and will involve up to 180,000 simulated flights and a total of 360,000
simulated flight hours [1].
To achieve approval for the Extended Service Goal package, Airbus is carrying out
full-scale fatigue tests on specially manufactured partial aircraft test sections. The
original A320 configuration will be taken into consideration, as well as the
specificities of each family type. All of the results will be compiled to show the
fatigue behaviour of the complete aircraft family. These tests will take into account
20 years of experience in A320 family operations.
The NEF3 fatigue test was started in August 2008 in order to reach the ESG1
milestone of 120,000 simulated flights in July 2009. The NEF2 fatigue test was
started in November 2008 in order to reach the ESG1 milestone of 120,000
simulated flights in July 2009 as well. The ESG2 milestone of 180,000 simulated
flights shall be completed prior to July 2011 for both NEF2 and NEF3.
End of March 2009 NEF2 had reached 50,000SF while NEF3 was progressing
already at 104,000 SF.
Figure 2 – Isometric view of the A320 NEF2 and NEF3 test set up
The NEF2 test article is supported statically determined by 6 hinged rods of the
restraint system blocking all 6 degrees of freedom. The rods are connected at the
forward bulkhead constrained in X-, Y- & Z-direction, at the rear bulkhead
constrained in Y-direction and at each main landing gear dummy constrained in Z-
direction.
The NEF3 test article is rigidly fixed at the bulkhead. This was achieved by welding
the bulkhead to a steel ring, which is bolted to the fuselage end. It was necessary to
design the restraint rig considering stiffness requirements to avoid large deflection
of the 19m freely suspended tail.
A modern test and load introduction concept was developed, which fulfils all given
requirements. In total 61 (NEF2) and 33 (NEF3) dual acting servo-hydraulic jacks
are installed to the test set up to simulate aerodynamic and inertia loads of the
aircraft structure.
The loads will be applied directly either via loading trees to seat and cargo rails,
fitting riveted to the structure, pads bonded onto the wings or they are introduced via
dummy structures.
25th ICAF Symposium – Rotterdam, 27–29 May 2009
Scaffolds are used as inspection rigs. They provide access to all parts of the test
article and test systems during inspection, maintenance and repair works. The
advantages of using scaffolds instead of a designed inspection rig are:
• minimal effort and costs during the planning (only the inspection levels
need to be defined)
• highly flexible rig adaption to the current requirements during the
installation phase
• fast dismantling and reinstallation to get access for repair works at the test
article
• reuse for future projects
quality. The figure below shows a pad group with an optimized load distribution
onto rib and spar.
The tough time schedule of the overall project ended up in a narrow time gap for pad
bonding. Therefore the time consuming turning of the wing and/or exclusive
provision of the wing at Airbus for pad bonding was not possible. The bonding had
to take place after final assembly of the wing to the fuselage and while the assembly
of the test rig continued in parallel. In order to fulfil the task the pad bonding had to
be done from below with an adapted bonding device to host the individual pad
layouts with a high reliability and quality.
For actuator control of the tests two different control & monitoring systems (CMS)
are used. Based on the complexity the NEF2 is operated by an IABG developed
system (70 channels) based on Logidyn components and NEF3 uses a SmarTEST
Elite system (40 channels). These systems also control the pressure inside the
fuselage. Each control channel is equipped with various monitoring features to
guarantee safe test operation. For additional safety, the NEF2 CMS monitors the
reactive loads measured by 6 struts and NEF3 CMS the displacements in x- and y-
direction of the tail cone.
Compared to the first A320 test, the loading program was much more extended for
NEF2 and NEF3:
• NEF2: 165 different flight types with about 7,800 different load cases
• NEF3: 270 different flight types with about 10,000 different load cases.
An FE-model for each of the test structures was used to generate appropriate and
optimized control parameters for the load cases within the flights.
The central data acquisition system (HBM MGCplus) serves both of the NEF2 and
NEF3 tests independently. For cost-efficient use of the DAS-Hardware, up to 3072
strain gauges can be connected via a 3-way connector board to the DAS. The DAS
itself is equipped with 1024 (expandable to 1344) strain gauge inputs and 70 inputs
for deflection transducers. Changing between 3 configurations – each of it can
contain up to 1024 strain gauges– is done by patch cables with multi pin connectors.
Data Acquisition is managed by the state of the art software system catman
Enterprise, designed especially for multi channel purposes.
5. TEST PERFORMANCE
Inspection Process
Job-Card Receipt of Processing of Job-Card
Administration
Job-Card
Inspection
Preparation
„w/o Damage“ „with Damage“
Handout of
Job-Card(s) Damage
to Inspector Log entry Registration
Damage List
Performance of No Job-Card
Inspection complete
back ?
Inspector
Yes
Damage
Yes
notification Damage
found? Finished
No DAMDOC
Preparation
The used NDT methods have been selected based on the inspection task and the
structure requirements. The following methods are being practised:
- General and Detailed Visual Inspection (GVI & DVI)
- Ultra Sonic Testing (UT) including Phased Array Ultrasonic Testing
(PAUT)
- High and Low Frequency Eddy current Testing (HFET & LFET) including
usage of four frequency eddy current testing for lap joints (LFET) and bore
holes with rotating probes
- X-Ray Testing (RT)
6. CONCLUSION
For the Extended Service Goal (ESG) program of the A320 Family, two major
airframe tests for the center fuselage with wings (NEF2) and the rear fuselage
(NEF3) have been erected at IABG Ottobrunn, Germany. Within 9 months, the
entire engineering, design and a considerable part of mechanical test set-up build
was completed in order to integrate the two test structures in time. Further
integration, instrumentation and commissioning could be completed in a second
compact time frame. Since July 2008 (NEF3) and September 2008 (NEF2),
respectively, both tests are progressing at a fast rate. Test completion is planned for
2011. The extraordinarily successful achievement of densely packed milestones up
to the current date was enabled by an efficient mix of proven technologies and
procedures and newly established advancements.
7. REFERENCES
[1] Airbus Letter November 2008
[2] A340-600 Full Scale Fatigue Test: A Further step forward into a efficient
structure qualification, Olaf Tusch & Klaus Woithe, ICAF 2001 –Volume II, 27-29
June 2001, Toulouse, France
25th ICAF Symposium – Rotterdam, 27–29 May 2009
[3] An efficient load introduction concept for the A380 full scale fatigue test, Felix
Schwarberg & Frank Eichelbaum, ICAF 2005 Volume I, 6-10 June 2005, Hamburg,
Germany