SCHEDULE PEKERJAAN

Juli 2023 - Oktober 2023

Jun-21 Jul-21 Aug-23 Sep-23 Oct-23


Bobot
No. Item Pekerjaan
Pekerjaan
26-Jun 3-Jul 10-Jul 17-Jul 24-Jul 31-Jul 7-Aug 14-Aug 21-Aug 28-Aug 4-Sep 11-Sep 18-Sep 25-Sep 2-Oct 9-Oct 16-Oct 23-Oct

1 PEKERJAAN PERSIAPAN 1.40% 0.47% 0.47% 0.47%


2 PEKERJAAN LANTAI DASAR 2.24% 0.32% 0.32% 0.32% 0.32% 0.32% 0.32% 0.32%
3 PEKERJAAN BETON 12.49% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83% 0.83%
4 PEKERJAAN DINDING 29.94% 2.00% 2.00% 2.00% 2.00% 2.00% 2.00% 2.00% 2.00% 2.00% 2.00% 2.00% 2.00% 2.00% 2.00% 2.00%
5 PEKERJAAN ATAP 11.81% 1.31% 1.31% 1.31% 1.31% 1.31% 1.31% 1.31% 1.31% 1.31%
6 PEKERJAAN LANTAI 9.49% 1.19% 1.19% 1.19% 1.19% 1.19% 1.19% 1.19% 1.19%
7 PEKERJAAN PINTU JENDELA 11.34% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42% 1.42%
8 PEKERJAAN PLAFOND 5.73% 1.15% 1.15% 1.15% 1.15% 1.15%
9 PEKERJAAN INSTALASI LISTRIK 4.03% 0.37% 0.37% 0.37% 0.37% 0.37% 0.37% 0.37% 0.37% 0.37% 0.37% 0.37%
10 PEKERJAAN PLAMBING 7.72% 2.57% 2.57% 2.57%
11 PEKERJAAN CAT 3.82% 1.91% 1.91%
TOTAL PROGRESS RENCANA MINGGUAN 100.00% 0.79% 4.80% 4.80% 4.70% 6.12% 6.12% 7.43% 7.11% 7.11% 7.07% 7.07% 7.07% 5.65% 8.22% 6.71% 5.40% 1.91% 1.91%
TARGET RENCANA PROGRESS 0.79% 5.59% 10.40% 15.10% 21.21% 27.33% 34.76% 41.87% 48.98% 56.05% 63.12% 70.19% 75.84% 84.07% 90.78% 96.18% 98.09% 100.00%
REALISASI PROGRESS PEKERJAAN
DEVIASI