OST - Comprehensive Claim Application For Extension of Time Implications-IAP
OST - Comprehensive Claim Application For Extension of Time Implications-IAP
OST - Comprehensive Claim Application For Extension of Time Implications-IAP
Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai,
U.A.E.
PART I
CLAIM NARRATIVE
Page 2 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
TABLE OF CONTENT
Page 3 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
PART- I CLAIM NARRATIVE
TABLE OF CONTENTS
Chapter 2 DEFINITIONS 8
Chapter 3 ABBREVIATIONS 10
Chapter 4 INTRODUCTION 11
Page 4 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
Chapter
1 EXECUTIVE SUMMARY
1.1 PREFACE
1.1.1. Where Messrs. Dubai Limited Investment L.L.C. (hereinafter called “the
Employer”), desire to execute a residential building located in Al Nahda
Second, Dubai U.A.E. (hereinafter called “the Project”).
1.1.2. Where the Employer and Messrs. OST Constructional Projects L.L.C.
(hereinafter called “the Main Contractor”) have entered into agreement to
perform the Works pertaining to the Project (hereinafter called “the Main
Contract”).
1.1.3. Where the Employer has appointed the Engineer of Messrs. Bel-Yoahah
Architectural & Eng. Consultants (hereinafter called “the Consultant” or “the
Engineer”) to act as the Engineer for the Main Contract.
1.1.4. Where the Main Contract’s Commencement Date means the date upon which
the Main Contractor need to commence the works, which was agreed between
the Employer and the Main Contractor to be 09 October 2016.
1.1.5. Where the Main Contract’s Time for Completion means the time allowed for the
completion of the works under the Main Contract, which was agreed between
the Employer and the Main Contractor to be 19 Months, commencing from the
Commencement Date and ending on 22 May 2018.
1.1.6. Several delay events have affected the execution of the Project, imposing
irrecoverable delays to the Time for Completion. This Claim has been made to
substantiate the Main Contractor’s entitlement for extension of Time for
Completion.
1.2.1. This Claim comprises the several factors that have affected the execution of
the Main Contract Works, the majority stemming from Variations initiated by the
Employer/Engineer and confirmed by the Main Contractor, delayed approval
for shop drawings or material, thus resulting in time implications, which induced
extensive delays to the Project’s Time for Completion.
Page 5 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
1.2.2. In Chapter (6) of this Claim, OST Constructional Projects, L.L.C. has introduced
the encountered delay events, and included the following titles for each of the
delay events:
1.2.3. In Chapter (7) of this Claim, OST Constructional Projects, L.L.C. displays the
attempted mitigation efforts / measures, in an endeavor to minimize the effects
these Exceptional Circumstances are having on the Contractor’s daily regular
operations at Site.
1.2.4. In Chapter (8) of this Claim, OST Constructional Projects, L.L.C. has attempted
to delineate the responsibilities regarding the effects imposed through reverting
to the Main Contract and the applicable provisions of Law.
1.2.5. In Part II of this Claim, OST Constructional Projects, L.L.C. has attempted to
determine in an objective manner the effect of the subject delay events,
through analyzing the impact of the delay events in terms of time, on the Main
Contract’s activities and the respective Time for Completion.
1.2.6. While OST Constructional Projects, L.L.C. hereby attempt to determine the
causes of the delay events. No part or parts of this document shall be
construed as an act of aggression or an act of accusation of incompetence
toward the Employer or the Engineer nor should the same be understood as an
attempt from OST Constructional Projects, L.L.C. to escape its obligations
under the Main Contract.
1.2.7. It is well understood by OST Constructional Projects, L.L.C. that all parties have
executed their obligations in the best of intentions, considering the
circumstances, for the benefit of the Project.
1.2.8. Moreover, OST Constructional Projects, L.L.C. hereby extends to the Employer
and the Engineer its cordial gratitude for the support it had received while
executing the Project and furthermore asserts its fullest cooperation and best
intentions.
Page 6 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
1.3 RESULTS
1.3.1. The several delay events have imposed delays to the Time for Completion.
1.3.2. OST Constructional Projects, L.L.C. has endeavoured to mitigate the delays
regardless of the party responsible thereto, keeping in mind that OST
Constructional Projects, L.L.C. shall not be responsible for the extent of such
mitigation.
1.3.4. OST Constructional Projects, L.L.C. is entitled to an extension of the Time for
Completion until 16 June 2019 as a final Time for Completion.
Page 7 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
Chapter
2 DEFINITIONS
2. DEFINITIONS:
2.1. In this Claim, as hereinafter defined, the following terms and expression shall
have the meanings hereby assigned to them:
2.5. Main Contract: means the Contract entered into between the Employer (Dubai
Limited Investment L.L.C.) and the Main Contractor (OST Constructional
Projects L.L.C.) for construction, completion, testing, commissioning, operation
and maintenance the Works for the Residential Buildings (G + 2P + 12 Floors +
Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E..
2.6. Commencement Date: means the Commencement Date of the Main Contract
Scope of Works in compliance with the Programme of Works.
2.7. Time for Completion: means the time for completing the execution of and
passing the Tests on Completion of the Works or any Section or part thereof
stated in the Contract (or as extended under Clause 44) calculated from the
Commencement Date.
2.8. Site: means the places provided by the Employer where the Works are to be
executed and any other places as may be specifically designated in the
Contract as forming part of the Site.
2.9. Variation: any change to the Works that is instructed or approved by the
Engineer and/or the Employer as confirmed by the Main Contractor.
2.11. Works: means the Permanent Works and the Temporary Works or either of
them as appropriate.
Page 8 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
2.12. Permanent Works: means the permanent works to be executed (including
Plant when it is installed in its final position on Site) in accordance with the
Contract.
2.13. Temporary Works: means all temporary works of every kind (other than
Contractor's Equipment) required in or about the execution and completion
of the Works and the remedying of any defects therein.
Page 9 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
Chapter
3 ABBREVIATIONS
3. ABBREVIATIONS:
Page 10 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
Chapter
4 INTRODUCTION
4. INTRODUCTION:
4.1. The Main Contractor has incurred substantial time impact due to delay events
that were out of its reasonable control. This application is submitted as an
application for Time analysis and Delay Register, with the related particulars of
the application, the delay events, and entitlement. The Main Contractor
believes that this application will highlight in detail that most of the delays
suffered in the Project were out of its control and the prolongation of the Time
for Completion was extremely beyond the Main Contractor’s control, which also
had caused the Main Contractor to incur undue direct and consequential
losses.
4.2. The main purpose of this Claim is to detail and record the chronological history
of all the delay events suffered by the Main Contractor during the execution of
Works along with all supporting documents, analysis, and entitlement
pertaining to the same.
4.3. The intention of this document is to present the additional entitlement which the
Main Contractor deserve based on the various delay events that were
encountered during the course of execution of the Main Contract Works.
4.4. The Main Contractor has incurred substantial time impact attributable to the
numerous Variations instructed by Engineer as well as the delayed approval of
the Project documents (i.e., shop drawings, materials, … etc.). These events
extended throughout the duration of the Project and affected all phases of the
Project. Several design changes were introduced by the Employer and the
Engineer at a late stage of the Project, which caused the Main Contractor to
incur undue cost and time implications that otherwise could have been avoided
should these conflicts have been resolved at an early stage of the Project.
4.5. The Main Contractor has suffered from the delayed issuance of building
permits and several other disruptions due to design modifications, additional
Works and delayed approvals. This in turn induced irrecoverable delays to the
Time for Completion.
Page 11 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
4.6. The Main Contractor Claim for extension of Time for Completion arising out of
the events detailed herein, as per the following:
4.7. The impediments and disruptions caused by these delay events have
adversely affected the Programme of Works, and affected the economic
viability of the Main Contractor’s scope of Works that were all beyond its
reasonable control which could not have been avoided by the use of due care
and diligence.
4.8. In line with the above, the Main Contractor has prepared this Claim application
comprising Main Contractor’s detailed particulars of the extension of Time
pursuant to the correlated Clauses of the Main Contract and in compliance with
the Laws of the United Arab Emirates.
Page 12 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
Chapter
5 PROJECT PARTICULARS
5.1 PROJECT PARTIES:
5.1.1 Employer:
M/s. Dubai Limited Investment L.L.C.
5.1.2 Engineer:
M/s. Bel-Yoahah Architectural & Eng. Consultants
Page 13 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
Chapter
LIST OF DELAY EVENTS AND
6 CHRONOLOGY
Completion Date : 22 May 2018
Through this Claim, the Main Contractor includes the following events, which induced
delays to the Time for Completion and prevented the Main Contractor from proceeding with
the Works in the manner it had tendered to carry out the same.
A. CHRONOLOGY
6.1.1. On 27 August 2017, via Inspection Request ref. OST/116/186 rev. 00 [Exhibit
6.1-A], the Main Contractor submitted the said Inspection Request for the
inspection of the post tension structural works for the second floor slab by the
Engineer. Wherein the Engineer approved the works in question on 27 August
2017 with comments for the Main Contractor to proceed accordingly.
6.1.2. On 27 August 2017, via Inspection Request ref. OST/116/182 rev. 01 [Exhibit
6.1-B], the Main Contractor submitted the said Inspection Request for the
inspection of the shuttering works for the second floor slab by the Engineer.
Wherein the Engineer approved the works in question on 27 August 2017 with
comments for the Main Contractor to proceed accordingly.
6.1.3. On 27 August 2017, via Inspection Request ref. OST/116/183 rev. 01 [Exhibit
6.1-C], the Main Contractor submitted the said Inspection Request for the
inspection of the reinforcement steel works for the second floor slab by the
Engineer. Wherein the Engineer approved the works in question on 27 August
2017 in order for the Main Contractor to proceed accordingly.
6.1.4. On 27 August 2017, via application form [Exhibit 6.1-D], the Main Contractor
attempted to submit to the Authorities the said application form for the structural
inspection of the second floor in order of the Contractor to proceed accordingly
with the proper course of action.
Page 14 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
However, the Authorities system showed, per [Exhibit 6.1-D], that the building’s
number was not shown on the system.
6.1.5. On 28 August 2017, via general message [Exhibit 6.1-E], the Main Contractor
sent to the Project parties a general message depicted the obstacles
encountered whilst submitting the required application form to the Authorities for
the inspection of the second floor stating that: “Building No. Not showing in the
system attached”.
6.1.6. On 28 August 2017, via structural/ shoring system checking request [Exhibit
6.1-F], the Main Contractor submitted the said request for the structural
inspection of the second floor slab by the Authorities.
6.1.7. On 28 August 2017, via [Exhibit 6.1-G], Dubai’s Municipality replied vide the
said portal: “please contact the permit section because the building card of this
project is cancelled”, rendering the Main Contractor hindered and unable to
proceed with the respective Works thereto on Site.
6.1.10. On 07 September 2017, via [Exhibit 6.1-J], the Main Contractor attempted,
once again, to apply for the structural inspection of the second floor vide Dubai
Municipality’s portal.
Page 15 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
till the Engineer has informed the Contractor verbally that the said issue has
been resolved, allowing the Main Contractor to reapply vide the said portal and
get the respective approval on 07 September.
Furthermore, the Main Contractor reserved its rights against the negative
implications resulted as a consequence of the matter in hand which his beyond
the Main Contractor’s liability/ culpability.
B. ANALYSIS
6.1.12. OST had suffered from the delays in cancelling the building’s number from
Dubai Municipality’s portal. Which had caused in delays / losses to the Main
Contractor and induced irrecoverable delays to the Time for Completion beyond
the Main Contractor’s reasonable control. The Main Contractor has made its
best endeavor towards its obligations with the numerous notices to the
Engineer, urging the Engineer to expedite the resolving of the issue, and
recording the adverse implication of not doing so by the Engineer.
6.1.13. The impediments and disruptions caused by the cancelling of the Project’s
building number on Dubai Municipality’s portal has adversely affected the
Programme of Works, as well as the economic viability of the Main Contractor’s
package. That were beyond the Main Contractor’s reasonable control and
could not have been avoided by use of due care and diligence.
A. CHRONOLOGY
Page 16 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
6.2.2. On 15 August 2017, via correspondence ref. BY/1395/MQ/0428/17 [Exhibit
6.2-B], the Engineer replied to the Main Contractor’s submitted quotations in
connection with the supply of light fittings for the Project. Wherein the Engineer
requested the Main Contractor to submit the following documents in order to
review and furnish to the Employer the quotations in question for his approval:
c. Submit warranty details for the proposed light fittings and accessories.
e. Confirm IP rating of all the light fittings from all the Vendors along with
area of installation details.
f. Propose LED type light fittings for recessed down lights and surface
mounted round lights. Contractor shall ensure the proposed LED lamps
are incompliance with latest DM circler.
g. Submit quantity take-off sheets as per the approved shop drawings for
our reference.
c. Submit warranty details for the proposed light fittings and accessories -
Attached.
Page 17 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
d. Confirm country of origin details including ballasts, lamps etc., –
Attached.
e. Confirm IP rating of all the light fittings along with area of installation
details – Attached, refer the compliance statement.
f. Propose LED type light fittings for recessed down lights and surface
mounted round lights. Ensure that the proposed LED lamps are in
compliance with latest DM circular. – Noted.
g. Submit quantity take-off sheets as per the approved shop drawings for
our reference – Attached.
c. Submit warranty details for the proposed light fittings and accessories -
Attached.
e. Confirm IP rating of all the light fittings along with area of installation
details – Attached, refer the compliance statement.
f. Propose LED type light fittings for recessed down lights and surface
mounted round lights. Ensure that the proposed LED lamps are in
compliance with latest DM circular. – Noted.
g. Submit quantity take-off sheets as per the approved shop drawings for
our reference – Attached.
Page 18 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
6.2.5. On 15 August 2017, via Technical Submittal ref. OST/116/183 rev. 00 [Exhibit
6.2-E], the Engineer replied to the Main Contractor’s submitted quotations in
connection with the supply of light fittings for the Project. Wherein the Engineer
rejected the said quotations and requested the Main Contractor to “Refer to the
comments on the attached sheet. Comply comments and resubmit ” pertaining
to the following:
a. General Comments:
a. Lamp color Is subject to Employer/Engineer/Architect approval.
b. Specific Comments:
a. AL GHANDI ELECTRONICS
i. ltem-01: - propose decorative type light fixture for living room
& Bedroom areas.
ii. No warranty included for lamp. Provide warranty for lamps.
iii. Provide at least 3- Year warranty for light fixtures instead of
one year.
iv. ltem-06:- Provide IP-54 type light fixture for laundry area.
v. ltem-08:- IP rating of proposed light fixture not matching with
design / requirements. Provide IP-65 light fixture for Sauna
area.
vi. ltem-09:- Provide IP-44/IP-54 Type light fixture for kitchen
area.
Page 19 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
vii. ltem-10:- Technical details not attached for detailed product
review.
viii. ltem-12:- IP rating of water tank light fixture not matching with
design/requirements. Provide IP-67 light fixture for water tank
as per design.
ix. ltems-13, 14, 15, and 16:- Provide IP-65 weather proof type
LED light fixture for all driveway, parking & service rooms.
x. ltem-17:- propose wall mounted (recessed) type light fixture
for top roof staircase.
xi. Ignore ltem-11 form the quotations & follow continuous
numbers for comment reference.
xii. Attached project specification compliance is partial. Attach
fully complied (All clauses against the supply of light fixtures)
signed & stamped project specification compliance report.
xiii. The Vendor to confirm the use of Dubai Lamps in the
quotation.
xiv. The Vendor shall consider quantities as per BOQ.
xv. Provide product warranty draft correspondence.
xvi. Confirm Country of Origin of all light fixtures. 'Made in China'
not acceptable.
xvii. Confirm Country of Origin Certificate will be provided for all
light Fixtures as per the part number during delivery.
Page 20 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
c. HUDA LIGHTING
i. Ballast & Lamp details (I.e. - make, ballast type, power rating
& Country of origin) to be mentioned in quotation/product
catalogue.
ii. ltem-01:- not Included in the quotation, attached quotation is
partial. Provide quotation as per BOQ.
iii. Propose LED type light fixtures instead of CFL.
iv. ltems-13, 14, 15, and 16:- Provide IP-65 weather proof type
LED light fixture for all driveway, parking & service rooms.
v. Attach fully complied (All clauses against the supply of light
fixtures) signed & stamped project specification compliance
report.
vi. The Vendor to confirm the use of Dubai Lamps in the
quotation.
vii. The Vendor shall consider quantities as per BOQ.
viii. ltem-10:- Provide IP-44/IP-54 type light fixtures for toilet
areas.
ix. ltem-18:- Recessed type LED light fixtures is preferred.
x. Provide complete warranty for light fixtures including
accessories & ballast.
xi. Product warranty draft correspondence to be attached.
xii. Confirm Country of Origin of all light fixtures. 'Made in China'
not acceptable.
xiii. Confirm Country of Origin Certificate will be provided for all
light Fixtures as per the part number during delivery.
Page 21 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
viii. ltems-12:- Propose suitable type water tank light fixtures
ix. Provide complete warranty for light fixtures including
accessories & ballast.
x. Product warranty draft correspondence to be attached.
xi. Confirm Country of Origin of all light fixtures. 'Made in China'
not acceptable.
xii. Confirm Country of Origin Certificate will be provided for all
Light Fixtures as per the part number during delivery.
Page 22 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
x. Confirm Country of Origin Certificate will be provided for all
Light Fixtures as per the part number during delivery.
6.2.6. On 10 October 2017, via Technical Submittal ref. OST/116/183 rev. 02 [Exhibit
6.2-F], the Main Contractor has once again submitted the required details in
connection with the light fittings for the Engineer’s review and approval and in
reply to the Engineer’s comments and requirements depicted within its
response for the dispatched Technical Submittal in question via [Exhibit 6.2-E].
6.2.7. On 18 October 2017, via Technical Submittal ref. OST/116/183 rev. 00 [Exhibit
6.2-G], the Engineer replied to the Main Contractor’s submitted quotations in
connection with the supply of light fittings for the Project. Wherein the Engineer
released the Technical Submittal in question with code (B) “Approved As
Noted” and, astonishingly, requesting the Main Contractor to again resubmit
the said Submittal, rendering the approval as null and void.
Page 23 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
b. SPECIFIC COMMENTS:
a. AL GHANDI ELECTRONICS
i. Not respond towards Rev-01 comments.
b. AL SHOLA Al MODEA LIGHTING LLC
i. Product country of origin China is not acceptable,
c. HUDA LIGHTING
i. SL No-13 propose lp-65 rating light fixture for parking,
Driveway & service rooms.
All of which ascertains the fact that such comments were not in conjunction
with the received code (B) reverting the Main Contractor back to square one.
Whereas the Main Contractor, for the overall benefit of the Project, has duly
resubmitted the requested samples for the Employer’s selection and approval
and such was carried out on 08 November 2017 for the Main Contractor to
proceed accordingly with the proper course of manner.
Page 24 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
6.2.10. On 07 January 2018, via email [Exhibit 6.2-J], the Engineer requested the Main
Contractor to provide samples of chandeliers for living rooms and bedrooms
from the supplier (M/s Lamparas) catalog, along with the respective Technical
Data sheets and comprehensive quotation for the Engineer’s review and
approval.
6.2.11. On 18 January 2018, via correspondence ref. OST/116/CON-019 [Exhibit 6.2-
K], the Main Contractor submitted the requested details for the chandeliers of
living rooms and bedrooms, and highlighted that the respective samples are
available on Site for selection.
Whereas the Engineer’s reluctant feedback came to the contrary of what was
accustomed to for the said documents. Whereas the Engineer requested the
Main Contractor to resubmit the said revised quotations via Technical Submittal
and not correspondence as previously directed, obstructing the Main
Contractor from proceeding the with the respective Works thereto on Site.
6.2.14. On 31 January 2018, via Technical Submittal ref. OST/116/ 183 rev. 04 [Exhibit
6.2-N], the Main Contractor has once again resubmitted the revised full and
final quotations for all the lighting fixtures as per the Employer requirements
and respective selection.
Wherein the Engineer’s feedback was received with code (B) “Approved As
Noted” carrying the following comments:
Page 25 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
b. Include 10% attic stock. The same to be handed over to Employer at
the time of handing over.
B. ANALYSIS
6.2.16. OST had suffered from the reluctant/ hesitant decisions by the Engineer
resulting in extensive delays in nominating the Project’s supplier for the lighting
fixtures. Which had caused in delays / losses to the Main Contractor and
induced irrecoverable delays to the Time for Completion beyond the Main
Contractor’s reasonable control. The Main Contractor has made its best
endeavor towards its obligations with the numerous notices to the Engineer,
urging the Engineer to expedite the resolving of the issue, and recording the
adverse implication of not doing so by the Engineer.
6.2.17. The impediments and disruptions caused by the extensive delays in nominating
the supplier for the Project’s lighting fixtures has adversely affected the
Programme of Works, as well as the economic viability of the Main Contractor’s
package. That were beyond the Main Contractor’s reasonable control and
could not have been avoided by use of due care and diligence.
Page 26 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
6.3. DELAYED RELEASE OF CONTRACTOR’S INTERIM PAYMENT
CERTIFICATES
A. CHRONOLOGY
6.3.1. Via the Project’s cash flow of the Project’s Programme [Exhibit 6.3-A], and as
highlighted hereunder, the Main Contractor was expected to receive an
average of Dhs 1,767,497.00 on a monthly basis in order to cover for its
expenses thereto that were progressively carried out on Site.
6.3.3. The Contractual duration for the release of payments by the Employer after the
receipt of the respective Certificate from the Engineer is 30 Days as defined in
Chapter (8) of the Claim hereunder.
6.3.4. Pertaining to several circumstances that were beyond the Main Contractor’s
reasonable control, several Interim Payments Certificates were delayed in their
respective release, incurring the Main Contractor irrecoverable losses imposing
extensive obstructions on the part of the Main Contractor in terms of the
progress of Works on Site as a consequence of the subsequent disruption in
the Main Contractor’s cash flow.
Page 27 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
Interim Certified Released Elapsed Time
Payment Amount Amount between
Time Payment
Certificate by the by the Certifying and
Scale Overdue
(IPC) Engineer Employer Releasing the
Number (Dhs) (Dhs) Payments
11-Jul-17 IPC (7) 575,273
15-Aug-17 IPC (8) 537,431
28-Aug-17 1,112,704 48 -18
12-Sep-17 IPC (9) 477,989
19-Oct-17 477,989 37 -7
09-Nov-17 IPC (11) 906,123 23
24-Dec-17 906,123 45 -15
20-Feb-18 IPC (14) 1,805,378
28-Mar-18 1,805,378 36 -6
09-Sep-18 IPC (21) 772,971
11-Oct-18 772,971 32 -2
18-Oct-18 IPC (22) 886,552
20-Nov-18 886,552 33 -3
26-Nov-18 IPC (23) 1,249,930
08-Jan-19 1,249,930 43 -13
Total 7,211,645 7,211,645 -64
Table 1 Delayed Released Payments Log
B. ANALYSIS
6.3.6. OST had suffered from the delays in releasing the certified payment amounts.
Which had caused in delays / losses to the Main Contractor and induced
irrecoverable delays to the Time for Completion beyond the Main Contractor’s
reasonable control. The Main Contractor has made its best endeavor towards
its obligations, bearing the Employer’s best interest in mind, urging the
Engineer/ Employer to expedite the resolving of the issue, whilst progressively
highlighting the adverse implications resulted as a consequence of the
aforesaid.
6.3.7. The impediments and disruptions caused by the delayed release of the
Project’s Interim Payment Certificates has adversely affected the Programme of
Works and the respective cash flow thereto, as well as the economic viability of
the Main Contractor’s package. That were beyond the Main Contractor’s
reasonable control and could not have been avoided by use of due care and
diligence.
Page 28 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
6.3.8. Accordingly, the Main Contractor seeks a reasonable adjustment to the
Contract’s Time for Completion, due to the occurrence of the above event that
had caused the Main Contractor to incur irrecoverable losses beyond its
reasonable control, as detailed further in Part II of this Claim.
Page 29 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
PART II – DESIGN CHANGES AND MODIFICATIONS TO THE SCOPE OF
WORKS BY THE ENGINEER
6.4. CHANGING FACADES FINISHES FROM ALUMINUM CLADDING INTO
PLASTER AND PAINTING
A. CHRONOLOGY
6.4.1. The Main Contractor was instructed to implement and carry out the
replacement of the elevations aluminum cladding works. Whereas such Works
would be replaced with the conventional finishes (i.e., plastering and painting)
for the said areas.
B. ANALYSIS
6.4.3. The instruction to replace the aluminum cladding external works for elevations
by the Engineer has obstructed the Main Contractor from proceeding with its
scope of Works on Site in the manner that has been originally tendered, which
subsequently caused extensive delays / disruptions to the Main Contractor’s
scope of works not relevant to the Main Contractor and beyond its reasonable
control.
6.4.4. The impediments and disruptions caused by the issuance of the instruction by
the Engineer had adversely affected the Project’s Programme and the
economic viability of the Project which could not have been avoided by the use
of due care and diligence by the Main Contractor. Whereas the said instruction
had caused the Main Contractor to prepare and resubmit the respectively
added workshop drawings and the subsequent works thereto.
6.4.5. Accordingly, the Main Contractor seeks a reasonable adjustment to the Main
Contract Time for Completion, due to the occurrence of the above event that
had caused the Main Contractor to incur losses beyond its reasonable control,
and had induced irrecoverable delays to the Time for Completion, as detailed
further in Part II of this Claim.
Page 30 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
PART III– ADDITIONAL SCOPE OF WORKS BY THE ENGINEER
A. CHRONOLOGY
6.5.1. On 08 November 2017, via the Request for Information (RFI) ref. RFI/ 003
[Exhibit 6.5-A], the Main Contractor released the RFI in question inquiring about
the fresh air duct branches that are passing either through the living or the
dining areas without any false ceiling to cover such areas.
6.5.2. On 08 November 2017, via the Request for Information (RFI) ref. RFI/ 003
[Exhibit 6.5-B], the Engineer responded to the Main Contractor inquires
released vide the RFI in question by stating the following:
B. ANALYSIS
6.5.3. The various modifications/changes and additional works that had been
instructed to the Main Contractor, due to the various Project’s design changes,
had caused delay to the Main Contractor’s engineering works and
subsequently had delayed the progress for the Project’s works on Site and
respective Site activities.
6.5.4. The Project’s Completion Date has been delayed due to the inclusion of the
additional false ceiling works to the scope of works that had not been initially
part of the Main Contract Works. In addition to that, the inclusion of the
additional quantities has been associated with obstruction of the Works on Site
that had affected/delayed the Contract’s Time for Completion.
6.5.5. Accordingly, the Main Contractor seeks a reasonable adjustment to the Main
Contract Time for Completion and Contract Price, due to the occurrence of the
above events that had caused the Main Contractor to incur losses beyond its
reasonable control, and had induced delays to the Time for Completion, as
detailed further in Part II of this Claim.
Page 31 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
PART IV– STOPPAGE OF WORKS ON SITE DUE TO THE ENCOUNTERED
EXCEPTIONALLY ADVERSE CLIMATIC CONDITIONS
A. CHRONOLOGY
B. ANALYSIS
6.6.3. The Main Contractor suffered from the occurrence of such exceptionally
adverse climatic conditions which consequently resulted in halting the progress
of the Main Contractor’s scope of Works on Site, leading to the inability to
redeploy the Contractor’s personnel to Site for extensive durations that has
adversely affected the progress of the Site activities and induced delays to the
Time for Completion.
Page 32 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
Chapter
7.1. INTRODUCTION
7.1.1. In this Chapter, the Main Contractor is displaying its efforts to minimize the
effect of the Exceptional Circumstances, as a consequence of the various delay
events encountered throughout the course of the Project.
7.1.2. The Contractor has a general duty to mitigate the effects on its Works of
Employer Risk Events. The duty to mitigate does not extend to require the
Contractor to add extra resources or to work outside its planned working hours.
The Contractor’s duty to mitigate its loss has two aspects: first, the Contractor
must take reasonable steps to minimize its loss; and secondly, the Contractor
must not take unreasonable steps that increase its loss.1
7.1.3. The Main Contractor does not have a duty to carry out any change in scope
any more efficiently than the original scope. Neither is the Main Contractor
obliged to expend money in order to attempt to mitigate the effect of an
Employer Risk Event. If the Employer wishes the Contractor to take measures
to mitigate the Employer Delay (whether by adding extra resources, by working
outside its planned working hours or otherwise), the Employer should agree to
pay the Contractor for the costs of those efforts.2
7.1.4. It is the obligation of the Main Contractor to proceed with the Works so as to
complete on or before the Completion Date. However, the method, speed and
timing of the activities forming the contract scope are generally left to the Main
Contractor’s discretion, subject to any stipulated prior process of acceptance of
method and/or programme.3
7.1.5. Even though such exceptional circumstances are providing massive pressure
over the Contractor’s expenses; the Contractor refrained from discharging any
of its personnel and/or labor, for the benefit of the Project, alternatively, the
Contractor adopted rotational shifts and working from home measures.
1
SCL Delay and Disruption Protocol 2nd Edition: February 2017 P. 7/79
2
SCL Delay and Disruption Protocol 2nd Edition: February 2017 P. 40-41/79
3
SCL Delay and Disruption Protocol 2nd Edition: February 2017 P. 41/79
Page 33 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
Chapter
ENTITLEMENT AND
8 DISCUSSION
8. ENTITLEMENT AND DISCUSSION
8.1. Introduction
1.1. In this Chapter, the Main Contractor has attempted to delineate the
responsibilities regarding the effects imposed through reverting to the Main
Contract.
1.2. The following Clauses and conditions are clear contractual entitlement to
substantiate the Main Contractor’s rights for an extension of Time. The bases of
the entitlement for the Main Contractor’s claim for extension of Time is the
provision stated in the Main Contract and under the provisions of fairness and
good faith as clearly stipulated within the Law of the United Arab Emirates.
8.2.1. Sub-Clause 5.2 [Language and Law] of the Particular Conditions of Contract
states that:
"(a) The Contractor shall within 7 days of receiving the order to commence
the Works, pursuant to Clause 41 hereof, submit to the Engineer for his
approval a programme showing the procedure in which he proposes to
carry out the Works.
(b) The programme shall be in the form of a Critical Path Method (CPM)
network analysis which shall show the earliest start (ES) and latest
finish (LF) dates, the length of duration and total float time applicable to
each activity. The critical path/paths shall be clearly highlighted.
Page 34 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
(c) The approved programme shall be the sole basis of assessing any
extension/ extensions of time in accordance with Clause 44 herein and
each month the Contractor shall submit details of any revisions to the
programmed sequences, logic and times.
8.2.3. Sub-Clause 20.3 [Loss or Damage Due to Employer's Risks] of the General
Conditions of the Contract states that:
“In the event of any such loss or damage happening from any of the risks
defined in Sub-Clause 20.4, or in combination with other risks, the
Contractor shall, if and to the extent required by the Engineer, rectify the
loss or damage and the Engineer shall determine an addition to the
Contract Price in accordance with Clause 52 and shall notify the Contractor
accordingly, with a copy to the Employer. In the event of any loss or
damage happening from a combination of Employer's and Contractor's
Risks, as defined by Sub-Clauses 20.4 and 20.5, the responsibility for
rectification of such loss or damage shall be that of the Contractor. Under
such circumstances, the Engineer shall, when determining an addition to
the Contract Price in accordance with Clause 52, take into account the
proportionate responsibility of both the Contractor and the Employer and
shall notify the Contractor accordingly with a copy to the Employer.”
8.2.4. Sub-Clause 20.4 [Employer's Risks] of the General Conditions of the Contract
states that:
Page 35 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
(d) pressure waves caused by aircraft or other aerial devices travelling at
sonic or supersonic speeds,
(f) loss or damage due to the use or occupation by the Employer of any
Section or part of the Permanent Works, except as may be provided for
in the Contract,
(g) loss or damage to the extent that it is due to the design of the Works,
other than any part of the design provided by the Contractor or for
which the Contractor is responsible,
(h) damage to crops being on the Site (save in so far as possession has
not been given to the Contractor),
(i) damage (other than that resulting from the Contractor's method of
construction) which is the unavoidable result of the construction of the
Works in accordance with the Contract,
(j) any interference, whether temporary or permanent with any right of way,
light, air, water, or other easement or quasi-easement which are the
unavoidable results of the construction of the Works in accordance with
the Contract,
“The Employer shall fix the date by which the Contractor is to commence
execution of the Works on Site and the Engineer shall issue a notice to this
effect to the Contractor, which notice shall be issued within the time stated
in the Appendix to Tender after the date of the Correspondence of
Acceptance. Thereafter, the Contractor shall proceed with the Works with
due expedition and without delay.”
Page 36 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
8.2.6. Sub-Clause 43.1 [Time for Completion] of the General Conditions of the
Contract states that:
8.2.7. Sub-Clause 44.1 [Extension of Time for Completion] of the General Conditions
of the Contract states that:
(e) other special circumstances which may occur, other than through a
default of or breach of contract by the Contractor or for which he is
responsible,
being such as fairly to entitle the Contractor to an extension of the Time for
Completion of the Works, or any Section or part thereof, the Engineer shall,
after due consultation with the Employer and the Contractor, determine the
amount of such extension and shall notify the Contractor accordingly, with
a copy to the Employer.”
“Provided that the Engineer shall not make any determination unless the
Contractor has
(a) within 28 days after such event has first arisen notified the Engineer
with a copy to the Employer, and
(b) within 28 days after such notification submitted to the Engineer detailed
particulars of any extension of time to which he may consider himself
entitled in order that such submission may be investigated at the time.
Page 37 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
Such detailed particulars shall include reference to the Programme
submitted to the Engineer pursuant to Clause 14 and shall clearly set out
the basis and justification for extension of time to which the Contractor is of
the opinion that he is entitled to receive.”
8.2.9. Sub-Clause 51.1 [Variations] of the General Conditions of the Contract states
that:
(b) omit any such work (but not if the omitted work is to be carried out by
the Employer or by another contractor),
(d) change the levels, lines, position and dimensions of any part of the
Works,
(e) execute additional work of any kind necessary for the completion of the
Works,
No such variations shall in any way vitiate or invalidate the Contract, but
the effect, if any, of all such variations shall be valued in accordance with
Clause 52. Provided that where the issue of an instruction to vary the
Works is necessitated by some default of or breach of contract by the
Contractor or for which he is responsible, any additional cost consequent
thereon or incidental
thereto which are attributable to such default shall be borne by the
Contractor and may be recoverable from the Contractor by the Employer
and may be deducted by the Employer from any monies due or to become
due to the Contractor.”
Page 38 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
8.2.10. Sub-Clause 51.2 [Instructions for Variations] of the General Conditions of the
Contract states that:
“The Contractor shall not make any such variation without an instruction of
the Engineer. Provided that no instruction shall be required for increase or
decrease in the quantity of any work where such increase or decrease is
not the result of an instruction given under this Clause, but is the result of
the quantities exceeding or being less than those stated in the Bill of
Quantities”
8.2.11. Sub-Clause 53.1 [Notice of Claims] of the General Conditions of the Contract
states that:
Page 39 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
the work, supply or contingencies to which such Provisional Sums relate as
the Engineer shall determine in accordance with this Clause The Engineer
shall notify the Contractor of any determination made under this Sub-
Clause, with a copy to the Employer.”
8.2.14. Sub-Clause 58.2 [Use of Provisional Sums] of the General Conditions of the
Contract states that:
“In respect of every Provisional Sum the Engineer shall have authority to
issue instructions for the execution of work or for the supply of goods,
materials, Plant or services by:
(a) the Contractor, in which case the Contractor shall be entitled to an
amount equal to the value thereof determined in accordance with
Clause 52,
“The Contractor shall submit to the Engineer after the end of each month
six copies, each signed by the Contractor or by the Contractor's
representative approved by the Engineer in accordance with Sub-Clause
15.1, of a statement, in such form as the Engineer after due consultation
with the Employer and the Contractor may from time to time prescribe,
showing the amounts to which the Contractor considers himself to be
entitled up to the end of the month in respect of:
(a) the value of the Permanent Works executed including the value of the
work of Nominated Subcontractors,
Page 40 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
(b) any other items in the Bill of Quantities including those for Contractor's
Equipment, Temporary Works, dayworks and the like,
(c) the percentage of the invoice value of listed materials, all as stated in
the Appendix to Tender, and Plant delivered by the Contractor on the
Site for incorporation in the Permanent Works but not incorporated in
such Works,
(d) any other sum to which the Contractor may be entitled under the
Contract.
8.2.17. Sub-Clause 60.2 [Monthly Payments] of the General Conditions of the Contract
states that:
(b) secondly, to the deduction, other than pursuant to Clause 47, of any
sums which may have become due and payable by the Contractor to
the Employer.
Provided that the Engineer shall not be bound to certify any payment under
this Sub-Clause if the net amount thereof, after all retentions and
deductions, would be less than the Minimum Amount of Interim Certificates
stated in the Appendix to Tender.
Page 41 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
8.2.18. Sub-Clause 69.1 [Default of Employer] of the Particular Conditions of the
Contract states that:
“(1) In the event of the Employer failing to pay to the Contractor the amount
due under any certificate of the Engineer within sixty (60) days after the
end of the period for payment stipulated in sub clause 60(6), subject to any
deduction that the Employer is entitled to make under the Contract, the
Contractor shall be entitled to terminate his employment under the Contract
after giving thirty days' prior written notice to the Employer, with a copy to
the Engineer.”
8.3. Caveat
3.1. This is an updated claim document, for the purpose of providing a supported
case for OST’s entitlement to an Extension of Time, as a result of the events
detailed in the claim submission. OST reserves its rights to amend, supplement,
omit or provide further information at any time should this be considered
appropriate by either party.
3.2. Neither the adopted methodology nor the claim generally takes any account of
any events taking place for reasons other than the subject matter of the claim or
for events occurring during the period of time not considered under the claim.
OST reserves all rights to pursue such matters separately.
Page 42 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
OST CONSTRUCTIONAL PROJECTS, L.L.C.
Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai,
U.A.E.
PART II
CLAIM METHODOLOGY
Page 43 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
PART II
TABLE OF CONTENTS
9.1. INTRODUCTION 45
9.2. CONCEPT 46
9.4. CONCLUSION 51
Page 44 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
Chapter
CONCEPT AND DELAY ANALYSIS
9
METHODOLOGY
9.1. INTRODUCTION
9.1.1. In this chapter, the Main Contractor analyzes the impact of the delay events
highlighted and mentioned in Part-I of this Claim, in terms of time effects, on the
Project and/or the Completion Date.
9.1.2. The computerized calculations of the critical path for applying this method are
attached to chapter 10 of this part under the “Impacted Programme of Works”.
9.1.3. The overall thrust of this analysis is to establish the impact of delay events on the
Project’s Programme of Works in a dynamic manner. The delay events that are
modeled are introduced into the Project Master Schedule, and linked in an
appropriate manner.
9.1.4. Having incorporated the delay events to the Project’s Programme of Works is then
modeled/recalculated. The resultant impact upon completion is determined to be the
critical delay impact of the introduced delay events.
Page 45 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
9.2. CONCEPT
9.2.1. The Programme used for this analysis is the Project’s approved Baseline Schedule,
as submitted by the Main Contractor,
9.2.2. Each delay event is inserted individually in the Project’s Baseline Schedule and
linked logically to the other correlated activities in order to identify the actual impact
of each individual event on the other Works’ activities and on the Completion Date
as well. This exercise will be principally used to define the damages.
9.2.3. Ultimately, all delay events will be presented together on the Project Baseline
Schedule in order to evaluate the integrated and net impact on the time for
completion.
9.2.4. The activities that ended beyond the Completion Date will be the main driver for the
adjustment of the time for completion and consequently the contractual Completion
Date.
9.2.5. The delay analysis is performed by using the Project Baseline schedule and
impacting it in successive iterations to evaluate the effect of delay events.
9.2.6. This analysis is performed to identify and calculate the impact of the delay events
that occurred during the Contract Time for Completion. The facts associated with
each delay event were examined and a “event fragnet” (a portion of a Critical Path
Method (CPM) schedule network) was developed for each event.
9.2.7. The insertion of an event activity representing the delay events and changes to the
Scope of Work into the Project Programme CPM allows its specific impact on the
Project to be integrated into the Project Programme.
9.2.8. The use of this methodology assures that the individual impact of each event is
properly considered with respect to its influence on the Project Baseline Programme.
9.2.9. When all the impacts (event activities) for a particular time period had been
developed and inserted into the Project Baseline Programme, the Critical Path
Method schedule was recalculated. [All schedule evaluations were conducted using
Primavera software].
9.2.10.The Project Baseline Programme is the timetable for implementation and completion
of the Works, including and integrating the acts of the Employer / the Engineer in
terms of review and approval of engineering submittals and the sequence for the
execution of the Works.
Page 46 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
9.2.11.The delay analysis methodology used is known as the (Impacted-As-Planned)
method or (Net Impact Analysis) and it is commonly used for delays analysis.
9.2.12.The Impacted Project Schedule may show a start date for certain activities later than
what actually have been performed in the Project, because the impact of most of the
events affects the Time for Completion of the activity rather than the start date of that
activity.
9.2.13.In the analysis, the delay event activity is added to the Project Baseline Programme
in order to demonstrate the influence of the event on the Project Baseline
Programme activities sequence and overall duration. Thus, incorporating delays and
impacts into the Project Baseline Programme as they were encountered.
9.3.1. A new Work Breakdown Structure (WBS) has been incorporated into the Project’s
Baseline Programme named with their relative event numbered as illustrated in Part
I of this Claim. In order to reflect the same impact effect on any device with different
users, all global calendars were changed into a project calendar. The analysis of
these delay events had been carried out as follows:
9.3.3. Event No. 1 – Delayed Approval for Inspection of the Second Floor Slab
For showing the Impact of this delay event, the Main Contractor added the delayed
activities assigned to the Project Baseline Programme activities with the listed details
to reflect the impact of each delay event.
Please refer to the below referenced exhibits depicting the assigned activities and
the relevant impact(s) thereto:
Page 47 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
works in question as an obstruction of the sequence of the Works on Site in order to
be able to calculate the magnitude of the incurred delays, which consequently led to
a total of 75 Calendar Days Extension of Time for the Project’s Time for Completion
as a consequence of the delays incurred by the Employer/ Engineer.
9.3.4. Event No. 2 – Delayed Nomination of the Light Fitting Supplier by the
Employer
For showing the Impact of this delay event, the Main Contractor added the delayed
activities assigned to the Project Baseline Programme activities with the listed details
to reflect the impact of each delay event.
Please refer to the below referenced exhibits depicting the assigned activities and
the relevant impact(s) thereto:
For showing the Impact of this delay event, the Main Contractor shows hereunder
the method utilized for the calculation of the irrecoverable losses resulted as a
consequence of the event in question.
The Main Contractor relied on the monthly average (viz; Dhs 1,767,495) as depicted
in Part I of this Claim hereinabove, and rendered such figure as a measured mile in
order to be set as a benchmark for the calculation of the incurred delays, which
consequently led to a total of 122 Calendar Days Extension of Time for the Project’s
Time for Completion, per the below equation:
7,211,645
=4.08 Months∗30 Days=122.4 Calendar Days
1,767,495
Page 48 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
9.3.6. DESIGN CHANGES AND MODIFICATIONS TO THE SCOPE OF
WORKS BY THE ENGINEER
9.3.7. Event No. 4 – Changing Facades Finishes from Aluminum Cladding into
Plaster and Painting
For showing the Impact of this delay event, the Main Contractor added the delayed
activities assigned to the Project Baseline Programme activities with the listed details
to reflect the impact of each delay event.
Please refer to the below referenced exhibits depicting the assigned activities and
the relevant impact(s) thereto:
9.3.9. Event No. 5 – Additional False Ceiling Works for All Typical Floors
For showing the Impact of this delay event, the Main Contractor adjusted the
calendars assigned to the Project’s Baseline Programme activities with the listed
details to reflect the impact of each delay event.
Please refer to the below referenced exhibits depicting the assigned activities and
the relevant impact(s) thereto:
The Main Contractor relied on the Released Requests for Information (RFI)s as
depicted in Part I of this Claim hereinabove, and rendered such instruction to carry
out and implement the additional scope of works on site as an obstruction to the
sequence of the Works on Site in order to be able to calculate the magnitude of the
incurred delays, which consequently led to a total of 13 Calendar Days Extension of
Time for the Project’s Time for Completion.
Page 49 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
9.3.10. STOPPAGE OF WORKS ON SITE DUE TO THE ENCOUNTERED
EXCEPTIONALLY ADVERSE CLIMATIC CONDITIONS
For showing the Impact of this delay event, the Main Contractor adjusted the
calendars assigned to the Project’s Baseline Programme activities with the listed
details to reflect the impact of each delay event.
Please refer to the below referenced exhibits depicting the assigned activities and
the relevant impact(s) thereto:
The Main Contractor adjusted the Project calendars assigned to the Project’s
Baseline Programme various activities by implementing the following variations to
the original calendars:
a. For the occurrence of 21 March 2017, the Main Contractor Rendered the days
21 March and 22 March 2017 as Non-Working Days in an endeavor to depict
the adverse implications of the event in question. Whereas the progress of
Works on Site was halted pertaining to the said occurrence in addition to the
fact that the Main Contractor was unable to redeploy its personnel to Site as a
consequence of such occurrence, whilst being able to redeploy only an
approximate amount of 50% of its personnel on 23 March 2017.
b. For the occurrence of 24 March and 25 March 2017, the Main Contractor
Rendered the days 24 March, 25 March and 26 March 2017 as Non-Working
Days in an endeavor to depict the adverse implications of the event in question.
Whereas the progress of Works on Site was halted pertaining to the said
occurrence in addition to the fact that the Main Contractor was unable to
redeploy its personnel to Site as a consequence of such occurrence.
Page 50 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
9.4. CONCLUSION
9.4.1. Several changes initiated by the Employer / the Engineer to the Main Contractor
impacted the timely execution of the Contract’s Scope of Works.
9.4.2. Several factors have contributed to the above, resulting in irrecoverable delays
which could not have been avoided with the use of due care and diligence.
9.4.3. From the “Delay Events Analysis” illustrated hereinabove, and subsequent to a
meticulous study to the critical path of the Works, OST Constructional Projects,
L.L.C. concludes a total of Three Hundred and Ninety (390) calendar days as an
overall delay beyond the Contractual Completion Date. This gives an adjusted
Completion Date on the 16 June 2019.
9.4.4. The Contractor is claiming for extension of the project time by 390 calendar days
and extension of Time for Completion as follows:
Page 51 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
Chapter
10 IMPACTED PROGRAMME
OVERALL
IMPACTED
PROGRAMMES
Page 52 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
Overall Baseline
Programme
Page 53 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
OVERALL IMPACTED
PROGRAMME
for Event 01
Page 54 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
OVERALL IMPACTED
PROGRAMME
for Event 02
Contractor Delay
Page 55 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
OVERALL IMPACTED
PROGRAMME
for Event 02
Employer Delay
Page 56 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
OVERALL IMPACTED
PROGRAMME
for Event 04
Page 57 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
OVERALL IMPACTED
PROGRAMME
for Event 05
Page 58 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.
OVERALL IMPACTED
PROGRAMME
for Event 06
Page 59 of 59
PROJECT : Residential Buildings (G + 2P + 12 Floors + Roof + Gym) on Plot No. 2410560 at al Nahda Second, Dubai, U.A.E.
MAIN CONTRACTOR : OST Constructional Projects, L.L.C.