Chap 3
Chap 3
Chap 3
FINANCE
HOAI NGUYEN
CORPORATE FINANCE DEPARTMENT
FACULTY OF BANKING AND FINANCE
FOREIGN TRADE UNIVERSITY
EMAIL: HOAINT@FTU.EDU.VN
CHAPTER 3:
INVESTMENT
PROJECTS
APPRAISAL
METHOD
4 QUESTIONS INVESTMENT DECISION
THAT
CORPORATE FUNDING DECISION
WHAT IF...
You have $10,000
PV is present value
r is the interest rate
t is the number of periods over which the cash is invested
Exercises
Discounting
Example
The Present Value of $100 to be
Received at a Future Date
PV is lower if:
Time period is longer
Interest rate is higher
Exercise 1
PV = $150/0.10 = $1,500
Growing Perpetuity
A growing stream of cash flows that lasts forever.
Annuity: A stream of cash flows that
least for a fixed number of period.
Summarize
How to Compare?
Semiannually Compounding
This annual rate of return is called either the effective annual rate (EAR) or
the effective annual yield (EAY)
Annual Percentage Rate (APR)
vs. Effective Annual Rate (EAR)
Year 0 1 2 3 4 5
Net
Recognizes time value of
money
Present
Considers risk
Value? Drawbacks
Requires detailed long-
term forecast of cash flows
Exercise
You have been assigned the task of evaluating two projects with the following
project free cash flows
Period
Allow quick evaluation
User cash flows rather than accounting
Trade-Offs profits
Biased toward liquidity
Drawbacks
Payback
Consider time value of money and risk
Period Drawbacks
Trade-Offs
Ignores cash flows after the discounted
payback period
Too much work! Should have calculated NPV
The Internal Rate of Return (IRR)
The discount rate that sets NPV All future cash flows are assumed Accept if the IRR > required
to zero to be reinvested at the IRR return
Select the highest IRR
Example
Consider a project with cashflows as below. The discount rate is 10%.
Calculate IRR.
With discount rate of 20%, NPV is less than 0. It means that IRR
lies between 15% and 20% (so that NPV will equal to 0).
Conclusion
At 15%, NPV = + 224
At 20%, NPV = - 208
An increase of 5% (from 15% to 20%) in the discount rate causes a fall of $432
(from $224 to -$208) in NPV
For the NPV to fall by only 224 (to zero) the discount rate would have to
increase by [224/432] x 5% = 2.59%
The discount rate of 15% + 2.59% = 17.59% would give a zero NPV for the
investment.
Projects may have as many IRRs as there are changes in the signs of
the cash flows
Benefits
IRR Trade-
Easy to understand and communicate
Considers the time value of money and risk
Project X 0 1
Project Y 0 1
PI Trade-
Easy to understand and communicate
Correct decision when evaluating
Drawback