Purpose 2
Purpose 2
Purpose 2
Construction of two six lane Vups including RE wall, Service Road and
Drain, at new ch. 31+050 near Budiya village junction and new
ch.33+580 near Gabheni village junction on Hazira port -surat -
Gujarat /Maharashtra border section of new NH-53 in State of Gujarat
The purpose of this document is to provide a detailed method statement indicating the
Work procedures for safe launching of Precast Girders work to be carried out at Hazira port -surat
-Gujarat /Maharashtra border section of new NH-53 in State of Gujarat, Budiya Gabheni junction.
NHAI Road project.
2. SCOPE OF WORKS
The scope of work covered under the procedure shall include transportation of pre-cast girder,
shifting of girder, lifting, placing in position, launching by approved method for major/minor
bridges, flyover, ROB etc.in the project:
Casting of PSC girder for main bridges is in two stages. sequence of construction is as follows:
Following scope of works shall be undertaken by girder launching method on the project:
No of spans: 8 no
No of PSC girder: 8 no
No of RCC girder: 16 no
No of girders per span: 4 no
Type of girders: “I” type
Length of girders(varying): 19.2 mtrs to 38.7 mtrs
Weight of girder(varying):app. 40 MT max.to 107 MT.
Casting of girders are being done near the erection site only
3. REFERENCE DOCUMENTS
Approved schematic drawings for erection / launching of pre-cast girders by cranes and trailers;
approved technical specifications including general & particular project specifications; MORTH
specifications; IS & IRC codes.
4. RESOURCES DEPLOYED:
a. manpower: as per annexure A-IX
b. EQUIPMENTS: as per annexure A-IV, A-V, A-VI, A-VII & A-VIII
5. WORK METHOLOGY:
i. 2 no hydraulic truck cranes of capacity not less than 200 MT with average working radius
of 8 Mtrs to lift 50 tons. the preferable capacities of two cranes shall be 250 MT and 350
MT (proposed make & models of the proposed cranes groove – TM 2500 (annexure A-IV)
capacity 250 MT, Demag HC 1010 (annexure A-V) or equivalent having capacity of 350
MT). load charts and specification of the cranes are enclosed here with for ready
reference.
ii. Girder will be shifted from the casting bed to the erection location either by using cranes
or by using Hydraulic axle modular trailers (minimum 2X2 I 4X4 axle line) with matching
prime mover approx. 280 1300 HP. Technical specifications of hydraulic axle modular
trailer -2 & 4 axle line. and prime mover are enclosed at annexure A-IV, A-VII&A-VIII.
iii. sling of minimum 38 mm Dia steel core wire and D-cycles of adequate capacity duly
tested shall have to be used and certified by the third party will be used for the work.
iv. Highly skilled riggers, signal men with sufficient experience to carry out such like works
shall be deployed for the erection works. The details of manpower are attached at
annexure A-IX
i. approaches to the site shall be prepared in a manner so it is fully safe for the cranes and
trailers to reach the desired location /launching location and should be as per HSE manual/
method statement.
ii. ground shall be well compacted around the casting bed and piers before the cranes &trailer
is placed. All due precautions as per the standard practices/ method statement shall be
taken.
c. shifting of PSC girders either by cranes or by using modular trailers (as per annexure-
A-I)
i. In case it is possible to shift the girders from the casting bed to the erection location in
one / two swings then cranes will be deployed for shifting. else, the modular trailer will be
placed near the casting bed and the two cranes shall be so placed that the girder can be
lifted at the two ends and placed at the Centre of the trailer. it will be ensured that girder
rest only at two points on the modular trailer and not all along its length.
ii. Before the cranes leave the girder on to the trailer the same will be secured properly on to
the modular trailer with help of chains and belts to be tightened with turn buckles.
iii. Having completed the loading of PSC girder the same shall be moved to the erection site
taking full safety precautions.
i. place the two cranes as shown in the drawing. (As per annexure –A-I)
ii. bring the modular trailer duly loaded with PSC girder in between the cranes as shown in the
drawing, in case the girder is shifted by using trailer.
iii. Lift the girder of trailer or from the ground as the case may be.
iv. Place the girder on to the wooden sleepers its final location.
v. Secure the girder on to the pier with help of temporary A-frame and release the girder off
the lifting shackles .(as per annexure A-III)
vi. Subsequently grout the bearings with GP-2non shrinkable / approved grout material.
vii. Once the grout attains its full strength, the wooden sleepers will be removed by use of
screw jacks.
Repeat the above procedure for erection of all the girders in the same span and for all the
as launching of girders is one of the riskiest Job which must tale utmost precaution at all
stages like; planning, establishing casing yard, casting segments, transporting segments,
fabrication and erection of launching girders, launching of segments, pre-stressing, auto
launching of girder etc.
u) the site conditions, including the ground where the machine will be set up, access roads and
ramps it must travel, space for loading and unloading and any obstacles that might impede
access or operation.
v) the contractor shall ensure that a valid certificate of fitness issues as per HSE manual is
available for all lifting appliances including synchronized mobile jack, pre-stressing hydraulic
jacks, jacks fitted with launching girders etc.
Quality assurance and quality control requirements shall be as per the QAQC manual and
project Specifications. EPC contractor shall ensure that the approved project policies, procedures,
instructions and documented evide0nce thereof, are effectively and efficiently implemented all
actions necessary to maintain the desired level of quality for the activities shall be exercised and
recorded in accordance with the contact requirements and QA/QC procedures.
8. DOCUMENTATION/RECORDS
All records and checklist, as specified in the method statement and as per directions of
engineer (PMC) shall have to be recorded and reported for launching of each girder, duly
approved by the authorized signatory of JSTPL