MRP - Solved Problem
MRP - Solved Problem
MRP - Solved Problem
Week
1 2 3 4 5 6
A 5 15 18 8 12 22
A B C
On hand 21 20 70
Q 20 40 Lot-for-lot
Lead time 1 2 1
Safety stock 0 0 10
A 1 2 3 4 5 6
Gross Requirements 5 15 18 8 12 22
Scheduled receipts
Projected available balance 16 1 3 15 3 1
Net requirements 17 5 19
Planned order receipts 20 20 20
Planned order releases 20 20 20
B 1 2 3 4 5 6
Gross Requirements 40 40 40
Scheduled receipts 32
Projected available balance 52 12 12 12 12 12
Net requirements 28 28
Planned order receipts 40 40
Planned order releases 40 40
C 1 2 3 4 5 6
Gross Requirements 40 20 60 20
Scheduled receipts
Projected available balance 70-40-10=20 0 0 0 0 0
Net requirements 60 20
Planned order receipts 60 20
Planned order releases 60 20
A
C B(2)
C
Lead Time 2 Weeks
Weeks 1 2 3 4 5 6 7 8
Gross Requirement 115 115 125 130 120 110 125 135
130 145
20 75
- 125
- 200
- -