006 - Method Statement - Sub Base
006 - Method Statement - Sub Base
PROJECT NO : 57/2023
REVISION CONTROL
Second Issue
01 26.02.2024
for Approval
Mohamed Fadel Mohamed Fadel Shoukat Riaz
Doc. No: BGC-MS-006 Rev 01 Page 1 of 10 Method Statement for Subbase Work
Date of issue: 26.02.2024 BASE GENERAL CONTRACTING
LLC
Office Civil Engineer Office Civil Engineer Project Manager
INDEX
1.0 PURPOSE
2.0 SCOPE
3.0 REFERENCES
7.0 PROCEDURE
Doc. No: BGC-MS-006 Rev 01 Page 2 of 10 Method Statement for Subbase Work
Date of issue: 26.02.2024 BASE GENERAL CONTRACTING
LLC
1.0 PURPOSE
The purpose of this document is to provide the guidelines for subbase work by satisfying all the
relevant specifications and requirements.
2.0 SCOPE
This document shall be applicable for subbase work under the project- 57/2023 for Improvement of Al
Khor St., UAQ.
3.0 REFERENCES
4.1 ABBREVIATIONS
4.2 DEFINITIONS
Doc. No: BGC-MS-006 Rev 01 Page 3 of 10 Method Statement for Subbase Work
Date of issue: 26.02.2024 BASE GENERAL CONTRACTING
LLC
May : This shall mean possible course of action.
Doc. No: BGC-MS-006 Rev 01 Page 4 of 10 Method Statement for Subbase Work
Date of issue: 26.02.2024 BASE GENERAL CONTRACTING
LLC
a) Responsible for overall execution, administration, monitoring and control of the project as per the
Contractual requirements, specifications & PQP.
b) Coordinate with Project Manager for obtaining necessary resources for the project and deploy as required.
c) Responsible for managing all interfaces with Client and Project Manager.
d) Responsible for actual progress of the work against planned program.
e) Obtain subcontractors Procedures / Plans / Method Statements, where applicable and coordinate approval
of the same.
f) Coordinate with the Procurement Unit in carrying out procurement activities for the project through Project
manager.
g) Liaise with Site Engineers to ensure timely completion of civil activities pertaining to the project
h) Analyze deviations, change of contract scope or delays, if required, and reschedule to meet target dates in
coordination with the Project Manager.
i) Appropriate actions shall be taken on all NCRs and Audit Non-Conformances raised in the Project.
j) Ensure through the QA/QC Engineer that all Corrective & Preventive Actions taken in the Project are
Effective.
k) Identify Training needs and Coordinate with appropriate function for fulfilling the Training Requirements.
l) Reports to the Project Manager.
He shall be overall responsible for safe execution of the complete activity including, but not limited to:
a) Organizing tools and equipment required to the work site.
b) Assigning work crew.
c) Sequence of activities to be carried out for the work as per this work procedure.
d) Stage Inspection & Surveillance.
e) Ensure all safety Regulations are followed as applicable.
f) Contract specific requirements for excavations, if any specified shall be identified and the requirements of
such specification shall prevail in addition to the non-conflicting requirements of this procedure.
g) Ensure & study the approved drawings & statements before starting the activity.
h) Communicate all HSE requirements to the entire working crew and ensure that they understand.
i) Thoroughly familiar with all MODES/RAY contract and general HSE requirements and understand it to
maintain a healthy and safe environment for employees and contract staff.
5.4 NOC Officer
Doc. No: BGC-MS-006 Rev 01 Page 5 of 10 Method Statement for Subbase Work
Date of issue: 26.02.2024 BASE GENERAL CONTRACTING
LLC
b) Executing monitoring and updating the Authority Approvals (NOCs) and works with regulatory authorities
to ensure that the required approvals are in place in a timely manner.
c) Developing relationships with key stakeholders to ensure all necessary permits are in place as required.
d) Tracking the status of approvals and ensuring government compliance.
e) Support in resolving authority approval and permit interface issues as necessary together with the wider
project team, develop systems to ensure that permits are current and valid for the activity being
undertaken.
f) Advising and informing appropriate staff and department of document and plan submittal requirements
5.6 Surveyor
a) Ensure all P & M Equipment being used for the activity are in good working condition.
b) Ensure P & M Operators are qualified & authorized to operate the relevant equipment.
c) Ensure the work area shall be barricaded.
d) The toolbox talk shall be carried out before starting the work.
e) Ensure all necessary PPEs are worn by workers involved in the work.
Doc. No: BGC-MS-006 Rev 01 Page 7 of 10 Method Statement for Subbase Work
Date of issue: 26.02.2024 BASE GENERAL CONTRACTING
LLC
f) Work shall be carried out in the daytime and if authorized, night work is permitted.
g) All sub-contractor men, material, machinery details to be collected and checked against insurance.
h) No work shall be allowed if temperature is more than 50 degree Celsius / high wind / more than 80%
humidity / inclement weather due to rain, lighting storm, fog or dark condition.
a) Tipper
b) Trailer
c) Loader/Bobcat
d) Tandem Power-driven Roller
e) Pneumatic Tired Roller
f) Vibrating Roller
g) Plate compactor
h) Grader
i) Water tanker
j) Shovel
k) Six-wheel
l) 3-Ton Pick up
m) Total station
n) Auto level / leveling staff
o) Measuring tape
p) Temporary Signs
q) Safety Barriers
r) Safety Traffic Cones
7.0 PROCEDURE
7.1 General
The following documents as a minimum shall be readily available for ready reference at work site.
Client specifications
Approved Method statement
Issued for Construction drawing &
Approved Material approval sheet
Doc. No: BGC-MS-006 Rev 01 Page 9 of 10 Method Statement for Subbase Work
Date of issue: 26.02.2024 BASE GENERAL CONTRACTING
LLC