Emergency Response Plan - Rev. 00
Emergency Response Plan - Rev. 00
Emergency Response Plan - Rev. 00
PLAN
NA Pipeline Junctions
Security Upgrade
Contract No. 6600050780
BI-10-13202-0001
Revision No.: 00
Doc. No. NZK-NAJSU-SFTY-003
EMERGENCY RESPONSE
DATE: July 20, 2022.
PLAN
REV. 00
REVISION CHANGES/HISTORY
Doc NZK-NAJSU-SFTY-003 GENERAL CONFIDENTIAL- This document and the information herein
contained are the confidential proprietary information of NA Pipeline
Junctions Security Upgrade project. Any Disclosure to third parties, use or
reproduction without proper authorization is strictly prohibited.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Table of Contents
1. Content .................................................................................................................... 6
2. Intent of the Plan ...................................................................................................... 6
3. Purpose .................................................................................................................... 6
4. Scope of Work.......................................................................................................... 7
5. Terms and Definitions .............................................................................................. 7
6. Reporting & Alerting ................................................................................................. 9
6.1 Types of Emergencies to be reported .............................................................. 10
6.1.1 Medical Emergency ................................................................................... 10
6.1.2 Fire Emergency ......................................................................................... 11
6.1.3 In case of the Power Failure. ..................................................................... 12
6.1.4 Chemical Spills. ......................................................................................... 12
6.1.5 Severe Weather Condition and Natural Disaster ....................................... 13
6.1.6 Bomb Treat ................................................................................................ 14
6.1.7 Fall from Heights, ...................................................................................... 15
6.1.8 Motor Vehicle Accidents/Collision (MVA-MVC) ......................................... 16
6.1.9 Confined Space Emergency and Rescue. ................................................. 17
6.1.10 Structure Collapse (Excavation and Scaffold) ........................................ 20
7. Credible Incident Scenarios ................................................................................... 21
8. Response Level: .................................................................................................... 21
8.1 Level 1—Minor incident .................................................................................... 21
8.2 Level 2- Emergency Condition. ........................................................................ 21
8.3 Level 3 - Search and Rescue. .......................................................................... 22
8.4 Level 4- Disaster .............................................................................................. 22
9. Person Discovering an Emergency ........................................................................ 22
9.1 Notification Procedure (Report to Emergency Response Team)...................... 22
10. Recovery and development plan. ........................................................................ 23
11. Safety Training and Awareness Program. ........................................................... 23
11.1 Training Procedure. ...................................................................................... 23
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
1. Content
This procedure outlines the overall Emergency Response and Emergency Control
Procedure for all job sites and facilities within the project scope of work/area as applicable.
The Naizak Project Emergency Control Centre is located in Naizak Site Project Office.
Saudi Aramco Emergency Control Centre will be the single focal point for Naizak as well
as our subcontractors during the project execution processes in case of disaster.
The intent of this plan is to describe the procedure, organization and equipment
necessary for essential personnel to control any emergency, which includes search and
rescue measures.
It is not the intent of this plan to detail individual worker actions to secure and make safe
his work area, which would be responsibility of all the site supervisors.
The emergency response planning scenarios shall be reviewed and updated either
annually or after the occurrence of any incident where variable recommendations have
been made.
Naizak shall ensure the Emergency Response Plan and Emergency Procedures are
specific for the operation and aligned with applicable SAPO Emergency Response Plan
and based on properly developed credible scenarios.
This plan will be applied for all facilities, and building for Naizak scope of the NA
Pipeline Junctions Security Upgrade (BI-10-13202-0001).
3. Purpose
The purpose of this Emergency Response Plan is to outline the individual responsibilities
and proper response for directing the activities required to contain and control an
emergency situation or disaster.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
4. Scope of Work
The purpose of the Upgrade Ethane Facility – NA Pipeline Junctions Security Upgrade
(BI-10-13202-0001) project is to:
The project shall provide Security Equipment Building (SEB), Checkpoint Support
Building (CSB), Anti-Vehicle Barriers at Main/Emergency Entrance, Auxiliary Gate,
Emergency Gate, Security Access Control System (SACS) equipped with Turnstiles. In
addition, installation of Anti-Vehicle Barrier - Crash Rated Fence (CRF) and Category-1
Fence according to the project requirements.
The Contractor shall provide Intrusion Detection and Assessment System (IDAS), Long
Range Detection & Assessment System (LRDAS), Perimeter Fence Lighting as part of
the security facilities upgrade.
The project scope shall include site grading and preparation of roads, asphalt pavement,
sidewalks, walkways and parking with all support utilities networks.
Tanajib P/L Junction (KM-22) in the Eastern Province, KSA (Northern Area).
Khursaniyah P/L Assembly (KM-191) in the Eastern Province, KSA (Northern
Area)
Juaymah Junction in the Eastern Province, KSA (Northern Area)
Jubail Interface-1 P/L Junction the Eastern Province, KSA (Northern Area)
Jubail Interface 2 P/L Junction in the Eastern Province, KSA (Northern Area)
JJBUT-1 Intermediate Trap-1 P/L Junction in the Eastern Province, KSA (Northern
Area)
JJBUT-1 Intermediate Trap-2 P/L Junction in the Eastern Province, KSA (Northern
Area)
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Incident: Anything else that takes place that may cause loss of work, injury or death,
which does not include loss of a vehicle, aircraft or structure.
Emergency Control Center (ECC): The location where the IM and support staff
assemble in response to an emergency or crisis
Incident Commander (IC): The person responsible for all decisions relating to the
execution of tactical response as specified in the respective ERP
Incident Command Post (ICP): The field location for tactical management of an
emergency, led by the IC
Triage - A method for rapid assessment of emergency care priorities. Triage involves the
sorting of and allocation of treatment to patients, especially crisis victims, according to a
system of priorities designed to maximize the number of survivors.
Work Zones - Delineated work zones clearly define areas where certain actions during
the response can take place and authorized personnel can work.
Hot zone - Restricted zone surrounding a fire or hazardous material incident; with outer
boundary far enough to prevent adverse effects from the incident outside the zone.
Properly trained and equipped response personnel will work in this zone.
Cold zone - Contains ICP and support functions necessary to control the incident. This
zone must be secure, allowing only response personnel and necessary advisors in this
area.
Anyone who observes an emergency situation shall immediately notify Saudi Aramco
Emergency Control Centre by the following:
Describe the emergency briefly; including the type (e.g. fire, explosion, gas release, MVA,
etc.)
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Provide details on a meeting point between the caller and emergency responder, such as
my name is…XXXX…. and badge # …XXXX... and contractor details, like Naizak and/or
any of the subcontractors.
Wait for Emergency Responders to repeat the message to ensure it is correct before you
hang up.
Once the Naizak Emergency Response Personnel has received an emergency call he
shall activate the Project Emergency Response Plan. If medical assistance is needed,
the Incident Post Commander shall call the Naizak Clinic on the phone or Radio and
request for the clinical assistance.
If required, the Incident Post Commander shall contact with Saudi Aramco Medical Centre
and request for the assistance.
SAPMT Safety Representative and Saudi Aramco Emergency Control Centre will be
notified of the situation via Phone/Radio
Medical Emergency
Fire Emergency
In case of Power Failure
Chemical Spills (fuels, gasoline, etc.)
Severe Weather Condition and Natural Disaster
Bomb Threat
Fall from Heights
Motor Vehicle Accidents/Collision (MVA-MVC)
Confined Space Emergency and Rescue
Collapse of Structure (Excavation, Scaffold, etc.).
6.1.1 Medical Emergency
Call medical emergency phone number (See attached emergency contact no.).
a) Site number
b) Ambulance
c) Fire Department
d) Others
Provide the Following Information
a) Nature of medical emergency,
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Deal with the spill in accordance with the instructions described in the
MSDS.
Small spills must be handled in the safe manner, while wearing the proper
PPE.
Review the general spill procedures.
6.1.5.1 Tornado.
6.1.5.2 Earthquake
Stay calm and wait instruction for from the emergency control commander.
Evacuated as instructed by emergency control commander.
Evacuate from Building as necessary.
6.1.5.3 Flood
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
6.1.5.4 Hurricane
Stay calm and wait instruction for from the emergency control commander.
Immediately Move out of low – Lying area.
Stay calm and wait instruction for from the emergency control commander.
Stay indoors if possible and seek shelter.
Use dust mask.
In the event a suspected bomb is found on the project the following steps
must be taken:
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
bomb threat. For that reason, alternative Muster Points for bomb threats
should be considered.
o Additionally –time permitting – an advance ERT should check the area for
suspicious persons or objects before allowing the area to be used as the
Muster Point. Stand-Off Distances below are for open ground. Ideally
evacuated persons should be shielded by earth banks or other buildings.
1. Bring the EWP to the accident site and use it to reach the suspended
worker.
2. Ensure that the rescue team are wearing full-body harnesses and attached
to appropriate anchor points in the EWP.
3. Ensure that the EWP has the load capacity for the both rescuer(s) and the
fallen, worker. And if the fallen worker is not conscious, two rescuers will
probably be, needed to safely handle the weight of the fallen worker.
4. Position the EWP platform below the worker and disconnect the worker’s,
lanyard when it is safe to do so. When the worker is safely on the EWP
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
1. If the fallen worker suspended from the life-line, move the worker (if
possible to an area that rescuers can access safely with ladder.
2. Set up the appropriate ladder to reach the fallen worker.
3. Rig separate lifeline for rescuers to use while carrying out the rescue from
the ladder.
4. If the fallen worker is not conscious or cannot reliably help with the rescue
at least two rescuers may be handled.
5. If the fallen worker suspended directly from lanyard or lifeline. Securely
attach a separate lowering line to the harness.
6. Other rescuers on the ground (or closest work surface) should lower the
fallen worker while the rescuer on the ladder guides the fallen worker to
the ground (or work surface).
7. Once the fallen worker has been brought to a safe location, administer first
aid and treat the person for suspension trauma and any other injury.
8. Arrange transportation to the nearest hospital for further treatment if
required.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Objectives
To rescue an unconscious & injured person from inside the tanks
(confined space).
Hazards:
Toxic gasses, oxygen deficiency, hazardous chemical contact, slips trips &
falls, rotating equipment (agitators) high pressure drain lines.
Emergency Response
Sound the alarm and notify emergency commander & supervisor and
Rescue Team
Stop operation & follow the emergency procedures
Organize equipment & Pre use inspection
Organize rescue team and haul team
Get crane on standby if required.
Medic takes trauma kit to tank top area
1. Watchman Alert and call for HELP and assistance. In a case that IP is not
attached to SRL.
2. In a case that IP attached to SRL or rescue rope, start pulling the IP.
3. Incident commander Process and control the Scene.
4. Medic or Firs Aider Collect all emergency equipment to be utilized and process
Scene.
5. Ambulance driver prepare ambulance and proceed to the nearest point.
6. Two worker Collect basket stretcher and rescue rope to the accident area.
7. Rescue team Upon arrival at the scene: Follows Incident Commander
Instructions:
8. Ensure that gas testing done, check / verify reading. Send team for rescue to
worker from confined space.
9. Assigned and Authorized Gas tester. Report to the team gas reading. Continue
Gas monitoring.
10. Two worker wear full body harness and don SCBA and wait for instruction
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
11. Two workers shall enter in to confined space as per emergency commander
Instruction.
12. Hook up SRL at safety harness D ring / parachute ring and informed watchman
to start lifting by Beam with winch.
13. Recovery of IP or worker from confined space with the used of Tripod and
winch.
14. IP placed directly to the basket stretcher. Medic to supervise on IP handling.
15. Medic shall assess the IP and shall give First Aid and performed CPR. If
required
16. Using manual lifting or slide the stretcher through the outside the head or upper
part of the stretcher must be secured with rescue rope to support and provide
smooth slide.
17. The head of IP or person first to provide good position.
18. IP at the stretcher into ambulance for evacuation
EMERGENCY ACTIONS
1. One of the watch men shall inform the Emergency commander or supervisors
and the construction manager of any emergency in the confined space.
2. Commander shall activate the Confined Space Vertical Rescue Emergency
Response Procedure.
3. All operations at the scene of the incident shall be stopped.
4. The Safety Officer and the First Aiders shall activate the Rescue Team and
proceed to the scene of the incident.
5. The emergency commander shall call and inform the Project manager of the
incident. He shall remain in the office to answer any incoming calls.
6. After initial assessment of the situation, the First Aider shall decide whether or
not to activate the Medevac procedure as per Naizak Emergency Response
Plan.
7. The rescue team shall wear full body harness and don the SCBA’s (if
necessary) and enter the Confined Space
8. The First Aider shall make a quick assessment of injury of the IP and apply first
aid accordingly.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
9. The medic shall then direct the rescue team in placing the IP to the stretcher
basket, insuring that the IP is properly secured in it.
10. The IP shall then be pulled up the tank using the tripod and winch system. In
the event that the tripod system cannot be effectively used, the IP can be pulled
out using crane.
11. After extraction of the IP, he shall be transferred to a safe location for thorough
assessment and further emergency treatment by the First Aider or medic.
12. If necessary, the IP shall be brought to the hospital using the company
ambulance and accompanied by the medic.
13. The Construction manager shall make a first notice of incident (FNI) to be
submitted to the project Manager.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
8. If the victim conscious and trapped pass them a shovel so that they can
attempt to self-rescue.
9. Sheeting and shoring, entry and disentanglement operations may be
carried out under the direction and supervision Emergency Team
personnel.
10. Initiate atmospheric monitoring.
11. Move spoils pile as needed to provide at clear area for ground pads.
12. Conduct debris removal above to expose victim if possible.
Naizak shall ensure that a contingency plan in place with the steps required
addressing the events such as oil spills, security threats and disease outbreaks.
1. MVA
2. FIRE
3. CRANE COLLAPSES
4. SCAFFOLD COLLAPSES
5. BOMB THREAD
6. SEARCH AND RESCUE
7. HOSTILE ATTACK
8. Response Level:
The person who shall discover the emergency situation must reach in calm and
responsible manner. Inappropriate action may worsen the situation and delay the
immediate response of action to be made.
When emergency alarm is sounded for any person, all personnel shall
immediately shut down their job, make it safe and proceed in an orderly manner
to the designated assembly point.
Naizak periodically conducts emergency response drills to perform and evaluate
emergency response procedure. And all personnel are required to take part in
these drills just as if it were an actual emergency as mentioned above.
The HSE Department will endeavor to ensure that all persons on the site are made
aware of the requirements of the emergency procedures.
Initial training with all personnel and then follow up training will be schedule annually
to keep persons informed of any changes which may take place and ensure they
remain mindful of equipment.
Subjects:
Confined Space Entry.
Only especially trained and properly equipped shall responders may enter confined
space. Standby personnel must train in confined space entry rescue notification
procedure.
Refresher training in confined space shall be provided annually or as required due
to changes in work site condition.
1. Rescue Procedures.
Training should be including in recognition of atmospheric and physical hazards.
Responders must be trained in proper rescue technique and equipment must
conduct simulated rescue drills.
2. First Aid Procedure.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Naizak shall ensure the nonemergency response personnel receive training in the
actions to take during an emergency event. Training shall provide to emergency
management personnel including management, support, planning team and
response personnel to know their roles and responsibilities.
Naizak shall ensure all effected personnel including visitors are made fully aware
of the contents of the Emergency Response Procedures and receive information
and induction training.
Naizak shall ensure all Subcontractors HSE Managers who will be directly involved
in emergency management as an integral part of the Emergency Response
Training (ERT) have had suitable and sufficient training and shall ensure
Emergency Response Personnel participate in necessary training to develop the
skills and tactics required to respond to an emergency event.
Drilling and exercise are required for training personnel, testing equipment, and
ensuring the validity of the emergency response plan and procedure. The only way
to ensure that emergency response plan can effectively be implemented and is to
test
Those in regular drills against specific hazards scenario is to access the validity of
the arrangements.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Command Control
Communication
Coordination
Policy Making.
Resource Adequacy.
Resource and manpower Allocation.
Inter-Organization and Outside Agency Cooperation.
Naizak shall ensures that the emergency exercises and drills are conducted that
evaluate the effectiveness of training and adequacy of the ERP.
NOTE: Frequency of emergency drill in a monthly basis
Necessary and appropriate safety training courses required for worker are provided
for supervisors before starting work. The immediate job of preventing accidents falls
upon the supervisors, because of the accident prevention and production control,
are closely associated supervisors functions. The most direct way to develop the
desired attitudes and impart the necessary information about safety to supervisors
is to give them safety training. The safety training for supervisor shall include legal
requirements, company and administrative policies and safety aspects of the work
likely to be undertaken by the supervisors.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Safe training practices must be integrated into training for specific skills. It should be
expected that those workers who have attended the recognized training
establishments. Would have necessary safety instruction.
The Emergency control commander is the person responsible for all aspects of an
emergency response, including quick developing incident objectives, Managing for
all incident operations application of the resources as well as responsibility for all
persons involved, the emergency control commander sets priorities and define the
organization of the incident response teams and the overall incident action plan.
Type of incident
Location of accident
Possible number of injuries and types
Evacuation Status
Proceed to main office and based on information available assess the situation.
Direct all activities.
Notified the necessary and required external emergency response team.
Close down all switchboards for all calls except those related to the emergency.
If injuries are reported, direct Site Nurse to the location were needed this may
only be done if the Site Nurse’s own safety will not be at risk.
The emergency control commander is responsible to ensure the emergency
plan is reviewed from time to time to ensure actions remain current.
Report to SAPMT during emergency situation.
Assess the situation and directs action to minimize damage and injury.
Ensure post incident reviews are held within 48 hours post incident to discuss
emergency and identify response plan strengths and improvement opportunity.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
The role of the deputy emergency control commander is to undertake the duties
of emergency control commander if he’s not available.
Deputy Emergency Commander will support emergency control commander
from the start of emergency through to its conclusion. This is to ensure that in
the event the emergency control commander is required to relinquish his duty
and is to leave the site at any time during the emergency.
Provides firs aid treatment to client suffering from minor injuries, burns, cuts.
Bruises and abrasions.
Provides stabilization, resuscitation and other life support/ First aid measures
for injuries and illness
Operation various equipment and machines for emergency situation, response
and airway management.
Assesses and stabilizes conditions to improve vital functions of the patient
utilizing common sense and good clinical judgment which do not require
physician’s evaluation according to establish emergency guidelines
Keeps and maintains the treatment rooms and equipment to make it functional
and reliable, a well prepared emergency room as a whole.
Ensures proper care of casualties and establishes procedures to be followed in
event of serious injuries such as means of obtaining prompt medical and
ambulant service.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Transportation manager will arrange vehicle and equipment needed for emergency
Transportation and rescue operation.
The finance and administration is responsible for all financial (Administrative, and cost
analysis aspects of the incident.
Attend planning meeting as required.
Manage all aspects of the incident.
Provide financial and cost analysis information as required.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
The Fire Fighting commander is responsible for carrying out day to day tasks of
running a firefight team. Such tasks include supervising fire watchman /fire warden
and firefighters at an emergency scene and recruiting, training and equipping them
for their respective duties. The Fire Fighting Commander may also be involved in
the fire prevention, fire inspection, disaster preparedness, emergency medical
services.
In the event of fire, the fire crew team shall report directly to the emergency response
commander to receive orders and instructions. They shall respond to the need of
the situation such as fire suppression and rescue, and that firefighting equipment is
available on the scene.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Search and Rescue is the search for and provision of aid to people who are in
distress or imminent danger. The general field of search and rescue includes many
specialty sub-fields, typically determined by the types of terrain the search is
conducted over.
The Emergency Response Plan should receive a complete review and update at least
once a year. Partial updates should be performed after significant changes in the
facility’s design (process/equipment building layout, operation/hazards of site); after
drill/exercise and incidents, to update telephone numbers and emergency equipment
lists; and to address personnel changes within the organization.
The emergency evacuation plan shall be displayed on safety Bulletin Board and shall
be distributed to each department.
Action to be taken
When emergency condition exist or on hearing the “STOP WORK ALARM) every
supervisor shall ensure the following:
Help in Emergency
In the event of an emergency situation (serious personal injury, fire, critical damage
to operating equipment, etc.) help may be obtained by contacting This may be
done:
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Note: NAIZAK will keep always update Emergency Contact Numbers list if any changes
in the list.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
16. APPENDICES
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Provide detailed description of units / equipment involved, as well as possible effects on them, on personnel, on
other units / equipment, outside the fence, etc.
A worker was using grinder in the laydown area at around 8:45am. The worker doesn’t have permit
and fire watchman even without fire extinguisher etc., so, the sparks which was generated from the grinder
was created a fire due to improper housekeeping of the area. Nearby coworker shouted “fire, fire & fire” and
the safety officer of the area was responded assess the scene and activated fire alarm and drive all the people
towards to nearest Assembly point area. Firefighting and ERT team were informed. Upon arrival on the
fire location started to Extinguish the fire.
B. Possible Causes
List all possible causes. This will help in identifying preventive measures.
1. No work permit
2. Lack of competent supervision by Engineer
3. No available fire watchman
4. Untrained / improper trained grinder operator.
5. Work pressure
6. No fire safety training
7. Using without safe guard
8. Poor housekeeping
Provide estimate of the size, areas affected, and duration of the emergency
1. Temporary stoppage of all construction activities for an hour resulting delay in work activities.
2. Loss of time to clean the burned area.
3. The grinder user cannot work properly due to psychological stress.
4. Time consumed for stand down safety meeting to all worker to discuss the incident.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
D. Effect on operations
List all possible effects on involved operations (including up and downstream) that may be affected.
1. Loss of time again to purchase and replacement of materials which was burned along with fire, materials
and equipment in laydown area being loss to the fire.
2. Delay in the construction activities due to non-availability of materials and equipment.
3. Time consumed for the investigation process by investigating team.
3. Stoppage of work day/s
4. Delay of works due to possible suspension of the worker. Loss of time for his replacement.
5. Closure of business at worst cases. Loss of job for their employees.
6. Loss of company reputation in market.
Identify specific locations and equipment involved and provide information on this items that may intensify the
situation and information that may need to be known by the responders (restricted access, quantities, and
locations of hazardous materials stored in the affected area, etc.)
1. Limited working area
2. Working at material storage area.
3. Poor housekeeping and material arrangement in the laydown area.
4. Failure to identify hazards.
F. Preventive Measures
Identify existing preventive measures in place and determine additional measures (engineering controls, etc.)
That might be put in effect.
Permit to work system is in place in the worksite. - Site engineers / Foremen shall acquire permit
to work for hot works activities to ensure all
precautions are in place.
Fire watchman is present on site. - Grinder user shall ensure to have a fire
watchman during performing grinding (hot
works) activities.
- Fire watchman shall be trained and to stay in
the work area 30 min after hot works was
Completed for site inspection.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
G. Initial Response
1. Call Naizak Emergency Response Team and call Naizak HSE Manager.
2. Naizak HSE Manager established contact with SAPMT and Naizak PM (EPC).
4. Naizak PM (EPC) call 911 (from a Saudi Aramco Telephone); 013-XXX-0911 (from outside phone or
mobile phone).
4. On-site Emergency Response Team leader to assess the situation and report to PM (EPC).
5. Unauthorized personal / workers are not allowed to enter the scene / location of the incident.
6. Investigation shall be conducted.
Information in this section shall be provided by the pre-incident plan team, which includes personnel from
applicable response and support organizations to develop and execute pre-incident plans. Identify all human and
material resources required, as well as those available, and provide recommendations for upgrades as required.
Resources Required Resources Available
Naizak Ambulance, ERT and Medical Team (Male Nurse, 1 Ambulance with First Aider
First Aider, ERT members).
Aramco Ambulance and medical team Call 911 (from a Saudi Aramco Telephone);
013-XXX- 0911 (from outside phone or
mobile phone).
Traffic Road Safety signs, lightings (Ice tower lights, flash Arranged on site as required.
lights).
Flagman controller / flagmen Trained and designated flagman on site.
Firefighting equipment i.e. fire extinguishers Must always in good condition, prepared and
arranged on site.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
First aid supplies, devices and other required medical Provided on site.
equipment.
Traffic road safety barriers i.e. safety cones, warning Provided on site.
tapes
Personal Protective Equipment (PPE). Provided on site.
Recommendations
Add all organizations that should review the Scenario Analysis Worksheet for comments / input on items A-H and
for identification of needed responses.
1. SAPMT
2. Naizak ERT / EPC
Assess risk / severity and probability of occurrence and assign a ranking to prioritize scenario.
Probability Consequences Ranking
1=most likely; 5=least likely 1=most severe; 5=least Probability X
severe Consequences
2 3 6
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
16.10 Scenario 2
Emergency Scenario Fall from Height Special Action Fire Alarm / Emergency
Siren
Provide detailed description of units / equipment involved, as well as possible effects on them, on personnel, on
other units / equipment, outside the fence, etc.
A worker who is working at height was trying to get down from a scaffold working platform at around 11:30
am at site, in this process due to misperception he missed the three point of contact got slipped and fell
down which was resulted an injury to his right leg. Immediately his coworker called his supervisor and
alerts the remaining team as well whereas the nearby safety officer raises the alarm of concern area and
informed ERT Team and medical team for further action. Upon arrival of medical team had given first aid
and send to the nearest hospital by Naizak Ambulance for further treatment.
B. Possible Causes
List all possible causes. This will help in identifying preventive measures.
1. No work permit
2. Lack of competent supervision by supervisor
3. No available of proper method statement & JSA
4. Untrained / improper trainer for work at height.
5. Inadequate scaffold & ladder fixing.
6. Misperception
7. Poor housekeeping
8. Work pressure / hurry on job.
9. Improper usage of PPE.
Provide estimate of the size, areas affected, and duration of the emergency
1. Temporary stoppage of all construction activities at the area for an hour resulting delay in work
activities.
2. Loss of time to clear the area.
3. The worker cannot work properly due to psychological stress.
4. Time consumed for stand down safety meeting to all worker to discuss the incident.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
D. Effect on operations
List all possible effects on involved operations (including up and downstream) that may be affected.
1. Loss of time again to erect and replacement of materials at incident area, erection of safe
working platform.
2. Delay in the construction activities due to non-availability of materials.
3. Time consumed for the investigation process by investigating team.
4. Stoppage of work day/s.
5. Delay of works due to possible suspension of the worker. Loss of time for his replacement.
6. Closure of business at worst cases. Loss of job for the employees.
7. Loss of company reputation in market.
Identify specific locations and equipment involved and provide information on this items that may intensify the
situation and information that may need to be known by the responders (restricted access, quantities, and
locations of hazardous materials stored in the affected area, etc.)
1. Limited working area
2. Working on unsafe / congested area.
3. Poor housekeeping.
4. Failure to identify hazards.
F. Preventive Measures
Identify existing preventive measures in place and determine additional measures (engineering controls, etc.)
that might be put in effect.
Permit to work system is in place in the worksite. - Site engineers / Foremen shall acquire permit
to work for hot works activities to ensure all
precautions are in place.
Work at height training done. - All the workers involved in work at height
works shall be trained at work at height training
including supervisor and foreman.
Safe scaffolding / work platform. - Make sure an adequate safe working platform
is available at site.
- Ensure all scaffolds and working platforms shall
be inspected regularly by a competent person.
Proper / safe ladder fixing. - Make sure to have and fixed a ladder as per the
requirements.
- All ladders shall be inspected frequently.
- Avoid using damaged ladders.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Competent site engineers / foremen are on site. - Site engineers / foremen shall ensure to
provide competent site supervision for all
working at height activities.
G. Initial Response
1. Call Naizak Emergency Response Team and call Naizak HSE Manager.
2. Naizak Manager established contact with SAPMT and Naizak PM (EPC).
3. Naizak PM (EPC) call 911 (from a Saudi Aramco Telephone); 013-XXX- 0911 ( from outside phone
or mobile phone).
4. On-site Emergency Response Team leader to assess the situation and report to PM (EPC).
5. Unauthorized personal / workers are not allowed to enter the scene / location of the incident.
6. Investigation shall be conducted.
Information in this section shall be provided by the pre-incident plan team, which includes personnel from
applicable response and support organizations to develop and execute pre-incident plans. Identify all human and
material resources required, as well as those available, and provide recommendations for upgrades as required.
Resources Required Resources Available
Naizak Ambulance, ERT and Medical Team (Male Nurse, 1 Ambulance with First Aider
First Aider, ERT members).
Aramco Ambulance and medical team Call 911 (from a Saudi Aramco Telephone); 013-
XXX- 0911 (from outside phone or mobile
phone).
Traffic Road Safety signs, lightings (I, e tower lights, flash Arranged on site as required.
lights).
Flagman controller / flagmen Trained and designated flagman on site.
Firefighting equipment i.e. fire extinguishers Must always in good condition, prepared and
arranged on site.
First aid supplies, devices and other required medical Provided on site.
equipment.
Traffic road safety barriers i.e. safety cones, warning Provided on site.
tapes
Personal Protective Equipment (PPE). Provided on site.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Recommendations
I. Key affected response. And support organization review
Add all organizations that should review the Scenario Analysis Worksheet for comments / input on items A-H and
for identification of needed responses.
1. SAPMT
2. Naizak ERT / EPC
Assess risk / severity and probability of occurrence and assign a ranking to prioritize scenario.
Probability Consequences Ranking
1=most likely; 5=least likely 1=most severe; 5=least Probability X
severe Consequences
2 3 6
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
16.11 Scenario 3
Provide detailed description of units / equipment involved, as well as possible effects on them, on personnel, on
other units / equipment, outside the fence, etc.
It has been reported that at 9:00 pm, some of our workers have fallen ill after eating meal of the food
supplier at our Camp. There are fears that the number of illness could rise as all of our employees had the
same food. A coworker and the room partner of the victim immediately call & explained the camp
supervisor and the camp supervisor alert all personal who stays in the camp by raising the alarm and driving
all towards to Assembly point. The camp supervisor informed the same to safety supervisor and ERT team
along with medical team for further action. The medical team immediately given first aid and taken to
hospital those victims for further treatment. An investigation is underway, but early indications suggest that
the food was contaminated. It is suspected that the vegetable or rice served contaminated residues of
this toxic substance.
B. Possible Causes
List all possible causes. This will help in identifying preventive measures.
1. Raw materials contain harmful micro-organisms.
2. Lack of competent supervision.
3. Harmful micro-organisms grow and procedure toxic during processing.
4. Untrained / improper training.
5. Harmful micro-organisms or toxins survive after heating.
6. Food contains harmful chemicals.
7. Poor hygienic practices.
8. Food contains extraneous physical objects.
Provide estimate of the size, areas affected, and duration of the emergency
1. Temporary stoppage of food supply.
5. Loss of time to clear the area.
6. The workers cannot work properly due to psychological stress.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
7. Time consumed for stand down safety meeting to all worker to discuss the incident.
D. Effect on operations
List all possible effects on involved operations (including up and downstream) that may be affected.
1. Loss of time again to arrange replacement of food supplier.
2. Loss of health
3. Time consumed for the investigation process by investigating team.
4. Stoppage of work day/s.
5. Delay of works due to possible suspension of the worker. Loss of time for his replacement.
6. Closure of business at worst cases. Loss of job for the employees.
7. Loss of company reputation in market.
8. Loss of money and trust with insurance.
Identify specific locations and equipment involved and provide information on this items that may intensify the
situation and information that may need to be known by the responders (restricted access, quantities, and
locations of hazardous materials stored in the affected area, etc.)
1. Storage, cooking, packing area.
2. Preparing food in unhygienic area.
3. Poor housekeeping.
4. Failure to identify hazards.
F. Preventive Measures
Identify existing preventive measures in place and determine additional measures (engineering controls, etc.)
that might be put in effect.
Using reputable suppliers. - Products bought from approved / licensed and
reputable suppliers.
Adequate freezing or chilling - Frozen / chilled foods should start at -18 to 4”
degrees.
Using proper ways to thaw frozen foods. - Frozen foods should thaw under refrigeration at 8
degree or below.
- Cool running water in waterproof package.
Cooking thoroughly - During cooking the core food temperature
should reach 75 degree or above.
Proper cooling. - Keep hot foods at 63 degree or above.
- Cold foods at 4 degrees or below and make sure
the consumption in two hours.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Transport and delivery - Delivery vehicles are clean and hygienic and are not
used for the transport of chemicals.
- Deliver persons have good personal hygiene
practices.
G. Initial Response
1. Call Naizak Emergency Response Team and call Naizak HSE Manager.
2. Naizak Manager established contact with SAPMT and Naizak PM (EPC).
3. Naizak PM (EPC) call 911 (from a Saudi Aramco Telephone); 013-XXX- 0911 (from outside phone
or mobile phone).
4. On-site Emergency Response Team leader to assess the situation and report to PM (EPC).
5. Unauthorized personal / workers are not allowed to enter the scene / location of the incident.
6. Investigation shall be conducted.
Information in this section shall be provided by the pre-incident plan team, which includes personnel from
applicable response and support organizations to develop and execute pre-incident plans. Identify all human and
material resources required, as well as those available, and provide recommendations for upgrades as required.
Resources Required Resources Available
Naizak Ambulance, ERT and Medical Team (Male Nurse, 1 Ambulance with First Aider
First Aider, ERT members).
Aramco Ambulance and medical team Call 911 (from a Saudi Aramco Telephone); 013-
XXX- 0911 (from outside phone or mobile
phone).
Purchase of raw material for food Raw materials obtained from approved /
licensed and reputable suppliers.
Make sure the products meet safety and
quality specifications with food safety
management systems.
Receiving of materials Avoid receiving the damaged packaging and
contaminated.
Storage area A clean and hygienic storage area shall be
used.
Make sure pest control done frequently.
Preparation & food Use appropriate methods of cooking according
food safety management system.
Avoid reheating of food.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Recommendations
I. Key affected response. And support organization review
Add all organizations that should review the Scenario Analysis Worksheet for comments / input on items A-H and
for identification of needed responses.
1. SAPMT
2. Naizak ERT / EPC
Assess risk / severity and probability of occurrence and assign a ranking to prioritize scenario.
Probability Consequences Ranking
1=most likely; 5=least likely 1=most severe; 5=least severe Probability X Consequences
2 3 6
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
16.12 Scenario 4
Provide detailed description of units / equipment involved, as well as possible effects on them, on
personnel, on other units / equipment, outside the fence, etc.
A worker who was working in confined space at around 2 pm, it has been reported that the worker
found collapsed and unconscious. Immediately nearby coworker called and explained the incident to
his supervisor and as well as the area safety officer. So, the area safety officer immediately alert other
employees working in the same area and drive them towards Assembly point and reported the same
to HSE Supervisor as well as medical team for further action. Upon arrival of Emergency Response
team and medical team took him to Ambulance and given first aid and them sent immediately to the
nearest hospital for further treatment.
B. Possible Causes
List all possible causes. This will help in identifying preventive measures.
1. No work permit
2. Lack of competent supervision by supervisor
3. No available of proper method statement & JSA
4. Untrained / improper trained for work in confined space works.
5. Inadequate entry and exit.
6. Failure to notify the risk.
7. Poor housekeeping
8. Improper usage of PPE.
9. Hazardous atmosphere.
Provide estimate of the size, areas affected, and duration of the emergency
1. Temporary stoppage of all construction activities at the area for an hour / more resulting delay in
work activities.
2. Loss of time to clear the area.
3. The worker cannot work properly due to psychological stress.
4. Time consumed for stand down safety meeting to all worker to discuss the incident.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
D. Effect on operations
List all possible effects on involved operations (including up and downstream) that may be affected.
Loss of time again to erect and replacement of materials at incident area and have a safe method
of confined space entry.
Delay in the construction activities due to non-availability of area entry.
Time consumed for the investigation process by investigating team.
Stoppage of work day/s until has safety work system in confined space.
Delay of works due to possible suspension of the worker. Loss of time for his replacement.
Closure of business at worst cases. Loss of job for the employees.
Loss of company reputation in market.
Identify specific locations and equipment involved and provide information on this items that may intensify
the situation and information that may need to be known by the responders (restricted access, quantities,
and locations of hazardous materials stored in the affected area, etc.)
Limited entry & exit of working area
Unsafe act & condition as well.
Poor housekeeping.
Failure to identify hazards.
Lack of awareness
Lack of permit & watch man
F. Preventive Measures
Identify existing preventive measures in place and determine additional measures (engineering controls,
etc.) that might be put in effect.
Permit to work system is in place in the worksite. - Site engineers / Foremen shall acquire
permit to work for hot works activities in
confined space to ensure all
precautions are in place.
Work in confined space training. - All the workers involved in work in
confined space shall be trained including
supervisor and foreman.
- Required personal protective equipment
shall be provided.
Safe entry & exit (safe system of work). - Make sure an adequate safe work system
is in place.
- Ensure a proper entry and exit is
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
available.
Fire watch person & Gas test. - A well trained and experienced watch
person is available at all times.
- Make sure a proper gas test shall be done
prior to start the job and after every 30
minutes and maintained a log as well.
Competent site engineers / foremen are on site - Site engineers / foremen shall ensure to
provide competent site supervision for
all Confined space activities.
G. Initial Response
1. Call Naizak Emergency Response Team and call Naizak HSE Manager.
2. Naizak Manager established contact with SAPMT and Naizak PM (EPC).
3. Naizak PM (EPC) call 911 (from a Saudi Aramco Telephone); 013-XXX- 0911 (from outside phone
or mobile phone).
4. On-site Emergency Response Team leader to assess the situation and report to PM (EPC).
5. Unauthorized personal / workers are not allowed to enter the scene / location of the incident.
6. Investigation shall be conducted.
Information in this section shall be provided by the pre-incident plan team, which includes personnel from
applicable response and support organizations to develop and execute pre-incident plans. Identify all human
and material resources required, as well as those available, and provide recommendations for upgrades as
required.
Resources Required Resources Available
Naizak Ambulance, ERT and Medical Team (Male Nurse, 1 Ambulance with Nurse & First Aider
First Aider, ERT members).
Aramco Ambulance and medical team Call 911 (from a Saudi Aramco Telephone 013-
XXX- 0911 (from outside phone or mobile
phone).
Special tools and equipment’s. Arranged Saudi Aramco approved gas tester.
PPE such as respirator, harness and lanyard,
gloves Communication equipment radio etc.
Lifting equipment for rescue.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Traffic Road Safety signs, lightings (I, e tower lights, flash Arranged on site as required to avoid
lights). inconvenience during ambulance usage.
Watch person Trained and designated flagman on site.
Firefighting equipment i.e. fire extinguishers Must always in good condition, prepared and
arranged on site.
First aid supplies, devices and other required medical Provided on site.
equipment.
Traffic road safety barriers i.e. safety cones, warning Provided on site.
tapes
Personal Protective Equipment (PPE). Provided on site.
Recommendations
I. Key affected response. And support organization review
Add all organizations that should review the Scenario Analysis Worksheet for comments / input on items A-
H and for identification of needed responses.
1. SAPMT
2. Naizak ERT / EPC
Assess risk / severity and probability of occurrence and assign a ranking to prioritize scenario.
Probability Consequences Ranking
1=most likely; 5=least likely 1=most severe; 5=least Probability X
severe Consequences
2 3 6
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
16.13 Scenario 5
Provide detailed description of units / equipment involved, as well as possible effects on them, on personnel,
on other units / equipment, outside the fence, etc.
At around 10 am on site in one of the location some excavation work doing by an excavator, during the
excavation the operator was not noticed that the base of the equipment is so close to the excavation which
is resulted that the equipment collapse in the excavation resulted an injury of the operator and damage of the
equipment as well. The coworker immediately called and explained the incident to his supervisor as well as
the area safety officer. So, immediately the safety officer raises an alarm of the concern area and advice the
people approach Assembly point of that area and then reported to ERT along with medical team for further
action. The ERT and medical team arrived immediately taken the operator into Ambulance and given
first aid and then sent to hospital for further treatment.
B. Possible Causes
List all possible causes. This will help in identifying preventive measures .
No work permit
Lack of competent supervision by supervisor
No available of proper method statement & JSA
Untrained / improper trained for work as operator.
Unsafe act.
Failure of equipment.
Poor housekeeping
Improper usage of PPE.
Hazardous atmosphere.
Provide estimate of the size, areas affected, and duration of the emergency
Temporary stoppage of all construction activities at the area for an hour / more resulting delay in
work activities.
Loss of time to clear the area.
The operator cannot work properly due to psychological stress.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Time consumed for stand down safety meeting to all worker to discuss the incident.
D. Effect on operations
List all possible effects on involved operations (including up and downstream) that may be affected.
Loss of time again to erect and replacement of materials at incident area.
Delay in the construction activities due to non-availability of area entry.
Time consumed for the investigation process by investigating team.
Stoppage of work day/s, until have safe work system.
Delay of works due to possible suspension of the operator. Loss of time for his
replacement.
Closure of business at worst cases. Loss of job for the employees.
Loss of company reputation in market.
Identify specific locations and equipment involved and provides information on this items that may
intensify the situation and information that may need to be known by the responders (restricted access,
quantities, and locations of hazardous materials stored in the affected area, etc.)
Lack of maintenance plan
Unsafe act & condition as well.
Poor housekeeping.
Failure to identify hazards.
Lack of awareness
Lack of permit & watch man
F. Preventive Measures
Identify existing preventive measures in place and determine additional measures (engineering controls,
etc.) that might be put in effect.
Permit to work system is in place in the worksite. - Site engineers / Foremen shall acquire
permit to work for hot works activities
to ensure all precautions are in place.
Heavy equipment operator training. - All the operators at work shall be
trained in safety driving and defensive
driving.
- Avoid using heavy equipment nearby
any excavation.
Flag man - Make sure a trained flag man is available
with all heavy equipment during work.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
G. Initial Response
1. Call Naizak Emergency Response Team and call Naizak HSE Manager.
2. Naizak Manager established contact with SAPMT and Naizak PM (EPC).
3. Naizak PM (EPC) call 911 (from a Saudi Aramco Telephone); 013-XXX- 0911 (from
outside phone or mobile phone).
4. On-site Emergency Response Team leader to assess the situation and report to PM (EPC).
5. Unauthorized personal / workers are not allowed to enter the scene / location of the incident.
6. Investigation shall be conducted.
Information in this section shall be provided by the pre-incident plan team, which includes personnel from
applicable response and support organizations to develop and execute pre-incident plans. Identify all human
and material resources required, as well as those available, and provide recommendations for upgrades as
required.
Resources Required Resources Available
Naizak Ambulance, ERT and Medical Team (Male Nurse, 1 Ambulance with Nurse & First Aider
First Aider, ERT members).
Aramco Ambulance and medical team Call 911 (from a Saudi Aramco Telephone); 013-
XXX- 0911 (from outside phone or mobile
phone).
Special tools and equipment’s. Arranged Saudi Aramco approved operator.
A proper equipment maintenance plan should
maintain.
Traffic Road Safety signs, lightings (I, e tower lights, flash Arranged on site as required to avoid
lights). inconvenience during ambulance usage.
Watch person Trained and designated flagman on site.
Firefighting equipment i.e. fire extinguishers Must always in good condition, prepared and
arranged on site.
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
First aid supplies, devices and other required medical Provided on site.
equipment.
Traffic road safety barriers i.e. safety cones, warning Provided on site.
tapes
Personal Protective Equipment (PPE). Provided on site.
Recommendations
I. Key affected response. And support organization review
Add all organizations that should review the Scenario Analysis Worksheet for comments / input on items A-
H and for identification of needed responses.
1. SAPMT
2. Naizak ERT / EPC
Assess risk / severity and probability of occurrence and assign a ranking to prioritize scenario.
Probability Consequences Ranking
1=most likely; 5=least likely 1=most severe; 5=least Probability X
severe Consequences
2 3 6
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Type of Emergency:
Fire Hazardous Material
Security/Hostile Medical
Motor Vehicle X Natural Disaster
Accident
Explosion
A. Description of the Scenario:
B. Possible Causes:
(List all possible causes; this will help in identifying preventive measures.)
No excavation plan
No shoring provided
Not appropriate sloping
Heavy Equipment vibration
C. Expected Size, Areas Affected, and Duration:
(Provide estimates of the size, the areas affected, and duration of the emergency.)
(List all possible effects on involved operations [including up & downstream] that may be affected.)
E. Location-specific/Equipment-specific Notes:
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
(Identify specific locations and equipment involved and provide information on items that may intensify the situation and information that
may need to be known by responders [restricted access; types, quantities, and locations of hazardous materials stored in the affected
area; etc.].)
(Identify existing preventive measures in place and determine additional measures [engineering controls, etc.] that might be put into
effect.)
Comments Recommendations
G. Initial Response:
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
(Information in this section shall be provided by the pre-incident plan team, which includes personnel from applicable
response and support organizations to develop and execute pre-incident plans. Identify all human and material resources
required, as well as those available, and provide recommendations for upgrades as required.)
(Add all organizations that should review the Scenario Analysis Worksheet for comments/input on items A-H and for
identification of needed responses.)
SA PMT
SA Proponent
SA PMT and Proponent Contractors
J. Evaluation and Ranking:
(Assess risk [severity and probability of occurrence] and assign a ranking to prioritize scenarios.)
(1=most likely; 5=least likely) (1=most severe; 5=least severe) (Probability x Consequences)
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Type of Emergency:
Fire X Hazardous Material
Security/Hostile Medical
Motor Vehicle Natural Disaster
Accident
Explosion
A. Description of the Scenario:
During the Generator tank refueling in TCF area, Diesel fuel overflowed and spilled and
contaminating the ground soil.
B. Possible Causes:
(List all possible causes; this will help in identifying preventive measures.)
(Provide estimates of the size, the areas affected, and duration of the emergency.)
(List all possible effects on involved operations [including up & downstream] that may be affected.)
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
(Identify specific locations and equipment involved and provide information on items that may intensify the situation and information that
may need to be known by responders [restricted access; types, quantities, and locations of hazardous materials stored in the affected
area; etc.].)
Generator station fuel tank storage area – lid cover not closed
Diesel fuel tanker truck- hose fittings and motor pump poor conditions
F. Preventive Measures:
(Identify existing preventive measures in place and determine additional measures [engineering controls, etc.] that might be put into
effect.)
Comments Recommendations
Wear appropriate PPE Contractor supervision must be well trained and held
Labeling signs and tags. accountable for their subordinates.
Tool box talk meeting All contractors should ensure all workers receive
Following Safety instructions adequate
Inadequate enforcement of SA procedures Safety orientation and continuous training on SA
Inadequate training requirements.
No Contractor stop work policy All contractors should implement and train workers on
Monitor the wind speed stop work policy and empower each worker to be able
to stop unsafe work.
Wind speed detector shall be available with operator at
all times monitored.
G. Initial Response:
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
(Information in this section shall be provided by the pre-incident plan team, which includes personnel from applicable
response and support organizations to develop and execute pre-incident plans. Identify all human and material resources
required, as well as those available, and provide recommendations for upgrades as required.)
(Add all organizations that should review the Scenario Analysis Worksheet for comments/input on items A-H and for
identification of needed responses.)
SA PMT
SA Proponent
SA PMT and Proponent Contractors
J. Evaluation and Ranking:
(Assess risk [severity and probability of occurrence] and assign a ranking to prioritize scenarios.)
(1=most likely; 5=least likely) (1=most severe; 5=least severe) (Probability x Consequences)
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Type of Emergency:
X Fire Hazardous Material
Security/Hostile Medical
Motor Vehicle Natural Disaster
Accident
Explosion
A. Description of the Scenario:
Bus driver noticed smoke & fire getting out from the bus engine when he switched on the engine and
passengers inside have to go out immediately outside and expected to proceed to assembly area.
B. Possible Causes:
(List all possible causes; this will help in identifying preventive measures.)
(Provide estimates of the size, the areas affected, and duration of the emergency.)
Warehouse and laydown area, Materials area, Clinic and TCF offices
D. Effect on Operations:
(List all possible effects on involved operations [including up & downstream] that may be affected.)
Work stopped or delayed start of work in the area, equipment and material damages, burn injury
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
E. Location-specific/Equipment-specific Notes:
(Identify specific locations and equipment involved and provide information on items that may intensify the situation and information that
may need to be known by responders [restricted access; types, quantities, and locations of hazardous materials stored in the affected
area; etc.].)
(Identify existing preventive measures in place and determine additional measures [engineering controls, etc.] that might be put into
effect.)
Fire extinguishers, water, fire blankets, sands, PPE, area isolation materials and signages
Comments Recommendations
G. Initial Response:
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
(Information in this section shall be provided by the pre-incident plan team, which includes personnel from applicable
response and support organizations to develop and execute pre-incident plans. Identify all human and material resources
required, as well as those available, and provide recommendations for upgrades as required.)
(Add all organizations that should review the Scenario Analysis Worksheet for comments/input on items A-H and for
identification of needed responses.)
SA PMT
SA Proponent
SA PMT and Proponent Contractors
J. Evaluation and Ranking:
(Assess risk [severity and probability of occurrence] and assign a ranking to prioritize scenarios.)
(1=most likely; 5=least likely) (1=most severe; 5=least severe) (Probability x Consequences)
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
4 Stretcher Available
6 Ambulance Available
7 Mannequin Available
11 Loudspeakers/Megaphone Available
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Location:
Mobile No.:
Manager: Samer Khaleel Shahin 0541499020
Level 1 Contact:
Work Home
SN Name Position Mobile No.
Tel. Tel Remarks
Level 2 Contact:
Work Home
SN Name Position Mobile No.
Tel. Tel Remarks
Level 3 Contact:
Work Home
SN Name Position Mobile No.
Tel. Tel Remarks
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780
Contract No.
CHAPTER TITLE EMERGENCY RESPONSE PLAN BI-10-13202-0001 REV. 00
6600050780