National foreword
This British Standard is the UK implementation of EN ISO 19650‑3:2020.
It is identical to ISO 19650‑3:2020.
The technical content of this BS EN ISO 19650-3 is intended as a
replacement for content found in PAS 1192‑3:2014, which is withdrawn.
The UK participation in its preparation was entrusted to Technical
Committee B/555, Construction design, modelling and data exchange.
A list of organizations represented on this committee can be obtained on
request to its committee manager.
This publication does not purport to include all the necessary provisions
of a contract. Users are responsible for its correct application.
© The British Standards Institution 2020
Published by BSI Standards Limited 2020
ISBN 978 0 539 00172 3
ICS 35.240.67; 91.010.01; 93.010
Compliance with a British Standard cannot confer immunity from
legal obligations.
This British Standard was published under the authority of the
Standards Policy and Strategy Committee on 31 August 2020.
English Version
CEN members are bound to comply with the CEN/CENELEC Internal Regulations which stipulate the conditions for giving
this European Standard the status of a national standard without any alteration. Up-to-date lists and bibliographical
references concerning such national standards may be obtained on application to the CEN-CENELEC Management Centre
or to any CEN member.
This European Standard exists in three official versions (English, French, German). A version in any other language
made by translation under the responsibility of a CEN member into its own language and notified to the CEN-CENELEC
Management Centre has the same status as the official versions.
CEN members are the national standards bodies of Austria, Belgium, Bulgaria, Croatia, Cyprus, Czech Republic, Denmark,
Estonia, Finland, France, Germany, Greece, Hungary, Iceland, Ireland, Italy, Latvia, Lithuania, Luxembourg, Malta,
Netherlands, Norway, Poland, Portugal, Republic of North Macedonia, Romania, Serbia, Slovakia, Slovenia, Spain, Sweden,
Switzerland, Turkey and United Kingdom.
© 2020 CEN All rights of exploitation in any form and by any means reserved Ref. No. EN ISO 19650‑3:2020: E
worldwide for CEN national Members
BS EN ISO 19650‑3:2020
EN ISO 19650‑3:2020 (E)
European foreword
This document (EN ISO 19650‑3:2020) has been prepared by Technical Committee ISO/TC 59 "Buildings
and civil engineering works" in collaboration with Technical Committee CEN/TC 442 “Building
Information Modelling (BIM)” the secretariat of which is held by SN.
This European Standard shall be given the status of a national standard, either by publication of an
identical text or by endorsement, at the latest by February 2021, and conflicting national standards
shall be withdrawn at the latest by February 2021.
Attention is drawn to the possibility that some of the elements of this document may be the subject of
patent rights. CEN shall not be held responsible for identifying any or all such patent rights.
According to the CEN-CENELEC Internal Regulations, the national standards organizations of the
following countries are bound to implement this European Standard: Austria, Belgium, Bulgaria,
Croatia, Cyprus, Czech Republic, Denmark, Estonia, Finland, France, Germany, Greece, Hungary, Iceland,
Ireland, Italy, Latvia, Lithuania, Luxembourg, Malta, Netherlands, Norway, Poland, Portugal, Republic
of North Macedonia, Romania, Serbia, Slovakia, Slovenia, Spain, Sweden, Switzerland, Turkey and the
United Kingdom.
Endorsement notice
The text of ISO 19650‑3:2020 has been approved by CEN as EN ISO 19650‑3:2020 without any
modification.
ii
BS EN ISO 19650‑3:2020
ISO 19650‑3:2020
Contents Page
Foreword...........................................................................................................................................................................................................................................v
Introduction................................................................................................................................................................................................................................. vi
1 Scope.................................................................................................................................................................................................................................. 1
2 Normative references....................................................................................................................................................................................... 1
3 Terms, definitions, and symbols........................................................................................................................................................... 1
3.1 Terms and definitions........................................................................................................................................................................ 1
3.2 Symbols for process diagrams.................................................................................................................................................... 2
4 Information management associated with the operational phase of assets.......................................... 2
4.1 Information management process associated with the operational phase of assets................. 2
4.2 Relationship between this document and ISO 19650‑2....................................................................................... 4
5 Information management process to support the operational phase of assets.................................. 4
5.1 Information management process — assessment and need........................................................................... 4
5.1.1 Appoint individuals to undertake the information management function.................... 4
5.1.2 Establish organizational information requirements......................................................................... 4
5.1.3 Identify the assets for which information shall be managed..................................................... 5
5.1.4 Establish the asset information requirements........................................................................................ 5
5.1.5 Identify the foreseeable trigger events for which information shall
be managed........................................................................................................................................................................... 5
5.1.6 Establish the asset information standard................................................................................................... 6
5.1.7 Establish the asset information production methods and procedures............................. 6
5.1.8 Establish the reference information and shared resources......................................................... 6
5.1.9 Establish the common data environment................................................................................................... 7
5.1.10 Establish links to enterprise systems............................................................................................................. 7
5.1.11 Establish the asset information model.......................................................................................................... 7
5.1.12 Establish processes to maintain the AIM..................................................................................................... 8
5.1.13 Establish the asset information protocol..................................................................................................... 8
5.1.14 Activities for assessment and need................................................................................................................... 9
5.2 Information management process — Invitation to tender/request to provide service........... 9
5.2.1 Decide the type of activity providing information............................................................................... 9
5.2.2 Establish the appointing party’s exchange information requirements.......................... 10
5.2.3 Assemble reference information and shared resources.............................................................. 10
5.2.4 Establish response requirements and evaluation criteria......................................................... 10
5.2.5 Compile information for the invitation to tender/request to provide service......... 11
5.2.6 Activities for invitation to tender/request to provide service............................................... 11
5.3 Information management process — Response to invitation to tender/request to
provide service...................................................................................................................................................................................... 12
5.3.1 Nominate individuals to undertake the information management function............. 12
5.3.2 Establish the delivery team’s (pre-appointment) BIM execution plan........................... 12
5.3.3 Assess task team capability and capacity................................................................................................. 12
5.3.4 Establish the delivery team’s capability and capacity................................................................... 13
5.3.5 Establish the delivery team’s mobilization plan................................................................................. 13
5.3.6 Establish the delivery team’s risk register.............................................................................................. 13
5.3.7 Compile the delivery team’s response......................................................................................................... 13
5.3.8 Activities for response to invitation to tender/request to provide service................ 14
5.4 Information management process — Appointment............................................................................................ 14
5.4.1 Confirm the delivery team’s BIM execution plan............................................................................... 14
5.4.2 Establish the delivery team’s detailed responsibility matrix.................................................. 15
5.4.3 Establish the lead appointed party’s EIR (ISO 19650‑3)............................................................ 15
5.4.4 Establish the task information delivery plan(s)................................................................................. 15
5.4.5 Establish the master information delivery plan................................................................................. 15
5.4.6 Complete lead appointed party’s appointment................................................................................... 16
5.4.7 Complete appointed party’s appointment............................................................................................... 16
Foreword
ISO (the International Organization for Standardization) is a worldwide federation of national standards
bodies (ISO member bodies). The work of preparing International Standards is normally carried out
through ISO technical committees. Each member body interested in a subject for which a technical
committee has been established has the right to be represented on that committee. International
organizations, governmental and non-governmental, in liaison with ISO, also take part in the work.
ISO collaborates closely with the International Electrotechnical Commission (IEC) on all matters of
electrotechnical standardization.
The procedures used to develop this document and those intended for its further maintenance are
described in the ISO/IEC Directives, Part 1. In particular, the different approval criteria needed for the
different types of ISO documents should be noted. This document was drafted in accordance with the
editorial rules of the ISO/IEC Directives, Part 2 (see www.iso.org/directives).
Attention is drawn to the possibility that some of the elements of this document may be the subject of
patent rights. ISO shall not be held responsible for identifying any or all such patent rights. Details of
any patent rights identified during the development of the document will be in the Introduction and/or
on the ISO list of patent declarations received (see www.iso.org/patents).
Any trade name used in this document is information given for the convenience of users and does not
constitute an endorsement.
For an explanation of the voluntary nature of standards, the meaning of ISO specific terms and
expressions related to conformity assessment, as well as information about ISO's adherence to the
World Trade Organization (WTO) principles in the Technical Barriers to Trade (TBT), see www.iso.
org/iso/foreword.html.
This document was prepared by ISO/TC 59, Buildings and civil engineering works, SC 13, Organization
and digitization of information about buildings and civil engineering works, including building information
modelling (BIM), in collaboration with the European Committee for Standardization (CEN) Technical
Committee CEN/TC 442, Building Information Modelling (BIM), in accordance with the Agreement on
technical cooperation between ISO and CEN (Vienna Agreement).
A list of all parts in the ISO 19650 series can be found on the ISO website.
Any feedback or questions on this document should be directed to the user’s national standards body. A
complete listing of these bodies can be found at www.iso.org/members.html.
Introduction
0.1 Purpose and application
This document is designed to enable an appointing party (such as an asset owner, asset operator or
outsourced asset management provider) to establish their requirements for information during the
operational phase of an asset. This document is also designed to enable them to provide the appropriate
collaborative environment to fulfil commercial goals. Within this environment, multiple appointed
parties can produce information in an effective and efficient manner.
This document is primarily intended for use by the following:
— those involved in the management of an asset and facility (see 0.2);
— those involved in the specification of appointments and the facilitation of collaborative working
during the entire life cycle of an asset;
— those involved in delivering asset management and facility management during the operational
phase of an asset (see 0.2); and
— those involved in specifying the information required for operational purposes that needs to be
captured during the delivery phase of an asset.
If this document is being applied in relation to a particular asset then this should be reflected in the
relevant appointments.
This document is applicable to assets of all sizes and all levels of complexity. This includes portfolios of
buildings, campuses, infrastructure networks, individual buildings and pieces of infrastructure such
as roads, bridges, footpaths, streetlights, water pipes or sewers. The requirements in this document
should be applied in a way that is proportionate and appropriate to the scale and complexity of the asset.
Continuity of information management over the lifetime of an asset is important and it is recommended
that all feasible steps (including transfer of the asset information model) are taken to ensure this
whenever an asset is transferred from one owner to another.
Figure 1 shows the application of information management during the operational phase (shaded)
in conjunction with the delivery phase (unshaded apart from points A and B where information is
transferred). Figure 1 also shows how information management according to the ISO 19650 series
takes place within the context of asset and project management which itself takes place within the
context of organizational management. ISO 9001, ISO 55000 and ISO 21500, indicated in Figure 1, are
not requirements for applying this document.
Key
AIM asset information model
PIM project information model
A start of delivery phase — transfer of relevant information from AIM to PIM
B start of operational phase — transfer of relevant information from PIM to AIM
C post-occupancy/implementation evaluation or performance review
D trigger events during the operational phase
NOTE Information can be transferred between PIM and AIM during the delivery phase as well as at points A and B.
The concepts and principles from ISO 19650‑1, concerning different forms of information requirements,
have been applied in this document. The application of these concepts and principles has been tailored
to respond to the particular nature of asset management activities. In support of this, a simplified
illustration of the progression of information requirements is shown in Figure 2.
The information management process specified in this document can be applied to trigger events that
are foreseen and scheduled in advance as well as to trigger events that are not scheduled in advance or
cannot be foreseen. These two types of trigger event differ in terms of when the preparatory activities
of identifying and appointing the lead appointed party can take place.
Examples of the first type of trigger event are: annual maintenance tasks, strategic estate reviews and
call-off arrangements for common-place repairs. For this type of trigger event, it is possible and sensible
to select and appoint the lead appointed party well before any of these trigger events takes place.
For the second type of trigger event there are two distinct scenarios. The first is the deliberate
decision to initiate a project such as the construction of a bridge or underpass. Here, the information
management process could follow either ISO 19650‑2 or this document. The decision will depend on
the scale and complexity and the requirements on those involved are stated in 4.2. The second scenario
includes trigger events that are so rare or unpredictable that having appointments in place can be
inappropriate or not possible. The selection and appointment occur after the trigger event takes place.
Examples include unexpected breakdowns of equipment, accidents and extreme floods.
Finally, there is the separate situation of an asset being acquired from an existing owner, where
information is exchanged as part of the transaction.
All these situations are catered for in the arrangement of Clause 5. Annex A provides guidance to
support some of the requirements contained in Clause 5. Clause 5 also includes illustrations of the
breakdown of each step in the information management process and a reminder of where each step
comes in the overall process, in Figures 5 to 12.
0.2 Asset management and facility management
Asset management and facility management have developed as two distinct management disciplines,
despite both of them being concerned with managing the physical assets and services of an organization.
Asset management and facility management have developed their own standards and language of
preferred terms.
This document recognizes that both asset management and facility management play their own
part in the lifecycle of an asset, but for simplicity the main body of this document use the term asset
management to cover both disciplines.
0.3 Use of phrase “shall consider”
This document makes use of the phrase “shall consider”, particularly in Clause 5. This phrase is used
to introduce a list of items that the person in question needs to think about carefully in connection
with the primary requirement described in the subclause. The amount of thought involved, the time
taken to complete it, and the need for supporting evidence will depend on the complexity of the asset,
the experience of the person(s) involved, and the requirements of any national policy on building
information modelling. On a relatively small or straightforward asset, it can be possible to complete, or
dismiss as not relevant, some of these “shall consider” items very quickly.
One way to help identify which of the “shall consider” statements are relevant can be to review each
statement and create templates for assets of different sizes and complexity.
0.4 National annex with relevant national standards
There are several standards required for the successful implementation of this document, relating
to specific regions or countries, that are currently not suitable for inclusion within an international
standard. As such, national standards bodies are encouraged to compile and document the standards,
relevant to the region or country they represent, within a national annex. National annexes can also
provide localized guidance and advice on how to implement this document for assets and trigger events
of varying complexity.
Key
A appointing party
B lead appointed party
C appointed party
... variable amount
1 asset/facility management and operation team
2 illustration of a delivery team
3 task teams
information requirements and information exchange
information coordination between lead appointed parties if required by appointing party
Figure 3 — Interface between parties and teams for the purpose of information management
1 Scope
This document specifies requirements for information management, in the form of a management
process, within the context of the operational phase of assets and the exchanges of information within
it, using building information modelling.
This document can be applied to all types of assets and by organizations of all types and sizes involved
in the operational phase of assets.
The requirements in this document can be achieved through direct actions carried out by the
organization in question or can be delegated to another party.
2 Normative references
The following documents are referred to in the text in such a way that some or all of their content
constitutes requirements of this document. For dated references, only the edition cited applies. For
undated references, the latest edition of the referenced document (including any amendments) applies.
ISO 12006‑2, Building construction — Organization of information about construction works — Part 2:
Framework for classification
ISO 19650‑1:2018, Organization and digitization of information about buildings and civil engineering
works, including building information modelling (BIM) — Information management using building
information modelling — Part 1: Concepts and principles
ISO 19650‑2, Organization and digitization of information about buildings and civil engineering works,
including building information modelling (BIM) — Information management using building information
modelling — Part 2: Delivery phase of the assets
ISO 19650‑5, Organization and digitization of information about buildings and civil engineering works,
including building information modelling (BIM) — Information management using building information
modelling — Part 5: Security-minded approach to information management
Note 2 to entry: Activity can also refer to the application of the elements of the asset management system.
Note 3 to entry: The term “activity” has a broad meaning and can include, for example, the approach, the planning,
the execution and implementation of a plan.
[SOURCE: ISO 55000:2014, 3.3.1, modified — In Note 3 to entry, "the plans and their implementation"
have been replaced by "the execution and implementation of a plan".]
3.1.2
facility management
facilities management
organizational function which integrates people, place and process within the built environment with
the purpose of improving the quality of life of people and the productivity of the core business
[SOURCE: ISO 41011:2017, 3.1.1, modified — The abbreviated term "FM" has been removed.]
start
trigger event
end
collapsed sub-process
decision
NOTE The symbols used within this document have been adapted from symbols defined within
ISO/IEC 19510.
4.1 Information management process associated with the operational phase of assets
The information management process (Figure 4) shall be applied throughout the operational phase of
each asset identified through the use of 5.1.3, and in the case of an existing asset shall be applied to all
legacy information relating to that asset.
The information management process shall operate within or link with such enterprise systems or
organizational functions as necessary to optimize its implementation.
Key
Information management Activity groupings Decision points, questions
activities and actions
1 assessment and need A activities undertaken during H type of trigger event providing
2 invitation to tender/request the operational phase of assets information
to provide service B activities undertaken for each K continuation of the appointment
3 response to invitation to tender/ appointment made before L continuation of this information
request to provide service trigger event management process
4 appointment C activities undertaken for each M via an appointment made before
5 mobilization appointment made after a trigger event
6 production of information trigger event or delivery phase N received from another
7 information model acceptance using ISO 19650‑2 appointing party/asset owner
by appointing party D activities undertaken when P via an appointment made after
8 AIM aggregation acquiring an asset a trigger event or delivery phase
E activities undertaken during the using ISO 19650‑2
procurement stage Q1 yes — lead appointed party
(of each appointment) waits for next trigger event
F activities undertaken during Q2 yes — lead appointed party
the information planning progresses to next delivery
stage (of each appointment) milestone
G activities undertaken during Q3 yes — appointing party still
the information production has responsibility for the asset
stage (of each appointment) R no
NOTE 1 This process is intended to reduce the quantity of information to be reconciled at step 8 and reduces the
effort of doing so.
NOTE 2 There can be several lead appointed parties responding to the same trigger event — see A.3 for
examples of trigger events.
NOTE 3 Activities identified by C can apply during the operational or the delivery phases of the lifecycle.
Activities identified by B and D apply during the operational phase of the lifecycle.
NOTE 4 Sub-processes within the information management activities 1 to 8 are shown in Figures 5 to 12.
The appointing party shall nominate individuals from within its organization to undertake the
information management function.
Alternatively, the appointing party can appoint a prospective lead appointed party or a third party to
undertake all or part of the information management function. In which case the appointing party shall
establish a scope of services for that appointment.
In doing this, the appointing party shall consider the tasks that the prospective lead appointed party or
third party shall be responsible for.
In all cases, the appointing party shall consider the capability and capacity of any individuals or
organizations being nominated or appointed to undertake the information management function.
The appointing party shall identify any existing organizational information requirements (OIR) or
establish, document and maintain its OIR, see Figure 2, to meet the needs of its organizational functions
and its asset management system.
NOTE 1 OIR can be derived from the appointing party itself and from its stakeholders (for example the asset
owner when the appointing party is the asset operator).
NOTE 3 Some typical activities that can give rise to OIR are listed in A.2.
The appointing party shall identify those assets where management of asset information can provide
net benefit, including assets that are planned to be built or acquired. In doing this, the appointing party
shall consider:
— the ownership of the assets and the information associated with them;
— any asset breakdown structure being used by the appointing party;
— the impact of each asset on the efficiency of the business operation;
— the impact of each asset on the effectiveness of the business operation;
— the criticality of each asset for key business operations; and
— the condition of each asset.
NOTE 1 The assessment of net benefit includes both costs and benefits. This assessment can be on the
basis of organizational criteria including, but not limited to, financial analysis, risk to health and safety, risk of
environmental damage, risk to corporate and personal reputation, the resources required to capture and maintain
information for each asset, the anticipated resources required to capture asset information retrospectively.
NOTE 2 For some organizations these considerations can be taken into account in the OIR (see 5.1.2).
For each asset identified in 5.1.3, the appointing party shall establish the asset information requirements
(AIR), see Figure 2, necessary to enable it to meet its OIR. The AIR shall include requirements from
all relevant interested parties, including departments within the appointing party and interested
third-party organizations such as local authorities or regulators. In doing this, the appointing party
shall consider:
— the purpose(s) for which asset information needs to be managed as an effective organizational
resource, see ISO 55000;
— the ownership of the assets and the information associated with them;
— information required across groups of assets as well as for individual assets; and
— where an ISO 55001 asset management system is in place, the impact of its asset management
strategy and plans.
NOTE 1 Some example AIR are listed in A.4.
NOTE 2 Where an ISO 55001 asset management system is in place, “appointing party” is synonymous with the
term “organization” in ISO 55001.
5.1.5 Identify the foreseeable trigger events for which information shall be managed
The appointing party shall identify and record foreseeable trigger events, representing those events
during the operational phase when new or updated information concerning an asset will be generated
or required.
NOTE 1 Some example trigger events are suggested in A.3. More than one trigger event can occur at
the same time.
NOTE 2 Different types of asset, particularly at system or equipment level, can be subject to identical or
similar trigger events. However, the asset management response and the asset information generated or updated
can be different in each case.
NOTE 3 Some trigger events can be identified independently from the assets, for example severe weather
or geological activities. Once the assets have been identified it is possible that other trigger events will
become apparent.
The appointing party shall establish any specific information standards required by the appointing
party’s organization within the asset information standard.
In doing this, the appointing party shall consider:
a) the exchange of information
— within the appointing party’s organization;
— between the appointing party and external stakeholders;
— between the appointing party and lead appointed parties specifically appointed through
ISO 19650‑2;
— between the prospective lead appointed party and the appointing party;
— between prospective lead appointed parties in the same asset management and
operation team; and
— between interdependent or successive asset management and operation teams;
b) the means of structuring information and classifying information (in accordance with the
framework in ISO 12006‑2);
c) the method of assignment for level of information need;
d) the use of information for any future delivery phase associated with the asset; and
e) the use of information during the operational phase.
The appointing party shall establish any specific information production methods and procedures
required by their organization within the asset information production methods and procedures.
In doing this, the appointing party shall consider:
a) the capture of existing asset information;
b) the generation, review or approval of new information;
c) the security of information; and
d) the delivery of information to the appointing party, including the format to be used such that
information exchange is compatible with the systems and processes already operated by the
appointing party.
The appointing party shall establish the reference information and resources that they intend to share
with the prospective lead appointed parties during the tender process and during the appointment,
using open data standards whenever possible to avoid interoperability issues.
NOTE 1 Reference information can come from a range of sources, for example from the appointing party itself,
from adjacent asset owners such as utility companies, from external providers, or from public sources.
NOTE 2 Shared resources can include templates for information generated to manage the information
management process itself (for example a master information delivery plan), templates for information
containers (for example data sets or documents), style libraries or object libraries.
The appointing party shall establish the common data environment (CDE) in accordance with
ISO 19650‑1:2018, Clause 12. This shall be a combination of workflow and information storage solutions,
to support the information management process for the asset(s).
The CDE shall enable:
a) each information container to have a unique ID, based on an agreed and documented convention;
b) each information container to have the following attributes assigned:
— status;
— revision;
— classification (in accordance with the framework established in ISO 12006‑2);
c) information containers to transition between states;
d) a journal of information transactions, recording name of user, date and time when information
containers transition between states; and
e) controlled access at the information container level.
If existing enterprise systems are used to store asset information then the appointing party shall
establish or adapt information quality and information security processes within those systems
to ensure they comply with the requirements of this document, irrespective of where or how the
information is stored.
NOTE 1 Existing enterprise systems can be outside the direct control of the appointing party.
NOTE 2 Examples of enterprise systems that can be linked into the AIM are given in A.5.
The appointing party shall establish or review and adapt as necessary the asset information model
(AIM) to hold all information specified in AIR related to the asset or assets identified in 5.1.3. The AIM
shall be a federated information model which can include contents from different information providers
(appointed parties).
In doing this, the appointing party shall consider:
a) the suitability of existing information systems;
b) the ability to integrate or link information from a project information model at any time
during a project;
c) any legal requirements relating to storage of information (and particularly personal information);
d) the ability of the AIM to separate information being used for analysis and reporting from
information being updated by asset delivery teams; and
e) the need for a security-minded approach to the design and operation of the AIM including the
appropriate requirements from ISO 19650‑5 and the management activities agreed as a result of
applying ISO 19650‑5.
NOTE 1 The AIM can be held across any combination of new and existing enterprise systems provided that
these are appropriately linked and the contents of the AIM are controlled using the common data environment
(CDE) workflow described in ISO 19650‑1.
NOTE 2 There are many ways of creating and structuring the AIM. This document does not specify or preclude
the use of particular storage technologies, provided that such technologies support the CDE workflow.
The appointing party shall establish or follow existing suitable processes to maintain the AIM for as
long as is appropriate. These shall include processes to:
— allocate tasks for the production, maintenance, retention, transmission, access to, assurance and
archiving of information;
— transfer AIM maintenance requirements and/or ownership of the AIM when there is a change of
asset owner or appointing party;
— establish the content, meaning, format and medium for representation, retention, transmission and
retrieval of information;
— establish version control, check integrity and verify information against AIR and update the AIM as
appropriate;
— improve information quality to support organizational objectives;
— archive or dispose of obsolete, unreliable or unwanted information;
— archive the AIM, in part or in whole, at decommissioning/end of life;
— ensure the AIM complies with requirements for security as described in ISO 19650‑5;
— store information in such a way that it is safe, readily retrievable and use preventative maintenance
to protect it from physical and technological deterioration or obsolescence; and
— maintain the agreed level of alignment between the contents of the AIM and the state of the
physical asset.
NOTE 1 The appropriate period for maintaining the AIM can be based on an expected period of ownership, the
length of an occupancy agreement, the period of an operating agreement, or the length of an asset management
agreement. The period can also be constrained by strategic, contractual, statutory, legal, regulatory, health and
safety, environmental, social as well as fiscal constraints.
NOTE 2 The agreed level of alignment can be defined in terms of the time interval between changes occurring
to the asset and those changes being reflected in the AIM.
The appointing party shall establish the asset information protocol to set out the rights and obligations
of the appointing party and the appointed parties in relation to the AIM, and shall incorporate the
information protocol into all appointments.
In doing this, the appointing party shall consider:
— obligations relating to the management or production of information, including use of the CDE;
— any warranties or liabilities associated with the AIM;
— background and foreground intellectual property rights relating to the AIM;
— the use of reference information and shared resources;
— the use of information during the appointment, including any associated licensing terms; and
Key
1.1 appoint individuals to undertake the information management function
1.2 establish organizational information requirements
1.3 identify assets for which information shall be managed
1.4 identify the asset information requirements
1.5 identify the foreseeable trigger events for which information shall be managed
1.6 establish the asset information standard
1.7 establish the asset information production methods and procedures
1.8 establish the reference information and shared resources
1.9 establish the common data environment
1.10 establish links to enterprise systems
1.11 establish the asset information model
1.12 establish processes to maintain the AIM
1.13 establish the asset information protocol
The appointing party shall appoint a lead appointed party in relation to each trigger event during the
operational phase, including trigger events not originally identified during 5.1.5. This decision affects
whether the information management process follows branch M, N or P in Figure 4.
The method of appointment shall be proportionate to the scale and complexity of the asset management
activities required to respond to the trigger event and shall take account of any specific procurement
processes the appointing party needs to follow.
NOTE 1 The appointment requirements related to asset information can be incorporated into the appointment
process for overall asset management activities.
NOTE 2 Where a request to provide service is made rather than a formal tendering process (for example to
appoint an in-house team), the requirement in 5.2.5 can be adapted accordingly.
For each appointment and trigger event, the appointing party shall establish the exchange information
requirements for this document [EIR (ISO 19650‑3)] necessary to enable it to meet its AIR, and therefore
to meet the appropriate OIR.
In doing this, the appointing party shall:
a) establish any security-minded considerations identified through ISO 19650‑5;
b) establish the information to be captured during the response to the trigger event, consistent with
any definition of level of information need (see ISO 19650‑1:2018, 11.2);
c) establish the timing and frequency of information exchange during the appointment; and
d) establish the acceptance criteria for each information requirement, and in doing so shall consider:
— the asset information standard,
— the asset information production methods and procedures, and
— the use of reference information or shared resources provided by the appointing party.
NOTE 1 This includes the trigger events identified in 5.1.5. In these cases, preparation of the EIR (ISO 19650‑3)
in advance of the trigger event happening means that the appointment of the lead appointed party or lead
appointed parties is not delayed. This is important in the case of trigger events that are likely to require an
emergency response, such as foreseeable breakdowns of critical equipment.
NOTE 2 This subclause is particularly important where the response to the trigger event initiates a new-build
or substantial refurbishment project.
The appointing party shall assemble the reference information or shared resources that they intend to
provide to the prospective lead appointed party during the tender process or as part of the appointment.
In doing this, the appointing party shall consider:
— reference information or shared resources identified in 5.1.8;
— information produced during previous appointments; and
— the status code associated with the information, as described in ISO 19650‑1:2018, 12.1.
The appointing party shall establish its evaluation criteria for responses received from prospective
lead appointed parties.
In doing this, the appointing party shall consider:
— the complexity of the information requirements;
— the alignment of the BIM execution plan with the asset information standard, the asset information
production methods and procedures, the asset information protocol and the EIR (ISO 19650‑3); and
— the levels of capability and capacity expected to be provided in the delivery team.
The appointing party shall compile the information to be included in the invitation to tender or in the
request to provide service. In doing this, the appointing party shall consider:
— the EIR (ISO 19650‑3);
— the relevant reference information and shared resources;
— the response requirements and evaluation criteria;
— the asset information standard;
— the asset information production methods and procedures; and
— the asset information protocol.
Key
2.1 decide the type of activity providing information
2.2 establish the appointing party’s EIR (ISO 19650‑3)
2.3 assemble reference information and shared resources
2.4 establish response requirements and evaluation criteria
2.5 compile information for the invitation to tender/request to provide service
The prospective lead appointed party shall nominate individuals from within its organization to
undertake the information management function on behalf of its delivery team.
Alternatively, the prospective lead appointed party can appoint a prospective appointed party or a third
party to undertake all or part of the information management function. In which case the prospective
lead appointed party shall establish a scope of services for that appointment.
In doing this, the prospective lead appointed party shall consider:
— the tasks that the prospective appointed party or third party shall be responsible for; and
— the capability and capacity of any individuals or organizations being nominated or appointed to
undertake the information management function.
The prospective lead appointed party shall establish the delivery team’s (pre-appointment) BIM
execution plan, to describe its approach and the resources required to achieve the requirements in the
EIR (ISO 19650‑3).
In doing this, the prospective lead appointed party shall consider:
— the resources required for the information management function;
— the timing, quantity and scope of information exchanges required by the appointing party;
— any requirement to federate information with other lead appointed parties; and
— the prospective lead appointed party’s plan to appoint other appointed parties as task teams within
their delivery team in the operational phase, including the need to pass some EIR (ISO 19650‑3) to
these appointed parties.
NOTE 1 The appointing party can specify the format for this description of approach and can provide guidance
or templates to prospective lead appointed parties.
NOTE 2 The prospective lead appointed party can add some of its own information requirements to any EIR
(ISO 19650‑3) passed on to an appointed party (see 5.4.3).
Each task team shall undertake an assessment of their capability and capacity to deliver information in
accordance with the EIR (ISO 19650‑3) and the delivery team’s information delivery plan.
In doing this, each task team shall consider:
— its capability and capacity to manage information, based on the relevant experience and training of
task team members with the asset information standard, and number of such task team members;
— its capability and capacity to produce information, based on the relevant experience and training
of task team members with the asset information production methods and procedures, and the
number of such task team members; and
— the availability of information technology (IT) within the task team, based on software and
hardware requirements set out either in the EIR (ISO 19650‑3) or the delivery team’s information
delivery plan.
The prospective lead appointed party shall establish the delivery team’s capability and capacity by
aggregating the assessments provided by each task team.
The prospective lead appointed party shall establish the delivery team’s mobilization plan, to be
implemented during mobilization (see 5.5).
In doing this, the prospective lead appointed party shall consider the delivery team’s approach,
timescales and responsibilities for:
— testing and documenting the information production methods and procedures;
— testing information exchange between task teams;
— testing information exchange with the appointing party;
— testing the CDE solution and access to shared information and resources;
— procuring, implementing, configuring and testing additional software, hardware and IT
infrastructure;
— developing additional shared resources to be used by the delivery team;
— undertaking education and/or training to develop the required capability within the delivery team;
— recruiting additional task teams or members of task teams to achieve the required capacity within
the delivery team; and
— supporting new members (organizations or individuals) that join the delivery team during the
appointment.
The prospective lead appointed party shall establish the delivery team’s risk register in relation to
production and delivery of information.
In doing this, the prospective lead appointed party shall consider:
— assumptions made by the delivery team in its BIM execution plan;
— the clarity of the appointing party’s EIR (ISO 19650‑3); and
— the requirements of the asset information standard and the asset information production methods
and procedures.
NOTE The delivery team’s risk register can be incorporated within other risk registers used during the
appointment.
The prospective lead appointed party shall compile the following items (where available) into the
delivery team's response:
— (pre-appointment) BIM execution plan (5.3.2);
— capability and capacity assessments (5.3.4);
— mobilization plan (5.3.5); and
— risk register (5.3.6).
Activities for response to invitation to tender/request to provide service are shown in Figure 7.
Key
3.1 nominate individuals to undertake information management function
3.2 establish the delivery team’s (pre-appointment) BIM execution plan
3.3 assess task team capability and capacity
3.4 establish the delivery team’s capability and capacity
3.5 establish the delivery team’s mobilization plan
3.6 establish the delivery team’s risk register
3.7 compile the delivery team’s response
The lead appointed party shall review and confirm the BIM execution plan prepared in 5.3.2, in
consultation with each task team. This shall include a review and confirmation of the resources (both
human and technical) to be deployed during the appointment, and testing of the technical approach to
be used during information exchange.
The lead appointed party shall communicate the BIM execution plan to all appointed parties, shall
keep it under review during the lead appointed party’s appointment and shall update and recirculate it
as necessary.
The lead appointed party shall establish a detailed responsibility matrix, to confirm the information to
be produced, when the information is to be exchanged with whom, and which task team is responsible
for its production. In doing this, the lead appointed party shall consider:
— the information delivery milestones;
— the capability and capacity across the delivery team;
— the asset information production methods and procedures;
— the elements of information container breakdown structure allocated to each task team; and
— the task team dependencies within the information production process.
Where a delivery team in the operational phase includes other appointed parties as task teams, the lead
appointed party shall issue to them appropriate EIR (ISO 19650‑3) and the associated considerations as
described in 5.2.2.
NOTE See 0.5 and Figure 3 for an explanation of the relationship between a lead appointed party and any
other appointed parties in a delivery team.
Each task team shall establish, and maintain throughout its appointment, a task information delivery
plan (TIDP).
In doing this, each task team shall consider:
— the asset management information delivery milestones;
— the task team’s responsibilities within the detailed responsibility matrix;
— the lead appointed party’s EIR (ISO 19650‑3);
— the availability of reference information and shared resources within the delivery team; and
— the time the task team will need to produce its information.
The TIDP shall list and identify for each information container:
— the unique ID and title;
— the predecessors or dependencies;
— the level of information need;
— the estimated production duration;
— the information author responsible for its production; and
— the delivery milestone(s).
The lead appointed party shall aggregate the TIDP from each task team to establish the delivery team’s
master information delivery plan (MIDP), inform each task team of any changes required to its TIDP, and
add or update any risks in the delivery team’s risk register informing the appointing party as required.
The appointing party shall appoint each lead appointed party, allowing sufficient time for the lead
appointed party to mobilize before information production needs to start.
In doing this, the appointing party shall consider the capability and capacity of each prospective lead
appointed party according to its pre-existing evaluation criteria (5.2.4).
NOTE Assessment of capability and capacity is an important activity to ensure that each delivery team, led
by a lead appointed party, is able to deliver effective management of information.
The appointing party shall ensure that the following are included in the completed appointment
documents for the lead appointed party and managed using change control:
— the appointing party’s EIR (ISO 19650‑3);
— the asset information standard (including any agreed additions or amendments);
— the asset information production methods and procedures (including any agreed additions or
amendments);
— the asset information protocol (including any agreed additions or amendments);
— the delivery team’s BIM execution plan; and
— the delivery team’s MIDP.
The lead appointed party shall appoint each appointed party, allowing sufficient time for the appointed
party to mobilize before information production needs to start.
In doing this, the lead appointed party shall ensure that the following are included in the completed
appointment documents for the appointed party and managed using change control:
— the lead appointed party’s EIR (ISO 19650‑3);
— the asset information standard (including any agreed additions or amendments);
— the asset information production methods and procedures (including any agreed additions or
amendments);
— the asset information protocol (including any agreed additions or amendments);
— the delivery team’s BIM execution plan; and
— the relevant TIDP.
Key
4.1 confirm the delivery team’s BIM execution plan
4.2 establish the delivery team’s detailed responsibility matrix
4.3 establish the lead appointed party’s EIR (ISO 19650‑3)
4.4 establish the task information delivery plans(s)
4.5 establish the master information delivery plan
4.6 complete lead appointed party’s appointment
4.7 complete appointed party’s appointment
The lead appointed party shall mobilize the resources, as set out in the delivery team’s mobilization
plan. In doing this, the lead appointed party shall confirm the resources across the delivery team, and
in doing this shall consider the approach towards training and education across the delivery team.
The lead appointed party shall mobilize the information technology, as set out in the delivery team’s
mobilization plan. In doing this, the lead appointed party shall:
— procure, implement, configure and test software, hardware and IT infrastructure (as required);
— test the use of the appointing party’s CDE;
— test the information exchange between task teams; and
— test the information exchange with the appointing party.
The lead appointed party shall test the asset information production methods and procedures, as set
out in the delivery team’s mobilization plan. In doing this, the lead appointed party shall:
— test and document the asset information production methods and procedures;
— validate the proposed information container breakdown structure as workable and refine
if necessary;
— develop shared resources to be used by the delivery team as necessary; and
— communicate the asset information production methods and procedures to all task teams within
their delivery team.
The lead appointed party shall ensure that all resources (both human and technical) as specified in 5.5.1
to 5.5.3, will remain in readiness for the occurrence of any trigger event covered by the appointment.
Key
5.1 mobilize resources
5.2 mobilize information technology
5.3 test the asset information production methods and procedures
5.4 maintain resources in readiness for a trigger event
Each task team shall check that they have access to the relevant reference information and shared
resources, within the CDE, before they generate information. If they do not have access, they shall
inform the lead appointed party as soon as practicable and assess the potential impact on their TIDP.
Each task team shall generate information, in the work in progress state, in accordance with their TIDP.
In doing this, the task team shall:
a) generate information that:
— complies with the asset information standard, and
— is in accordance with the asset information production methods and procedures;
b) not generate information that:
— exceeds the required level of information need,
— extends beyond the allocated element of the information container breakdown structure, and
— duplicates information generated by other task teams;
c) coordinate and cross reference all information with information shared with the appropriate
suitability within the CDE.
In the event of a coordination issue, the relevant task teams shall collaborate to identify a possible
resolution. If a resolution cannot be found the task teams shall notify the lead appointed party.
Each task team shall undertake a quality assurance check of each information container, in accordance
with the asset information production methods and procedures and with the asset information standard.
Once the check is complete, the task team shall:
a) if the check is successful:
— mark the information container as checked,
— record the outcome of the check; or
b) if the check is unsuccessful:
— reject the information container, and
— inform the information author of the outcome and corrective action required.
NOTE 1 Some of these checks can be automated within the CDE.
NOTE 2 A quality assurance check does not check the accuracy or appropriateness of the information within
the information container and is not a replacement for review and approval (5.6.4).
Each task team shall review the information within each information container before sharing the
information container within the CDE.
To facilitate the continuous coordination of information across each element of its information
model, the delivery team shall undertake an information model review, in accordance with the asset
information production methods and procedures and the asset information standard.
In doing this, the delivery team shall consider:
— the EIR (ISO 19650‑3) and acceptance criteria issued to the lead appointed party by the
appointing party;
— the EIR (ISO 19650‑3) and acceptance criteria issued to the task teams by the lead appointed party; and
— the information containers listed within the delivery team’s MIDP.
To enable a decision to authorize the delivery of the delivery team’s information model to the appointing
party, the lead appointed party shall review the information model in accordance with the asset
information production methods and procedures and the asset information standard.
In doing this, the lead appointed party shall consider the same items as were considered by the task
teams in 5.6.4 and by the delivery team in 5.6.5.
Once the review is complete, the lead appointed party shall:
a) if the review is successful:
— authorize the delivery team’s information model, and
— instruct each task team to mark their information containers within the CDE as suitable for
appointing party acceptance; or
b) if the review is unsuccessful:
— record why the review was unsuccessful,
Key
6.1 check availability of reference information and shared resources
6.2 generate information
6.3 undertake quality assurance check
6.4 review information and approve for sharing
6.5 review information model
6.6 authorize information model for delivery to the appointing party
X new information container revision
If the process follows branches M or P in Figure 4 the lead appointed party shall submit the delivery
team’s information model for appointing party acceptance within the CDE.
If the process follows branch N in Figure 4 the appointing party shall receive the information model
from the other appointing party or asset owner.
The appointing party shall review the information model received in 5.7.1 in accordance with the asset
information production methods and procedures.
In doing this, the appointing party shall consider:
— its AIR (particularly for a process that follows branch N in Figure 4);
— its EIR (ISO 19650‑3) and acceptance criteria issued to the lead appointed party (for a process that
follows branches M or P in Figure 4);
— the delivery team’s MIDP (for a process that has followed branches M or P in Figure 4);
— the level of information need identified as a result of 5.1.6 and 5.4.4; and
— delivery of information against the above.
Once the review is complete, the appointing party shall:
a) if the review is successful:
— accept the information model as a deliverable within the CDE, and either
— instruct the lead appointed party to mark each information container in the information model
as being in the published state (for a process that follows branches M or P in Figure 4), or
— mark each information container in the information model as being in the published state (for a
process that follows branch N in Figure 4); or
b) if the review is unsuccessful:
— record why the review was unsuccessful,
— reject the information model, and either
— instruct the lead appointed party to amend the information model and resubmit it for appointing
party acceptance (for a process that follows branches M or P in Figure 4), or
— identify the changes required in the information model and either request the other appointing
party/asset owner to make those changes or make the changes itself (for a process that follows
branch N in Figure 4).
Partial acceptance of an information model can lead to coordination issues and it is recommended that
the appointing party either accepts or rejects the whole information model submitted by the delivery
team or received from the other appointing party/asset owner.
Activities for information model acceptance by appointing party are shown in Figure 11.
Key
7.1 submit information model for appointing party acceptance
7.2 review and accept the information model
Y information model rejected by appointing party
The appointing party shall be responsible for the process to incorporate an accepted information model
into its AIM and reconcile that information with the existing contents of the AIM, irrespective of its
source. This shall include a process to incorporate the accepted information model into its existing
enterprise systems, where appropriate.
The appointing party shall review whether the AIM continues to fulfil the requirements of 5.1.11 and
is being maintained according to 5.1.12. If either of these is not met, then the appointing party shall
implement appropriate mitigating measures.
Key
8.1 aggregate an accepted information model into the AIM
8.2 review and continue maintenance of the AIM
Annex A
(informative)
A.1 General
This annex contains guidance to support some of the requirements contained in Clause 5. The lists in
A.2 to A.5 are only examples of activities, events, information requirements and systems and should not
be considered as comprehensive or complete. Appointing parties should use these examples to inform
the development of their information requirements. Additional guidance is also contained in ISO 55002.
— asset replacement;
— end-of-life works, such as decommissioning, demolition or deactivation and preservation;
— planning for and, where appropriate, implementing an emergency response;
— risk assessment of an asset;
— change in value of an asset;
— change in regulations applying to an asset;
— change in information demanded by an appropriate regulator;
— change in organizational requirements relating to the asset, for example change of operating
parameters or conditions;
— change in ownership of an asset;
— change in operator of an asset; and
— change in maintainer of an asset.
NOTE As stated in 4.2, it is possible for the information management response to a trigger event to involve
ISO 19650‑2 as well as this document.
Bibliography
[1] ISO 6707‑1, Buildings and civil engineering works — Vocabulary — Part 1: General terms
[2] ISO 9001, Quality management systems — Requirements
[3] ISO/IEC 19510, Information technology — Object Management Group Business Process Model
and Notation
[4] ISO 21500, Guidance on project management
[5] ISO 41001, Facility management — Management systems — Requirements with guidance for use
[6] ISO 41011:2017, Facility management — Vocabulary
[7] ISO 55000:2014, Asset management — Overview, principles and terminology
[8] ISO 55001, Asset management — Management systems — Requirements
[9] ISO 55002, Asset management — Management systems — Guidelines for the application
of ISO 55001
Buying standards PLUS is an updating service exclusive to BSI Subscribing Members. You will
automatically receive the latest hard copy of your standards when they’re
You can buy and download PDF versions of BSI publications, including British and revised or replaced.
adopted European and international standards, through our website at bsigroup.
com/shop, where hard copies can also be purchased. To find out more about becoming a BSI Subscribing Member and the benefits
of membership, please visit bsigroup.com/shop.
If you need international and foreign standards from other Standards Development
Organizations, hard copies can be ordered from our Customer Services team. With a Multi-User Network Licence (MUNL) you are able to host standards
publications on your intranet. Licences can cover as few or as many users as you
Copyright in BSI publications wish. With updates supplied as soon as they’re available, you can be sure your
documentation is current. For further information, email cservices@bsigroup.com.
All the content in BSI publications, including British Standards, is the property
of and copyrighted by BSI or some person or entity that owns copyright in the Revisions
information used (such as the international standardization bodies) and has
formally licensed such information to BSI for commercial publication and use. Our British Standards and other publications are updated by amendment or revision.
Save for the provisions below, you may not transfer, share or disseminate any We continually improve the quality of our products and services to benefit your
portion of the standard to any other person. You may not adapt, distribute, business. If you find an inaccuracy or ambiguity within a British Standard or other
commercially exploit or publicly display the standard or any portion thereof in any BSI publication please inform the Knowledge Centre.
manner whatsoever without BSI’s prior written consent.
Useful Contacts
Storing and using standards Customer Services
Standards purchased in soft copy format: Tel: +44 345 086 9001
• A British Standard purchased in soft copy format is licensed to a sole named Email: cservices@bsigroup.com
user for personal or internal company use only.
Subscriptions
• The standard may be stored on more than one device provided that it is Tel: +44 345 086 9001
accessible by the sole named user only and that only one copy is accessed at Email: subscriptions@bsigroup.com
any one time.
• A single paper copy may be printed for personal or internal company use only. Knowledge Centre
Tel: +44 20 8996 7004
Standards purchased in hard copy format: Email: knowledgecentre@bsigroup.com
• A British Standard purchased in hard copy format is for personal or internal
company use only. Copyright & Licensing
Tel: +44 20 8996 7070
• It may not be further reproduced – in any format – to create an additional copy.
This includes scanning of the document. Email: copyright@bsigroup.com
If you need more than one copy of the document, or if you wish to share the BSI Group Headquarters
document on an internal network, you can save money by choosing a subscription
product (see ‘Subscriptions’). 389 Chiswick High Road London W4 4AL UK