Progress Report TB. Sahoya 2 (17-7-2024)

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

PROGRESS OF TB.

SAHOYA 02 (DOCKING REPAIR)

No Item Descriptions Progress Work Group 5% 10% 15% 20% 25% 30% 35% 40% 45% 50% 55% 60% 65% STD

1 DOCKING PREPARATION 4.10% 100.00% 5%


2 HULL CONTRACTION 20.00% 200.00% 20%
3 OTHER 15.00% 100.00% 15%
4 OUTFITTING 15.00% 100.00% 15%
5 PROPULSI 15.00% 100.00% 15%
6 ENGINE ROOM 14.58% 100.00% 15%
7 BLASTING/PAITING 15.00% 100.00% 15%

TOTAL PROGRESS VESSEL 98.68% 100.00%

PROGRESS OF TB. SAHOYA


-D -D -D D D D1 D2 D3 D4 D5 D6 D7 D8 D9 D 10 D 11 D 12 D 13 D 14 D 15
02 (DOCKING REPAIR)

TANGGAL 2 9 / 0 6 / 2 4 3 0 / 0 6 / 2 4 0 1/ 0 7 / 2 4 0 2 / 0 7 / 2 4 0 3 / 0 7 / 2 4 0 4 / 0 7 / 2 4 0 5 / 0 7 / 2 4 0 6 / 0 7 / 2 4 0 7 / 0 7 / 2 4 0 8 / 0 7 / 2 4 0 9 / 0 7 / 2 4 10 / 0 7 / 2 4 11/ 0 7 / 2 4 12 / 0 7 / 2 4 13 / 0 7 / 2 4 14 / 0 7 / 2 4 15 / 0 7 / 2 4 16 / 0 7 / 2 4 17 / 0 7 / 2 4 18 / 0 7 / 2 4

Plan Progress 0 .7 5 % 0 .7 5 % 0 .7 5 % 3 .0 0 % 4 .5 0 % 7 .8 5 % 11.8 8 % 18 .2 7 % 2 4 .9 6 % 3 0 .6 2 % 3 7 .2 6 % 4 6 .11% 5 4 .5 0 % 6 4 .5 4 % 7 2 .8 5 % 8 7 .11% 9 8 .0 0 % 10 0 .0 0 % 10 0 .0 0 % 10 0 .0 0 %


Realization Progress 0 .5 0 % 1.8 8 % 3 .0 0 % 3 .0 0 % 4 .0 0 % 7 .8 0 % 11.8 9 % 18 .2 5 % 2 4 .9 9 % 3 1.0 0 % 3 7 .3 0 % 4 6 .2 9 % 5 4 .5 5 % 6 5 .0 0 % 7 2 .9 9 % 8 7 .9 0 % 9 2 .8 9 % 9 6 .2 5 %

-0.25% 1.13% 2.25% 0.00% -0.50% -0.05% 0.01% -0.02% 0.03% 0.38% 0.04% 0.18% 0.05% 0.46% 0.14% 0.79% -5.11% -3.75%

TB. SAHOYA 02
100.00%
90.00%
80.00%
70.00%
60.00%
50.00%
40.00%
30.00%
20.00%
10.00%
0.00%
29/06/24 30/06/24 01/07/24 02/07/24 03/07/24 04/07/24 05/07/24 06/07/24 07/07/24 08/07/24 09/07/24 10/07/24 11/07/24 12/07/24 13/07/24 14/07/24 15/07/24 16/07/24 17/07/24 18/07/24
-D -D -D D D D1 D2 D3 D4 D5 D6 D7 D8 D9 D10 D11 D12 D13 D14 D15

Plan Progress Realization Progress

Note :

1. Proses undocking (tgl 17 Juli 2024)