GENERAL ABSTRACT
TOTAL = 12517300 /-
ABSTRACT OF COST
Sr.No. Description of Item Qty Rate Unit Amount
ROAD WORK
1 Dismantling of road metalling. 2733 2851.20 % Cft 77923 /-
2 Dismantling and removing road pavement, 10933 3806.35 % Cft 416148 /-
etc., including screening and stacking of
byproducts upto one chain lead (30 metre).
3 Regular excavation un-dressed (Un-suaitable 31000 6415.20 %o Cft 198871 /-
material)
4 Compaction with power road roller 3100 1802.50 %o Cft 5588 /-
5 Shifting of un-suitable material. 33733 15305.43 %o Cft 516298 /-
6 Better fill material 86800 3300.25 % Cft 2864617 /-
7 Relaying of dismantled material of road 9840 7425.75 % Cft 730672 /-
pavement used as sub Base Course
10 Providing and laying bituminous priming coat, 14400 2182.10 % Sft 314222 /-
using 10 lbs. kerosene oil and 10 lbs. binder
per 100 Sft. or 0.5 Kg kerosene and 0.5 Kg
binder per square metre
11 Providing and laying plant premixed 14400 20351.37 % Sft 2930597 /-
bituminous carpet 2.5" Thick 4% including
compaction and finishing to required camber,
grade and density.
12 Providing and laying bituminous tack coat, 14400 1156.40 % Sft 166522 /-
using 10 lbs. of bitumen per 100 Sft (0.49 Kg of
bitumen per sq.m.)
ROAD STRUCTURE
1 Construction of side drain 30 7150.34 P.Rft 214510 /-
Total 214510 /-
ROAD FURNITURE
1 Painting traffic lane 5" (125 mm) wide with 1800 47.85 P.Rft 86130 /-
reflective clorinated rubber (TP) paint
including glass beads comlpete in all respect.
1 Total 110132 /-
ABSTRACT OF QUANTITY
ROAD WROK
Qty as per item No. 4 90% Total 9840 Cft 9840 Cft
8 Providing and laying of Sub Base-Course of pitrun gravel of approved quality and
grade, including placing mixing, spreading and compaction of Sub Base course
material to required depth, camber and grade to achieve 100% maximum modified
AASHO dry density, in including carriage all material to site of work.Complete in all
respects.
600 x 24 x 1 = 14400 Cft
D/d qty as per item No.9 = -9840 Cft
Total = 4560 Cft 4560 Cft
12 Providing and laying bituminous tack coat, using 10 lbs. of bitumen per 100 Sft (0.49
Kg of bitumen per sq.m.)
600 x 24 = 14400 Sft
Total = 14400 Sft 14400 Sft
13 Providing and laying plant premixed bituminous carpet 1.5" Thick 4.50% including
compaction and finishing to required camber, grade and density.
600 x 24 = 14400 Sft
Total = 14400 Sft 14400 Sft
ROAD STRUCTURE
1 Construction of side drain = 30 Rft 30 Rft
ROAD FURNITURE
1 Painting traffic lane 5" (125 mm) wide with reflective clorinated
rubber (TP) paint including glass beads comlpete in all respect.