Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

HAL Make-II Procedure - 10 Dec 2019

Download as pdf or txt
Download as pdf or txt
You are on page 1of 21

MAKE-II PROCEDURE AT

HINDUSTAN AERONAUTICS LIMITED

HINDUSTAN AERONAUTICS LIMITED

CORPORATE OFFICE, BANGALORE

10 DECEMBER, 2019
Contents

Sl.
Topic Page No.
No.
1 Introduction 1
2 Development Process steps 1
3 Formation of Indigenization Committee 2
4 Formulation and approval of Proposal 3
5 Identification & Hosting of items 8
6 Issue of EoI 9
7 Evaluation of EoI responses 9
8 Issue of Nil Value Project Sanction Order 10
9 Design and Development 10
10 Time Overrun 11
Solicitation of Commercial offers after successful
11 11
D&D
12 Qualification Testing(QT) / Flight Trial Evaluation 12
Commercial Negotiations by Contract Negotiation
13 13
Committee (CNC)
14 Multiple technological solutions 13
15 Intellectual Property Rights (IPRs) 14
16 Project Management, Review and Monitoring 14
17 Foreclosure/ Reduction in quantity 15
18 Deficient delivery 15
19 Additional requirement 16
20 Miscellaneous 16
Annexure-I: Indicative Eligibility Criteria for
21 17
responding to EoI
Annexure-II: Categories & Domains of startups
22 18
eligible for participation in Make-II

Make-II Procedure for Hindustan Aeronautics Limited (HAL) Page | ii


Abbreviations

CDR Critical Design Review


CEMILAC Centre for Military Airworthiness and Certification
CFA Competent Finance Authority
CNC Contract Negotiation Committee
D&D Design & Development
DA Development Agency
DGAQA Directorate General Aeronautical Quality Assurance
DPP Defence Procurement Procedure
DPSU Defence Public Sector Unit
EOI Expression of Interest
GHE Ground Handling Equipment
GSE Ground Support Equipment
IC Indigenization Committee
IDDM Indigenously Designed Developed and Manufactured
IV&V Independent Verification and Validation
LQT Limited Qualification Testing
LRU Line Replaceable Unit
MOD Ministry of Defence
MOU Memorandum of Understanding
NRC Non-Recurring Costs
OEM Original Equipment Manufacturer
PDR Preliminary Design Review
PNC Price Negotiation Committee
QT Qualification Testing
RC Recurring Costs
RFP Request for Proposal
ROM Rough Order of Magnitude
SOF Safety of Flight
SOW Scope of Work
SVC Single Vendor Case
TTGE Tool Tester Ground Equipment

Make-II Procedure for Hindustan Aeronautics Limited (HAL) Page | iii


Framework for implementation of ‘Make-II’ Procedure

Introduction

1. With the emerging dynamism of private sector and with the aim of achieving
substantive self-reliance in defence production, it is imperative that HAL harnesses the
potential of the private sector.

2. The ‘Make-II’ procedure notified by MoD is part of “Make” procedure of the DPP-
2016 with an objective of wider participation of Indian industry and impetus for
MSME/start-ups sector. As per MoD letter No. D.O No. 18(2)/18/MII-
OFB&DPSUs/DP(Plg-MS) dated 07 Mar, 2019, MoD had directed DPSUs to incorporate
a similar procedure into their existing procurement procedures. The present Framework
is being issued in compliance with this directive. In this sub-category of Make-II, no HAL
funding is envisaged for Design & Development (D&D) but there has to be an assurance
of Supply Order to be placed on the lowest bidding Development Agency (DA) on
successful development.

3. Indian vendors as detailed in Annexure-I to this framework are eligible for


participation as per the Make-II procedure for D&D and subsequent supply of items.

4. The salient points applicable specifically for Make-II framework are detailed in this
procedure. Aspects which are not stated specifically herein are to be guided by the normal
procurement procedure in HAL.

5. Projects under this framework will involve development of equipment/ system or


their sub-systems/assembly/ sub-assemblies/components/material, primarily for import
substitution, wherever commercial viability can be established.

6. Projects with estimated cost (Design & development phase and Procurement
phase) not exceeding Rs 250 Lakhs, will be earmarked for MSMEs/Startups. However, if
no MSME /Startup expresses interest for any such proposal, the same may be opened
up for the general category of vendors.

Development Process steps:

7. The development & procurement process under this scheme would involve the
following stages/ activities:-
i. Formulation of Proposal by Indigenization Committee (IC).

Make-II Procedure for Hindustan Aeronautics Limited (HAL) Page | 1


ii. Approval of proposal by Competent Authority.
iii. Issue of Expression of Interest (EOI)
iv. Evaluation of EOI responses
v. Award of Nil value Project Sanction Order
vi. Design and Development.
vii. Solicitation of Commercial Offer
viii. Qualification Testing (QT) & Flight Trial evaluation.
ix. Opening of commercial bids and evaluation of the offers
x. Commercial negotiations by Contract Negotiation Committee (CNC).
xi. Award of Procurement Contract

Formation of Indigenization Committee (IC)

8. HAL will identify the potential Make-II projects on the basis of requirement of the
customers, Indigenization plan, or other valid considerations. An Indigenization
Committee shall be constituted for this purpose at each Division and carry out functions
as detailed below.
a) An Indigenization Committee shall be constituted with representatives (as
applicable) from Indigenization group/cell, Design Liaison Group, Manufacturing,
Planning and Quality Assurance as members. Further, reps of the concerned R&D
Centre and/or Certification agency may be co-opted if necessary. The committee
will be constituted with the approval of Divisional Head. The senior-most member
of the committee preferably at AGM/ DGM level should be the Head of the
Committee. Head of the Committee may co-opt additional members for specific
cases and specific periods as required.
b) All procurement activities under this Procedure should be handled by a team
comprising of rep(s) from Divisional IMM & Finance.
c) Indigenization Committee and Procurement Team shall, inter-alia, carry out the
following important functions: -

Indigenization Committee (IC):


i. Preparing of Proposal, EOI & RFP.
ii. Technical Evaluation of EOI/RFP responses.
iii. Assisting IMM department in Commercial Evaluation of EOI/RFP
iv. Monitoring and reporting on the progress of the project.
v. Handholding of the DA to provide guidance, to resolve problems and to
improve the probability of success of the project

Make-II Procedure for Hindustan Aeronautics Limited (HAL) Page | 2


vi. Coordination of utilization of HAL facilities for tests, integration on aircraft, etc.
as required
vii. Any other responsibilities as entrusted by the Head of Division.

Procurement Team :
i. Issue of EOI/RFP and receipt of responses
ii. Commercial Evaluation of EOI/RFP responses
iii. Issue of Project Sanction Order.
iv. Issue of Production Order
v. Post-Order administration of contractual issues/matters

Formulation and Approval of proposal:

9. Indigenization Committee (IC) will formulate the proposal as described below.

9.1. The proposal to the CFA at the EOI stage will be structured around the following
considerations:
i. Visibility of orders from HAL’s customers. Firm Orders can be committed to the
DA. Anticipated quantity can be committed if the corresponding Order from
HAL’s customer is already being processed under applicable DPP and if there
is a high probability of it being approved by the CFA. Quantity estimate should
also consider Spares, Floats, replacement after expiry of TTL, etc. as
appropriate. For ROH, in general, 5 years requirement can be taken as a basis
unless a higher demand can be convincingly proved. If any additional quantity
is envisaged (or arises later), a Repeat Order provision can be included in the
EOI/RFP.
ii. Economic viability of the project. Economic viability is to be assessed based
on the estimated unit price of the item to be developed. The estimated unit
price (or benchmark price) will be determined as follows.
1. Import substitution cases: The landed cost of the imported item coupled
with the expected price reduction due to indigenization, declining price trend
in the market, etc. as assessed by the Indigenization Committee, plus the
amortization of the estimated cost of D&D.
2. Other cases: Technical estimate by the Indigenization Committee based on
the price of functionally similar items or nearest comparable items, data in
the public domain or any other reliable source.
3. In both the above cases, the estimated unit price should include taxes,

Make-II Procedure for Hindustan Aeronautics Limited (HAL) Page | 3


levies, etc. as applicable. In case the item needs accompanying essential
deliverables such as mounting tray, connectors, etc. for its intended use,
then the price of such deliverables also should be included in the estimated
unit price.

For assessment of economic viability, the following check should be applied.


 Import substitution cases: The Estimated unit price should be less than or
equal to the landed cost of the imported item. The indigenization Committee
can waive this condition if sufficient justification including strategic benefit,
self-reliance, need to address obsolescence, etc. exists.
 Other cases: Price reasonability of the item would be sufficient to establish
economic viability of the project as well.

9.2. The value for determination of the CFA for approving the proposals would be the
estimated unit price multiplied by the total quantity estimated for the Production stage.

9.3. The proposal to the CFA will contain the following:


i. Background of the proposal, including the reasons for selection of the specific
product/item.
ii. Scope of Work (SOW) for the project including any part of the SOW that will
be done by HAL to be brought out. Providing long term product support should
also be a part of the SOW.
iii. Deliverables from the DA to HAL during the D&D stage. This could include
Engineering unit, SOF unit, etc. to be used for testing and integration and
associated items like Connectors, Mounting trays, Testers, Documentation,
etc. as applicable.
iv. Technical specifications/ Preliminary specifications of the item(s) to be
developed
v. Estimated Unit price (without amortization) and NRC details to be mentioned.
vi. Required timeframes/schedules for PDR, CDR, realization of Engineering unit,
SOF unit, LQT/QT units, Rig test, Software IV&V, Flight Trials, Field Evaluation
and final certification as applicable should be indicated.
vii. Estimated Quantity as per 9.1.i above.
viii. Estimated total cost as per Para 9.2 above
ix. Acceptability of Multiple Technological Solutions. (Details at para no. 25)
x. Draft EOI as per 9.5 below.
xi. Number of DA’s to be shortlisted after evaluation of EOI responses. (See Note
below).

Make-II Procedure for Hindustan Aeronautics Limited (HAL) Page | 4


xii. List of test facilities/ other facilities/ items/ consumables that will be offered for
the purposes of D&D as detailed at 9.4 below.
xiii. Evaluation Criteria for assessment of EOI responses. (Refer Para 9.5 xii)
xiv. Economic viability as per Para 9.1.ii
xv. Planned dates of issue of EOI, due date for Receipt of responses
Note :
a. If the Certification of the item involves substantial efforts in testing and
integration on HAL platforms and therefore supporting multiple vendors
might lead to high cost, clash of priorities and/or inordinate delays, then
generally only one vendor should be selected at the EOI stage based on
the lowest ROM price. In this case, as part of EOI, vendors are required to
submit fully amortized ROM prices (Unit price at Production stage including
amortized cost of D&D).
b. For certain specific items, the Indigenization Committee may decide to
select two vendors at EOI stage. In these cases as part of EOI, vendors are
required to submit fully amortized ROM prices (Unit price at Production
stage including amortized cost of D&D). Amongst technically qualified
vendors, two vendors offering the lowest ROM prices (L1 and L2) will be
considered for granting nil value project sanction order.
c. In all other cases, no ROM prices need be sought as part of the EOI. The
DAs should be shortlisted based on Technical Evaluation. The pricing
element is sought only as part of Commercial RFP.

9.4 Test facilities/ items/ consumables offered by HAL


a. For making prototypes or conducting tests, the vendor may require to use HAL’s
facilities such as Wind Tunnel, Rigs, Labs, Process/Heat Treatment shops, etc.
These can be offered to the DA on chargeable basis or free of cost. The unit
rate (per hour, per occasion, etc.) of such facilities being offered by HAL at cost
& test facilities being offered FOC should be mentioned in the EOI. However,
the value of the test facilities offered on FOC basis should be brought to the
notice of CFA while seeking approval for the proposal. The DA will be required
to estimate the quantity (in hours, no. of times, etc.), apply the unit rates
specified by HAL and arrive at the cost for such utilization of HAL facilities.
These costs also to be taken into consideration by the Vendor for amortizing
the D&D cost while submitting the proposal to HAL.
b. If flight tests are involved for Qualification/Certification, the per-hour rate for
such testing should be mentioned in the EOI. If integration of the item on any
HAL aircraft or other platform involves changes to the aircraft/platform, the
incremental costs for such modifications/de-modification should also be
charged to the vendor. A consolidated cost of such modification / de-

Make-II Procedure for Hindustan Aeronautics Limited (HAL) Page | 5


modification to be paid to HAL by the DA should be estimated upfront and
indicated in the EOI. These costs also to be taken into consideration by the
Vendor for amortizing the D&D cost while submitting the proposal to HAL..
c. During the D&D stage, every time the DA desires to utilize any HAL facility as
above, he should make a request to HAL. In turn, HAL should raise an invoice
on the DA for the payment involved computed based on the rates mentioned in
the EOI or as mutually agreed. The payments can be in stages if the vendor is
unable to pay in advance.
d. If such utilization of HAL facilities to an extent more than what was originally
included in the D&D cost is necessitated (for example, if the item fails in a test,
has to be redesigned and tested again), a specific request should be raised by
the DA and the payment should be made as above. These payments will not
form part of the D&D cost and will therefore not be eligible to be amortized.

9.5 The EOI should contain the following. (Additional information if necessary can also
be included).
i. Scope of Work (SOW) for the project (if any part of the SOW will be done by
HAL, the details have to be mentioned).
ii. Technical specifications / Preliminary specifications of the item to developed
iii. Deliverables from the DA to HAL during the D&D stage. This could include
Engineering unit, SOF unit, etc. to be used for testing and integration and
associated items like Connectors, Mounting trays, Testers, Documentation,
etc. as applicable.
iv. HAL’s estimate of the amortised unit price which is inclusive of the design &
development cost.
v. Required timeframes/schedules for PDR, CDR, realization of Engineering unit,
SOF unit, LQT/QT units, Rig test, Software IV&V, Flight Trials, Field Evaluation
and final certification as applicable should be indicated and vendor should
either confirm or offer his estimate of the schedule which should not be
materially different from what HAL requires.
vi. The aspect of placement of Nil value sanction order/s only to One/Two/Multiple
Vendor to be brought out. Point no : 9.3 (xi) and corresponding Note refers.
vii. If the intention is to shortlist only one or two vendors at the EOI stage, then
Vendor should be requested to quote the fully amortized ROM unit price at the
Production stage. All taxes, duties, etc. included in these cost estimates should
also be sought from the vendor.
viii. Quantities estimated for the Production stage. Firm and Optional quantities can
be stated if so required. Year-wise distribution of Production quantities should
be included if applicable.

Make-II Procedure for Hindustan Aeronautics Limited (HAL) Page | 6


ix. In case multiple vendors are to be issued with Project Sanction Orders, it
should be stated that in general, only the lowest bidder (L1) will be considered
for ordering at the Production stage. In case two vendors are acceptable to
HAL during the Production stage, the EOI should state the manner in which
quantity will be distributed (usually 60:40) and the need for L-2 vendor to agree
to L-1 price and terms.
x. Indigenous Content: The DA should assure that the item(s) deliverable to HAL
during Production stage will have at least 40% Indigenous Content(IC). If the
extant guidelines issued by the MoD permits a lower level of IC for the item to
be developed, the same can be adopted. The vendor should indicate through
credible proof/computations in his EOI response that the IC will be met. It
should also be mentioned that if the mandatory IC is not met (or not likely to be
met as per HAL’s assessment) in the unit used for LQT/QT as applicable, HAL
will be under no obligation to issue Purchase order to the DA. The EOI should
state that the mandatory IC should be maintained during the Production stage
also.
Indigenous Content (IC) shall be mandatorily reported by all stages (tiers) of
manufacturing/ production/ assembly to their higher stages (tiers). All stages
(tiers) are required to aggregate indigenous content based on certifications and
inputs from lower tiers, as well as on the basis of their own procurement actions
and manufacturing activities undertaken. The final aggregation of IC shall be
undertaken by the prime (main) contractor with whom a contract/ PO is signed
by HAL.
The HAL/ MoD reserve the right to conduct an audit of all certificationsand
costs relevant to IC at all or any stages (tiers) of manufacturing/ production/
assembly, starting from the Tier -1 vendor downwards. Applicable DPP will be
referred for defining IC.
xi. List of test facilities/ other facilities/ items/ consumables that will be offered for
the purposes of D&D including their unit rates (as detailed at Para 9.4) should
be stated in the EOI. In his response, the vendor should quote his
quantity/frequency of usage of these facilities and arrive at the cost by applying
these unit rates. The other relevant details and conditions in Para 9.4 should
also be mentioned in the EOI.
xii. Evaluation Criteria for assessment of EOI responses should be provided.
These should include the following.
a. Compliance to Scope of the project including supply of deliverables.
b. Compliance to Technical Specifications
c. Compliance to mandatory Indigenous Content
d. Conformance to the time schedule of D&D

Make-II Procedure for Hindustan Aeronautics Limited (HAL) Page | 7


e. Vendor’s response to utilization of HAL facilities including agreeing to
the unit rates and quoting the quantity/frequency of such utilization.
f. Whether the D&D cost and the unit price during Production stage has
been quoted by the vendor with details as mentioned in the EOI.
g. Specific acceptance of the conditions specified in the EOI and
agreement to abide by them
h. Completeness and comprehensiveness of the vendor’s response
i. Vendor’s confirmation that he has read and understood the HAL Make-
II Procedure as provided on HAL website and would abide by the
procedure and conditions stated therein.
xiii. Due date for submission of response to the EOI.
xiv. Stage at which RFP will be issued (after SOF testing, after LQT/QT, etc. as
decided by HAL) and the conditions subject to which RFP will be issued
(meeting defined time schedule, meeting or likelihood of meeting Technical
Specifications, etc. as decided by HAL).
xv. Vendor’s CEMILAC/DGAQA approval status/plan.

10. Approval of Competent Authority as per DoP (not less than Head of Division)
would be obtained for the proposal formulated as per point no. 9.

11. This provisioning will be valid for six months for issuance of EOI. For cases where
EOI is not issued within six months from accord of approval, Head of the Division can
revalidate the approval based on due justification by the Indigenization Committee.

Identification & Hosting of Items:

12.1. List of projects identified shall be hosted on HAL’s Make in India web portal and
clearly demarcated as “Make-II” so that vendors become aware that they will have to
make up-front investment in Design & Development (D&D).

12.2. Indigenization Department in Corporate Office will make a senior executive in


charge of Make-II specific activities (designated as Nodal Officer). Upon approval of the
EOI by CFA, the divisions will send the EOIs along with a short abstract to the Nodal
Officer who will check whether any another Division has floated EOI for the same or
essentially same item(s). If no such duplication is present, he will host the abstract on the
portal and simultaneously ask the Division originating the EOI to host the EOI on the e-
procurement portal of HAL.

Make-II Procedure for Hindustan Aeronautics Limited (HAL) Page | 8


Issue of EOI:

13. The EOI will be issued as below.


a. The procurement team shall host the EOI (as approved by the CFA) on the e-
tendering portal of HAL after clearance from the Nodal Officer as mentioned
at 12.2 above.
b. The Nodal Officer shall indicate EOI hosting status in the list hosted under
Make-II in the Make in India portal and provide reference to the EOI tender

Evaluation of EOI responses:

14.1 Responses to EOI shall be evaluated as per criteria given in the EOI and a report
shall be finalized by the Indigenization Committee. Prior to this, the Indigenization
Committee and/or the procurement team may interact with the concerned vendors to
obtain clarifications as necessary. At first, those vendors whose technical responses are
acceptable should be shortlisted.

14.2 If multiple vendors are shortlisted, but the intention was stated in the EOI that only
one vendor will be chosen, then the vendor whose quote is the lowest in terms of fully
amortized ROM price should be selected. If two vendors were planned to be selected
as per EOI , then the L-1 and L-2 based on ROM price should be chosen. If any vendor
backs out, the offer should be made to the next vendor in the increasing order of total
cost. [refer note a & b of point no. 9.3 and point no. 9.5(vii)]

14.3 In cases of EOI which had not sought for ROM prices then all the technically
qualified Vendors will be short listed.

14.4 The finalized report with recommendation on shortlisted DA(s) on whom Nil value
Project Sanction Orders are proposed to be issued along with the draft Orders will be put
up to the CFA for approval. CFA will be determined in line with Para 9.2 with the change
that estimated prices will be replaced with prices indicated in the EOI response or as
amended as above. If multiple DA’s are proposed to be issued Project Sanction Order,
the maximum cost among the shortlisted DA’s can be taken as the basis to determine the
CFA. In case ROM price is not sought in EOI, the proposal will be progressed on the
value as determined at 9.2.

15. Generally, Project shall be progressed even if only one EOI respondent is found
meeting the evaluation criteria.

Make-II Procedure for Hindustan Aeronautics Limited (HAL) Page | 9


Issue of Nil Value Project Sanction Order

16. Project Sanction Order with ‘Nil’ financial implications to HAL shall be issued after
obtaining approval of the competent authority. The Order should contain the following
stipulations in addition to general terms and conditions.
 Estimated Quantity involved during the Production stage.
 Unit rates for availing HAL’s facilities and agreed Hours/frequency of utilization
 Schedule of D&D and conditions under which time extensions will be granted.
 Prerequisites to be met by the DA(s) for them to expect to receive an RFP for
Production stage. This could include successfully crossing defined milestones (like
SOF Unit, LQT, QT, etc.) and the likelihood of meeting the technical specifications
of the item being developed.
 In case of urgent/ time bound projects, specific last dates by which PDR,CDR,
LQT, QT or any other milestone should mandatorily be met by the DA(s) to stay in
the race should be mentioned. In case the DA fails to meet these prerequisites
and/or criteria, the Sanction Order will be short closed by HAL without any financial
implications to itself.
 In case Acceptability of Multiple Technological Solutions was indicated in the EOI,
the same has to be reiterated in the project sanction order. Besides the distribution
pattern and the methodology of distribution as covered in EOI has to be clearly
mentioned.

Design and Development:

17. Indigenization Committee will act as the primary interface for DA(s) during the
design and development stage and will facilitate the following: -
i. Provision of requisite professional inputs/documentation/samples to the DA(s).
ii. Providing clarifications to the DA(s) on functional and/or operational aspects of
the equipment, testing of prototype(s) and certification
iii. Coordination of testing and acceptance of prototype(s)
iv. Coordination with HAL Divisions where the DA needs to utilize HAL
infrastructure and facilities during the course of development and testing.
v. On request by the vendor(s), provision of appropriate sample for study (if
feasible) on loan basis. In case this is not feasible, the vendor(s) may be
permitted to study the sample at HAL premises.

Make-II Procedure for Hindustan Aeronautics Limited (HAL) Page | 10


Time Overrun:

18. The approval of extension of timelines for any ‘Make-II’ project may be
recommended by the Indigenization Committee and approval sought from the Head of
the Division. In case multiple vendors are developing the same item, the time extension
should apply to all the vendors. Such extensions should not critically affect the schedule
of the basic project (or product to be launched) for which the item is being developed.
Vendors who fail to complete the development (or cross predetermined milestones to
make them eligible to receive the RFP) within the extended schedule should be
considered as unsuccessful.

Solicitation of Commercial offers after successful D&D:

19. In order to ensure that there is no large time gap between the end of development
and placement of the Production Order, the commercial solicitation process through an
RFP should begin sufficiently in advance. At the same time, it should be ensured that
such a process should not be initiated even before sufficient positive indications are
available that the development will likely result in a successful product. Preconditions to
become eligible to receive an RFP will be as mentioned in the Project Sanction Order.

20. The RFP should be issued as per the usual commercial procedures followed by
HAL. Considering the nature of this RFP, all DA’s who have successfully crossed the
predetermined milestone of development (as stated in the Project Sanction Order) would
be shortlisted as technically qualified and the Commercial offers would be solicited from
them. In addition to the normal contents of the RFP, the following specifics should be
mentioned.
(a) Year-wise distribution of quantity as required by HAL (Financial Year basis is
preferable). The RFP should also state that the actual pattern of Ordering can be
different from what is indicated in the RFP and that the Order stream can be
terminated at any point of time due to factors beyond the control of HAL.
(b) The Vendor is required indicate the total D&D price and the production unit price
separately. However the D&D price will be paid pro-rata along with the production
unit price against deliveries.
(c) If the deliveries are spread over several years, the DA should be asked to quote
year-wise prices or an escalation formula along with a base year price. (In case of
strong Learning Curve effects, it could be possible that the prices can remain
constant over the years or even reduce over the years). In such cases where the
cash outgo from HAL will be spread over several years, DCF technique should be
used to determine L-1, L-2, etc. on Present Value basis.

Make-II Procedure for Hindustan Aeronautics Limited (HAL) Page | 11


(d) The fully amortised Unit price at the RFP stage generally need to be the same as
or less than the ROM price quoted during EOI stage [refer note a & b of point no.
9.3 and point no. 9.5(vii)]. However, considering the risks inherent in D&D
programmes, HAL can consider, based on substantiation provided by the
vendor(s), accepting up to 10% increase with respect to the ROM price quoted at
the EOI stage. In case the price quoted is beyond this 10% limit, but the only
vendor/ L-1 vendor agrees to bring it down within the limit during the Price
Negotiation stage, HAL can accept the same. This 10% will exclude normal
escalation applicable in case HAL alters the delivery pattern with respect to what
was indicated in the EOI.
(e) Even though RFP is issued to a certain DA, he can be dropped from the race at
any stage if he fails to meet the success criteria as defined in the Project Sanction
Order at any stage after issue of the RFP (for example, RFP was issued after
clearing the LQT stage, but the DA failed later during the QT stage).
(f) In case DA’s have utilized certain HAL facilities offered FOC for development of
the item, the successful DA’s should not directly deal with HAL’s customers for
such items.

21. Determination of the CFA for RFP issuance: Cases where only one DA is involved
from the beginning will be treated as Single Tender cases. Cases where two DA’s began
development but only one DA successfully developed the item will be treated as
Resultant Single Vendor case. All others will be treated as Limited tender cases with two
DAs. Value for determination of the CFA will be the total cost estimated for the Production
stage. (Unit price including amortization and taxes, etc. as quoted/agreed at the EOI
stage multiplied by the total quantity estimated for the Production stage including optional
quantity if any.

Qualification Testing(QT) / Flight Trial Evaluation:

22. Lab , Environmental , integration, Rig tests and Flight trials as agreed at the EOI
stage would be carried out by HAL to validate the performance of the prototype(s) offered
by DA/DA’s. In case multiple DA’s are involved, there could be a clash of priorities in
terms of time slots available. In such cases, HAL should sequence the tests at its
convenience and the DA(s) affected by such shifting of test slots should be given a
corresponding time extension for completing the development. Based on the outcome of
Limited QT/QT/ flight trials as cleared by DGAQA/ CEMILAC, etc. as applicable, the
Indigenization Committee will declare successful DAs, to enable further progression for
procurement.

Make-II Procedure for Hindustan Aeronautics Limited (HAL) Page | 12


Commercial Negotiations by Contract Negotiation Committee
(CNC):

23. The Procurement team will carry out all processes from opening of commercial
bids & commercial evaluation to final selection of vendor (and in case of multiple
successful DA’s, the quantity distribution to each DA where applicable) and negotiation
of P.O./Contract clauses with the DA(s). Head of the Indigenization Committee should
also be part of the CNC so as to ensure continuity. Besides if any additional member of
IC need to be co-opted the same can be done. Negotiations in case of multivendor
projects having procurement cost less than Rs 5 crore shall be carried out only in special
circumstances with reasons to be recorded. However, CNC will carry out negotiations for
all single vendor cases, other than resultant single vendor cases, irrespective of value of
the project. Generally, no negotiation should be carried out, even in single vendor cases,
if the L-1 price is lower than the import parity price by 20% or more.

24. After negotiations, the extant procurement procedure of HAL would be followed
and the Procurement contract/ Purchase Order would be signed.

Multiple technological solutions:

25. In cases involving large quantities and where multiple technological solutions are
acceptable, an option may be provided in the EoI and subsequently in the Commercial
RFP for the ‘procurement’ phase for procurement of specified quantities (in the ratio of
60:40) from L1 & L2 vendor who have successfully developed the product, on the
condition that the L2 vendor accepts the price and terms & conditions quoted by the L1
vendor. In case L2 vendor does not agree to match with L1 price, the next successful
DAs say L3 shall be offered to match L1 price and so on progressively.

26. As explained earlier, if the costs/time/effort in integration and testing (including


flight testing) of the item under development is prohibitive, only one DA will be issued the
Project Sanction Order. Otherwise, for risk management, better price discovery, etc.,
multiple DAs can be selected and issued with Project Sanction Orders. In cases involving
multiple DA’s, DA’s other than the ones on whom production orders have been placed
will be issued a certificate indicating that the product has been successfully trial evaluated
by HAL. Further, if the DA’s continue development of the item after design corrections,
etc., HAL shall render minor assistance as necessary to such DA’s to obtain certification
from CEMILAC or DGCA as applicable to facilitate such vendors to explore other markets
and remain in the production of the product. Such assistance may be rendered as per
mutually agreed terms. Whenever a DA has successfully completed development under
the present Make-II procedure and irrespective of whether the Production Order for the

Make-II Procedure for Hindustan Aeronautics Limited (HAL) Page | 13


item has been issued by HAL or not, HAL on request by the DA should issue testimonials
showing for which platform or ground system the item was developed, what trials have
been done in HAL, associated test results, etc. for the DA to explore business outside
HAL. While issuing such testimonials (or certificates mentioned above), third party
confidential information should not be disclosed. Also, no NDA or Confidentiality clauses
in MOUs and Contracts to which HAL is a signatory (or such obligation not to disclose
certain information applies to HAL as a government owned company) should be
breached. In case of doubt, a generic certificate/testimony can be issued without
mentioning specific details like platform, etc. Heads of Divisions are authorized under this
procedure to sign and issue certificates and testimonials mentioned above.

Intellectual Property Rights (IPRs):

27. HAL and the successful DA(s) on whom Production Orders have been placed by
HAL shall be co-owners of Intellectual Property generated during the project including
rights of sale and after-sale service of the item developed. Each of the co-owners can
exploit the IP to its benefit, independently or jointly, with or without the consent of other
co-owner(s). Where DA’s have utilized certain HAL facilities offered FOC for development
of the items, the successful DA’s should not directly deal with HAL’s customers for such
items. However, this generic provision doesn’t affect the right of the parties to make any
other mutual agreement as to the exact manner in which the IPR will be utilized on a
case-by-case basis, including non-compete agreements. As the manufacturing and ROH
technology will be available only with the DA(s), in order to enable independent
exploitation of the IP by HAL, the transfer of technology for manufacturing and ROH in
the form of comprehensive and complete documentation (such as production drawings &
Design/technology documents) should be supplied by the DA(s) if so required by HAL.
HAL at its discretion can waive its rights over the IP and permit the DA(s) to retain the
IPR in an exclusive basis. The converse condition also will be permissible.

Project Management, Review and Monitoring:

28. The progress of the project would be monitored by Indigenization Committee on a


regular basis. HAL may engage services of independent consultants/experts on need
basis for assessing the physical and/or financial progress of any project.

29. Review of the projects shall be carried out by the Divisional Head and a Quarterly
Status Report should be forwarded to Corporate Indigenization Cell for consolidation and
reporting to DDP/ MoD.

Make-II Procedure for Hindustan Aeronautics Limited (HAL) Page | 14


Foreclosure/ Reduction in quantity
30. No foreclosure of any development Project will be done other than for reasons
mentioned in this Procedure. Serious breach of contractual terms by the DA,
unsatisfactory progress of the project, serious design deficiencies, repeated failures
during testing, quoting unacceptably high prices for the production stage, etc. are valid
reasons for foreclosure. If HAL’s EOI or RFP is based on an existing or anticipated Order
from its customer(s), and if such Order gets foreclosed or does not materialize, then the
related Project Sanction Order or the Supply Order can be foreclosed by HAL.
(a) In case the foreclosure is done during the Production stage, the unamortized
portion of the cost of D&D will be reimbursed by HAL to the DA(s). For this
purpose, it will be assumed that the cost of D&D is uniformly amortized over the
firm quantity mentioned in the Production Order. (If “D” is the cost of D&D, “Q” is
the firm quantity and “q” is the quantity cancelled, then the reimbursement will be
equal to D×[q/Q].
(b) Generally, foreclosure is not done before the development process is completed.
However in exceptional cases where the foreclosure is done during the D&D
stage, for reasons attributable to HAL, the irreversible financial commitments
made by the DA(s) up to the date of HAL notifying the foreclosure will be
reimbursed to the DA(s). For this purpose, the DA(s) should submit a claim
verified and signed by its/their Auditor(s) along with documentary evidence. HAL
will independently verify the evidences presented and determine the amount to
be reimbursed. Such amount should have a clear proportionality to the cost of the
work completed out of the cost of the total SOW that prevailed at the start of the
project. The reimbursement shall not exceed the cost of D&D in any case. All
usable or salvageable assets and material covered under the reimbursement
claim (and remaining in the possession of the vendor) and documentation
generated during the period before foreclosure are to be handed over to HAL.
(c) Notwithstanding anything mentioned under (a) and (b) above, no reimbursement
shall be made to the DA(s) if the foreclosure is due to reasons attributable to the
DA(s). Such reasons could include serious breach of contractual terms,
unsatisfactory progress of the project, serious design deficiencies, repeated
failures during testing, demanding higher prices/ erratic supply/ poor quality during
the production stage, etc.

Deficient delivery
31. In case the successful DA (L-1) does not supply the production quantity in
accordance with the contract, the pending quantity will be taken up for procurement as
follows:
- If two DA’s are involved in supply at L-1 rate & terms as per a quantity distribution
arrangement, the DA other than the one in default will be requested to take up the
pending quantity in addition to his own.

Make-II Procedure for Hindustan Aeronautics Limited (HAL) Page | 15


- If the above arrangement did not exist originally, a fresh Tender can be issued to
the other DA(s) who met the success criteria at the development stage but did not
get the Production Order. The prices and terms can be negotiated afresh with the
lowest bidder/bidders.
- The DA in default should transfer Drawings, Tools, Test Equipment, etc. used in
production and ROH to HAL free of cost so as to continue production.
- The balance portion of the cost of D&D as part of amortization will also not be paid
to the Vendor in default. No further punitive action other than imposition of LD
should be taken against the DA in default.

Additional requirement
32. If the quantity is likely to turn out to be higher than what is originally assessed
during the EOI stage, the supply Contract with the DA pursuant to the RFP can have
Option/Repeat Order clause to cover the additional quantity likely to materialize later. In
case such increase in quantity could not be anticipated, and no Option/Repeat Order
clause exists, a fresh Single or Limited Tender should be issued depending on whether
one or more successful DA’s is/are available. If due to lapse of time, the other DA might
not be in a position to set up production facilities or to make supplies, then a fresh Single
Tender should be issued to the existing supplier.

Miscellaneous
33. All EOIs and RFPs issued under this procedure should make a reference to this
procedure (which should be accessible to all potential vendors through HAL’s Make-in-
India web portal) and state that although certain terms and conditions may not be present
in the EOI/ RFI, vendors should explicitly state and agree in their responses that they
have read and understood the procedure and that they agree to abide by it in dealing with
issues during their engagement with HAL for any Make-II project.

34. Although this Make-II procedure is broadly modelled on the similar procedure
promulgated through the DPP-2016, it is clarified that no related provision in the DPP-
2016 (or its later versions) shall apply to the HAL procedure by implication, extrapolation,
generalization or wide interpretation. Dispute resolution under this procedure will be as
per the mechanism specified in the EOI/RFP/Contract as applicable at the appropriate
stage when the dispute arises.

35. Headings used in this procedure are merely for convenience of reference and
organization of ideas. As such, the headings in no way shall limit understanding or
interpretation of the subject matter dealt with through this procedure in a holistic manner.

-XXX-

Make-II Procedure for Hindustan Aeronautics Limited (HAL) Page | 16


Annexure-1
Indicative Eligibility Criteria for responding to EoI

1. All the entities (except start-ups/ MSMEs) satisfying all of the following criteria shall be
considered as an eligible ‘Indian Vendor’ for evaluation of EoI by Indigenisation
Committee (IC).

i. Public limited company, private limited company, partnership firms, limited


liability partnership, one Person Company, sole proprietorship registered as
per applicable Indian laws. In addition, such entity shall also possess or be in
the process of acquiring a license if the product to be developed under this
Make-II procedure requires license as per the licensing policy of the
Department for Promotion of Industry and Internal Trade.
ii. The entity has to be owned and controlled by resident Indian citizens; entity
with excess of 49% foreign investment will not be eligible to take part in
Make-II.

2. Criteria for Startups/MSME:

i. Startups recognized by Department for Promotion of Industry and Internal


Trade under the eligible Domain/Category as per Annexure-II, shall be eligible
to participate.
ii. MSMEs registered as per provisions of Micro, Small & Medium Enterprises
Development (MSMED) Act, 2006
iii. For projects with estimated cost (Design & development phase and
Procurement phase) not exceeding Rs 250 Lakhs, no separate technical/
financial criteria be defined for both ‘startups’ and ‘MSMEs, to encourage their
participation.

****

Make-II Procedure for Hindustan Aeronautics Limited (HAL) Page | 17


Annexure-II

Categories & Domains of startups eligible for participation in Make-II


Sl.No Category
(i) Engineering
(ii) Manufacturing
(iii) Research
(iv) Government

Sl. No Industry Domain


(i) Aeronautics/Aerospace &Defence
(ii) Analytics
(iii) Augmented/Virtual Reality
(iv) Automotive
(v) Computer Vision
(vi) IT Services
(vii) Telecommunications and Networking
(viii) Green Technology
(ix) Internet of Things
(x) Nanotechnology
(xi) Renewable Energy
(xii) Robotics
(xiii) Security Solutions
(xiv) Technology Hardware

Make-II Procedure for Hindustan Aeronautics Limited (HAL) Page | 18

You might also like