Checklist Sheet
Checklist Sheet
Checklist Sheet
Manager Excavator
Quantity Surveyor Bulldozer
Surveyor/Geodetic Grader `
Supervisor Traxcavator
Concrete Foreman JCB
Steel Bender Poker Vibrator
Earthworks Foreman Plate Compactor
Carpenters Vibrating Roller
Masons Tipper Trucks
Operators Concrete Mixers
Drivers Water Pump
Labourers Water Tanker
Security
Mechanic
Site Activities
Material on Site
Testing
Surveying
Name: Name:
Signature: Signature:
Date: Date:
DEOKE CONSULT
(CIVIL AND STRUCTURAL ENGINEERS)
SUPPLY OF MATERIALS
Contract: CONSTRUCTION OF CONCRETE BRIDGE
Contract No:
Employer: DEPARTMENT OF URBAN ROADS
Engineer: DEOKE CONSULT
Contractor:
SECTION:
Ref.NO. :
ARRIVAL DISPOSAL REMARKS &
DATE TYPE OF MATERIAL QUANTITY WAYBILL SERIAL
TIME TIME INSPECTION
SUBJECT: _____________________________________________________________
Details of work:
Location:
Material used:
Labour content:
Sketches:
(Reference)
(Date)
In accordance with the provisions of Sub-Clause 52.4 of the Conditions of Contract you are hereby
instructucted to execute the following works on a Dayworks basis:
This work shall be valued in accordance with Sub-Clause 52.4 of the Conditions of Contracts and th
included in your accounts against (insert item number) in the signed BoQ.
These sub-total for this Dayworks Order shall be given separately at the end of the Bill Section
(insert Number) in your subsequenct claims for interim payment.
(insert signature)
(insert name)
Engineer's Representative
30
DEOKE CONSULT
(E N G I N E E R S, ARCHITECTS & D E V. C O N S U L T A N T S)
(Reference)
(Date)
31
DEOKE CONSULT
(E N G I N E E R S, A R C H I T E C T S & D E V. C O N S U L T A N T S)
Material Equipment
Labourers Others
32
DEOKE CONSULT
(E N G I N E E R S, A R C H I T E C T S & D E V. C O N S U L T A N T S)
INSPECTION SHEET
Contract: CONSTRUCTION OF STEEL BRIDGES
Contract No:
Employer: DEPARTMENT OF FEEDER ROADS
Engineer: ARCSCALE CONSULT
Contractor:
SECTION:
General Site Clearance Date
Item No.: Location
Item Description Unit Q'ty Item Description Unit Q'ty
Materials Equipment
Labourers Others
INSPECTION BY CHIEF RESIDENT ENGINEER'S STAFF APPROVED BY THE CHIEF RESIDENT ENGINEER
Name: Name:
Signature: Signature:
Date: Date:
33
ARCSCALE CONSULT
(E N G I N E E R S, A R C H I T E C T S & D E V. C O N S U L T A N T S)
INSPECTION SHEET
Contract: CONSTRUCTION OF STEEL BRIDGES
Contract No:
Employer: DEPARTMENT OF FEEDER ROADS
Engineer: ARCSCALE CONSULT
Contractor:
SECTION:
Preparation Works Date
Setting out, Geometric Tolerance and Rectification Location
Item Description Unit Q'ty Item Description Unit Q'ty
Materials Equipment
Labourers Others
INSPECTION BY CHIEF RESIDENT ENGINEER'S STAFF APPROVED BY THE CHIEF RESIDENT ENGINEER
Name: Name:
Signature: Signature:
Date: Date:
34
EUDIA-PLUS ENGINEERING SERVICES LIMITED
NON CONFORMANCE REPORT (NCR)
CONTRACT: PROPOSED THREE BLOCK, 10 STOREY 1,2&3 BEDROOM APARTMENTS AT SHIASHIE, EAST LEGON
CONTRACTOR: CLIFTON HOMES
ENGINEER: EUDIA-PLUS ENGINEERING SERVICES LIMITED
CLIENT: CLIFTON HOMES
DATE : TIME : NCR No. :
COMPONENT/ACTIVITY:
CONDITION :
LOCATION
REMEDIAL ACTION
ACTION
SKETCHES
LOCATION
ACTION TAKEN
……………………………………………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
ACTION TAKEN…………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
……………………………………………………………………………………………………………………………………………………………………………………..
REPORTED BY APPROVED BY DISTRIBUTION
Sign: ……………………………………………….. Sign: ……………………………………………….a. Team Leader
b. Site Engineer
Name: …………………………………………….. Name: …………………………………………….c. Chief Resident Engineer
d. Quantity Surveyor
Position: ………………………………………… Position: ……………………………………… e. Senior Surveyor
f. Contractor's Representative
Date: ………………………………………………. Date: ………………………………………………
ARCSCALE CONSULT
(E N G I N E E R S, A R C H I T E C T S & D E V. C O N S U L T A N T S)
PROGRAMME OF WORKS
CONTRACT : CONSTRUCTION OF STEEL BRIDGES
CONTRACT No. :
CONTRACTOR: LOCATION: ……………………………(CENTRAL REGION) DATE: ………………………..
Year
No. WORK ITEMS Unit Qty Months 1 2 3 4 5 6 7 8 9 10 11 12
Weeks
1 Mobilization sum
5 Reinforced Concrete
Bridge Foundation m³
Abutment Walls m³
Culverts m³
8 Sub-base (Road) m²
13 Demolization sum
43
ARCSCALE CONSULT
(E N G I N E E R S, A R C H I T E C T S & D E V. C O N S U L T A N T S)
13 Demolization
44
ARCSCALE CONSULT
(E N G I N E E R S, A R C H I T E C T S & D E V. C O N S U L T A N T S)
PROGRESS REPORT
DATE:
CONTRACT: CONSTRUCTION OF STEEL BRIDGE
CONTRACTOR:
REGION : CENTRAL
COMMENCEMENT DATE:
COMPLETION DATE:
ORIGINAL CONTRACT SUM:
REVISED CONTRACT SUM:
PREVIOUS EXPENDITURE:
VALUE OF CURRENT WORK:
TOTAL EXPENDITURE TO - DATE :
PERCENTAGE OF WORK COMPLETED TO - DATE:
NO PHYSICAL DETAILS BRIEF DESCRIPTION OF % OF CONTRACT % COMPLETED
OF WORK TO BE DONE WORK TO BE DONE VALUE TO - DATE
OR AMOUNT IN BOQ
1 GENERAL ITEMS
2 BRIDGE FOUNDATION
3 APPROACH ROAD
4 BRIDGE COMPONENTS
5 RELIEF CULVERTS
6 ROADS
TOTAL
Signature …………………………..
45
ARCSCALE CONSULT
(E N G I N E E R S, A R C H I T E C T S & D E V. C O N S U L T A N T S)
Slump:
46
TRIAL MIX OF CONCRETE FOR CLASS
46
ARCSCALE CONSULT
(E N G I N E E R S, A R C H I T E C T S & D E V. C O N S U L T A N T S)
47
TESTED BY CHECKED BY APPROVED BY
47
CONCRETE CUBE COMPRESSIVE STRENGTH
47
ARCSCALE CONSULT
(E N G I N E E R S, A R C H I T E C T S & D E V. C O N S U L T A N T S)
48
TESTED BY CHECKED BY APPROVED BY
48
ARCSCALE CONSULT
(E N G I N E E R S, A R C H I T E C T S & D E V. C O N S U L T A N T S)
2. Source of Material
Chippings Sand
Cement Admixture
3. Aggregate
Aggregate Max Size Flakiness Index Specific Absorption Unit Abrasion
Gravity Weight
Chippings
Sand
4. Cement
Specific Setting Time Normal Soundness Compressive Strength
Gravity Initial (hr) Final (hr) Consistence (%) 3 days (kg/cm²) 7 days (kg/cm²)
49
DEOKE CONSULT
(E N G I N E E R S, A R C H I T E C T S & D E V. C O N S U L T A N T S)
52
ARCSCALE CONSULT
(E N G I N E E R S, A R C H I T E C T S & D E V. C O N S U L T A N T S)
M Backfill
A
T
E Gradation
R
I Compaction
A
L Compaction
CBR
Penetration
Sampling Concrete
Asphalt
Prime Coating
Compressive Strength
Proofrolling Test
Slump Test
PREPARED BY APPROVED BY
Name: Name:
Signature: Signature:
Date: Date:
ARCSCALE CONSULT
(E N G I N E E R S, A R C H I T E C T S & D E V. C O N S U L T A N T S)
SECTION:
No. SI
CONTRACT: Construction of Steel Bridges CONTRACT No.:
DATE:
TO:
Contractor's Representative:
Carry out works in accordance to the paid items in the Bill of Quantities.
Carry out the following work at day work rates. Time sheets must be signed by the engineer.
DESCRIPTION OF WORKS.
The contract/works completion date and price are / are not altered as a result of this instruction.
PIER
WEST ABUTMENT
DEOKE CONSULT
(CIVIL AND STRUCTURAL ENGINEERS)
DEOKE CONSULT
(CIVIL AND STRUCTURAL ENGINEERS)