PROJECT Name

NEW CAPITAL
INSPECTION AND TEST PLAN
MASONRY WORK

Contractor REDCON SPAIN CONTRACTING Ref.ITP NO : ITP 1


Package No. 1183 Rev. : 2
Description of Work MASONRY Date : 24-1-2021
Location ENTRADA NEW CAPITAL

Inspection Parties / Type of


Inspection
Work phase (description of Project Specification Test Method / Type Record (ICL, Test
NO Codes and Standards Acceptance Criteria Frequency ( Witness or Hold Point) Remarks
Inspection / Testing) Ref. of Inspection Report)
CONTRACTOR
MIMAR
(Q.C)

Sec04810-part 1,
1 Material approval. ASTM 140 ,1314 Sec 042000 each building Approved MIR T/H T/H
1.05

2 Mortar Proportions & Mixing ASTM C 270,476,1506 visual inspection Sec 042000 TEST RESULT v S

each floor for eah


3 CURING visual inspection S S
building

each floor for eah


4 fixed point for check level visual inspection IR H H
building

5 check line and axis IR S S

visual inspection
Application of first course of dimensional approved shop
6 IR H H
masonry and wall ties. check,alignment drawings
and plumb

In Process Wall Building visual inspection


dimensional approved shop
7 (joints,alignment,accessories, ASTM A 496 S S
Max. Hight /day work and check,alignment drawings
grouting around ties/openings) and plumb

approved shop
8 LINTEL LEVEL IR H H
drawings

approved shop
9 SILL LEVEL IR H H
drawings

visual inspection
Final Inspection of masonry
dimensional approved shop
10 work and curing BLOCK ASTM A 496 IR H H
check,alignment drawings
FILLER WITH FULL HEIGHT.
and plumb
CONSTRUCTION
DISTRIBUTION: CONSULT OTHER
MANAGER
ANT S ABBREVIATIONS : VERIFICATION CODES
SC - Subcontractor H-HOLD
C - Contractor W - WITNESS
RA - Regulatory Authority S-Surveillance
T-TEST

4.33 Inspection and Test Plan : Inspection and Test Plan