I PURPOSE
II APPLICATION
To define and describe the Process Failure Mode & Effect Analysis procedure as
required by the automotive customer. In addition, the procedure shall only be
implemented for process or product that is ISO/TS 16949:2002 prerequisite.
III RESPONSIBLE
IV DEFINITION
V PROCEDURE
1.2 PFMEA team member shall consist of QA, production, engineering, tool room,
store, purchasing, and planning for brainstorming purpose.
1.3 PFMEA should be completed before trial production. Therefore, the key date should
be defined clearly in the PFMEA report.
2.1 The team should conduct preliminary analysis by referring to the relevant process
flow chart and control plan, which cover right from in-coming inspection until
delivery of final product.
2.2 PFMEA team members should study the details of all the processes in the flow
chart and control plan in-order to understand the process requirements before
PFMEA to be carried out.
2.3 Relevant reports such as inspection report, reject report, rework report, scrap
report, customer complaint records, drawing, spec, etc. may be referred before
PFMEA being performed.
3.1 Together, the team shall deduce, evaluate, review and assign the following
item/parameter into each designated column in the PFMEA report.
Relevant data / reports may be used for reference purposes before the ranking
for occurrence being decided. Appropriate QC tools such as fishbone diagram
may be used for brainstorming purposes.
3.2 To fill in the current process control according to present Control plan. Current
process control for consideration are those that :
Prevent the cause of failure mode from occurring such as daily preventive
maintenance
Subsequently the team members will then assign appropriate ranking for
detection & fill in detection column.
3.3 The team shall compute the risk priority number (RPN).
3.5 However, when RPN <100, if Severity X Occurrence >=36, then recommended
action should be identified.
Process Failure Mode And Effect Analysis
Operational Procedure : OP- 7.3.1.1 Revision: 4 Page 6/7
3.6 The intent of any recommended action is to reduce any one or all of the
occurrence, severity and / or detection rankings.
The team shall determine and select responsible person / selection to take up
the responsibility to improve the designated process characteristic and decide
the completion date for the task.
4.1 The PFMEA team leader shall follow up on the task given to selected section or
person and get the required feedback / response for reassigning the severity,
occurrence and detection (into each designated column) and compute the new
risk priority number for each characteristic. The resulting RPN shall be reviewed
in order to justify any additional action required.
4.2 The team shall be responsible in assuring that all recommended action is
effectively implemented so that process improvement is achieved.
4.3 The PFMEA report is a living document & should always reflect the latest
design level & practices in the production floor. Therefore, it should be revised if
necessary.
Process Failure Mode And Effect Analysis
Operational Procedure : OP- 7.3.1.1 Revision: 4 Page 7/7
VI REFERENCE
Control Plan
VIII APPENDIX
Nil