BUAD 802 Summary
BUAD 802 Summary
BUAD 802 Summary
Operations strategy:
✓ Strategic planning is a process that brings to life the mission and vision of enterprise.
✓ The implicit objective of a business strategy is to deliver sustained superiority, not just average,
performance relative to the competition
✓ To deliver superior performance, a firm must strive to select product attributes that are distinct from
those of its competition and create business processes that are more effective than its competition.
✓ Operational effectiveness refers to any number of practices that allow a company to better utilise its
inputs by reducing defects in products or developing products faster ”
✓ Corporate strategy defines the businesses in which the corporation will participate and specifies how
key corporate resources will be acquired and allocated to each business.
✓ Business strategy defines the scope of each division or business unit in terms of the attributes of the
products that it will offer and the market segments that it will serve.
✓ functional strategy defines the purpose for marketing, operations, and finance—the three main
functions in most organisations:
a. Marketing: identify and target customers BU wants to serve
b. Operations: designs, plans, and manages processes through which BU servers customers
c. Finance: acquires and allocate resources needed by BU to serve customers
Process analysis
✓ The aim of the analysis phase of a business process design project is to understand how the processes
of a business function and interact; the aim of the design phase is to improve the way that those
processes operate and interact.
✓ Understand the organisation and its purpose or “mission” and relate this to the organisation’s current
business processes.
✓ Identify and analyse the collection of processes and activities currently operational within the
organisation, and ascertain how far they achieve the business objectives.
✓ There are two type: Strategic(Managers) and Tactical(Executors)
✓ The result of process analysis is fed into design phase in order to:
o Investigate options for achieving improvement by redesigning the processes currently in
operation.
o Identify and prioritise areas for improvement.
o Implement process design according to an agreed schedule.
✓ Data: is information that has been translated into a form that is more convenient to move or process
✓ Information: data that are processed to be useful; provides answers to "who," "what," "where," and
"when" questions.
✓ Knowledge: application of data and information; answers "how" questions.
✓ Understanding: appreciation of "why".
✓ Wisdom: evaluating understanding.
✓ Data Protect Act is the main piece of legislation that governs the protection of personal data within a
country.
✓ Basic Economic Decision making is the process of identifying alternative course of action and selecting
an appropriate alternative in a given decision situation.
o Identifying alternative courses of action means that an ideal solution may not exist or might not
be identifiable.
o Selecting an appropriate alternative implies, that there may be a number of appropriate
alternatives and that inappropriate alternatives are to be evaluated and rejected. Thus,
judgment is fundamental to decision making.
✓ The three B.E.D every nation should make include; knowing the commodities to manufacture or
produce, second, the process of manufacturing the best quality and last, the market available and the
competitive advantage.
Inventory management:
✓ An Inventory is:
o A detailed, itemised list, report, or record of things in one’s possession, especially a periodic
survey of all goods and materials in stock.
o The process of making such a list, report, or record.
o The items listed in such a report or record.
o The quantity of goods and materials on hand; stock.
o An evaluation or a survey, as of abilities, assets, or resources.
✓ Inventory Management: It is a science primarily about specifying the shape and percentage of stocked
goods
✓ Inventory is divided into:
o Merchandize: Items purchased from other crafters to be sold in your shop.
o Manufacturing
▪ Raw Materials: Materials purchased to produce a product
▪ Work-In-Progress: Materials in various stages of production
▪ Finished Goods: Finished goods ready for market.
Business forecasting
✓ Sales Forecast: to forecast the demand for those goods. Manufactures need to know how much to
produce. Wholesalers and retailers need to know now much to stock
✓ A predecessor event: an event (or events) that immediately precedes some other event without
any other events intervening.
✓ A successor event: an event (or events) that immediately follows some other event without any
other events intervening.
✓ Activity: is the actual performance of a task. It consumes time, it requires resources (such as
labour, materials, space, machinery), cannot be completed until the event preceding it has
occurred.
✓ Optimistic time (O): the minimum possible time required to accomplish a task, assuming
everything proceeds better than is normally expected.
✓ Pessimistic time (P): the maximum possible time required to accomplish a task, assuming
everything goes wrong (but excluding major catastrophes).
✓ Most likely time (M): the best estimate of the time required to accomplish a task, assuming
everything proceeds as normal.
✓ Expected time (TE): the best estimate of the time required to accomplish a task. TE = (O + 4M + P)
÷6
✓ Float or Slack is the amount of time that a task in a project network can be delayed without
causing a delay
✓ Critical Path: the longest possible continuous pathway taken from the initial event to the terminal
event.it determines total calendar time
✓ Critical Activity: An activity that has total float equal to zero. Activity with zero float does not
mean it is on the critical path.
✓ Lead time: the time by which a predecessor event must be completed in order to allow sufficient
time for the activities that must elapse before a specific PERT event reaches completion.
✓ Lag time: the earliest time by which a successor event can follow a specific PERT event.
✓ Slack: the slack of an event is a measure of the excess time and resources available in achieving
this event. Positive slack would indicate ahead of schedule; negative slack would indicate behind
schedule; and zero slack would indicate on schedule.
✓ The critical path method (CPM) is a step-by-step project management technique for process
planning that defines critical and non-critical tasks with the goal of preventing time-frame
problems and process bottlenecks.
✓ Main Objective: to determine how best to reduce the time required to perform routine and
repetitive tasks that are needed to support an organization
✓ Critical path analysis is an extension of the bar chart. The CPM uses a work breakdown
structure, where all projects are divided into individual tasks or activities.
✓ It helps decision makers to identify the best estimates (based on accurate information) of the
time that is needed to complete the project.
✓ The network diagram also offers a prediction of the completion time of the project, and can help in
the planning and scheduling of the activities needed for the completion of the project.
✓ Identifying the critical path for the project is the next stage of the analysis of the network diagram.
✓ CPM also encourages a disciplined and logical approach to planning, scheduling and managing a
project over a long period of time.
✓ Optimisation of the time-cost relationship in project management is also possible using the CPM, as
managers can visually identify the activities that can pose a problem if not managed and monitored
effectively over a period of time.
✓ Tracking the CPM is also helpful. Managers can identify areas where attention needs to be focused.
✓ Scheduling of activities is possible. The CPM identifies the entire chain of activities.
✓ The CPM also identifies slack and floats time in the project. Thus, project managers can identify
when resources can be reallocated to different activities and the shifting and moving of activities to
best optimize the utilisation of the resources.
✓ In many large projects, there can be more than one critical path in the network diagram mapped
out. When such a situation arises, CPM can help managers identify suitable plan of actions to
handle these multiple critical paths.
✓ PERT planning involves the following steps which are described below:
o Identify the specific activities and milestones.
o Determine the proper sequence of the activities
o Construct a network diagram
o Estimate the time required for each activity
✓ PERT assumes a beta probability distribution for the time estimates:
o Expected time = ( Optimistic + 4 x Most likely + Pessimistic ) / 6
o This expected time may be displayed on the network diagram.
o To calculate the variance for each activity completion time, if three standard deviation times
were selected for the optimistic and pessimistic times, then there are six standard deviations
between them, so the variance is given by:[(Pessimistic - Optimistic) / 62]
✓ A PERT chart presents a graphic illustration of a project as a network diagram consisting of numbered
nodes (either circles or rectangles) representing events, or milestones in the project linked by labeled
vectors (directional lines), representing tasks in the project.
✓ PERT planning involves the following steps:
o Identify the specific activities and milestones.
o Determine the proper sequence of the activities.
o Construct a network diagram.
o Estimate the time required for each activity.
o Determine the critical path.
o Update the PERT chart as the project progresses.
✓ Linear programming is a mathematical technique used in computer modelling (simulation) to find the
best possible solution in allocating limited resources (energy,machines, materials, money, personnel,
space, time etc.) to achieve maximum profit or minimum cost.
Developments in operations management