17IPST028
17IPST028
17IPST028
Abstract—Results of field measurement of trapped charges adequate energy absorption capability for other transients on
on a 275 kV cable will be presented. The instrumentation and the cable such as energisation with no trapped charges,
calibration method used in the measurement will be discussed. It lighting on the relevant overhead lines connected to the cable
will be shown that if the cable is not force-discharged by means of and external faults, all of which had been considered during
earth switches, the trapped charges will decay very slowly. The
design stage.
atmospheric parameters such as humidity and temperature affect
the discharge time, which also depends on how much of the It is usually assumed that the trapped charges on an isolated
circuit is exposed to open air. cable are drained to earth within a short time of a few hours
The measurement results are used in EMTP-ATP simulation through the cable insulation losses. Very few test results of
to confirm that trapped charges may be sufficient to cause sheath cable charging and discharging can be found in the literature
voltage limiters (SVL) of the cable to fail. The number of SVL [4]. No guideline is provided by IEC or CIGRE on the
breakdown depends on the mode of SVL failure, i.e. whether it discharge time of extra high voltage (EHV) single phase
attains low impedance (short circuit) or open circuit when the cables. For this reason, National Grid, UK, performed a series
energy absorbed exceeds the rating. of cable discharge tests on a 275 kV pressurized-oil-filled
(POF) cable of 21 km length, to examine the discharge time of
Keyword: ATP-EMTP, cable trapped charges, cable discharge
time, cable sheath transients, SVL failure. the cable after being isolated and the effect of trapped charges
on the sheath voltage limiters (SVL) failure [3], [5]. Reference
I. BACKGROUND [6] investigated the effect of cable faults on SVL failure.
The paper describes the method of instrumentation used for
T HE phenomena of cable charging and discharging have
been a concern to cable engineers especially when
performing commissioning tests and during maintenance work
measuring dc charges on the cable and estimates discharge
time constant. Field mill devices were used to carry out non-
[1], [2]. Also, the charging/discharging phenomena have intrusive tests. The paper presents the result of calibration tests
received especial attention from utilities which are using high- in the laboratory that were necessary to confirm the linearity
voltage (HV) cables for voltage control during periods of light of transfer ratio of the probe for measuring the system voltage
load which requires nightly switching of cables. For this (50 Hz) and that due to trapped charges (a decaying dc signal),
particular activity the earth switches of the cable are not when the measurement probes are placed in the field.
usually used due to excessive wear and tear of switch contacts
and also, in accordance with their internal recommendations II. THE CABLE UNDER STUDY
for safety and security of supply, some utilities require that The cable circuit considered in the study consists of two
earth switches can only be operated if relevant staff is present parallel, three-phase, 275 kV, 1600 mm2, copper conductor,
in the substation. oil-filled paper insulated cables. Each circuit consists of three
A study was carried out to investigate the root cause of single phase cables. They connect substations (S/S) A and B.
excessive SVL failures in a number of EHV cables. The The cable detail is given in [3], which also illustrates the
EMTP programme was used to model a cable circuit with high crossbonding used in the cable installation considered in the
SVL failure rate. The results of the study were presented in study. The cores are transposed at every junction, which leads
IPST 2013 [3]. The study showed that if sufficient trapped to more balanced impedances in all three phases. The sheaths
charges remain on the isolated cable long enough, i.e. until the are cross-bonded as shown in [3].
next switching action some six to eight hours later, then there Fig. 1, illustrates the high level layout at S/S A and B.
was very high probability that the overvoltage surges on the Circuit 2 is used nightly for voltage control by switching it out
core and thus sheath were sufficient enough to cause SVL of service during the night usually between 22:00 and 7:00 the
failure. It was shown that this was the only condition that next day. The switching is done remotely from the National
would lead to failure and that the SVL would have had Control Centre. Although both circuits have earth switches at
both ends, they are only operated when the cables are taken
- out of service for a long period of time, e.g. maintenance. For
F. Ghassemi, S. Dennis, A Ainsley, are with National Grid Electricity regular voltage control switching, these switches are not
Transmission, National Grid House, Warwick Technology Park, Gallows
Hill, Warwick EC34 6DA, United Kingdom. operated because (i) they can only be operated locally at the
Email: forooz.ghassemi@nationalgrid.com substations for safety issues, and (ii) to avoid excessive wear
M. Haddad, S. Robson are with Cardiff University, Cardiff CF10 3XQ, and tear of isolator switches contacts. Both S/S A and B are
United Kingdom. unmanned.
The cables lengths for Circuit 1 and Circuit 2 are
Paper submitted to the International Conference on Power Systems respectively 21.22 km 21.74 km. The cables are placed in
Transients (IPST2017) in Seoul, Republic of Korea, June 26-29, 2017. trenches along the route with an average depth of 1 meter.
They enter tunnels in the vicinity of substations for a short
distance. The cable sealing ends at ground level are connected A series of tests were carried out to examine relationship
to a piece of overhead horizontal busbar with a length of about between the input, i.e. electrostatic field and the output
13.5 m as depicted in Fig. 2. The busbar is supported by two voltage. This was essential to ensure that the field mill has
vertical insulator poles, each with a vertical axial length (not constant transfer ratio between input and output signals for
creepage) of approximately 2.4 m. The isolator switches L21 both dc and ac signals, which in turn allows the field mill to be
and L22 are situated at the end of the busbar sections. calibrated in the field when it is installed under the live busbar
As can be seen from Fig. 1, the voltage transducers at both for 50 Hz voltage and measuring correctly when the cable is
ends of the cables (not shown in Fig. 2) are of capacitive switched out of service with trapped charges, e.g. dc voltage,
voltage transformer type with no dc transfer capability. This on the cable.
means that the trapped charges can only drain through the A metal plate was used as the source of electric fields. In
cable insulation losses and stray resistance of the outdoor order to increase the capacitance of the plate with respect to
insulation string at both ends. earth a 12 F capacitor was connected to the plate, which was
Circuit then energised to the mains voltage of 220 V, 50 Hz. The
To S/S A
Breaker Isolator neutral of the mains was earthed. The metal plate was raised
CCT1
Fig. 9. Rate of Change of Voltage for 21/7/2015 Fig. 12.a, illustrates the voltages in red and yellow phases.
The blue phase measurement is missing. This was due to flat
Fig. 10.a, illustrates the voltages for a de-energisation in battery in the field mill and associated recorder, which was
30/7/2015. It can be seen that the voltages reached nearly 2 pu detected after measurement was done. It can be seen that the
and decayed to a very low level by the time the cable was re- voltage in red phase reaches 1.3 pu at the time of de-
energised. Fig. 10.b shows the change in atmospheric energisation reducing to about 0.3 pu the next day at around 7
parameters. It can be observed that the relative humidity was am when it starts to increase again. The temperature was not
very high reaching 100% while the temperature dropped to as particularly low and it starts to increase at around 4 am on
low as 6 C. The duration of high humidity was relatively 1/8/2015 reaching 18 C at the time of the switching.
long. Two distinct time constants can be observed, first was Likewise, the humidity reduces sharply in the morning. Fig.
13, shows the rate of change of voltage on the cable. The voltage and temperature of the cable (core/insulation) [5]. As
positive rate of change of voltage just before energisation is can be seen from all the records shown in this paper the initial
shown by the broken straight line. The increase in the phase rate of change of voltage on the cable changes within a couple
voltages can be attributed to the coupling with the live of hours after de-energisation. This is influenced not only by
adjacent busbar and increase in the system loading, which in the atmospheric parameters but also the voltage magnitude on
turn induces higher voltage in the cable. This increase offset the core.
the discharge of the cable through the insulator strings.
Therefore, depending on the substation layout, the V. MAINTENANCE RECORDS
disconnected cable may in fact be charged up due to induction, The cable has 18 junction boxes, of which 14 contain
if it is not earthed. SVLs, hence a total of 42 SVLs limit the sheath voltage.
Which phase SVL fails most appear to be random but usually
at least two phases SVLs fail in each junction box. Almost
always, the SVLs close to the substation when switching is
done have failed.
Two maintenance reports will be presented in this section.
The objective is to check whether any correlation between
atmospheric parameters and SVL failures exists.
In March 2011, there was fire in one of the junction boxes.
All three SVLs in the junction box had catastrophically failed
(destroyed). The subsequent check on earthing and
connections in the junction box showed that all were
according to the guidelines. The SVLs were changed and the
cable was put back in service. Thermovision tests showed that
no hotspot existed in the junction box and all connections,
Fig. 12.a. Three Phase Voltages for 31/7/2015
including earthing, were satisfactory.
The weather record for spring 2011 revealed that March
2011 was exceptionally warm and dry month. It was one of
the warmest on record with much below average rainfall
(http://www.metoffice.gov.uk/climate/uk/interesting#y2011).
On 18/06/2015, the cable was de-energised for routine
maintenance. Six SVLs on the route had to be changed. The
test to assess the SVL condition involves applying a test
voltage and measuring the leakage current. If the current
exceeds the declared value by the manufacturer the SVL is
discarded. At this point of time all SVLs were healthy.
The cable was put back in service and then taken out on
18/7/2015. In total 13 SVLs were found to have failed. Note
that, network loading reduces to a minimum of about 36% of
the maximum load in winter, therefore the cable is used more
regularly for voltage control. Inspection of the weather records
Fig. 12.b. THP for 31/7/2015
revealed that June /July of 2015 were one of hottest period on
record. The temperature on 1/7/2015 set a new record
(http://www.metoffice.gov.uk/climate/uk/interesting#y2015).
The maintenance and SVL failure records very well
correlate with the weather condition and findings of this paper.
VIII. REFERENCES
[1] IEC 60141-1 :1993 : Tests on oil-filled and gas-pressure cables and their
accessories - Part 1: Oil-filled, paper or polypropylene paper laminate
insulated, metal-sheathed cables and accessories for alternating voltages
up to and including 500 kV, 1993.
Fig. 18. Energy Absorbed by SVL in JB2174 with Linear Resistance- [2] CIGRE WG C4.502, "Power System Technical Performance Issues
Inductance Representing Failed SVL Related to the Application of Long HVAC Cables," CIGRE Technical
Brochure, No. 556, Oct. 2013.
[3] F. Ghassemi.: Effect of trapped charges on cable SVL failure, IPST
2013, Paper ID-219, Vancouver (Canada) June 2013.
[4] M. Takaoka, “The potential distribution of direct current oil-filled
cable”, IEEE Trans. Power Apparatus and Systems, vol. PAS-90, no. 6,
pp. 2622-2630, 1971.
[5] I. Lafaia, F. Ghassemi, A. Ametani, J. Mahseredjian, S. Dennis,
A. Haddad, S. Robson.: Experimental and theoretical analysis of cable
discharge, IEEE Trans. on PRWD, DOI:
10.1109/TPWRD.2016.2602361, August 2016.
[6] A. Ametani, C. T. Wan.: Sheath overvoltages due to a fault on an EHV
cable, IPST-1995, pp. 87-92, 1995.
[7] P. Tant, B. Bolsens, T. Sels, D. Van Dommelen, J. Driesen, R. Belmans:.
Design and Application of a Field Mill as a High-Voltage DC Meter,
IEEE Trans. Instrumentation and Measurement, Vol. 56, Issue: 4, 2007.
[8] F. Ghassemi, S. Dennis, A. Ainsley, A. Haddad, S. Robson.:
Measurement of Cable Trapped Charges and Discharge, EEUG 2016
Fig. 19. Energy Absorbed by SVL in JB2167 with Linear Resistance- Conference,, Paper 104, Birmingham, UK, September 2016.
Inductance Representing Failed SVL