GCC PMC Contracting 2022 03112022
GCC PMC Contracting 2022 03112022
GCC PMC Contracting 2022 03112022
GENERAL CONDITIONS
OF CONTRACT - 2022 www.nbccindia.com
PMC Works
YOUTUBE: NBCC(India)Limited
TWITTER : twitter.com/OfficialNBCC Driving Sustainable Development
FACEBOOK : www.facebook.com/OfficialNBCC - Make a Difference
NBCC (INDIA) LIMITED
(A Government of India Enterprise)
NBCC Bhawan, Lodhi Road, New Delhi-110003
CIN-L74899DL1960GOI003335
www.nbccindia.com
GENERAL CONDITIONS
OF CONTRACT - 2022
PMC Works
INDEX
VOLUME – I
CLAUSE DESCRIPTION PAGE NO.
NO.
SECTION – 1
MEMORANDUM (Annexure – I) 9– 10
SECTION – 2
Forms (A to J) 27–36
7.0 Escalation 44
23.0 Payments 56
46.0 Land for Labour Huts/ Site Office and Storage Accommodation 69
83.0 Jurisdiction 87
84.0 Third Party Safety Audit 87
Appendix A to L 106-118
SECTION - 5
Date: …………………………..
1.0 NBCC invites online percentage rate /item rate open tenders from experienced
and eligible Contractors for ………………………… (Name of Work) for ……………………..
(Name of Client/Owner) at ………………… (Location) and as per schedule as
under:
A. Work Experience:
a. Three similar works each costing not less than 40% of the estimated
cost put to tender
OR
b. Two similar works each costing not less than 50% of the estimated cost
put to tender
OR
c. One similar work costing not less than 80% of the estimated cost put to
tender.
iii) (a) The value of executed works, for the purpose of this clause shall also
include the value of any materials (such as cement, steel, etc.),
services (scaffolding, batching-plant, other machinery, etc.), which
have been supplied by client/employer free of cost/ on discounted price
to the contractor, and which have not been already included in the
‘value of works executed’ that is reflected/declared on the relevant
‘experience certificate’ or ‘Letter of Award’. Such exclusion shall be
specifically mentioned on the Letter of Award, “Experience Certificate’
and the ‘value of free supplies’ shall be separately certified by the
employer, or in cases where the employer is a private entity, by a
practicing cost/chartered accountant (holding valid certificate of
practice), However work executed as labour contract shall not be
considered.
iv) Joint-venture / consortia of firms / companies and Foreign bidders are not
eligible to quote for the Tender.
(v) The bidders submitting experience certificate for the works done in joint
venture (JV)/consortium with other firms/companies, their proportionate
experience to the extent of its share in the JV/consortium or work done by
them shall only be allowed on submitting the valid proof of their share/ work
done.
(b) For the purpose of evaluation of Bidders, the conversion rate of such a
currency into INR shall be the daily representative exchange rate
published by the IMF as on 7 (Seven) days prior to the Last Date of
Submission of tender including extension(s) given if any.
iv) The Bidder should at least have earned profit in minimum one year in
the available last three consecutive balance sheets.
The bidders are required to upload and submit page of summarised Balance
Sheet (Audited) and also page of summarised Profit & Loss Account (Audited)
for last three years.
3.0 The intending tenderer must read the terms and conditions of NBCC carefully.
He should only submit his tender if he considers himself eligible and he is in
possession of all the documents required. Information and Instructions for
Tenderers posted on Website(s) shall form part of Tender Document.
5.0 The Tender Document as uploaded can be viewed and downloaded free of
cost by anyone including intending tenderer. But the tender can only be
submitted on the e-tender website after having digital signature by the bidder
and after uploading all the requisite scanned documents.
7.0 The tenderers are required to quote strictly as per terms and conditions,
specifications, standards given in the tender documents and not to stipulate
any deviations.
8.0 The bidders are advised in their own interest to submit their bid documents
well in advance from last date/time of submission of bids so as to avoid
problems which the bidders may face in submission at last moment /during
rush hours.
However, after submission of the tender the tenderer can re-submit revised
tender any number of times but before last time and date of submission of
tender as notified.
9.0 When it is desired by NBCC to submit revised financial tender then it shall be
mandatory to submit revised financial tender. If not submitted then the
tender submitted earlier shall become invalid.
10.0 On opening date, the tenderer can login and see the tender opening process.
11.0 Contractor can upload documents in the form of JPG format and PDF format.
12.0 Contractor is required to upload scanned copies of all the documents including
valid GST registration/EPF registration, PAN No. as stipulated in the tender
document.
13.0 If the contractor is found ineligible after opening of tenders, or his tender is
found invalid, cost of tender document and processing fee shall not be
refunded.
14.0 Notwithstanding anything stated above, NBCC reserves the right to assess the
capabilities and capacity of the tenderer to perform the contract, in the overall
interest of NBCC. In case, tenderer’s capabilities and capacities are not found
satisfactory, NBCC reserves the right to reject the tender.
16.0 In case of Percentage Rate Tender, Contractor must ensure to quote single
percentage rate. The column meant for quoting rate in figures appears in pink
colour and the moment rate is entered, it turns sky blue. The Rate shall be
Quoted upto 2 Decimals.
If the tenderer has not quoted for all the items/the entire requirement as
specified in the respective schedule/ BOQ, the bid submitted by him shall be
treated as unresponsive and be ignored.
17.0 The tenderer(s) if required, may submit queries, if any, through E-mail and in
writing to the tender inviting authority to seek clarifications within 7 days from
the date of uploading of Tender on website but latest by so as to reach NBCC
office not less than 2 days prior to the date of Pre-bid meeting (if to be held as
per NIT). NBCC will reply only those queries which are essentially required for
submission of bids. NBCC will not reply the queries which are not considered fit
like replies of which can be implied /found in the NIT/ Tender Documents or
which are not relevant or in contravention to NIT/Tender Documents, queries
received after 7 days from the date of uploading of Tender on website, request
for extension of time for opening of technical bids, etc. Technical Bids are to be
opened on the scheduled dates. Requests for Extension of opening of Technical
Bids will not be entertained.
The Pre-Bid meeting shall be attended by the intending bidders only and not by
vendors/manufacturers. Further, the intending bidders should depute their
authorized person with authorization letter in original to attend the pre-bid
meeting.
18.0 Integrity Pact (For all contracts valuing Rs.5.00 Crores and above)
18.1 Integrity Pact duly signed by the tenderer shall be submitted. Any tender
without uploading pre-signed integrity Pact shall be liable for rejection.
(iv) The Independent External Monitors (IEMs) has the right to access without
restriction to all Project documentations of the Employer including that
provided by the Contractor. The Contractor will also grant the Monitor,
upon his request and demonstration of a valid interest, unrestricted and
unconditional access to his Project Documentations. The same is
applicable to Subcontractors. The Monitor is under contractual obligation
to treat the information and documents of the Bidder / Contractor / Sub-
Contractors etc. with confidentiality.
20.0 All the uploaded documents shall be considered as duly signed by contractor/
authorized representative.
21.0 NBCC reserves the right to reject any or all tenders or cancel/withdraw the
invitation for bid without assigning any reasons whatsoever thereof. NBCC does
not bind itself to accept lowest tender. The NBCC reserves the right to award
the work to a single party or to split the work amongst two or more parties as
deemed necessary without assigning any reason thereof. The contractor is
bound to accept the portion of work as offered by NBCC after split up at the
quoted/ negotiated rates. No claim of the contractor whatsoever shall be
entertained by NBCC on this account.
22.0 For all scheduled BOQ items, the nomenclature/rates/unit of applicable DSR
items shall be applicable. In case, any ambiguity is observed in scheduled BOQ
items, nomenclature, unit and rate of relevant DSR item will hold good.
23.0 Canvassing in connection with the tender is strictly prohibited, and such
canvassed tenders submitted by the contractor will be liable to be rejected and
his earnest money shall be absolutely forfeited.
24.0 In case of any query, please contact Shri ……………………………. Ph. No.
011- …………/……………… during Office hours.
(……………)
………………………………………….
2) Client/Owner
10) Validity of Tender ITT / 8.0 150 (One Hundred Fifty) Days from
date of opening of tender
13) Time allowed for ITT / 17.1 The date of start of contract shall be
starting the work reckoned from 10 days after the date
of issue of letter of Award.
17) Recovery rate of work CC /71 Rs.40000/- per person per month
force supplied by NBCC (Rupees Forty thousand per person
to Contractor per month only) plus GST @ 18% or
as per prevailing rate on the date of
recovery.
18) Defect Liability Period CC /38.0 Twenty Four months from the date of
taking over of the works by the NBCC
or client whichever is later.
INSTRUCTIONS TO TENDERER
(PAGE No. 11 to 36)
Instructions to Tenderers (ITT)
1.0 Online percentage rate /item rate open tenders are invited from
experienced and eligible Contractors for ………………………… (Name of
Work)” for …………………….. (Name of Client/Owner) at …………………
(Location)
2.0 The work is estimated to cost Rs. …………… Lacs. This estimate, however,
is given merely as a rough guide.
3.0 The tender document as uploaded can be seen on website
www.tenderwizard.com/NBCC or www.eprocure.gov.in and can be
downloaded free of cost.
(i) The Bid will be rejected by NBCC as non-responsive and shall not be
considered in case EMD is not received of the requisite amount
and/or Bank Guarantee (if opted) in the physical form.
(iii) The EMD of the successful bidder will be discharged after the
contractor has furnished the required acceptable performance
guarantee.
a) if the bidder withdraws the bid after bid opening during the period
of validity;
g) If the bidder does not intimate the names of persons who are
working with him in any capacity or are subsequently employed
by him who are near relatives to any officers of NBCC and/or
name of bidder’s near relative who is posted in the project
office/concerned Zonal/SBG/ /RBG office of NBCC.
10.0 The tenders shall be strictly as per the conditions of contract. Tenders
with any additional condition(s)/modifications shall be rejected. Tenders
in which, any of the prescribed conditions are not fulfilled or found
incomplete in any respect are liable to be rejected.
11.0 The witnesses to the Tender/Contract Agreement shall be other than the
tenderer/ tenderers competing for this work and must indicate full
name, address, and status/occupation with dated signatures.
17.0 The drawings with the tender documents are Tender Drawing and are
indicative only.
18.0 ADDENDA/ CORRIGENDA
Addenda/Corrigenda to the tender documents may be issued prior to the
date of submission of the tender to clarify or effect modification in
specification and/or contract terms included in various tender
documents. The tenderer shall suitably take into consideration such
Addenda/Corrigenda while submitting his tender. The tenderer shall
return such Addenda/ Corrigenda duly signed and stamped as
confirmation of its receipt & acceptance and submit along with the
tender document. All addenda/ Corrigenda shall be signed and stamped
on each page by the tenderer and shall become part of the tender and
contract documents.
19.0 SITE VISIT AND COLLECTING LOCAL INFORMATION
Before tendering, the tenderers are advised to visit the site, its
surroundings to assess and satisfy themselves about the local conditions
such as the working and other constraints at site, approach roads to the
site, availability of water & power supply, application of taxes, duties
and levies as applicable & any other relevant information required by
them to execute complete scope of work. The tenderer may obtain all
necessary information as to risks, weather conditions, contingencies &
other circumstances (insurgencies etc.) which may influence or affect
their tender prices. Tenderer shall be deemed to have considered site
conditions whether he has inspected it or not and to have satisfied
himself in all respect before quoting his rates and no claim or extra
charges whatsoever in this regard shall be entertained / payable by the
NBCC at a later date.
20.0 ACCESS BY ROAD
Contractor, if necessary, shall build temporary access roads to the
actual site of construction for the works at his own cost to make the site
accessible. The Contractor shall maintain the same in motorable
condition at all the times as directed by Engineer-in-Charge at his own
cost. The contractor shall be required to permit the use of any roads so
constructed by him for vehicles of NBCC or any other agencies/
contractors who may be engaged on the project site, free of cost.
21.2 The efforts will be made by the NBCC to handover the site to the
Contractor free of encumbrances. However, in case of any delay in
handing over of the site to the Contractor, the NBCC shall only
consider suitable extension of time for the execution of the work.
It should be clearly understood that the NBCC shall not consider
any revision in contract price or any other compensation
whatsoever viz. towards idleness of Contractor’s labour, equipment
etc.
26.0 The benefits under the Govt. policies as under shall be available to the
eligible bidders on submitting relevant supporting documents.
1. Public Purchase (Preference to make in India) order 2017 or any
further revision at any later date
2. MSMED Act, 2006 and Public Procurement Policy for MSEs, Order-
2012 or any further revision at any later date - The policy shall be
applicable to Exclusive Service and Supply Contract wherein Supplier
provides goods or services at his own without being procured full or
part of it from the market.
PHYSICAL MILESTONES
i) This has reference to above referred tender. I/We have read/viewed all the terms
& conditions and are pleased to submit our tender for the above work and I/We
hereby unconditionally accept the tender conditions and tender documents in its
entirety for the above work.
ii) I/we are eligible to submit the tender for the subject tender and I/We are in
possession of all the documents required.
iii) Should this tender be accepted, I/We agree to abide by and fulfill all terms and
conditions referred to above and as contained in tender documents elsewhere and
in default thereof, to forfeit and pay NBCC, or its successors or its authorized
nominees such sums of money as are stipulated in the notice inviting tenders and
tender documents.
Yours faithfully,
Dated _________________
Preamble
The Principal intends to award, under laid down organizational procedures, contract(s)
for (Name of the contract)……………(hereinafter referred to as the
‘Project’). The Principal necessarily requires full compliance with all relevant laws of
the land, rules, regulations, economic use of resources and of fairness/ transparency
in its relations with its Bidder(s) and/or Contractor(s).
In order to achieve these goals, the Principal will appoint an Independent External
Monitor (IEM), who will monitor the tender process and the execution of the contract
for compliance with the Integrity Pact by all parties concerned, for all works covered in
the Project.
To meet the purpose aforesaid both the parties have agreed to comply this Integrity
Agreement (hereinafter referred to as "Integrity Pact" or "Pact"), the terms and
conditions of which shall also be read as integral part and parcel of the Tender/Bid
documents and Contract between the parties.
Obligations on Principal
The Employer is committed to follow the principle of Transparency, Equity and
Competitiveness in Public Procurement.
(1) The Principal commits itself to take all measures necessary to prevent corruption
and to observe the following principles: -
b. The Principal will, during the tender process treat all Contractor(s)/Bidder(s) with
equity and reason. The Principal will in particular, before and during the tender
process, provide to all Contractor(s)/Bidder(s) the same information and will not
provide to any Contractor(s)/Bidder(s), confidential/additional information
through which the Contractor(s)/Bidder(s) could obtain an advantage in relation
to the tender process or the contract execution.
c. The Principal will exclude from the process all known prejudiced persons. The
Principal shall obtain bids from only those parties who have been short-listed or
(2) If the Principal obtains information on the conduct of any of its employees,
Contractor(s) and/or Bidder(s), which is a criminal offence under the IPC/PC Act,
or if there be a substantive suspicion in this regard, the Principal will inform the
Chief Vigilance Officer or the principal will take remedial actions as per
department/conduct rules and subject to its discretion, can additionally
initiate disciplinary actions.
(3) The Principal will enter into agreements with identical conditions with all
Contractor(s)/Bidder(s) for the different Work Packages in the aforesaid
Project.
(4) The Principal will disqualify from the tender process all Contractor(s)/Bidder(s)
with estimated cost of work put to tender of Rs 5.0 crores and above, who do not
sign this Pact or violate its provisions.
Obligations on Bidder/Contractor
To accept and comply with the Integrity Agreement in letter and spirit and further
agree that execution of the said Integrity Agreement shall be separate and
distinct from the main contract, which will come into existence when tender/bid is
finally accepted by Employer. Duration of the Integrity Agreement shall be in the
line with section 8 of the Integrity Agreement.
(a) The Bidder(s) / Contractor(s) will not, directly or through any other person or
firm offer, promise or give to any of the Principal’s employees involved in the
tender process or the execution of the contract any material or other benefit
which he/she is not legally entitled to, in order to obtain in exchange any
advantage, of any kind whatsoever, during the tender process or during the
execution of the contract.
(b) The Bidder(s)/Contractor(s) will not enter with other Bidders into any
undisclosed agreement or understanding, whether formal or informal. This
applies in particular to prices, specifications, certifications, subsidiary
contracts, submission or non-submission of bids or any other actions to
restrict competitiveness or to introduce cartelization in the bidding process.
(c) The Bidder(s)/Contractor(s) will not commit any offence under the relevant
IPC/PC Act. Further the Bidder(s)/Contractor(s) will not use improperly, for
purpose of competition or personal gain, or pass on to others, any information
(d) The Bidder(s) / Contractor(s) of foreign origin shall disclose the name and
address of the Agents/representatives in India, if any. Similarly the Bidder(s)
/ Contractor(s) of Indian Nationality shall furnish the name and address of
the foreign principals, if any. Either the Indian agent on behalf of the foreign
principal or the foreign principal directly could bid in a tender but not both. It
shall be incumbent on the Indian agent and the foreign principal to Adhere to
the relevant guidelines of Government of India, issued from Time to time
regarding availing services of Indian Agents for foreign Suppliers.
(e) The Bidder(s) / Contractor(s) will, when submitting his bid, disclose any and
all payments he has made, is committed to or intends to make to agents,
brokers or any other intermediaries in connection with the award of the
contract.
(f) The Bidder(s) / Contractor(s) to disclose any transgression with any other
company that may impinge on the anti-corruption principle.
(3) The Bidder(s) / Contractor(s) will not instigate third persons to commit offences
outlined above or be an accessory to such offences.
(4) The Bidder(s)/Contractor(s) will not, directly or through any other person or firm
indulge in fraudulent practice means a wilful misrepresentation or omission of
facts or submission of fake/forged documents in order to induce public official to
act in reliance thereof, with the purpose of obtaining unjust advantage by or
causing damage to justified interest of others and/or to influence the procurement
process to the detriment of the Government interests.
(5) The Bidder(s)/Contractor(s) will not, directly or through any other person or firm
use Coercive Practices (means the act of obtaining something, compelling an
action or influencing a decision through intimidation, threat or the use of force
directly or indirectly, where potential or actual injury may befall upon a person,
his/ her reputation or property to influence their participation in the tendering
process).
(6) The Bidder(s)/Contractor(s) signing IP shall not approach the Courts while
representing the matters to IEM and he/she will await their decision in the matter.
Without prejudice to any rights that may be available to the Employer under law or
the Contract or its established policies and laid down procedures, the Employer shall
have the following rights in case of breach of this Integrity Pact by the
Bidder(s)/Contractor(s) and the Bidder/ Contractor accepts and undertakes to respect
and uphold the Employer absolute right:
(3) If it is observed after payment of final bill but before the expiry of validity of
Integrity Pact that the contractor has committed a transgression, through a
violation of any of the terms under Section 2 above or any other term(s) of this
Pact, during the execution of contract, the Principal will be entitled to exclude the
contractor from further tender/contract award processes.
(4) The exclusion will be imposed for a minimum period of six (6) months and a
maximum period of three (3) years.
(1) If the Principal has disqualified the Bidder(s)/Contractor(s) from the tender
process prior to the awarding of the Project according to Section 3, the Earnest
Money Deposit (EMD)/ Bid Security furnished, if any, along with the offer, as per
terms of the Invitation of Tender, shall also be forfeited. The
Bidder(s)/Contractor(s) understands and agrees that this will be in addition to the
disqualification and exclusion of the Contractor(s)/Bidder(s) as may be imposed
by the Principal, in terms of Section 3 above.
(2) If, at any time after the awarding of the Project, the Principal has terminated the
contract according to Section 3, or if the Principal is entitled to terminate the
contract according to Section 3, the Security Deposit/Performance Bank
Guarantee furnished by the contractor, if any, as per the terms of the
NIT/Contract shall be forfeited without prejudice to any other legal rights and
remedies available to the Principal under the relevant clauses of General/ Special
Conditions of Contract.
The Contractor(s)/Bidder(s) understands and agrees that this will be in addition to the
disqualification and exclusion of the Bidder(s)/Contractor(s), as may be imposed by
the Principal in terms of Section 3 above.
(2) If at any point of time during the tender process or after the awarding of the
Contract, it is found that the Bidder(s)/Contractor(s) has made an incorrect
statement on this subject, he can be disqualified from the tender process or if, as
the case may be, that the Contract, is already awarded, it will be terminated for
such reason and the Bidder(s)/Contractor(s) can be black listed in terms of
Section 3 above.
(3) If the Bidder/Contractor can prove that he has resorted / recouped the damage
caused by him and has installed a suitable corruption prevention system, the
Employer may, at its own discretion, revoke the exclusion prematurely.
(1) The Principal shall, in case where the Project Value is in excess of Rs 5.0 crore
and above, appoint competent and credible Independent External Monitor(s) with
clearance from Central Vigilance Commission. The Monitor shall review
independently, the cases referred to it to assess whether and to what extent the
parties concerned comply with the obligations under this Integrity Pact.
(2) In case of non-compliance of the provisions of the Integrity Pact, the complaint/
non-compliance is to be lodged by the aggrieved party with the Nodal Officer only,
as shall be appointed by the CMD, NBCC. The Nodal Officer shall refer the
complaint/ non-compliance so received by him to the aforesaid Monitor.
(3) The Monitor will not be subject to any instructions by the representatives of the
parties and will perform its functions neutrally and independently. The Monitor
shall report to the Chairman-cum-Managing Director, NBCC.
(4) The Bidder(s) / Contractor(s) accepts that the Monitor shall have the right to
access, without restriction, all Project documentation of the Principal including
that provided by the Contractor. The Contractor will also grant the Monitor, upon
his/her request and demonstration of a valid interest, unrestricted and
unconditional access to its project documentation. The Monitor is under
contractual obligation to treat the information and documents of the Bidder(s) /
Contractor(s) with confidentiality.
(5) The Principal will provide to the Monitor, sufficient information about all meetings
among the parties related to the Project, provided such meetings could have an
impact on the contractual relations between the Principal and the Contractor.
(6) As soon as the Monitor notes, or believes to note, a violation of this Pact, he will
so inform the Principal and request the Principal to discontinue and/or take
corrective action, or to take other relevant action(s). The Monitor can in this
regard submit non-binding recommendations. However, beyond this, the Monitor
has no right to demand from the parties that they act in a specific manner and/or
refrain from action and/or tolerate action.
(7) The Monitor will submit a written report to the CMD, NBCC within 4 to 6 weeks
from the date of reference or intimation to it and, should the occasion arise,
(8) If the Monitor has reported to the CMD, NBCC, of a substantiated suspicion of an
offence under relevant IPC/PC Act, and the CMD, NBCC, has not, within the
reasonable time taken visible action to proceed against such offence or reported it
to the Chief Vigilance Officer, the Monitor may also transmit this information
directly to the Chief Vigilance Officer, NBCC.
(9) The word ‘Monitor’ means Independent External Monitor and includes both
singular and plural forms.
(10) For ensuring the desired transparency and objectivity in dealing with the
complaints arising out of any tendering process, the matter should be examined
by the full panel of IEMs jointly as far as possible, who would look into the
records, conduct an investigation, and submit their joint recommendations to the
Management.
(11) IEM should examine the process integrity, they are not expected to concern
themselves with fixing of responsibility of officers. Complaints alleging malafide
on the part of any officer of the organisation should be looked into by the CVO of
the concerned organisation.
(12) The role of IEM is advisory, would not be legally binding and it is restricted to
resolving issued raised by an intending bidder regarding any aspect of the tender
which allegedly restricts competition or bias towards some bidders. At the same
time, it must be understood that IEMs are not consultants to the Management.
Their role is independent in nature and the advice once tendered would not be
subject to review at the request of the organisations.
(13) Issues like warranty / guarantee etc. should be outside the purview of IEMs.
(14) The role of the CVO of the organization shall remain unaffected by the presence
of IEMs. A matter being examined by the IEMs can be separately investigated by
the CVO in terms of the provisions of the CVC Act or Vigilance Manual, If a
complaint is received by him/her or directed to him/her by the commission
This Pact shall come into force when both parties have legally signed it. The Pact shall
expire, in case of the Contractor(s), 3 (three) months after the last payment under
the Contract is made and in case of the unsuccessful Bidder(s), 2 (two) months after
the contract for the project has been awarded.
If any claims is made / lodged during this time, the same shall be binding and
continue to be valid despite the lapse of this pact as specified above, unless it is
discharged / determined by CMD of NBCC.
(1) This agreement is subject to Indian Law. Place of performance and jurisdiction is
the Registered Office of the Principal, i.e. New Delhi.
(4) Should one or several provisions of this agreement turn out to be invalid, the
remainder of this agreement shall remain valid and binding. In such a case, the
parties will strive to come to an agreement in accordance to their original
intentions.
(5) Wherever he or his as indicated in the above sections, the same may be read as
he/she or his/her, as the case may be.
(6) It is agreed term and condition that any dispute or difference arising between the
parties with regard to the terms of this Integrity Agreement / Pact, any action
taken by the Principal in accordance with this Integrity Agreement! Pact or
interpretation thereof shall not be subject to arbitration
________________________ ___________________
(For & On behalf of the Principal) (For & On behalf of
Bidder/ Contractor)
(Office Seal) (Office Seal)
Place_________
Date _________
Witness 1:
(Name& Address) _______________________
_______________________
Witness 2:
(Name & Address) ______________________
______________________
2.
3.
Additional
Details of Work Experience pertaining to “Additional Qualifying Criteria” (as per NIT, if any) Criteria
Details
4.
5.
1. Certified that the Completion Certificates of above works are enclosed with the
Tender Documents.
2. Details mentioned in the above Form are as per Completion Certificates and
have not been presumed.
3. If any detail is not mentioned in the Work Completion Certificate, documentary
proof of the details like drawings, LOA, BOQ, completion certificate/occupation
certificate, copy of final bill, etc. is to be submitted and uploaded on Tender
Website along with the Completion Certificate.
4. If any of the above works are executed in JV, Then bidder shall submit such
details in FORM-B.
Final/
Approved Cost of Cost of
Value of Items Work on
Type of Contract supplied completion,
Reference.
Name of Work i.e. Date and Date (excl. by including
Name Name of Date of & Page No
S. Work Bidders’s Residential / No. of of items employer cost of
of JV Completion of
No and its Share % Non Completion Start supplied free of supplies
Clients member Documenta
location in JV Residential Certificate free of cost or at free of cost
ry Proof
Building cost by fixed or at fixed
the rates rate
employer) (‘Y’) (X+Y)
(‘X’)
1
2
3
Additional
Details of Work Experience pertaining to Additional Qualifying Criteria as per NIT (if any) Criteria
Details
4.
5.
If any detail is not mentioned in the Work Completion Certificate, documentary proof
of detail is to be submitted and uploaded on Tender Website along with the
Completion Certificate.
FINANCIAL DETAILS
a b C
i.) Profit/Loss
1. Summarised page of Audited Profit & Loss Account of previous three Financial Years
duly certified by the chartered account, is to be submitted.
S. Name Name Project No. And Cost of Payments TDS Year wise
No. of of Cost Date of the work Received Corresponding TDS as per
Work Clients in Completion on as per to the Form-
Crores Certificate completion TDS Payments 26AS/Form
in Crores In Crores 16A relating
to the work
1.
2.
3.
Note: Value of Work done will be considered equivalent to the amount received as per
the TDS Certificates.
In case of multiple contracts undertaken from a Client, details of TDS/Form- 26AS for
each work mentioned above need to be segregated and given separately.
This form need to be supported with Form-26AS taken in HTML format or Form -16A.
UDIN :
This is to state that to the best of our knowledge and information that
It is clarified that the above information is furnished and this certificate is being issued
at the specific request of the customer.
Name, designation,
Signature with seal
Notes:-
1. The certificate should have been issued within 6 months from original last date of
the submission of the tender.
1. Name of Applicant/Company
4. Contact Person:
Telephone Nos.
Fax Nos.
Mobile
5. Type of Organization:
a) An individual
b) A proprietary firm
c) A firm in partnership
(Attach copy of Partnership)
d) A Limited Company
(Attach copy of Article of Association)
9. Bank Details :
Name of Bank,
Address of Bank Branch,
Account No.,
RTGS, IFS Code
Name of Contractor____________________
AFFIDAVIT
3. I shall have no objection in case NBCC verifies those from issuing authority (ies). I
shall also have no objection in providing the original copy of any of the
document(s), in case NBCC demands so for verification.
DEPONENT
DEPONENT
Name
City
Postal Code
Contact Person
Email ID
CLAUSES OF CONTRACT
(PAGE No. 37 to 89)
CLAUSES OF CONTRACT (CC)
1.0 DEFINITIONS
The Contract means the documents forming the tender and acceptance
thereof and the formal agreement executed between the competent
authority on behalf of NBCC (India) Limited and the contractor, together with
the documents referred to therein including these conditions, the
specifications, designs, drawings and instructions issued from time to
time by the Engineer-in-Charge and all these documents taken together,
shall be deemed to form one contract and shall be complementary to one
another.
1.1 NBCC (India) Limited, hereinafter called 'NBCC' propose to get the works
executed as mentioned in the Contract on behalf of Owner/ Client as
Implementing agency/Executing Agency.
1.2 In the contract, the following expressions shall, unless the context
otherwise requires, have the meanings, hereby respectively assigned to
them: -
d) CONTRACT VALUE means the sum for which the tender is accepted as per the
letter of Award.
j) MONTH means English Calendar month ‘Day’ means a Calendar day of 24 Hrs
each.
k) NBCC shall means NBCC (India) Limited, a company registered under the
Indian Company Act 1956, with its registered office at NBCC Bhawan, Lodhi
Road, New Delhi or its Administrative officers or its engineer or other
employees authorized to deal with any matter with which these persons are
concerned and authorized on its behalf.
l) OWNER/ CLIENT means the Government, Organization, Ministry,
Department, Society, Cooperative, JV Entities (whether incorporated or
unincorporated or registered as the case may be) etc. who has awarded the
work/ project to NBCC and/ or appointed NBCC as Implementing / Executing
Agency/ Project Manager and/ or for whom NBCC is acting as an agent and on
whose behalf NBCC is entering into the contract and getting the work executed.
m) SCHEDULE(s) referred to in these conditions shall mean the standard
schedule of rates of the government mentioned in the Memorandum
(Annexure-I) with the amendments thereto issued up to the date of receipt of
the tender.
n) SITE means the lands and other places on, under, in or through which
the works are to be executed or carried out and any other lands or places
provided by NBCC/client/owner or used for the purpose of the contract.
o) TENDER means the Contractor’s priced offer to NBCC for the execution and
completion of the work and the remedying of any defects therein in accordance
with the provisions of the Contract, as accepted by the Letter of Award or
Award letter. The word TENDER is synonymous with Tender and the word
TENDER DOCUMENTS with “Tendering Documents” or “offer documents”.
p) WRITING means any manuscript typed written or printed statement under or
over signature and/or seal as the case may be.
q) Works or Work shall unless there be something either in the subject or
context repugnant to such construction, be construed and taken to mean the
works by or by virtue of the contract contracted to be executed whether
temporary or permanent, and whether original, altered, substituted or
additional.
r) Headings in the clauses/ conditions of tender documents are for convenience
only and shall not be used for interpretation of the clause/condition.
s) Words imparting the singular meaning only also include the plurals and vice
versa where the context requires. Words importing persons or parties shall
include firms and corporations and organizations having legal capacities.
t) Excepted Risk are risks due to riots (other than those on account of
contractor’s employees), war (whether declared or not) invasion, act of
foreign enemies, hostilities, civil war, rebellion revolution, insurrection,
military or usurped power, any acts of Government, damages from aircraft,
acts of God, such as earthquake, lightening and unprecedented floods, and
other causes over which the contractor has no control and accepted as such by
the NBCC or causes solely due to use or occupation by Government of the part
of the works in respect of which a certificate of completion has been issued or a
cause solely due to NBCC’s faulty design of works.
2.2 NBCC reserve the right of forfeiture of the performance guarantee in the event
of termination of contract or non-fulfilment under any of the clauses/ conditions
of contract.
2.4 In case the contractor fails to submit the performance guarantee(s) of the
requisite amount within the stipulated period or extended period, letter of
Award automatically will stand withdrawn and EMD of the contractor shall
be forfeited.
2.5 In case part scope of work has been satisfactorily completed and handed over
to Client/NBCC by the contractor and the remaining work/buildings are under
hold/suspended for more than 3 months due to some hindrance beyond control
of contractor or due to non-availability of site/clearance from Client/NBCC, the
performance bank guarantee/FDR submitted by the contractor and available
with NBCC as on date, on specific request of the contractor, may be released
and returned back to the contractor in lieu of submission and due verification of
a fresh PBG/FDR of the equivalent amount towards balance work.
3.2 If the amount of Security Deposit deducted in cash is more than Rs.10.00
lakhs (Rupees Ten lakhs only), the excess amount beyond Rs. 10 Lakhs can be
replaced by the contractor by submission of Bank Guarantee on maximum
three times for contracts valued upto Rs. 300 crore, and upto five times for
contracts valued above Rs. 300 Crore in the prescribed proforma of NBCC or
Fixed Deposit Receipt (FDR) pledged in favour of NBCC (India) Limited of
equivalent amount from any Nationalized Bank or all Commercial Scheduled
Bank. Only the Original Contract Value will be counted for this purpose. The
Bank Guarantee/ FDR shall be initially valid up to the 3 months beyond the
3.4 NBCC reserves the right of part or full forfeiture of security deposit in addition
to other claims in the event of contractor’s failure to fulfill any of the
contractual obligations or in the event of termination of contract as per
terms and conditions of contract.
iii) The Balance twenty-five (25%) percent of total mobilization advance shall
be paid on completion of 10% of work in terms of cost and after the
contractor has fully mobilized the work at site.
The advance so paid to the Contractor shall only be used in execution of this
Contract including setting up of site office and site laboratory, complete
mobilization of plant and machinery, scaffolding & shuttering materials etc.
4.2 The mobilization advance bear simple interest at the rate as mentioned in
the Memorandum (Annexure-I) and shall be calculated from the date of
payment to the date of recovery (365 days in a year) both days inclusive, on
the outstanding amount of advance. Recovery of such mobilization advanced
The contractor shall construct suitable go-down at the site of work for safe
storage of the materials against any possible damages due to sun, rain,
dampness, fire, theft etc. at his own cost. He shall also employ necessary
watch & ward establishment for the purpose at his costs and risks.
6.1 The time for the completion of the work shall, in the event of any
deviations resulting in additional cost over the tendered value sum being
ordered be extended, if requested by the contractor, as follows:
(i) in the proportion which the additional cost of the altered, additional or
substituted work bears to the original tendered value plus
(ii) 25% of the time calculated in (i) above or such further additional time as
may be considered reasonable by the Engineer-in-Charge.
6.2 If the extra items include any work for which no rate is specified in the
contract, then such work shall be carried out at the rates entered in the
schedule of rates (as mentioned in Memorandum (Annexure-I)) for Civil/
Sanitary Works minus/plus the percentage which the tendered amount of
scheduled items bears with the estimated amount of schedule items based on
the Schedule of Rates (as mentioned in Memorandum (Annexure-I)for Civil/
Sanitary Works). The scheduled item means the items appearing in the
Schedule of Rates (as mentioned in Memorandum (Annexure-I) for Civil/
Sanitary Works) which shall be applicable in this clause. This clause will apply
mutates mutandis to electrical work except that Electrical Schedule of Rates as
mentioned in Memorandum (Annexure-I) will be considered in place of Civil/
Sanitary works Schedule of rates as mentioned in Memorandum (Annexure-I).
However, in the case of extra item(s), (items that are completely new, and are
in addition to the items contained in the contract, and not included in the
schedule of rates (as mentioned in Memorandum (Annexure-I)), the contractor
may within fifteen days of receipt of order or occurrence of the item(s) claim
rates, supported by proper analysis, for the work and the engineer-in-charge
shall within one month of the receipt of the claims supported by analysis, after
giving consideration to the analysis of the rates submitted by the contractor,
determine the rates on the basis of the market rates and the contractor shall
be paid in accordance with the rates so determined.
(a) If the market rate for the substituted item so determined is more than
the market rate of agreement item (to be substituted), the rate payable
to the contractor for the substituted item shall be the rate for the
agreement item (to be substituted) so increased to the extent of the
difference between the market rates of substituted item and the
agreement item (to be substituted).
(b) If the market rate for the substituted item so determined is less than the
market rate of the agreement (to be substituted), the rate payable to the
contractor for the substituted item shall be the rate for the agreement
item (to be substituted) so decreased to the extent of the difference
between the market rates of substituted item and the agreement item (to
be substituted)
6.3 The provisions of the preceding paragraph shall also apply to the decrease
in the rates of items for the work in excess of the limits laid down in
Memorandum (Annexure-I), and the Engineer-in-charge shall after giving
notice of the contractor within one month of occurrence of the excess and
after taking into consideration any reply received from him within fifteen
days of the receipt of the notice revise the rates for the work in question
within one month of the expiry of the said period of fifteen days having
regard to the market rates.
6.4 The contractor shall send to the Engineer-in-Charge once every three months,
an up to date account giving complete details of all claims for additional
payments to which the contractor may consider himself entitled and of all
additional work ordered by the Engineer-in-Charge which he has
executed during the preceding quarter failing which the contractor shall be
deemed to have waived his right. However, the Engineer-in-charge may
authorize consideration of such claims on merits.
(i) For Buildings: All works upto 1.2 metres above ground level or up to floor
1 level whichever is lower.
(ii) For abutments, piers and well steining: All works upto 1.2m above the
bed level.
(v) For basement: All works upto 1.2m above ground level or upto floor 1
level whichever is lower.
(vi) For Roads, all items of excavation and filling including treatment of sub
base.
6.7 Market Rates to be determined as per various sub-clauses under the clause 6.0
shall be on the basis of prevailing rates of Material excluding GST (unless
mentioned otherwise), Relevant Labour authority rate for Labour,
market rates of T&P etc. plus 15% towards Contractors’ Profits and
Overheads.
7.0 ESCALATION
No claim on account of any escalation on whatsoever ground shall be
entertained at any stage of works. All rates as per Bill of Quantities (BOQ)
quoted by contractor shall be firm and fixed for entire contract period as well
as extended period for completion of the works. No escalation shall be
applicable on this contract.
Provided always that the total amount of compensation for delay to be paid
under this Condition shall not exceed 10% of the Awarded Value of work
(exclusive of GST)or of the Tendered Value of the item or group of items of
work (exclusive of GST)for which a separate period of completion is originally
given. The amount of compensation may be adjusted or set-off against any
sum payable to the Contractor under this or any other contract with NBCC.
In case, the contractor does not achieve a particular milestone mentioned
elsewhere in the tender document or the re-scheduled milestone(s), the
amount shown against that milestone shall be withheld, to be adjusted
against the compensation levied at the final grant of Extension of Time.
With-holding of this amount or failure to achieve a milestone, shall be
automatic without any notice to the Contractor. However, the withheld amount
against the milestone shall be released on achieving that milestone
subsequently. In case the contractor f a i l s t o a c h i e v e a m i l e s t o n e
a n d subsequent milestone(s), the amount mentioned against each
milestone(s) not completed shall be withheld combinely. Further, no interest,
whatsoever, shall be payable on such withheld amount.
ii) If the contractor has, without reasonable cause, suspended the progress of
the work or has failed to proceed with the work with due diligence so that
in the opinion of the Engineer-in-Charge (which shall be final and binding)
he will be unable to secure completion of the work by the date for
completion and continues to do so after a notice in writing of seven days
from the Engineer-in-Charge; or
iii) If the contractor fails to complete the work within the stipulated date or
items of work with individual date of completion, if any stipulated, on or
before such date(s) of completion and does not complete them within the
period specified in a notice given in writing in that behalf by the Engineer-
in-Charge; or
vi) If the contractor shall enter into a contract with NBCC in connection with
which commission has been paid or agreed to be paid by him or to his
knowledge, unless the particulars of any such commission and the terms of
payment thereof have been previously disclosed in writing to the Engineer-
in-Charge; or
vii) If the contractor shall obtain a contract with NBCC as a result of wrong
tendering or other non-bona-fide methods of competitive tendering or
commits breach of Integrity Pact; or
viii) If the contractor being an individual, or if a firm, any partner thereof shall
at any time be adjudged insolvent or have a receiving order or order for
administration of his estate made against him or shall take any
proceedings for liquidation or composition (other than a voluntary
liquidation for the purpose of amalgamation or reconstruction) under any
Insolvency Act for the time being in force or make any conveyance or
assignment of his effects or composition or arrangement for the benefit of
his creditors or purport so to do, or if any application be made under any
Insolvency Act for the time being in force for the sequestration of his
estate or if a trust deed be executed by him for benefit of his creditors; or
ix) If the contractor being a company, shall pass a resolution or the Court
shall make an order for the winding up of the company, or a receiver or
manager on behalf of the debenture holders or otherwise shall be
appointed or circumstances shall arise which entitle the Court or debenture
holders to appoint a receiver or manager; or
x) If the contractor shall suffer an execution being levied on his goods and
allow it to be continued for a period of 21 days, or.
When the contractor has made himself liable for action under any of the
cases aforesaid, the Engineer-in-Charge may without prejudice to any
other right or remedy which shall have accrued or shall accrue hereafter to
NBCC, by a notice in writing to cancel the contract as whole or only such
items of work in default from the Contract, the Engineer-in-charge shall
have powers:
b) To employ labour and to supply materials to carry out the work or any part
of the work debiting the contractor with the cost of the labour and the price
of the materials of the amount of which cost and price certified by the
Engineer-in-Charge shall be final and conclusive) and/ or
11.2 Any sums in excess of the amounts due to NBCC and unsold materials,
constructional plant etc. shall be returned to the contractor, provided always
that if cost or anticipated cost of completion by NBCC of the works or part of
the works is less than the amount which the contractor would have been paid
had he completed the works or part of the works, such benefit shall not accrue
to the contractor.
11.3 In the event of anyone or more of the above courses being adopted by the
Engineer-in-Charge the contractor shall have no claim to compensation for
any loss sustained by him by reasons of his having purchased or procured
any materials or entered into any engagements or made any advances on
account or with a view to the execution of the work or the performance of
the contract. And in case action is taken under any of the provision
aforesaid the contractor shall not be entitled to recover or be paid any sum
for any work thereof or actually performed under this contract unless and
until the Engineer-in-Charge has certified in writing the performance of
such work and the value payable in respect thereof and he shall only be
entitled to be paid the value so certified.
(ii) Commits default in complying with any of the terms and conditions of the
contract and does not remedy it or takes effective steps to remedy it
within 7 days even after a notice in writing is given in that behalf by the
Engineer-in-Charge; or
(iii) Fails to complete the work(s) or items of work with individual dates of
completion, on or before the date(s) so determined, and does not
complete them within the period specified in the notice given in writing in
that behalf by the Engineer-in-Charge.
(a) Take possession of the site and any materials, constructional plant,
implements, stores, etc., thereon; and/or
(b) Carry out the part work / part incomplete work of any item(s) by
any means at the risk and cost of the contractor.
i) force-majeure or
vi) Non-availability of stores, which are responsibility of the NBCC or, Lack of
statutory approvals, that are beyond the scope of works of the contractor, or
vii) Non-availability or break down of tools and plant to be supplied or
supplied by NBCC or,
viii) Any other cause which, in the absolute discretion of the NBCC, is beyond
the Contractor’s control, then upon the happening of any such event
causing delay, the Contractor shall immediately give notice thereof in
writing to the Engineer-in-Charge within 07 days but shall
nevertheless use constantly his best endeavour to prevent or make good
the delay and shall do all that may be reasonably required to the
satisfaction of the Engineer-in-Charge to proceed with the works.
16.4 Request for rescheduling of Milestones and extension of time, to be eligible for
consideration, shall be made by the Contractor in writing within fourteen
days of the happening of the event causing delay alongwith the reasons in
18.2 Notwithstanding anything contained in clause 18.1, the contractor shall ensure
payment of appropriate taxes, cess, levies, etc. on the items of supplies and
works made good under the contract. The contractor shall take/ obtain
registration under the applicable enactment levying tax/ levy/cess on supply
of goods or services under the contract and issue invoice having all the
particulars prescribed under the applicable provisions of the law, including.
description of goods/services, rate and amount of tax paid or payable on the
supplies made under the contract, so that NBCC can avail credit of such tax,
wherever applicable. The contractor shall comply with all applicable provision
of Goods and Service Tax (GST) levied by Union Government and State
Governments (CGST, UTGST, SGST and IGST). The contractor shall get
himself registered and discharge his obligations for payment of taxes, filing of
returns etc. under the appropriate provisions of law in respect of all the taxes,
duties, levies, cess, etc. NBCC would have right to seek necessary evidence
that the contractor is registered under the law and duly discharging its
obligations under the tax law, enabling NBCC to avail input tax credit.
Whenever interest is payable on reversal of Input Tax Credit (ITC) for non-
payment of value and tax of supply under GST Act, due to any default on
contractor’s part (i.e due to poor performance/quality or non-fulfilment of
terms of contract), the amount of interest so levied on NBCC shall be
recovered from the contractor.
18.3 In case any law requires NBCC to pay tax/ levy/cess on the contract price
under any law for the time being in force, (such as GST, royalty on minerals,
works contract taxes on reverse charge basis, etc.) the amount of
tax/levy/cess so deposited by NBCC on this behalf would be considered as
paid to the contractor and, accordingly, the price payable to the contractor
would stand reduced to that extent.
18.4 In case the contractor does not deposit or file the tax/levy/cess with
appropriate authority/department, and which is payable-by or lived on
contractor on account of execution of this contract, or if any such
tax/levy/cess (such as GST, WCT, royalty on minerals etc.) is deposited by or
recovered from NBCC but is actually payable by or levied on the contractor,
or, if the contractor has not provided the invoice or other relevant document
pertaining to deposit/credit of such tax/levy/cess to NBCC, showing/ proving
deposit of appropriate the amount of tax/levy/cess, or has not uploaded the
document in computerised tax network as per prevailing law, leading to non-
availability of inputs credit of the tax to NBCC, the amount equivalent to such
tax shall be deducted from the contract price.
18.5 Stamp duty and registration charges, if any, payable on the executed contract
document, shall be borne by the contractor. .
18.6 Tax deduction at source, if any, shall be made by NBCC as per law applicable
from time to time from the amount payable to the contractor. .
19.0 Deleted.
Engineer-In charge has to ensure that Insurance policies are submitted by the
contractor within 15 days from the date of issue of LOA. In case of failure of
the contractor to obtain contractors all risk policy, insurance under workman
compensation act and third party insurance as described above, NBCC reserves
the right of forfeiture of the Performance Bank Guarantee.
22.4 (Refer clause 73.2) The contractor shall at all times indemnify NBCC and
Owner against all claims, damages or compensation under the provision of
Payment of wages act-1936, Minimum Wages Act-1948 Code on Wages, 2019,
Employer’s liability Act-1938, the workmen’s compensation Act-1947, Industrial
Disputes Act-1947 and Maternity Benefit Act-1961 or any modifications thereof
or any other law in force or as consequence of any accident or injury to
any workman or other persons in or about the works, whether in the
employment of the contractor or not, against all costs, charges and expenses
of any suit, action or proceedings arising out of such incident or injury and
against all sum or sums which may with the consent of the contractor be paid
to compromise or compound any such claim. Without limiting his obligations
and liabilities as above provided, the contractor shall insure against all claims,
damages or compensation payable under the Workmen’s Compensation Act
1923 or any modification thereof or any other law relating thereto.
23.3 All payments shall be released by way of e-transfer through RTGS in India
directly at their Bank account by NBCC.
GST shall also be recoverable as extra from all applicable recoveries e.g.
Workmen recovery, LD etc. made from the bills of contractor.
23.4.3 An undertaking to the effect that it is only the sole willingness of contractor
to avail the Financial Assistance indemnifying NBCC against any future claim
on account of the Financial Assistance granted may be obtained as per
prescribed format.
Whenever bill is due for payment, the contractor would initially submit draft
computerized measurement sheets and these measurements would be got
checked/test checked from the Engineer-in-Charge and/or his authorized
representative. The contractor will, thereafter, incorporate such changes as
may be done during these checks/test checks in his draft computerized
measurements, and submit it to NBCC online through e-billing portal available
in the NBCC website. All the required documents e.g. measurement sheet,
quality test reports, ESIC/EPF challans, Tax invoice, theoretical v/s actual
consumption of material etc. shall also be uploaded in the module. No payment
of RA bill shall be released until all obligations and documents as above as per
direction of Engineer In-charge are uploaded in the portal.
The contractor shall, without extra charge, provide all assistance with every
appliance, labour and other things necessary for checking of measurements
/levels by the Engineer-in-Charge or his representative.
The contractor shall give not less than seven days’ notice to the Engineer-
in-Charge or his authorized representative in charge of the work before
covering up or otherwise placing beyond the reach of checking and/or test
checking the measurement of any work in order that the same may be
It is also a term of this contract that checking and/or test checking the
measurements of any item of work in the measurement book and/or its
payment in the interim, on account of final bill shall not be considered as
conclusive evidence as to the sufficiency of any work or material to which it
relates nor shall it relieve the contractor from liabilities from any over
measurement or defects noticed till completion of the defects liability period.
26.2 It is an agreed term of the contract that the sum of money or moneys so
withheld or retained under the lien referred to above by the Engineer-in-
Charge or NBCC will be kept withheld or retained as such by the Engineer-
in-Charge or NBCC till the claim arising out of or under the contract is
determined by the competent court and that the contractor will have no
claim for interest or damages whatsoever on any account in respect of
such withholding or retention under the lien referred to above and duly
notified as such to the contractor. For the purpose of this clause, where
the contractor is a partnership firm or a limited company, the Engineer-in-
Charge or the NBCC shall be entitled to withhold and also have a lien to
retain towards such claimed amount or amounts in whole or in part from
any sum found payable to any partner/limited company, as the case may
be whether in his individual capacity or otherwise. NBCC shall have the
right to cause an audit and technical examination of the works and the
final bills of the contractor including all supporting vouchers, abstract, etc,
to be made after payment of the final bill and if as a result of such audit
The contractor shall execute the whole and every part of the work in the
most substantial and workman like manner both as regards materials and
otherwise in every respect in strict accordance with the specifications. The
contractor shall also conform exactly, fully and faithfully to the design,
drawings and instructions in writing in respect of the work assigned by the
Engineer-in-Charge.
The contractor shall comply with the provisions of the contract and execute
the works with care and diligence and maintain the works and provide all
labour and materials, tools and plants including for measurements and
supervision of all works, structural plans and other things of temporary or
permanent nature required for such execution and maintenance in so far as
the necessity for providing these, is specified or is reasonably inferred from
the contract. The contractor shall take full responsibility for adequacy,
suitability and safety of all the works and methods of construction.
29.2 The above provisions shall not absolve the contractor from the quality of
final product and in getting the material and workmanship quality checked
and approved from the Engineer-in-Charge of NBCC.
29.3 The contractor shall well in advance, produce samples of all materials, articles,
fittings, accessories etc. that he proposes to use and get them approved in
writing by NBCC. The materials, articles etc. as approved shall be labelled as
such and shall be signed by NBCC and the Contractor’s representative.
29.4 The approved samples shall be kept in the custody of the Engineer-in- Charge
of NBCC till completion of the work. Thereafter the samples except those
destroyed during testing shall be returned to the contractor. No
payment will be made to the contractor for the samples or samples
destroyed in testing.
29.5 The brands of all materials, articles fittings etc. approved together with the
names of the manufacturers and firms from which supplies have been
arranged shall be recorded in the site order book.
29.6 The contractor shall set up and maintain at his cost, a field testing
laboratory for all day to day tests at his own cost to the satisfaction of the
Engineer-in-Charge. This field testing laboratory shall be provided with
equipment and facilities to carry out all mandatory field tests as per
MORTH/CPWD (as the case may be) specifications. The laboratory building
shall be constructed and installed with the appropriate facilities,
Temperature and humidity controls shall be available wherever necessary
during testing of samples. All equipments shall be provided by the Contractor
so as to be compatible with the testing requirements specified. The Contractor
shall maintain all the equipments in good working condition for the duration of
the contract. The Contractor shall provide approved qualified personnel to run
the laboratory for the duration of the Contract. The number of staff and
equipment available must at all times be sufficient to keep pace with the
sampling and testing programme as required by the Engineer-in-charge. The
Contractor shall fully service the site laboratory and shall supply everything
necessary for its proper functioning, including all transport needed to move
equipment and samples to and from sampling points on the site, etc. The
Contractor shall re-calibrate all measuring devices whenever so required by the
Engineer-in-charge and shall submit the results of such calibration without
delay. All field test shall be carried out in the presence of NBCC’s
representative. All costs towards samples, materials, collection, transport,
manpower, testing etc. shall be borne by the Contractor and are deemed to be
included in the rates quoted by him in the bill of quantities.
32.2 The contractor shall mobilise all tools, machinery, equipment, including
installation of Reverse Osmosis plant for timely and safe completion of work as
per applicable quality standards and specifications mentioned in the contract.
The Contractor shall mandatorily install RO plant with all Batching plants
irrespective of the value of project. If RMC is being used at any site, then the
availability of RO plant at RMC plant must be ensured. The contractor shall
ensure un-interrupted supplies of water & electricity at site for construction and
related purposes, and shall obtain temporary water & electricity connections at
its own. For small activities other than concreting, the contractor shall install
water-purification equipment, to bring it in conformity with required quality
standards.
32.3 It shall be the responsibility of the contractor to obtain the approval for any
revision and/or modification desired by him from NBCC before
implementation.
32.5 It is mandatory for the contractor to provide safety equipments and gadgets to
his all workers, supervisory and Technical staff engaged in the execution of the
work while working. The minimum requirement (but not limited to) shall be
gum boots, safety helmets, Rubber hand gloves, face masks, safety nets,
safety belts, goggles etc. as per work requirements. Sufficient nos. of these
equipments and gadgets shall also be provided to NBCC by the contractor at
his own cost for use of NBCC Officials and/ or workforce while
working/supervision of work at site. No staff/ worker shall be allowed to enter
the site without these equipments/ gadgets.
32.6 All designs, drawings, bill of quantities, etc., except Bar Bending Schedule,
Shop & Fabrication drawings, for all works shall be supplied to the
contractor for their scope of work all buildings services and development
works by NBCC in phased manner as the works progress. However, it shall
be the duty and responsibility of the contractor to bring to the notice of the
NBCC in writing as to any variation, discrepancy or any other changes required
and to obtain revised drawings and designs and / or approval of the NBCC in
writing for the same.
32.8 All materials, construction plants and equipments etc. once brought by the
contractor within the project area, will not be allowed to be removed from
the premises without the written permission of the Engineer-in-charge.
Similarly, all enabling works built by the contractor for the main construction
undertaken by him, shall not be dismantled and removed without the written
authority of the NBCC.
32.9 Contractor shall have to prepare the Bar Bending Schedule, shop and
fabrication drawings free of cost, if required for any of the items of work.
Five copies of these drawings each including for revision will be submitted
to NBCC for approval. Before executing the item, shop drawings and bar
bending schedule should be approved by NBCC.
32.10 NBCC shall supply Work Force in the various categories to assist the
contractor in execution of the works on recoverable basis as per provision
mentioned elsewhere in the contract.
32.11 All contractors’ plant, machinery and equipment shall be kept in perfect
condition during currency of the contract.
All the quality reports (i.e. checklists & registers) shall be maintained
/submitted by the Contractor as per NBCC QA-QC manual. Checklists &
Registers enclosed in the QA-QC manual shall be followed while carrying out
Construction activities (items). If any item is not covered by the
Checklist/Register, the Format for the same may be developed and submitted
to Engineer-in-Charge for approval and the same shall be adopted. These filled
in reports shall be duly signed by representatives of contractor and NBCC. All
the costs associated with Printing of Formats and testing of materials required
as per technical specifications or by Engineer-in-charge shall be included in the
Contractor’s quoted rates in the Schedule/ Bill of quantities.
34.1 For the contracts having tendered value Rs. 100 Crore and above, the
contractor shall arrange and provide a system of real time monitoring of
project by installing adequate numbers of good quality IP based cameras at all
critical locations of the project having Pan/ Tilt/ Zoom (PTZ) capability duly
integrated with cloud thereby providing facility of accessing photographs
showing progress of construction from anywhere and anytime to monitor the
status of the project.
35.3 If the contractor shall fail to comply with the requirements of this Clause
35.2(i) above then,
(A) The Engineer-in-Charge may at the expense of the contractor
(i) remove such scaffolding, surplus materials and rubbish etc.,
and/or
(ii) dispose of the same as he thinks fit and clean off such dirt as
aforesaid,
and,
(B) The contractor shall have no claim in respect of scaffolding or surplus
materials as aforesaid except for any sum actually realized by the sale
thereof less actual cost incurred on removal of materials / debris / malba
etc.
35.4 The Contractor shall responsible for handing over of project including signing of
inventories by the client and shall obtain final work completion certificate in
favour of NBCC (India) Ltd from client in the attached format at Annexure-
4.8A. Necessary support for the same, shall however, be provided by NBCC. No
payment of final bill shall be released to the contractor until final work
completion certificate is obtained from client.
It shall be the responsibility of the contractor to see that the building under
construction is not occupied by anybody in un-authorized manner during
construction, and is handed over to the Engineer-in-Charge with vacant
possession of complete building. If such building though completed is
occupied illegally, then the Engineer-in-Charge shall have the option to
refuse to accept the said building/buildings in that position. Any delay in
acceptance on this account will be treated as the delay in completion and
for such delay, a levy of compensation upto 5% of tendered value of work
may be imposed by the Engineer-in-Charge whose decision shall be final
both with regard to the justification and quantum and shall be binding on
the contractor.
39.2 The contractor may entrust specialist items of works like MEP services, HVAC,
Lifts, Building Management System, Water Proofing, and Data &
Communication networking, interiors, landscaping etc. to the agencies
specialized in the specific trade. The contractor shall give the names and
details of such firm whom it is going to employ for approval of NBCC. These
details shall include the expertise, financial status, technical manpower,
equipment, resources and list of works executed and on hand of the specialist
agency. Further, prior written approval is required from NBCC to deploy such
agency / sub-contractor.
39.3 The terms & conditions applicable to the contractor in respect of the proposed
sub-contract, the same terms & conditions shall be imposed on the sub-
contractor to enable the contractor to comply with his obligations under the
contract with NBCC.
The sub-contractor should fulfill the qualifying criteria for contractor for the
proposed value of sub-contract similarly provided in the NIT of the project.
39.4 Notwithstanding any consent to sub-contract given by the Engineer-in-Charge
if in his opinion it is considered necessary, the Engineer-in-Charge shall have
full authority to order the removal of any sub-contractor from the site or off-
site place of manufacture or storage.
40.0 FORCE MAJEURE
Any delay in or failure to perform of either party, shall not constitute default so
as to give rise to any claim for damages, to the extent such delay or failure to
perform is caused by an act of God, or by fire, explosion, flood or other natural
catastrophe, governmental legislation, orders or regulation etc. Failure of the
client / owner to hand over the entire site and / or release funds for the
project, to NBCC, shall also constitute force majeure. The time for performance
of the obligation by the parties shall be deemed to be extended for a period
equal to the duration of the force majeure event. Both parties shall make their
best efforts to minimize the delay caused by the force majeure event. If the
failure / delay of the client /owner in handing over the entire site and / or in
releasing the funds continues even on the expiry of the stipulated date of
completion, NBCC, may, at the request of the contractor, foreclose the
contract without any liability to either party. In the event of such
foreclosure, the contractor shall not be entitled to any compensation
whatsoever. If prior to such foreclosure the contractor has brought any
materials to the site, the Engineer-in-Charge shall always have the option
46.2 In the event the contractor has to shift his labour campus at any time during
execution of the work on the instructions of local authorities or as per the
requirement of the work progress or as may be required by NBCC, he shall
comply with such instructions at his cost and risk and no claim whatsoever
shall be entertained on this account.
The contractor shall collect the total quantity of tar or bitumen required for
the work as per standard formula, before the process of painting started
The quantities shown against the various items of work are only
approximate quantities which may vary as per the actual requirement at
site. No item which is not covered in the bill of quantities shall be executed
by the Contractor without the approval of the NBCC. In case any
Extra/Substituted item is carried out without specific-approval, the same
will not be paid.
52.0 WATER PROOF TREATMENT AND ANTI-TERMITE TREATMENT
52.1 The water proof treatment shall be of type and specifications as given in
the schedule of quantities and/or specifications/ design-basis-report mentioned
in tender documents.
52.2 The water-proofing treatment of basement, roofs, water retaining areas and
termite infestation shall be and remain fully effective for a period of not
less than 10(Ten) years to be reckoned from the date of expiring of the
Defect Liability period, prescribed in the contract. At any time during the
said guarantee period if NBCC finds any defects in the said treatment or
any evidence of re- infestation, dampness, leakage in any part of buildings or
structure and notifies the contractor of the same, the contractor shall be liable
to rectify the defect or give re-treatment and shall commence the work or
such rectification or re-treatment within fifteen days from the date of issue
of such letter to him. If the contractor fails to commence such work within
the stipulated period, the NBCC may encash the Bank Guarantee submitted by
the contractor in this regard and get the same done by another agency and the
decision of the Engineer-in-Charge of NBCC shall be final and binding upon
him.
52.3 Re-treatment if required shall be attended to and carried out by the
Contractor within fifteen days of the notice from Engineer-in-Charge of
NBCC.
52.4 The NBCC reserves the right to get the quality of treatment checked in
accordance with recognized test methods and in case it is found that the
chemicals with the required concentration and rate of application have not
been applied, or the water proofing treatment is not done as per specifications,
the contractor will be required to do the re-treatment in accordance with the
required concentration & specifications at no extra cost failing which no
payment for such work will be made. The extent of work thus rejected shall be
determined by NBCC.
52.5 Water proofing and Anti-termite treatment shall be got done through approved
/ specialized agencies only with prior approval of Engineer-in-Charge.
52.6 The contractor shall make such arrangement as may be necessary to safe
guard the workers and residents of the building against any poisonous effect of
the chemicals used during the execution of the work.
55.2 The register of cement & steel shall be kept at site in the safe custody of
NBCC’s Engineer during progress of the work. This provision will not,
however, absolve the contractor from the quality of the final product.
The contractor shall provide safe and approachable access to the site/structure
for inspections including installation of inspection lifts where the height of the
building /structure is 25m or more. The expenditure incurred towards
installation of inspection lifts is to be borne by the contractor and is deemed to
be included in contractor’s bid amount.
The work during its progress or after its completion may also be
inspected, by Chief Technical Examiner of Government of India (CTE) and/
or an inspecting authority of State Government of State in which work is
executed and/or by third party checks by owner/ clients. The compliance
of observations/improvements as suggested by the inspecting officers of
NBCC/CTE/ State authorities/ Owners shall be obligatory on the part of the
Contractor at the cost of contractor.
65.2 When the whole of the works or the items or the groups of items of work
have been completed the contractor will give a notice to that effect to the
Engineer in writing. The Engineer shall within 7 days of the date of receipt
of such notice inspect the works and give instructions in writing to the
contractor specifying the balance items of work which are required to be
done by the contractor and shall also notify the contractor of any defect in
the works affecting completion.
65.3 The contractor shall during the course of execution prepare and keep updated a
complete set of ‘as built’ drawings to show each and every change from the
contract drawings, changes recorded shall be countersigned by the Engineer-
in-Charge and the contractor. Four copies of ‘as built’ drawings shall be
supplied to NBCC by the contractor within 30 days of the completion. All costs
incurred in this respect shall be borne by the contractor.
67.2 Within 15 days of Letter of Award, the contractor shall submit a site
organisational chart and resume including details of experience of the Project-
in-Charge and other staff proposed to be deputed by him and the
technical team shall be deputed by them on the Project after getting approval
from Engineer-in-Charge. If desired by the contractor at later date, the
Project-in-Charge and other staff whose resume is approved by NBCC can
be replaced with prior written approval of NBCC and replacement shall be
with equivalent or superior candidate only. Decision of Engineer-in-Charge
shall be final and binding on the contractor.
67.3 Even after approving the site organizational chart, the Engineer-in-Charge
due to technical reasons and exigency of work can direct the contractor to
depute such additional staff as in view of Engineer-in-Charge is necessary
and having qualification and experience as approved by the Engineer-in-
Charge. The removal of such additional staff from the site shall only be
with the prior written approval of Engineer-in-Charge. The contractor shall not
be paid anything extra whatsoever on account of deployment of
additional staff and decision of the Engineer-in-Charge shall be final and
binding on the contractor.
67.4 In case the contractor fails to employ the staff as aforesaid he shall be liable to
pay a reasonable amount not exceeding a sum of Rs.50,000 (Rupees Fifty
Thousand only) for each month of default in the case of each person. The
decision of the Engineer-in-charge as to number of Technical Staff to be
adequate for the project and the period for which the desired strength of
technical staff was not employed by the contractor and as to the
reasonableness of the amount to be deducted on this account shall be final and
binding on the contractor as to the amount and the contractor’s liability to pay
the said amount.
70.2 The contractor shall also make sufficient arrangement for photography/
videography so that photographs video can be taken of any specific activity at
any point of time. The contractor shall also make arrangement of software like
MS Project etc. for the purpose of preparing progress report etc.
70.3 The contractor shall make all arrangements for ground breaking
ceremony/inaugural function etc. for the project as required and the cost
towards it deemed to be included in his rates/offer. Any expenditure already
incurred/to be incurred by NBCC, shall be recovered from the contractor.
71.2 NBCC shall deploy the work force as per table below. The recovery shall be
effected for the period for which NBCC workforce is actually deployed during
stipulated time of completion including extended period, if any.
71.3 The recovery amount as per 71.2 above on account of deployment of work
force of NBCC shall not exceed the amount equivalent to the maximum
number of workforce as per table below for the stipulated time of
completion of the project.
71.5 Further, the monthly rate per work force is for the purpose of recovery only
and in no way shall be construed to be the rate applicable for working out
analysis, justification of rates, extra items, claims etc.
The contractor shall also comply with the provisions of the building and
other Construction Workers (Regulation of Employment & Conditions of
Service) Act, 1996 and the building and other Construction Workers Welfare
Cess Act, 1996.
The contractor shall not engage any labour below the age of 18 under any
circumstances. The provisions under Child Labour (Prohibition and Regulation)
Amendment Act. 2016 should be strictly adhered to. In case of any non-
compliance to the requirements of Labour laws, the contractor shall be liable
for all consequences or any penalty imposed in this regard.
The contractor shall also declare in each running bill that he has not engaged
any labour below the age of 18 in the project.
The Contractor shall ensure that all the skilled workers hired/ employed/
deployed at the project shall be certified through “Recognition of Prior Learning
(RPL)” program and if not already certified then, he will get all the skilled
workers certified through “Recognition of Prior (RPL)” program within two
months from the date of commencement of work or from the date of hiring the
workers at his own cost.
(ii) The contractor shall, notwithstanding the provisions of any contract to the
contrary, cause to be paid fair wage to labour indirectly engaged on the
work, including any labour engaged by his sub-contractors in connection
with the said work, as if the labour had been immediately employed by
him.
(iv) In respect of all labour directly or indirectly employed in the works for
performance of the contractor’s part of this contract, the contractor shall
comply with or cause to be complied with the NBCC contractor’s Labour
Regulations in regard to payment of wages, wage period, deductions from
wages recovery of wages not paid and deductions unauthorisedly made,
maintenance of wage books or wage slips, publication of scale of wages
and other terms of employment, inspection and submission of periodical
returns and all other matters of the like nature or as per the provisions of
the Contract Labour (Regulation and Abolition) Act, 1970, and the Contract
Labour (Regulation and Abolition) Central Rules, 1971, wherever
applicable.
(v) (a) The Engineer-in-Charge concerned shall have the right to deduct from
the moneys due to the contractor any sum required or estimated to be
required for making good the loss suffered by a worker or workers by
reason of non-fulfilment of the conditions of the contract for the
benefit of the workers, non-payment of wages or of deductions made
from his or their wages which are not justified by their terms of the
contract or non-observance of the Regulations.
(b) Under the provision of Minimum Wages (Central) Rules, 1950, the
contractor is bound to allow to the labours directly or indirectly
employed in the works one-day rest for 6 days continuous work and
pay wages at the same rate as for duty. In the event of default, the
Engineer-in-Charge shall have the right to deduct the sum or sums not
paid on account of wages for weekly holidays to any labours and pay
the same to the persons entitled thereto from any money due to the
contractor by the Engineer-in-Charge concerned
(vi) The contractor shall comply with the provisions of the Payment of Wages
Act, 1936, Minimum Wages Act, 1948/ Code on Wages, 2019, Employees
Liability Act, 1938, Workmen’s Compensation Act, 1923, Industrial
Disputes Act, 1947, Maternity Benefits Act, 1961, and the Contractor’s
Labour (Regulation and Abolition) Act 1970, or the modifications thereof
The contractor shall at his own cost take all precautions to ensure safety of
life and property by providing necessary barriers, lights, watchmen etc.
During the progress of work as directed by Engineer-in- charge
73.4.2 The Contractor shall submit proof of having valid EPF registration certificate.
He shall within 7 days of the close of every month, submit to NBCC a
statement showing the recoveries of contributions in respect of each
employee employed by or through him and shall furnish to NBCC such
information as the NBCC is required to furnish under the provisions of para 36
B of the EPF scheme 1952 to the EPF authorities and other information
required by EPFO authorities from time to time. He shall also submit a copy of
challan every month in token of proof of having deposited the subscription
and contribution of workers engaged on the project.
The contractor shall also ensure the compliance of EPF & MP Act, 1952 by the
sub-contractors, if any, engaged by the contractor for the above said work.
The contractor shall submit affidavit to indemnify and save harmless the
Corporation from and against all actions, suits, proceedings, losses, costs,
damages, charges, claims and demands of every nature and description
brought or recovered against the Corporation by reasons of any act or
omission of the Contractor, his agents or employees in connection with
complying the provisions of the Employees Provident Fund & Miscellaneous
Provisions Act, 1952 as amended from time to time. All sums payable by way
of compensation / penalty / damages / interest on the outstanding amounts
payable by the Contractor shall be considered as reasonable and be payable
by the Contractor to the Corporation immediately and if the Contractor does
73.4.3 The Contractor shall submit proof of having valid ESI registration for
Construction site workers located in the ESI implemented areas for every
construction site worker before his/her engagement on the NBCC site of
works as per requirement of ESI act, 1948 amended upto date and rules
made there under.
The contractors are required to ensure that in ESI implemented areas, every
construction site worker has been registered online and they are required to
ensure that these workers and their families have got their photography and
capturing of biometrics at nearest ESIC branch office and got their respective
Pehchan cards (from ESIC office) issued for extension of ESI benefits to all
the engaged construction site workers.
The contractors are required to submit proof of having registered / got issued
Pehchan cards in respect of every Construction site worker in ESI
implemented areas before engagement on NBCC site of works.
The contractors are required to comply with all the relevant provisions of ESI
act, 1948 as amended from time to time and deposit of his contribution as
may be required under the above said act to the ESI authorities at required
intervals / time of deposit and submit the proof to NBCC.
The contractor shall at all times indemnify NBCC and Owner against all claims,
damages or compensation under the provision of ESI Act, 1948 or any
modifications thereof or as consequence of any accident or injury to any
workman or other persons in or about the works, whether in the employment
of the contractor or not, against all costs, charges and expenses of any suit,
action or proceedings arising out of such incident or injury and against all sum
or sums which may with the consent of the contractor be paid to compromise
or Compound any such claim.
e) The number of female workers who have been allowed Maternity Benefits
and the amount paid to them.
Failing which the contractor shall be liable to pay to NBCC, a sum not
exceeding Rs.200/- for each default or materially incorrect statement. The
decision of the NBCC shall be final in deducting from any bill due to the
contractor; the amount levied as fine and is binding on the contractor.
73.7 In respect of all labour directly or indirectly employed in the works for the
performance of the contractor’s part of this contract, the contractor shall
comply with or cause to be complied with all the rules framed by
Government from time to time for the protection of health and sanitary
arrangements for workers employed by the NBCC and its contractors.
1. Leave:
(i) In the case of delivery - maternity leave not exceeding 8 weeks, 4 weeks up
to and including the day of delivery and 4 weeks following that day,
(ii) In the case of miscarriage –upto 3 weeks from the date of miscarriage.
2. Pay:
(i) in the case of delivery - leave pay during maternity leave will be at the rate
of the women’s average daily earnings, calculated on total wages earned on
the days when full time work was done during a period of three months
immediately preceding the date on which she gives notice that she expects
to be confined or at the rate of Rupee one only a day whichever is greater.
(ii) In the case of miscarriage - leave pay at the rate of average daily earning
calculated on the total wages earned on the days when full time work was
done during a period of three months immediately preceding the date of
such miscarriage.
73.10 The contractor(s) shall at his/their own cost provide his/their labour with a
sufficient number of huts (hereinafter referred to as the camp) of the
following specifications on a suitable plot of land to be approved by the
Engineer-in-Charge.
(i) (a) The minimum height of each hut at the eaves level shall be 2.10m (7 ft.)
and the floor area to be provided will be at the rate of 2.7 sq.m. (30
sq.ft.) for each member of the worker’s family staying with the labourer.
(c) The contractor(s) shall also construct temporary latrines and urinals for
the use of the labourers each, on the scale of not less than four per
each one hundred of the total strength, separate latrines and urinals
being provided for women.
(b) The contractor(s) shall provide each hut with proper ventilation.
(c) All doors, windows, and ventilators shall be provided with suitable
leaves for security purposes.
(d) There shall be kept an open space of at least 7.2m (8 yards) between
the rows of huts which may be reduced to 6m (20 ft.) according to the
availability of site with the approval of the Engineer-in-Charge. Back to
back construction will be allowed.
(iii) Water Supply - The contractor(s) shall provide adequate supply of water
for the use of labourers. The provisions shall not be less than two gallons
of pure and wholesome water per head per day for drinking purposes and
three gallons of clean water per head per day for bathing and washing
purposes. Where piped water supply is available, supply shall be at stand
posts and where the supply is from wells or river, tanks which may be of
metal or masonry, shall be provided. The contractor(s) shall also at his/
their own cost make arrangements for laying pipe lines for water supply
to his/ their labour camp from the existing mains wherever available, and
shall pay all fees and charges thereof.
(iv) The site selected for the camp shall be high ground, removed from jungle.
(vii) The contractor(s) shall make necessary arrangements for keeping the
camp area sufficiently lighted to avoid accidents to the workers.
The contractor shall be further responsible for maintaining such register &
records; giving such particulars of Building workers employed by him, the
work performed by them, the number of hours of work which shall
constitute a normal working day, the wages paid to them, the receipts given by
them and, such other particulars in such form as may be prescribed by the
authority or NBCC.
In the event of contractor failing to comply with the above clause(s) in part
or in full, NBCC, without prejudice to any other rights or remedy available
under law or any other clause(s) of contract, shall be at absolute liberty to
forfeit any sum or sums that are payable or could become payable on account
of execution of contract work and decision of Engineer-in-charge shall be final
& binding in this regard on the contractor.
75.0 RECOVERY OF COMPENSATION PAID TO WORKMEN
In every case in which by virtue of the provisions sub-section (1) of Section
12, of the Workmen’s Compensation Act, 1923, NBCC is obliged to pay
compensation to a workman employed by the contractor, in execution of
the works, NBCC will recover from the contractor, the amount of the
compensation so paid; and, without prejudice to the rights of the NBCC
under sub-section (2) of Section 12, of the said Act, NBCC shall be at liberty to
recover such amount or any part thereof by deducting it from the security
deposit or from any sum due to the contractor whether under this contract or
otherwise. NBCC shall not be bound to contest any claim made against it under
sub-section (1) of Section 12, of the said Act, except on the written request of
the contractor and upon his giving to NBCC full security for all costs for which
NBCC might become liable in consequence of contesting such claim.
80.3 The contractor shall strictly adhere by the provisions, for the time being in
force, of law relating to works or any regulations and bylaws made by any
local authority or any water & lighting agencies or any undertakings within
the limits of the jurisdiction of which the work is proposed to be executed.
The contractor shall be bound to give to the authorities concerned such
notices and take all approvals as may be provided in the law, regulations or
83.0 JURISDICTION
The agreement shall be executed at Delhi on non-judicial stamp paper
purchased in Delhi and the courts in Delhi alone will have jurisdiction to deal
with matters arising there from, to the exclusion of all other courts.
84.0 THIRD PARTY SAFETY AUDIT: (APPLICABLE FOR PROJECTS VALUING RS. 50
CRORE AND ABOVE)
An experienced and reputed agency shall be engaged/ appointed by the contractor
at all the projects valuing Rs.50 crore and above from the agencies empanelled by
NBCC for Monitoring & Auditing of Safety measures in the construction work. The
scope of work of the agency so engaged shall be as under:
2. Training
To increase the safety consciousness of the workforce and the supervisory
staffs, periodic training and motivation towards safe practices are to be
conducted by agency. The training should of visual i.e. through videos &
physical i.e. mock drills etc. The agency will conduct mock drills also.
4. The agency shall liaison with law enforcing bodies, statutory bodies, media /
press or any other bodies concerned in case of any untoward incidents.
However, statutory payments, if any, shall be paid by deployed main
contractor / NBCC.
5. The agency shall engage and deploy the qualified and sufficient number of
manpower to audit all the safety measures and Workman Safety provisions as
per NBCC safety guidelines at the site as per following qualifications, however,
the decision of Engineer In-charge in this regard shall be final and binding:
S. Description Remarks
No.
1. Senior Safety A recognised degree/diploma or equivalent
Officer (Overall in any branch of engineering or technology;
In-charge) has had practical experience of working in a
construction project site in supervisory
capacity for a period of not less than 10-15
years;
Possesses a degree or diploma in
construction / industrial safety recognized by
the Central / State Government.
6. The duties of Safety Audit agency shall further include the following: -
a) Plan and organize measures necessary for creating a safe working
environment for all workmen engaged at site and to prevent any kind of
personal injuries and damage to property;
b) To advise on safety aspects in all job studies, and to carry out detailed job
safety studies of selected jobs and to formulate Job Hazard Analysis
Report and Safety Manual during initial mobilization stage of the project.
c) Prepare action proposed to be taken to prevent personal injuries and
damage to property.
d) Conduct site safety inspections, in order to observe the physical
conditions of work and the work practices and procedures followed by
workers and to render advice on measures to be adopted for removing the
unsafe physical conditions and preventing unsafe actions by workers and
to ensure that the same will be implemented at site. To prepare & submit
visit report to Engineer-in-charge.
e) To report and investigate accidents and near‐misses and to recommend
the preventive measures so as to ensure non‐occurrence of such cases
and to ensure.
f) To maintain such records as are necessary relating to accidents,
dangerous occurrences and industrial diseases.
g) To organise in association with the concerned departments, campaigns,
competitions, contests and other activities which will create awareness
and will develop and maintain the interest of the workers in establishing
and maintaining safe conditions of work and procedures.
h) To design and conduct suitable training and educational programme for
the prevention of personal injuries.
i) Visit to workman camps and monitoring & ensuring the total hygienic
conditions are provided for workman.
2.0 Scaffolding or staging more than 3.6m (12 feet) above the ground or floor,
swung or suspended from an overhead support or erected with stationery
support shall have a guard rail properly attached or bolted, braced and
otherwise secured at least 90 cm. (3 feet) high above the floor or platform
of such scaffolding or staging and extending along the entire length of the
outside and ends thereof with only such opening as may be necessary for
the delivery of materials. Such scaffolding or staging shall be so fastened
as to prevent it from swaying from the building or structure.
7.1 All roads and open areas adjacent to the work site shall either be closed or
suitably protected.
7.3 All practical steps shall be taken to prevent danger to persons employed
from risk or fire or explosion or flooding. No floor, roof or other part of the
building shall be overloaded with debris or materials as to render it unsafe.
8.1 Workers employed on mixing asphaltic materials, cement and lime mortars
shall be provided with protective footwear and protective goggles.
8.2 Those engaged in white washing and mixing or stacking of cement bags or
any materials which are injurious to the eye shall be provided with
protective goggles.
8.3 Those engaged in welding works shall be provided with welders protective eye
shields.
8.4 Stone breakers shall be provided with protective goggles and protective
clothing and seated at sufficiently safe interval.
8.5 When workers are employed for works in sewers and manholes, which are in
active use, the Contractors shall ensure that the manhole covers are opened
and ventilated at-least for an hour before the workers are allowed to get into
the manholes, and the manholes so opened shall be cordoned off with suitable
railing and provided with warning signals or boards to prevent accident the
public. In addition, the contractor shall ensure that the following safety
measures are adhered to:
a. Entry for workers into the sewer line shall not be allowed except under
supervision of the JE or any other higher officer.
8.6 The Contractor shall not employ men and women below the age of 18 years
on the work of painting with products containing lead in any form wherever
men above the age of 18 are employed on the work of lead painting the
following precautions should be taken.
8.6.1 No paint containing lead or lead products shall be used except in the form of
paste or readymade paint.
8.6.4.1 a) White lead, sulphate or lead work products containing those pigments shall
not be used in painting operation except in the form of paste or of paints
ready for use.
8.6.4.3 a) Cases of lead poisoning and of suspected lead poisoning shall be notified
and shall be subsequently verified by a medical man appointed by the
competent authorities of NBCC.
b) The NBCC may require when necessary a medical examination of workers.
c) Instructions with regard to the special hygienic precautions to be taken in
the painting trade shall be distributed to working painters.
9.0 When the work is done near any place where there is risk of drowning, all
necessary equipments should be provided and kept ready for use and all
necessary steps taken for prompt rescue of any person in danger and
adequate provisions should be made for prompt first aid treatment for all
injuries likely to be sustained during the course of the work.
10.0 Use of hoisting machines and tackle including their attachment encourage
and supports shall conform to the following standard of conditions.
10.1 a) these shall be of good mechanical construction, sound material and adequate
strength and free from patent, defects and shall be kept in good working
order.
b) Every rope used in hoisting or lowering materials or as a means of suspension
shall be of durable quality and adequate strength, and free from patent
defects.
10.2 Every crane driver or hoisting appliance operator shall be properly qualified
and no person under the age of 21 years should be in-charge of any hoisting
machine including any scaffolding, winch or giving signals to operator.
10.3 In case of every hoisting machine and of every chain ring hook, shackle
swivel and pulley block used in hoisting or as means of suspension the safe
working load shall be ascertained by adequate means. Every hoisting machine
and all gear referred to above shall be plainly marked with the safe working
load. In case of a hoisting machine having a variable safe working load, each
10.4 In case of NBCC machines, the safe working load shall be notified by the
Engineer-in-Charge. As regards Contractor’s machines the Contractor shall
notify the safe working load of the machine to the Engineer-in-charge
whenever he brings any machinery to site of work and get verified by the
Engineer-in-Charge.
11.0 Motors gearing, transmission electric wiring and other dangerous parts of
hoisting appliances should be provided with efficient safeguard. Hoisting
appliances should be provided with such means as will reduce to the
minimum the risk of accidental descent of the load. Adequate precautions
should be taken to reduce the minimum the risk of any part of a suspended
load becoming accidentally displaced. When workers are employed on
electrical installations, which are already energized, insulating mats, wearing
apparel, such as gloves sleeves and boots as may be necessary be provided.
The worker should not wear any rings, watches and carry keys or other
materials, which are good conductors of electricity.
12.0 All scaffold, ladders, and other safety devices mentioned or described herein
shall be maintained in safe condition and no scaffold ladder or equipment
shall be altered or removed while it is in use. Adequate washing facilities
should be provided at or near places of work.
13.0 These safety provisions should be brought to the notice of all concerned by
display on a notice board at a prominent place of work spot. The person
responsible for compliance of the safety codes shall be named therein by the
contractor.
15.0 Notwithstanding the above Clauses from (i) to (xiv) there is nothing in these
to exempt the contractor from the operations of any other Act or Rule in
force in the Republic of India.
1.0 APPLICATION
These rules shall apply to all building and construction works in which 20
(twenty) or more workers are ordinarily employed or are proposed to be
employed in any day during the period during which the contractor work is
in progress.
2.0 DEFINITION
Work place means a place where twenty or more workers are ordinarily
employed or are proposed to be employed in connection with construction
work on any day during the period during which the contract work is in
progress.
3.2 The First-Aid boxes shall be distinctly marked with a red cross on white
background and shall contain the following equipments:
3.2.1 a) For work places in which number of contract labour employed does not
exceed 50, Each First-Aid box shall contain the following equipments:
i. Small sterilized dressings.
vi. 1 (30 ml) bottle containing salvolatile having the dose and mode of
administration indicated on the label.
vi) 1 (60 ml.) bottle containing a two percent iodine alcoholic solution.
vii) 1 (60 ml.) bottle containing salvolatile having the dose and mode of
administration indicated on the label.
viii) 1 - roll of adhesive plaster.
ix) 1 snake - bite lancet.
x) 1 (30 gms.) Bottle of potassium permanganate crystals.
xi) 1 pair of scissors.
xii) 1 copy of the First-Aid leaf-let issued by the Director General, Factory
Advice Service and Labour Institutes, Government of India.
xiii) A bottle containing 100 tablets (each of 5 grams) of aspirin.
xiv) Ointment for burns.
xv) A bottle of suitable surgical antiseptic solution.
3.4 Nothing except the prescribed contents shall be kept in the First Aid box.
3.5 The First Aid box shall be kept in charge of a responsible person who shall
always be readily available during the working hours of the work place.
3.6 A person in charge of the First-Aid box shall be a person trained in First-Aid
treatment in work places where the number of labour employed is 150 or
more.
3.7 In work places where the number of labour employed is 500 or more and
hospital facilities are not available within easy distance of the works, first-
Aid Posts shall be established and run by a trained Compounder. The
Compounder shall be on duty and shall be available at all hours when the
workers are at work.
3.8 Where work places are situated in places, which are not towns of cities, a
suitable motor transport shall be kept readily available to carry injured
person or persons suddenly taken ill to the nearest hospital.
4.3 Every water supply of storage shall be at a distance of not less than 50 feet
from any latrines drain or other source of pollution, where water has to be
drawn from an existing well which is within such proximity of latrine, drain
or any other source of pollution, the well shall be properly chlorinated before
water is drawn from it for drinking. All such wells shall be entirely closed in
and be provided with a trap-door which shall be dust and water-proof.
4.4 A reliable pump shall be fitted to each covered well, trap-door shall be kept
locked and opened only for cleaning or inspection which shall be done at
least once a month.
5.2 Separate and adequate screening facilities shall be provided for the use of
male and female workers.
5.3 Such facilities shall be conveniently accessible and shall be kept clean and
hygienic condition.
a) Where females are employed there shall be at least one latrine for every
25 females.
b) Where males are employed, there shall be at least one latrine for every 25
males.
Provided that where the number of males or females exceeds 100, it shall be
sufficient if there is one latrine for 25 males or females, as the case may be,
upto the first 100, and one for every 50 thereafter.
6.2 Every latrine shall be under cover and so partitioned off as to secure privacy,
and shall have a proper door and fastenings.
6.4 (a)Where workers of both sexes are employed, there shall be displayed
outside each block of latrine and urinal, a notice in the language understood
by the majority of the workers "For Men only" or "For Women only" as the
case may be.
(b)The notice shall also bear the figure of man or of a woman, as the case
may be.
6.5 There shall be at least one urinal for male workers upto 50 and one for
female workers upto 50 employed at a time. Provided that where the number
of male or female workmen, as the case may be, exceeds 500, it shall be
sufficient if there is one urinal for every 50 males or females upto the first 500
and one for every 100 or part thereof, thereafter.
b) Latrines and urinals other than those connected with a flush sewerage
system shall comply with the requirements of the Public Health Authorities.
6.9 The Contractor shall, at his own expense, carry out all instruction issued to
him by the Engineer-in-Charge to effect proper disposal of night soil and
other conservancy work in respect of the Contractor's workmen or
employees on the site. The Contractor shall be responsible for payment of
any charges which may be levied by Municipal or Cantonment Authority for
execution of such work on his behalf.
8.0 CRECHES
8.1 A every work place, at which 20 or more women workers are ordinarily
employed, there shall be provided two rooms of reasonable dimensions for
the use of their children under the age of six years. One room shall be used as
a play room for the children and the other as their bedrooms.
The rooms shall be constructed on standard not lower than the following:
i) Thatched roof
iii) Planks spread over the mud floor and covered with matting
8.2 The rooms shall be provided with suitable and sufficient openings for light
and ventilation. There shall be adequate provision of sweepers to keep the
places clean.
8.3 The Contractor shall supply adequate number of toys and games in the
playroom and sufficient number of cots and beddings in the bed-room.
9.0 CANTEENS
9.1 In every work place where the work regarding the employment of contract
labour is likely to continue for six months and wherein contract labour
numbering one hundred or more are ordinarily employed, an adequate
canteen shall be provided by the Contractor for the use of such labour.
9.2 The canteen shall be maintained by the Contractor in an efficient manner.
9.3 The canteen shall consist of at least a dining hall, kitchen, and storeroom,
pantry and washing places separately for workers and utensils.
9.4 The canteen shall be sufficiently lighted at all times when any person has
access to it.
9.5 The floor shall be made of smooth and impervious material and inside walls
shall be lime washed or colour washed at least once in each year.
Provided that the inside walls of the kitchen shall be lime-washed every four
months.
9.6 The premises of the canteen shall be maintained in a clean and sanitary
condition.
9.7 Waste Water shall be carried away in suitable covered drains and shall not
be allowed to accumulate so as to cause a nuisance.
9.8 Suitable arrangements shall be made for the collection and disposal of
garbage.
9.9 The dining hall shall accommodate at a time 30 persons of the labour working
at time.
9.10 The floor area of the dining hall, excluding the area occupied by the service
counter and any furniture except tables and chair shall not be less than one
square metre per dinner to be accommodated.
9.11 a) A portion of the dining hall, and service counter shall be partitioned off
and reserved for women workers in proportion to their number.
9.12 Sufficient tables, stool, chairs or benches shall be available for the number
of dinners to be accommodated.
9.13.1 a)There shall be provided and maintained sufficient utensils, crockery,
furniture and any other equipment necessary for the efficient running of the
canteen.
b) The furniture, utensils and other equipment shall be maintained in a clean
and hygienic condition.
9.13.2 a) Suitable clean clothes for the employees serving in the canteen shall be
provided and maintained.
b) A service counter, if provided, shall have top of smooth and impervious
material.
9.14 The food stuffs and other items to be served in the canteen shall be in
conformity with the normal habits of the labour.
9.15 The charge for food stuffs, beverages and any other items served in the
canteen shall be based on 'No profit' No loss' and shall be conspicuously
displayed in the canteen.
9.16 In arriving at price of food stuffs, and other articles served in the canteen,
the following items shall not be taken into consideration as expenditure,
namely:
a) The rent of land building;
b) The depreciation and maintenance charges for the building and equipment
provided for the canteen;
d) The water charges and other charges incurred for lighting and ventilation;
e) The interest and amounts spent on the provision and maintenance and
equipment provided for in the canteen;
9.17 The accounts pertaining to the canteen shall be audited once every 12 months
by registered accountants and auditors.
11.0 AMENDMENTS
NBCC may from time to time, add to or amend these rules and issue such
directions as it may consider necessary for the purpose of removing any
difficulty which may arise in the administration hereof.
2.2 "Fair Wages" means wages whether for time or piece work fixed and notified
under the provisions of the minimum Wages Act/ Code on Wages, 2019 from
time to time.
2.3 "Contractor" shall include every person who undertake to produce a given
result other than a mere supply of goods or articles of manufacture through
labour or who supplies labour for any work and includes a sub-contractor.
2.4 "Wages" shall have the same meaning as defined in the Payment of Wages
Act/ Code on Wages, 2019.
2.4.1 Normally working hours of an adult employee should not exceed 9 hours a
day. The working day shall be so arranged that inclusive of interval for rest,
if any, it shall not spread over more than 12 hours on any day.
2.4.2 When an adult worker is made to work for more than 9 hours on any day or
for more than 48 hours in any week he shall be paid overtime for the extra
hours put in by him at double the ordinary rate of wages.
2.4.3.2 Whether the Minimum Wages prescribed by the Government under the
Minimum Wages Act/ Code on Wages, 2019 are not inclusive of the wages
for the weekly day of rest, the worker shall be entitled to rest day wages at
the rate applicable to the next preceding day, provided he has worked under
the same contractor for a continuous period of not less than 6 days.
4.5 All payments of wages shall be made on a working day at the work premises
and during the working time and on a date notified in advance and in case
the work is completed before the expiry of the wage period, final payment
shall be made within 48 hours of the last working day.
4.6 Wages due to every worker shall be paid to him direct or to other person
authorized by him in this behalf.
4.8 Wages shall be paid without any deductions of any kind except those
specified by the Central Government by general or special order in this
behalf or permissible under the Payment of Wages Act 1956/ Code on Wages,
2019.
4.9 A notice showing the wage period and the place and time of disbursement of
wages shall be displayed at the place of work and a copy sent by the
contractor to the Engineer-in-Charge under acknowledgment.
4.10 It shall be the duty of the contractor to ensure the disbursement of wages in
the presence of the Engineer or any other authorized representatives of the
Engineer-in-Charge who will be required to be present at the place and time
of disbursement of wages by the contractor to workmen.
4.11 The contractor shall obtain from the Engineer or any other authorized
representative of the Engineer-in-Charge as the case may be, a certificate
a) Fines
b) Deductions for absence from duty i.e. from the place or the places
where by the terms of his employment he is required to work. The
amount of deduction shall be in proportion to the period for which
he was absent.
e) Any other deduction, which the Central Government may from time
to time allow.
5.2 No fines should be imposed on any worker save in respect of such acts and
omissions on his part as have been approved by the Chief Labour
Commissioner.
NOTE: An approved list of Acts and Omissions for which fines can be imposed is
enclosed at Appendix-I.
5.3 No fine shall be imposed on a worker and no deduction for damage or loss
shall be made from his wages until the worker has been given an
opportunity of showing cause against such fines or deductions.
5.4 The total amount of fine which may be imposed in any one wage period on a
worker shall not exceed an amount equal to three paisa in a Rupee of the
total wages, payable to him in respect of that wage period.
5.5 No fine imposed on any worker shall be recovered from him in installment,
or after the expiry of sixty days from the date on which it was imposed.
5.6 Every fine shall be deemed to have been imposed on the day of the act or
omission in respect of which it was imposed.
6.3 The contractor shall maintain a "Wage Register" in respect of all workmen
employed by him on the work in form (Appendix-D).
7.4 The card shall remain in possession of the worker during the wage period
under reference.
7.5 The contractor shall complete the wage slip portion on the reverse of the
card at least a day prior to the disbursement of wages in respect of the
wage period under reference.
7.6 The contractor shall obtain the signature or thump impression of the worker
on the wage slip at the time of disbursement of wages and retain the card
with himself.
14.0 AMENDMENTS
The NBCC may from to time, add or amend the regulations and on any
question as to the application, interpretation or effect of these regulations
the decision of the Zonal Chief concerned shall be final.
LABOUR BOARD
Name of work
Name of Contractor
Address of Contractor
Date:
S. Category Minimum Actual Number present Remarks
No. wage fixed wages paid
Weekly Holiday
Wage Period
Working hours
Rest interval
FORM 13
See rule 75
____________________________________________________________________
MUSTER ROLL
1. 2. 3. 4. 5. 6.
1 2 3 4 5
REGISTER OF WAGES
WAGE SLIP
6. Deductions if any
WAGE CARD
Initials: ___________________________
Signature
The wage card is valid for one month from the date of issue.
EMPLOYMENT CARD
3. Nature of Employment/Designation
5. Wage Period
6. Tenure of employment
7. Remarks
Signature of Contractor
(SERVICE CERTIFICATE)
Identification Marks
Father's/Husbands Name
1. 2. 3. 4. 5. 6.
Signature
REGISTER OF FINES
1. 2. 3. 4. 5. 6.
6 Habitual negligence.
7 Smoking near or around the area where combustible or other materials are
locked.
8 Habitual indiscipline.
10 Sleeping on duty.
12 Giving the false information regarding name, age, fathers name etc.
19 Collection or canvassing for the collection of any money within the premises of
an establishment unless authorized by the employer.
20. Holding meeting inside the premises without previous sanction of the employers.
1. 2. 3. 4. 5. 6.
REGISTER OF ADVANCES
1. 2. 3. 4. 5. 6.
7. 8. 9. 10. 11.
REGISTER OF OVERTIME
7 8 9 10 11 12
P A R T –I
1. Name of Contractor
3. Agreement No.
Extension granted
9. Reasons for which extension have been previously given (copies of the previous
application should be attached)
10. Hindrances on account of which extension is applied for with dates on which
hindrances occurred, and the period for which these are likely to last.
a) Serial No.
b) Nature of hindrance
b) Date of Occurrence
h) Remarks, if any
Total period for which extension is now applied for on account of hindrances
mentioned above …………. Month/ days.
SIGNATURE OF CONTRACTOR
DATE
(PART – II)
i) Serial No.
4. Engineer-in-charge recommendations.
The present progress of the work should be stated and whether the work is likely to be
completed by the date up to which extension has been applied for. If extension of
time is not recommended, what compensation is proposed to be levied under the
agreement.
SIGNATURTE OF ENGINEER-IN-CHARGE
P A R T –III
To
NAME
SUBJECT:
Dear Sir(s)
The date of completion for the above mentioned work, is ……… as stipulated in the
agreement, dated …………
Provided that notwithstanding the extension hereby granted, time is and shall still
continue to be the essence of the said agreement.
Yours faithfully,
(Judicial Stamp paper of appropriate value as per stamp Act-of respective state)
We, the....... Bank, lastly undertake not to revoke this guarantee during its currency
without the prior consent of NBCC in writing and this guarantee shall remain valid
upto.......... upon expiry of which, we shall be relieved of our liability under this
guarantee thereafter.
DATED:
WITNESS.
1.
2.
WHEREAS, the terms and conditions of the contract require the contractor to furnish
a bank guarantee for Rs............... (Rupees...................) being ............% of the
total value of the contract for proper execution and due fulfilment of the
terms and conditions contained in the contract.
We, the.......... Bank, (hereinafter called “The Bank”) which expression shall unless
repugnant to the subject or context include its successors and assigns) having our
registered office at ….... and branch office at ....... hereby unconditionally and
irrevocably undertake and guarantee payment to NBCC forthwith on the same day
on demand in writing and without protest or demur of any and all moneys
payable by the contractor/supplier to NBCC under, in respect orin connection
with the execution/supply of and performance of the works/equipment, inclusive
of any loss, damages, charges, expenses and costs caused to or suffered by or
which would be caused to or suffered by NBCC by reason of any breach by the
contractor/supplier of any of the terms and conditions contained in the contract as
specified in the notice of demand made by NBCC to the bank with reference to this
guarantee up to and aggregate limit of Rs. ............. (Rupees .........only) the bank
hereby agrees with NBCC that:
1. This Guarantee shall be continuing guarantee and shall remain valid and
irrevocable for all claims of NBCC and liabilities of Supplier/Contractor till the
date of expiry of BG i.e. …………. The claim period of the Bank Guarantee shall be
for a period of 12 Months after the date of expiry of BG.
2. NBCC shall have the fullest liberty without our consent and without
affecting in any manner our obligations and liabilities hereunder to vary any of
the terms and conditions of the said contract or to extend time for performance
of contract by the contractor from time to time or to postpone for any time or
from time to time any of the powers exercisable by NBCC against the
contractor/supplier under the contract and forbear or enforce any of the terms
and conditions relating to the said contract and we shall not be relieved from
our liability by reason of any such variations or extension being granted to the
contractor or for any forbearance, act or omission on the part of NBCC or
any indulgence by NBCC to the contractor or by any such matter or thing
whatsoever, which under the law relating to the sureties would, but for this
provision, have effect of so relieving us.
6. The Bank hereby waives all rights at any time inconsistent with the terms of
this Guarantee and the obligations of the bank in terms hereof, shall not be
otherwise effected or suspended by reasons of any dispute or disputes having
been raised by the supplier/contractor (whether or not pending before
any Arbitrator, Tribunal or Court) or any denial of liability by the
supplier/contractor stopping or preventing or purporting to stop or prevent any
payment by the Bank to NBCC in terms hereof.
Notwithstanding anything contained herein before our liability under this guarantee is
restricted to Rs. ................ (Rupees............................only). This guarantee will
expire on...... Any claim under this Guarantee must be received by us within 12
Months after the date of expiry.
1._______________
2._______________
(Judicial Stamp paper of appropriate value as per stamp Act-of respective state)
In consideration of the NBCC (India) Ltd., having its Registered Office at NBCC,
Bhawan, Lodhi Road, New Delhi -110003 (hereinafter called “NBCC”) which
expression shallunless repugnant to the subject or context include its successors and
assigns having awarded to M/s......................................... .......(hereinafter called
“the Supplier/Contractor”) having its registered Head Office at....... which expression
shall unless repugnant to the subject or context includes its successors and assigns)
a Contract in terms inter-alia of NBCC’s letter NO......................dated..........and the
Contract/Purchase Conditions of NBCC and upon the condition of the
Supplier/Contractor furnishing Security for the performance of the Supplier’s
obligations and /or discharge of the contractor’s/supplier’s liability under and/or in
connection with the said supply contract upto a sum of Rs...............
(Rupees.......................... only). We, the ...................Bank (hereinafter called “The
Bank”) which expression shall unless repugnant to the subject or context include its
successors and assigns having our registered office at ….... and branch office at
....... hereby undertake and guarantee payment to NBCC forthwith on the same
day on demand in writing and without protest or demur of any and all moneys
payable by the supplier/contractor to NBCC under, in respect or in connection
with the said contract inclusive of all the losses, damages, costs, charges and
expenses and other moneys payable in respect of the above as specified in any
notice of demand made by NBCC to the Bank with reference to this guarantee upto
and aggregate limit of Rs…......(Rupees.....................only) and the bank hereby
agree with NBCC that:
1. This Guarantee shall be continuing guarantee and shall remain valid and
irrevocable for all claims of NBCC and liabilities of Supplier/Contractor till the
date of expiry of BG i.e. …………. The claim period of the Bank Guarantee shall be
for a period of 12 months after the date of expiry of BG.
3. NBCC shall be at liberty without reference to the Bank and without affecting the
full liability of the Bank hereunder to take any other security in respect of the
Supplier’s/Contractor’s obligations and/ or liabilities under or in connection with
the said supply/contract or to grant time and / or indulgence to the supplier /
contractor or to increase or otherwise vary the prices or the total contract value
or to release or to forbear from enforcement of all or any of the conditions
under the said supply / contract and / or the remedies of NBCC under any
other security/securities now or hereafter held by NBCC and no such dealings,
increase(s) or other indulgence(s) or arrangement(s) with the supplier /
contractor or releasing or forbearance whatsoever shall have the effect of
6. The Bank hereby waives all rights at any time inconsistent with the terms of
this Guarantee and the obligations of the Bank in terms hereof shall not
be otherwise affected or suspended by reason of any dispute or disputes having
been raised by the supplier / contractor (whether or not pending before any
Arbitrator, Tribunal or Court) or any denial or liability by the supplier/
contractor stopping/ preventing or purporting to stop or prevent any payment
by the Bank to NBCC in terms thereof.
Notwithstanding anything contained herein before our liability under this guarantee is
restricted to Rs. ................ (Rupees............................only). This guarantee will
expire on...... Any claim under this Guarantee must be received by us within 12
months after the date of expiry.
Place
Date
WITNESS:
1. 2.
In consideration of the NBCC (India) Ltd., having its Registered Office at NBCC,
Bhawan, Lodhi Road, New Delhi -110003 (hereinafter called “NBCC” which
expression shall unless repugnant to the subject or context include its successor and
assigns) having agreed under the terms and conditions of Contract No .... dated
....made between M/s............... (hereinafter called the “The Supplier /Contractor”)
having its Registered Head Office at.......... which expression shall unless repugnant
to the subject or context include its successors and assigns and NBCC in connection
with (name of work) (hereinafter called “the said contract”) to make at the request of
the Contractor a Mobilization Advance of Rs. _______ carrying interest @ … % p.a.
for utilizing it for the purpose of the Contract on his furnishing a guarantee
acceptable to NBCC, we the ............ Bank (hereinafter called “The Bank”) which
expression shall unless repugnant to the subject or context include its successor and
assigns and having our registered office at ….... and branch office at ....... here by
unconditionally and irrevocably undertake and guarantee payment to NBCC forthwith
on the same day on demand in writing and without protest or demur the said
advance along with interest as provided according to the terms and conditions of the
contract up to and aggregate limit of Rs .......... (Rupees .........only) inclusive of
interest @ …….% p.a and the Bank hereby agree with NBCC that:
1. This Guarantee shall be continuing guarantee and shall remain valid and
irrevocable for all claims of NBCC and liabilities of tenderer till the date of expiry
of BG i.e. …………. The claim period of the Bank Guarantee shall be for a period of
12 months after the date of expiry of BG.
2. NBCC shall be the sole judge of and as to whether the amount claimed has fallen
due to NBCC under the said agreement or whether the said Contractor has not
utilized the said advance or any part thereof for the purpose of the Contract and
the extent of loss or damage caused to or suffered by NBCC on account of the
said advance together with interest not being recovered in full and the decision
of NBCC that the amount has fallen due from’ contractor or the said Contractor
has not utilized the said advance or any part thereto for the purpose of the
contract and as to the amount or amounts of loss or damage caused to or
suffered by NBCC shall be final and binding on us.
3. Guarantee herein contained shall remain in full force and effect till NBCC certify
that the said advance with interest has been fully recovered from the said
contractor and accordingly discharges this Guarantee. NBCC shall have no claims
under this Guarantee unless a notice of the claims under this Guarantee has
been served on the Bank within 12 months after the expiry of the said Bank
Guarantee in which case the same shall be enforceable against the Bank.
4. This Guarantee shall not be determined or affected by the liquidation or winding
up, dissolution or change of constitution or insolvency of the supplier /
contractor but shall in all respects and for all purposes be binding and operative
until payment of all moneys payable to NBCC in terms thereof or till the expiry of
the Bank Guarantee including claim period of Bank Guarantee, whichever is
earlier.
6. The Bank hereby waives all rights at any time inconsistent with the terms of
this Guarantee and the obligations of the Bank in terms hereof shall not
be otherwise affected or suspended by reason of any dispute or disputes having
been raised by the Supplier /Contractor (whether or not pending before any
Arbitrator, Tribunal or Court) or any denial or liability by the Supplier/
Contractor stopping/ preventing or purporting to stop or prevent any payment
by the Bank to NBCC in terms thereof.
7. NBCC shall have the fullest liberty without affecting in any way the liability of the
Bank under this Guarantee or indemnity from time to time to vary any of the
terms and conditions of the said Contract or the advance or to extend time of
performance by the said Contractor or to postpone for any time and from time to
time of the powers exercisable by it against the said Contractor and either to
enforce or forbear from enforcing any of terms and conditions governing the said
Contract or the advance or securities available to NBCC and the said Bank shall
not be released from its liability under these presents by any exercise by NBCC
of the liberty with reference to the matters aforesaid or by reasons of time being
given to the said Contractor or any other forbearance, act or omission on the
part of NBCC or any indulgence by NBCC to the said Contractor or of any other
matter or thing whatsoever which under the law relating to sureties would but
for this provision have the effect of so releasing the bank from its such liability.
8. It shall not be necessary for NBCC to proceed against the Contractor before
proceeding against the Bank and Guarantee herein contained shall be
enforceable against the Bank notwithstanding any security which NBCC may
have obtained or obtain from the Contractor or shall at the time when
proceedings are taken against the Bank hereunder be outstanding or unrealized.
Notwithstanding anything contained herein before our liability under this guarantee is
restricted to Rs. ................ (Rupees............................only). This guarantee will
expire on...... Any claim under this Guarantee must be received by us within 12
months after the date of expiry.
Witness:
1.
2.
Ref. No.:
Date:
To,
NBCC (I) Limited,
------------------------
------------------------
Dear Sir
Except as provided above, all other terms and conditions of original Bank Guaarantee
No. ........................dated .............................. shall remain unaltered and binding.
Please treat this as an integral part of the original Guarantee to which it would be
deemed to have been attached.
Signature....................................................
Name.........................................................
Designation................................................
Authorised vide Power
of Attorney No..........................................
Dated...........................................................
1. This Guarantee shall be continuing guarantee and shall remain valid and
irrevocable for all claims of NBCC and liabilities of Supplier/Contractor till the
date of expiry of BG i.e. …………. The claim period of the Bank Guarantee
shall be for a period of 12 months after the date of expiry of BG.
3. NBCC shall be at liberty without reference to the Bank and without affecting the
full liability of the Bank hereunder to take any other security in respect of the
Supplier’s/Contractor’s obligations and/ or liabilities under or in connection with
the said supply/contract or to grant time and / or indulgence to the supplier /
contractor or to increase or otherwise vary the prices or the total contract
value or to release or to forbear from enforcement of all or any of the
conditions under the said supply / contract and / or the remedies of NBCC
6. The Bank hereby waives all rights at any time inconsistent with the terms of
this Guarantee and the obligations of the Bank in terms hereof shall not
be otherwise affected or suspended by reason of any dispute or disputes
having been raised by the supplier / contractor (whether or not pending
before any Arbitrator, Tribunal or Court) or any denial or liability by the
supplier/ contractor stopping/ preventing or purporting to stop or prevent
any payment by the Bank to NBCC in terms thereof.
During this period of guarantee the guarantor shall make good all defects and for that
matter shall replace at his risk and cost such wooden member as may be damaged by
termite and in case of any other defect being found, he shall render the building
termite proof at his cost to the satisfaction of the Engineer-in-charge and shall
commence the works of such rectification within seven days from date of issuing
notice from the Engineer-in-Charge calling upon him to rectify the defects falling which
the work shall be got done by NBCC/ OWNER by some other contractor at the
guarantor's cost and risk and in the later case the decision of the Engineer-in-charge
as to the cost recoverable from the guarantor shall be final and binding.
That if the Guarantor fails to execute the Anti-Termite treatment or commits breaches
hereunder then the Guarantor will indemnify NBCC against all losses damages, cost
expenses or otherwise which may be incurred by him by reasons of any default on the
part of the guarantor in performance and observance of this supplemental Agreement.
As to the amount of loss and or damage and/or cost incurred by NBCC/ OWNER
decision of the Engineer-in-charge will be final and binding on the parties.
2.
1.
2.
(Judicial Stamp paper of appropriate value as per stamp Act-of respective state)
In consideration of the NBCC (India) Ltd., having its Registered Office at NBCC,
Bhawan, Lodhi Road, New Delhi -110003 (hereinafter called “NBCC”) which
expression shall unless repugnant to the subject or context include its successors
and assigns having awarded to M/s......................................... .......(hereinafter
called “the Supplier/Contractor”) having its registered Head Office at.......
which expression shall unless repugnant to the subject or context includes its
successors and assigns) a Contract in terms inter-alia of NBCC’s letter
NO......................dated..........and the Contract/Purchase Conditions of NBCC
and upon the condition of the Supplier/Contractor furnishing Security for the
performance of the Supplier’s obligations and /or discharge of the
contractor’s/supplier’s liability for removal of defects in Water Proofing
treatment under the said contract upto a sum of Rs...............
(Rupees.......................... only). We, the ...................Bank (hereinafter called
“The Bank”) which expression shall unless repugnant to the subject or context
include its successors and assigns having our registered office at ….... and
branch office at ....... hereby undertake and guarantee payment to NBCC
forthwith on the same day on demand in writing and without protest or demur of
any and all moneys payable by the supplier/contractor to NBCC under, in
respect or in connection with the said contract inclusive of all the losses,
damages, costs, charges and expenses and other moneys payable in respect of
the above as specified in any notice of demand made by NBCC to the Bank with
reference to this guarantee upto and aggregate limit of
Rs…......(Rupees.....................only) and the Bank hereby agree with NBCC
that:
1. This Guarantee shall be continuing guarantee and shall remain valid and
irrevocable for all claims of NBCC and liabilities of Supplier/Contractor till the
date of expiry of BG i.e. …………. The claim period of the Bank Guarantee
shall be for a period of 12 months after the date of expiry of BG.
3. NBCC shall be at liberty without reference to the Bank and without affecting the
full liability of the Bank hereunder to take any other security in respect of the
Supplier’s/Contractor’s obligations and/ or liabilities under or in connection with
the said supply/contract or to grant time and / or indulgence to the supplier /
contractor or to increase or otherwise vary the prices or the total contract
value or to release or to forbear from enforcement of all or any of the
conditions under the said supply / contract and / or the remedies of NBCC
6. The Bank hereby waives all rights at any time inconsistent with the terms of
this Guarantee and the obligations of the Bank in terms hereof shall not
be otherwise affected or suspended by reason of any dispute or disputes
having been raised by the supplier / contractor (whether or not pending
before any Arbitrator, Tribunal or Court) or any denial or liability by the
supplier/ contractor stopping/ preventing or purporting to stop or prevent
any payment by the Bank to NBCC in terms thereof.
The agreement made this ……………..day of ……………..Two thousand One and ……..
between …………………………… (hereinafter called Guarantor of the one part) and the
NBCC (India) Limited (hereinafter called the Execution Agency of the other part).
AND WHEREAS the Guarantor agreed to give a guarantee to the effect that the said
structures will remain water and leak proof for ten years from the date of handing
over of the structure of water proofing treatment.
NOW THE GUARANTOR hereby guarantees that water proofing treatment given by him
will render the structures completely leak proof and the minimum life of such water
proofing treatment shall be ten years to be reckoned from the date after the
maintenance period prescribed in the contract.
Provided that the Guarantor will not be responsible for leakage caused by earthquake
or structural defects or misuse of roof or alteration and for such purpose.
a) Misuse of roof shall mean any operation, which will damage proofing treatment,
like chopping of fire wood and things of the same nature which might cause
damage to the roof.
During this period of guarantee, the Guarantor shall make good all defects and in case
of any defect being found render the building water proof to the satisfaction of the
Engineer-in-Charge at his cost and shall commence the work for such rectification
within seven days from the date of issue of notice from the Engineer-in-Charge calling
upon him to rectify the defects failing which the work shall be got done by the NBCC
by some other Contractor at the guarantor’s cost and risk. The decision of Engineer-
in-Charge as to the cost, payable by the Guarantor shall be final and binding.
That if the Guarantor fails to execute the water proofing or commits breach there-
under, then the Guarantor will indemnify the principal and his successors against all
laws damage, cost, expense or otherwise which may be incurred by him by reason of
any default on the part of the GUARANTOR in performance and observance of this
supplementary agreement. As to the amount of loss and / or damage and/ or cost
incurred by the NBCC, the decision of the Engineer-in-Charge will final and binding on
the parties.
1.
2.
In presence of:
1.
2.
And whereas the Contractor has applied to the Engineer that he may be or be given
credited for materials brought by him to the site of the work subject to the said
agreement for use in construction of the work.
NOW THIS INDENTURE WITNESSETH that in pursuance of the said agreement and in
consideration of the sum of Rs._____________ (Rupees ___________ only) paid to
the contractor by the Engineer. The receipt where the Contractor hereby
acknowledges and of such advance or credited (if any) as may be made to him as
aforesaid the Contractor hereby covenants and agrees with The Engineer and declares
as follows:
1. That all sums given as advance or credit by The Engineer to the Contractor as
aforesaid shall be employed by the Constructor in or toward the execution of the
said works and for no other purpose whatsoever.
2. That the material for which the advance or credit is given are offered to and
accepted by The Engineer as security and are absolutely the Contractor's own
property and free from encumbrances of any kind the Contractor will not make
any application for or receives further advance or credit on the security or
material which are not absolutely his own property and free from encumbrances
of any kind and the Contractor shall indemnify The Engineer against any claims
to any material in respect of which advance or credit has been made to him as
aforesaid.
3. That the said material and all other material on the security of which any further
advance or advances or credit may be given as aforesaid (hereinafter called the
said materials) shall be used by the Contractor s solely in the execution of the
said works in accordance with the direction of the Engineer and in terms of said
agreement.
4. That the Contractor shall make at his own cost all necessary and adequate
arrangement for the proper safe custody and protection against all risks of the
said material and that until used in the construction as aforesaid the material
shall remain at the site of the said works in Contractor's custody and on his
responsibility and shall at all times be open to inspection by The Engineer. In the
events of the materials or any part thereof being stolen, destroyed or damaged
or becoming deteriorated in greater degree than in due to reasonable use and
wear thereof the Contractor will replace the same with other materials of like
quality of repair and make good the same as required by The Engineer.
5. That said material shall not on any account be removed from the site of work
expect with the written permission of The Engineer.
6. That the advance shall be repayable in full when or before Contractor receives
payment from The Engineer of the price payable to him for the said work under
the term and provisions of the said agreement. Provided that if any intermediate
7. That if the Contractor shall at any time make at any default in the performance
of observance in respect of any of the terms and provisions of the said
agreement or of that provisions the total amount of the advance or advances
that may still be owing to The Engineer, shall immediately on the happening of
such default be repayable by the Contractor to The Engineer together with
interest thereon at 12% p.a. from the date of respective dated to such advance
or advances to the date of payment and with all costs. Damages and expenses
incurred by The Engineer in or for recovery hereof or the Contractor hereby
covenants and agrees with The Engineer to repay and pay the same respective
to him accordingly.
8. That the Contractor hereby charges all the said materials with the repayment to
The Engineer of all sums advances or credit as aforesaid and all costs. Charges,
damages and expenses payable under these presents PROVIDED ALWAYS it is
hereby agreed and declared that notwithstanding anything in the said agreement
and without prejudice to the powers contained therein if and wherever the
covenant for payment and repayment herein before contained shall be become
enforceable and the money owing shall not be paid in accordance therewith. The
Engineer may at any time thereafter adopt all or any of the following courses he
may deem best:
a. Seize the utilize the said material or any part thereof in the completion of the
said works in accordance with the provision in that behalf contained in the
said agreement debating the Contractor with the actual cost of effecting such
completion and the amount due in respect of advance or credit under these
presents and crediting the Contractor with value of work done as if he has
carried it out in accordance with the said agreement and the rates thereby
provided if the balance is against the Contractor is to pay the same to the
engineer on demand.
b. Remove and sell by public action the seized materials or any part thereof and
out of the money arising from the sale repay the engineer under these
presents and pay over the surplus (if any) to the Contractor.
c. Deduct all or any part of the moneys owing from any sums due to the
contractor under said agreement.
9. Expect in the event of such default on the part of contractor as aforesaid,
interest or the said advance shall not be payable.
10. That in the event of conflict between the provisions of these presents and the
said agreements, the provision of these presents shall prevail and in the event of
any dispute or difference arising over the construction or effect of these
presents, the settlement of which has not been hereinbefore expressly provided
for the same shall so far as is lawful be subject to jurisdiction of Delhi courts
only.
IN WITNESS whereof the said the engineer and the contractor hereunto set their
respective hands and seals the day year first above written.
This agreement made this day of (Month) (Year), between the NBCC (India)
Limited (NBCC), a company incorporated under the Companies Act, 1956 having its
RegisteredOffice at NBCC Bhawan, Lodhi Road, New Delhi – 110 003 (hereinafter
referred to as the “NBCC” which expression shall include its administrators,
successors, executors and assigns) of the one part and M/s (NAMEOF
CONTRACTOR) (hereinafter referred to as the ‘Contractor’ which expression shall
unless the context requiresotherwise include its administrators, successors, executors
and permitted assigns) of the other part.
NBCC has awarded the contract to (NAME OF CONTRACTOR) for the work of
(NAME OF WORK) on the terms and conditions in its letter of intent No.
__________ dated ________ and the documents referred to therein. The award has
taken effect from (DATE) i.e. the date of issue of aforesaid letter of intent. The terms
and expressions used in this agreement shall have the same meanings as are
assigned to them in the “Contract Documents” referred to in the succeeding Article.
2.1 The contract shall be performed strictly as per the terms and conditions
stipulated herein and in the following documents attached herewith (hereinafter
referred to as “Contract Documents”).
a) NBCC Notice Inviting Tender vide No. ________ date ______and NBCC’s
tender documents consisting of:
v) ______________________________________________
2.2 NBCC’s detailed Letter of Intent No. _________ dated ____ including Bill of
Quantities. Agreed time schedule, Contractor’s Organisation Chart and list of
Plant and Equipments submitted by Contractor.
2.3 All the aforesaid contract documents referred to in Para 2.1 and 2.2 above shall
form an integral part of this Agreement, in so far as the same or any part
thereof column, to the tender documents and what has been specifically agreed
to by NBCC in its Letter of Intent. Any matter inconsistent therewith, contrary or
repugnant thereto or deviations taken by the Contractor in its “TENDER” but not
agreed to specifically by NBCC in its Letter of Intent, shall be deemed to have
been withdrawn by the Contractor without any cost implication to NBCC. For the
sake of brevity, this Agreement alongwith its aforesaid contract documents and
Letter of Intent shall be referred to as the “Contract”.
3.2 The scope of work shall also include all such items which are not specifically
mentioned in the Contract Documents but which are reasonably implied for the
satisfactory completion of the entire scope of work envisaged under this contract
unless otherwise specifically excluded from the scope of work in the Letter of
Intent.
3.4 Time is the essence of the Contract and it shall be strictly adhered to. The
progress of work shall conform to agreed works schedule/contract documents
and Letter of Intent.
3.5 This agreement constitutes full and complete understanding between the parties
and terms of the presents. It shall supersede all prior correspondence to the
extent of inconsistency or repugnancy to the terms and conditions contained in
Agreement. Any modification of the Agreement shall be effected only by a
written instrument signed by the authorized representative of both the parties.
3.6 The total contract price for the entire scope of this contract as detailed in Letter
of Intent is Rs. ____________________________________________ (Rupees
_____________________________ only), which shall be governed by the
stipulations of the contract documents.
5.1 The Laws applicable to this contract shall be the laws in force in India and
jurisdiction of Delhi Court (s) only.
Notice of default given by either party to the other party under the Agreement
shall be in writing and shall be deemed to have been duly and properly served
upon the parties hereto, if delivered against acknowledgment due or by FAX or
by registered mail duly addressed to the signatories at the address mentioned
herein above.
WITNESS: WITNESS:
1. 1.
NBCC has awarded the (Name of the Project)………………………… vide LoA No. …………….
Dated……………….. and Agreement dated……......., to M/s ………………………………………,
having its Regd. Office/ Head Office at ……………………………, hereinafter referred to as
“contractor”.
2. In terms of the Clause 23.2 of the General Conditions of Contract the contractor is
entitled for payment only when NBCC receives the corresponding payment against
the bill from the client/owner of the project. However, since no corresponding
payment against the bill has been released by the client/owner, on the
contractor’s specific request for financial assistance under Clause 23.4 of the
General Conditions of Contract, NBCC has shown its willingness to extend financial
assistance amounting to Rs. ………………… (Rs …………………………….) to the contractor
for use in execution of the aforementioned work(s).
3. The sum(s) released under the said Clause 23.4 as financial assistance by NBCC
shall be utilised by the contractor in or toward the execution of the said works and
for no other purpose whatsoever.
5. The sum(s) released under the said Clause 23.4 as financial assistance along with
interest thereon shall be adjusted/recovered by NBCC from the corresponding
payment received from the client/owner as stipulated in the said Clause 23.4 or at
NBCC’s sole discretion from any other dues at any stage of the contract or from
any other work(s) being executed by contractor on behalf of NBCC.
These wagesare not less than the minimum rates applicable to all the
employees and no other dues are payable to any employee.
3. That I and the sub-contractor engaged by me for the above said work, if any,
have covered all the eligible employees under Employees Provident Funds and
Miscellaneous Provisions Act, 1952 and the Employees State Insurance Act,
1948 and deposited the Contributions for the months up to ------------------
-------and as such no amount towards EPF/ESI contributions, whatsoever is
payable, is pending.
Authorised Signatory
(Name & Seal of Company)
Date:____________
Witness:
1. _________________
2. _________________
No. Dated
This is to certify that M/s NBCC (India) Limited, NBCC Bhawan, Lodhi Road, New
Delhi-110003 has successfully completed and handed over the work/Project of
_________________________ as per Technical specifications, drawings and
meeting norms of contract agreement/MOU. The details of project are given
below:-
S. Description Details
No.
1 Name of Project/
Work
2 Sanction letter/
Agreement No. &
date
3 Sanctioned cost Rs.
By and Between
NBCC (India) Ltd., having its Registered Office at NBCC, Bhawan, Lodhi Road, New
Delhi -110003 (hereinafter called NBCC) which expression shall unless be
repugnant to the context include its successors and assigns of the second part.
WHEREAS vide LOA bearing No_______ dated ______ the Contractor was
awarded the work of __________ (hereinafter referred to as “said work”).
2) That the Contractor agrees to the said amount of Rs. ___________ being
deducted/ adjusted from any/all payment due or that may become due to
the Contractor from NBCC.
5) That any dispute arising out of this indenture of Indemnity shall be subject
to the exclusive jurisdiction of the courts at New Delhi only.
Contractor/Indemnifier
Witness
1.
2.