2013 Behavior of Surrounding Soil During Construction Using Pipe Jacking in Deep Strata
2013 Behavior of Surrounding Soil During Construction Using Pipe Jacking in Deep Strata
2013 Behavior of Surrounding Soil During Construction Using Pipe Jacking in Deep Strata
Copyright © 2013 Takashi Senda et al. This is an open access article distributed under the Creative Commons Attribution License,
which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
ABSTRACT
In Japan when urban infrastructures need to be constructed, the difficulty of utilizing the ground or shallow strata will
lead to a more frequent use of the deep strata. The common construction methods are open-cut, pipe jacking, and shield
methods. In recent years, a new pipe jacking method has been established that can be adapted to 20 m below the ground
or more. Using this method, the drivage machine and the jacking pipe continue to move an underground until the com-
pletion of the driving. Therefore an over-cutting area (so-called tail-void) must be formed to lower the friction between
the ground and the pipe. The tail-void is filled with lubrications. However, because the stress release from the ground
continues to advance when the tail-void is formed, hence there are some challenges required to cope with the stability of
the surrounding ground. In order to utilize the pipe jacking method in the deeper strata layers, the theory, analysis and
installation of tail-void have to be systemized, and such systematic data must be stored. Therefore, the conditions of
tail-void in the deep pipe jacking method are discussed using numerical analyses.
ing surface of drivage machine and its contact ground, vage machine.
generation of tail-void, and lubricant. Those analysis 3) By repetition of the pushing process, if the rear-end
were considered using the finite element method, which driving after one concrete pipe length (2.5 m) is driving
produce great results for the prediction of deformation in, connect another pipe.
behavior of the ground during the shield construction. 4) After driving is completed, recover the drivage ma-
From this point of view, this method was adopted for chine from the arrival pit.
analyzing the pipe jacking method [2]. More widely used techniques that are now being used
elsewhere for micro-tunneling, use remote control dri-
2. What is the Pipe Jacking vage methods in conjunction with pipe jacking. During
In the pipe jacking method, drivage machine is set at the the pushing processes, the mud slurry is injected into the
head of the pipeline and the pipes are jacked forward face and tail-void, which is between the pipe and the soil.
with the hydraulic jack, located at the starting shaft. After tail-void is filled by the slurry, soil is stabilized due
The pipe jacking, like many other methods of below to the slurry pressure. To minimize ground deformation
ground construction, is best employed in stable, water in the pushing process, it is necessary to maintain the
free soil conditions. Unfortunately, with the demands on slurry pressure that was kept on the underground water
available space and the need to provide more services, it pressure at plus 20 kPa [5].
is not always possible to select stable strata, which means Thus, tail-void plays an important role in reducing the
that contractors have to contend with difficult ground be- friction resistance in pushing the pipes and maintaining
low the water table [3,4]. The slurry pipe jacking system earth covering pressure.
is applicable to the above situations.
Figure 1 shows the pipe jacking system scheme. This 3. Numerical Analysis
system can be used to construct pipe tunnels up to 3000 The boundary conditions of the ground, where the pipe
mm in diameter and construct both long (maximum length: jacking construction is made, are so complex and wide-
1000 m) and curved tunnels (minimum curvature radius: ranging that in many cases 3-dimentional effect cannot
25 m). be ignored when considering the design of the pipe jack-
Recent technological developments have led to suc- ing construction. Therefore, excavation elements were
cessful methods for stabilizing unstable strata by exclud- used to create a 3-dimentional finite element method con-
ing water from excavations by means of tail-void with sidering the actual construction process of pipe jacking
mud slurry. This system meets modern environmental construction.
standards. This type of mud slurry is formed by water, de-
composed granite soil, carboxyl methyl cellulose, lost 3.1. Outline of Analysis
circulation control material, bentonite, fine aggregate,
and other materials. Figure 2 shows an illustration of the In the pipe jacking construction, just after the drivage
pipe and the soil in this system. The proportional mixes machine passes by the tail, the tail-void is generated due
vary the viscosity and the seepage capacity of the mud to the difference of the outer diameter of each pipe,
slurry and will be determined by whether mud slurry is which releases stress in the ground. As the actual con-
required to strengthen the soil. struction lubricant is injected into the tail-void to prevent
This system is used as follows: the ground from deformation due to stress release caused
1) Install the pushing equipment in the starting pit, and by formation of the tail-void in the ground. To simulate
then set the drivage machine. this situation in the analysis, a nodal force equivalent to
2) Extend the rear-end pushing jack and push the dri- the injection pressure is applied to the soil element where
4. Results and Discussion Figure 3. Young’s modulus and Poisson’s ratio elapsed time
after injection.
Figure 5 shows the deformations of the crown at the tail-
void during pipe jacking of 10, 20 and 30 m. The pres-
sure of the cutting face was acted against the front face of
5. Conclusion
Based on the analytical results, it was found that if the
Figure 8. Relationship between the vertical displacement on
earth covering in the deeper ground increases, the sur- the surface and the distance from the center.
rounding soil during the pipe jacking construction, and
the tail-void in particular, must be looked at, due to the
increased deformation.
Now that long distance and narrow curve jacking tech-
niques have been established and watertight joints for
installation have been rapidly developed, the pipe jacking
method can be applied to the pipe installation in under-
ground deeper than 20 m of earth covering. However, the
stress release of the ground continues along with the for-
mation of tail-void. Therefore, there are many challenges
to cope with for the improvement of stability in the sur-
rounding ground.
Figure 5. Effect on the deformation by differences of thrust While the drivage machine approaches and passes by,
length: L (m). the stress and strain conditions change with time. Plural
factors, such as changing position of drivage machine
and surrounding friction, can often affect the ground si-
multaneously. In addition, a long-term ground subsi-
dence followed by the ground deformation at the time of
construction can be caused directly by the soil distur-
bance resulting from the ground deformation during con-
struction. Therefore most of the ground deformations caused
by the pipe jacking construction may be caused by chang-
ing stress and strain conditions over the course of con-
struction.
That is why the discussion of appropriate lubricants
Figure 6. Effect on the deformation by differences of earth and injection methods, etc. in preparation for such chang-
covering: H (m). es is inevitable.
REFERENCES
[1] Japan Tunneling Association, “Trend of Using Deep Un-
derground and Activity Report,” 1997.
[2] H. Akagi and K. Komiya, “Ground Behavioral Analysis
in Consideration of the Construction Process of Shield
Tunneling in Finite Element Method,” Journal of Japan
Society of Civil Engineers, Vol. III-25, No. 481, 1993, pp.
59- 68.
[3] J. M. Cole, “Pipe Jacking Case Histories, Tunnels and Tun-
neling,” 1977.
Figure 7. Effect on the deformation by differences of soils. [4] C. M. Hough, “Pipe Jacking Case Histories, Tunnels and