Week 1 - Methods of Prestress
Week 1 - Methods of Prestress
Week 1 - Methods of Prestress
Introduction
This prestressing of the steel may be performed either before or after pouring of the
concrete. Thus, two methods of prestressing a concrete beam are available:
PRETENSIONING and POSTTENSIONING.
“
Pretensioning
Pretensioning
▫ Moving partial assemblies from a factory often cost less than moving pre-
production resources to each site
▫ Deploying on-site can add costs; prefabricating assemblies can save costs by
reducing onsite work.
▫ Factory tools such as jigs, cranes, and conveyors, can make production faster and
more precise.
▫ Consistent indoor environments of factories eliminate most impacts of weather
on production.
▫ Cranes and reusable factory supports can allow shapes and sequences without
expensive on-site falsework.
Advantages
▫ Factory tools such as shake tables and hydraulic testers can offer added quality
assurance
▫ high-precision factory tools can aid more controlled movement of building heat
and air, for lower energy consumption and healthier buildings.
▫ Factory production can facilitate more optimal usage, recycling, noise capture,
and dust capture
▫ Machine-mediated parts movement and freedom from wind and rain can improve
construction safety.
Disadvantages
The tendons are not placed in direct contact with the concrete, but are encapsulated
within a protective sleeve or duct which is either cast into the concrete structure or
placed adjacent to it.
Post-tensioning
The large forces required to tension the tendons result in a significant permanent
compression being applied to the concrete once the tendon is “locked-off” at the
anchorage
1. In Stage 1, the strands or tendons are
fed through the ducts.
In bonded post tensioning, the tendons are permanently bonded to the surrounding
concrete by the in-situ grouting of their encapsulating ducting (after tendon
tensioning).
Bonded Post-Tensioning
Following concreting and tensioning, the ducts are pressure-grouted and the tendon
stressing-ends sealed against corrosion.
“
Grouting of Post-Tensioned Tendons
Grouting
The grouting procedure shall be carried out not later than 2 weeks of stressing. The
anchorage ends of the cable are sealed with the same grade of concrete after the
stressing is completed
Pre-grouting Procedure
▫ If any traces of oils are found applied on the steel for preventing corrosion, they
should be removed before grouting operation.
▫ For cleaning and wetting of the surfaces of the duct walls, clean potable water is
flushed into the ducts.
▫ The water should be drained through the lowest vent pipe or by blowing oil-free
compressed air through the duct.
Pre-grouting Procedure
▫ All outlet points including vent openings should be kept open prior to the
commencement of injection grout.
▫ Before grouting process, all air in the pump and hose should be expelled. The
suction circuit of the pump should be airtight.
Injection of Grout
▫ The grout should be allowed to flow freely from the other end until the
consistency of the grout at this end is the same as that of the grout at the injection
end.
Injection of Grout
▫ The grout should be allowed to flow freely from the other end until the
consistency of the grout at this end is the same as that of the grout at the injection
end.
▫ When the grout flows at the other end, it should be closed off and building up of
pressure commenced. Full injection pressure at about 0.5Mpa is maintained for at
least 1 min to ensure effective grouting.
▫ For vertical cables or cables inclined more than 66 degrees to the horizontal, the
injection should be effected from the lowest anchorage or vent of the duct.
▫ The method of injection should ensure complete filling of ducts. To verify this, it is
advisable to compare the volume of the space to be fitted by the injected grout
with the quantity of grout actually injected.
“
Benefits of Bonded Post-Tensioning
Reduced Reliance on End-Anchorage Integrity
Bonded tendons are connected to the surrounding concrete along their full length by
high-strength grout. As a result, any inadvertent severing of the tendon or failure of an
end anchorage has only a very localized impact on tendon performance.
Increased Ultimate Strength in Flexure
Any flexure of the structure is directly resisted by the tendon strains at that same
location. This results in significantly higher tensile strains in the tendons, allowing their
full yield strength to be realized, and producing a higher ultimate load quality.
Improved Cracked Control
The absence of strain redistribution in bonded tendons may limit the impact that any
localized overheating has on the overall structure. As a result, bonded structures may
display higher capacity to resist fire conditions
“
Unbonded Post-Tensioning
Unbonded Post-Tension
Being permanently isolated from concrete, unbonded tendons are able to be readily
de-stressed, re-stressed and/or replaced should they become damage or need their
force levels to be modified in-service
Superior Overload Performance
Although having lower ultimate strength than bonded tendons, unbonded tendons’
ability to redistribute strains over their full length can give them superior pre-collapse
ductility.