NHBC Standards 2024 6
NHBC Standards 2024 6
NHBC Standards 2024 6
6.1
External masonry walls
This chapter gives guidance on meeting the Technical
Requirements for external masonry walls.
6.1.1 Compliance 01
6.1.2 Provision of information 02
6.1.3 Structural design 02
6.1.4 Fire resistance 05
6.1.5 Acoustic resistance 06
6.1.6 Exposure 06
6.1.7 Thermal insulation 10
6.1.8 Concrete blocks 14
6.1.9 Bricks 14
6.1.10 Stone masonry 16
6.1.11 Construction of masonry walls 16
6.1.12 Lintels 21
6.1.13 Materials suitable for mortar 23
6.1.14 Mortar 23
6.1.15 Render 25
6.1.16 Cladding 25
6.1.17 DPCs and cavity trays 27
6.1.18 Wall ties and bedjoint
reinforcements 33
6.1.19 Handling materials 34
6.1.20 Protection of the works
during construction 35
For figure reference tables in this chapter, please go to the end of the chapter
1 External masonry walls I 2024
Chapter 6.1
Introduction
This chapter provides guidance on external masonry which is used for the outer and inner leaves of a cavity wall construction,
cladding to framed structures and to the limited solid wall construction used in housebuilding such as garages. General guidance
on masonry cavity wall construction including the masonry inner leaf of a cavity wall are also provided within this chapter.
The guidance is consistent and complementary to that provided within Chapter 6.9 Curtain walling and cladding which should be
used for products and systems falling under that description.
There is a strong link to all chapters in Part 6 of this standards, particularly Chapters 6.2 – 6.5, 6.10 and 6.11.
The aim of this chapter is to provide clarity for external and cavity walls constructed of clay and concrete bricks and blocks as
well as natural stone.
Coordinating size Size of a coordinating space allocated to a masonry unit including allowances for joints
Coursing unit Masonry unit, commonly of brick sizes, used to assist in achieving the storey height of a wall in
conjunction with full height blocks
Fully filled cavity The insulation thickness is such that the it will be in full contact with both leaves of masonry
when the building meets normal construction tolerances
Manufactured stone masonry Facing masonry unit having at least one exposed face with a close structure formed from
unit either one or two homogeneous mixtures of aggregate, cementitious binder and other
materials moulded under pressure and/or vibration and with or without further processing,
intended to resemble and be used as an alternative to natural stone
Masonry Assemblage of masonry units laid in a specified pattern and joined together with mortar
Masonry unit Preformed component intended for use in masonry construction
Natural stone masonry unit Masonry unit manufactured from natural stone
Recessed joints Where the mortar is raked out, about 5mm from the wall face. There are certain exposure
conditions where these should not be used (clause 6.1.6)
Work size Size of masonry unit specified for its manufacture, to which the actual size conforms within
permissible deviations
Where proprietary products are to be used, manufacturers generally have specific requirements for fixing and/or assembly.
This information should also be made available for reference on site so that work can be carried out satisfactorily in accordance
with the design and specification.
6.1
c) concentrated loads f) damp proof courses.
Lateral restraint
Lateral restraint provided by concrete floors:
Concrete floors, with a minimum bearing of 90mm onto the wall, can provide adequate restraint. Concrete floors running parallel
to, and not built into, walls require restraint straps to provide restraint to the wall.
Lateral restraint provided by timber floors:
Timber joisted floors can provide adequate restraint when joists are carried by ordinary hangers to BS EN 845-1, and connected
to the wall with restraint straps. In buildings up to two storeys, timber joisted floors can provide adequate restraint without
strapping when:
z the minimum bearing onto masonry is 90mm z joists are carried by BS EN 845-1 restraint-type hangers
(or 75mm onto a timber wall plate), or with performance equivalent to a restraint strap spaced at a
maximum of 2m centres.
3 External masonry walls I 2024
Chapter 6.1
Lateral restraint provided by buttressing walls Figure 1: Lateral restraint by buttressing wall
Concentrated loads
Concentrated loads should be designed by a suitably qualified Engineer, for example at the bearing of trimmers, lintels, multi-ply
trusses or steel beams.
Where bearing stresses under concentrated loads are greater than the strength of the supporting masonry wall, padstones and
spreaders should be provided.
Padstones and spreaders may be required, to support concentrated loads.
Bonding
Where partition walls abut an external wall constructed of similar materials, fully bonded or tied joints are acceptable. Partition
walls may act as buttressing walls mentioned above. To reduce the risk of cracking, a tied joint is preferable where:
6.1
z materials have dissimilar shrinkage or expansion z there is a connection between a load-bearing wall on
characteristics, eg dense concrete and aircrete concrete foundations and a non load-bearing wall supported on a
ground-bearing slab.
Tied joints should be formed using expanded metal, wire wall ties or a proprietary equivalent, spaced at maximum 300mm intervals.
Dissimilar materials should not be used in the same wall (eg clay bricks as “make up” courses in concrete blockwork walls).
Movement joints
Movement joints should be included in long lengths of walling to control expansion or contraction of masonry panels and reduce
unsightly cracking and detailed so that stability is maintained. Where possible, joints should be hidden in corners, or behind
rainwater pipes, and:
z run the full height of the superstructure masonry wall z continue from those provided in the substructure to the
z should not coincide with window and door openings superstructure (movement joints may be needed in the
superstructure and not in the substructure, providing
suitable allowance is made for relative movement).
Vertical movement joints should be provided in the outer leaf, in accordance with Table 1.
2024 I External masonry walls 4
Chapter 6.1
Notes
1 Manufacturer’s guidance for the provision of movement joints and bed joint reinforcement should be considered.
2 For clay bricks, the joint width in mm should be spacing in metres+30%. i.e at 8m movement joint spacing the joint width should be 10mm.
3 Lightweight concrete masonry units are generally made of aggregates that have a gross density not exceeding 1,500 kg/m³. Dense concrete masonry units are
generally made of aggregate that have a gross density exceeding 1,500 kg/m³.
4 The ratio of length to height of the panels should generally not exceed 3:1.
5 As defined within PD 6697.
6 Located no more than 7.5m from an external corner.
The spacing of the first movement joint from a return should Figure 2: Movement joint sealant
not be more than half of the dimension in Table 1.
Movement joints are not generally necessary in the inner leaf
of cavity walls, but consideration should be given to providing:
z movement joints in rooms with straight unbroken lengths of
wall over 6m
z bed joint reinforcement as an alternative to movement joints
in areas of risk, eg under window openings.
6.1
Wall ties should be provided on either side of movement joints, in accordance with Clause 6.1.18.
Where masonry walls form panels in a framed structure, movement joints should be provided in accordance with BS EN 1996-2
and PD 6697.
Movement joints should be formed using the correct materials, and account taken of:
z joint width and depth z surface preparation and backing materials
z anticipated movement and capability of the material z likely design life of the joint.
Clay bricks expand and require movement joints formed from easily compressible materials, such as:
z flexible cellular polyethylene z foam rubber.
z cellular polyurethane
Concrete bricks and blocks contract, and the following materials are acceptable for use in contraction joints:
z hemp z cork.
z fibreboard
The joints should be formed using semi-rigid, closed cell polyethylene or other suitable materials.
To perform effectively a sealant in a movement joint should be applied against a suitable debonding joint filler board/backing rod
so that the sealant only adheres to the two opposing masonry faces.
5 External masonry walls I 2024
Chapter 6.1
Cavity barriers need to achieve a minimum of 30 minutes’ integrity (E 30) and 15 minutes’ insulation (I 15).
Vertical cavity barriers, where required, should extend below the DPC and care should be taken to ensure continuity of cavity
barriers where cavity barriers are installed at DPC level.
Where cavity barriers are used, they should be sized appropriately for the dimensions of the cavity. Normally they are installed
under compression and as such maintaining the design cavity width is critical.
Significant reduction in cavity width will mean that the barrier cannot be fitted without creating problems for the following leaf
6.1
of masonry. Significant widening in the cavity width will mean that the barrier may not be fitted with the appropriate level of
compression and its performance may be impaired.
Concealed spaces
Where cladding is fitted to a masonry substrate wall, cavity barriers should be provided. Cavity barriers to concealed spaces
behind external cladding should be positioned:
z at the edges of cavities including eaves and verges, around z at the junction between an external cavity wall and every
openings such as windows and doors and entry/exit points compartment floor and compartment wall.
for services
2024 I External masonry walls 6
Chapter 6.1
The density of external walls and the position of openings adjacent to separating walls should be in accordance with Building
Regulations and, where relevant, an assessment which complies with Technical Requirement R3. Refer to the Robust Details
Handbook for the specification of separating wall and floor constructions and their associated flanking walls.
Where different block materials are used eg, aggregate separating wall with aircrete inner leaf, differential drying and cracking
can occur, so it is important that the separating wall goes through (and not up to) the inner leaf.
6.1
External walls shall be suitable for their exposure and resist the passage of moisture to the inside of
the home. Issues to be taken into account include:
a) durability c) freeze/thaw cycles.
b) rain penetration
Durability
Masonry can become saturated, and may remain so for long periods. Therefore, precautions should be taken to resist frost
damage and sulfate attack affecting:
z parapet walls and copings z masonry below the DPC at ground level
z sills and projections z freestanding walls.
Masonry units and mortar should comply with BS EN 1996-1-1 and be used in accordance with Table 15 of PD6697 and the
manufacturer’s recommendations. In addition, mortar mixes should be selected from BS EN 998-2 Table NA.1, and only cement
types listed in BS EN 998-2 NA1.2 should be used.
Cement with sulfate-resisting properties should be used where S1 clay bricks are used in the following situations:
z below the DPC where there are sulfates present in z parapets
the ground z freestanding walls
z below the DPC where there is a high risk of saturation z rendered walls
z retaining walls z areas of severe, or very severe, exposure to driving rain.
Reclaimed bricks should only be used where in accordance with Technical Requirement R3.
7 External masonry walls I 2024
Chapter 6.1
Rain penetration
In prolonged periods of driving rain, water will penetrate the outer leaf of a masonry wall. The following should be taken
into account:
z site-specific exposure to wind-driven rain z wall tie drips should be located in the centre of the
z suitability of the wall construction and insulation method clear cavity
z design detailing for the local exposure, and the likely quality z cavity trays, DPCs and weep vents should be installed in
of workmanship on site accordance with this guidance.
z single skin garage walls, additional care needs to be taken
to ensure this type of structure does not allow for water
penetration prematurely
Exposed parts of the building should be given particular attention when selecting a suitable construction method, as this may
affect the choice for the whole building.
Complete resistance can only be achieved with an impervious cladding. However, the following approaches can reduce the risk
of rain penetration:
z providing cladding to the wall z designing protective features to keep the wall dry, eg
z increasing the clear cavity width (minimum 50mm) or the projecting sills and deep overhanging eaves and verges
width of full-fill cavity insulation (increasing the cavity width z ensuring mortar joints are fully filled. Where full-fill cavity
for full-fill cavity insulation greatly reduces the risk of rain insulation is proposed, recessed joints should not be used
passing through the cavity) z following the recommendations of any assessment of the
z rendering the wall and specifying crack-resistant insulation and the manufacturer’s recommendations
backing material z ensuring that cavities are not bridged.
Dornoch
Lerwick
Inverness
Aberdeen
Dundee
Perth
Stirling
Dunbar
Glasgow Edinburgh
Ayr
Londonderry
Newcastle
Carlisle
Enniskillen Belfast Stranraer Alston
Dungannon Workington Middlesborough
Darlington Whitby
Ripon
York
Hebden Bridge
Hull
Skelmersdale
6.1
Colwyn Bay Doncaster
Manchester Grimsby
Bangor Sheffield
Chester Macclesfield Lincoln
Skegness
Bala Nottingham
Stafford
Shrewsbury Leicester
Norwich
Llanidloes Birmingham Peterborough
Llandrindod Wells Northampton
Hay-on-Wye Cambridge
Brecon Colchester
Gloucester Luton
Swansea Swindon Welwyn Garden City
Bristol Newbury London
CardiffWeston-super-Mare Staines
Watchet Aldershot
Barnstable Taunton Gatwick Dover
Southampton
Exeter Brighton
Poole
Eastbourne
Sidmouth
Exposure zones Exposure to wind-driven rain (litres/m² per spell) Variations to the exposure shown on
the map can only be made by site-specific
Very severe 100 or more calculations using BS 8104 “Assessing
exposure of walls to wind driven rain”
Severe 56.5 to less than 100 and the table above.
Freeze/thaw cycles
Common factors which affect the level of freeze/thaw cycles include:
z degree of exposure (incidence of frost) z localised protection of the masonry by roof overhangs,
z saturation of the masonry trees and other buildings.
z frost resistance of the masonry
Good detailing can limit persistent wetting and reduce the risk of frost attack:
z paths should drain away from walls to avoid saturating z a coping or capping should be provided for all parapet walls,
bricks near the ground chimneys and freestanding walls, unless clay bricks of F2
z sills, copings and similar features should have a weathered and S2 classification to BS EN 771-1 are used
upper surface z masonry units and mortar should be used in accordance
with Table 15 of PD6697.
Copings should have:
z an overhang z a continuous supported DPC which projects beyond the line
z throatings a minimum of 30mm clear of the wall of the wall.
The manufacturer should be consulted to ensure that the G KY frost attack do not simultaneously
occur in any part.
proposed decorative finish will not have a detrimental EH
impact on the brickwork durability ML
TD
KA
z in Scotland, all clay bricks used as facings should be
frost-resistant, F2,S2 or F2,S1 to BS EN 771-11 and all DG
NE
concrete bricks used as facings should be 22 N/mm2 to CA
DH SR
BS EN 771-3.
DL TS
The insulation value of the wall must meet the requirements of the Building Regulations. Cold bridging should be avoided.
Particular care is needed:
z at openings z behind or around components installed in the cavity such
z between external walls and roofs, internal walls and floors as sub-floor vents, inset meter boxes, cavity trays or
windposts.
6.1
Materials shall be considered as full fill cavity insulation where:
z they are designed to be in full contact with both leaves z described as full fill in their technical approval document
of masonry although a narrow residual cavity is retained between the
outer leaf and the outer face of the insulation.
Partial fill cavity insulation materials shall be installed on the cavity face of the inner leaf and the appropriate residual cavity to the
outer leaf as specified in ‘Construction Type’ is maintained.
All injected and blown fill insulation systems, including blown mineral wool, and expanded polystyrene beads should be:
z installed by the certificate holder or their approved z installed by operatives trained by the assessment holder
installers subject to the certification bodies assessment and and approved by the assessment holder and the
surveillance scheme assessing organisation.
Installation
Workmanship should be maintained when installing insulation to minimise the risk of damp penetration or condensation to the
inner leaf. Gaps in the insulation layer can provide routes for moisture ingress from the outer leaf to the inner leaf and also create
localised cold spots where condensation can form. Gaps between the board and the inner leaf can result in thermal bypass (this
is exacerbated by gaps at board junctions). Insulation material should be:
z close butted with no gaps z fully engaged with the adjacent board edges where a ship
z in full contact with the inner leaf lap or other interlocking edge detail is provided
z taped at the joints where it is formed of rigid boards with z installed in accordance with the
non-compressible edges1 manufacturer’s recommendations.
Note
1 Where the insulation has a low e facing the tape face shall have the same low e value.
11 External masonry walls I 2024
Chapter 6.1
Where wall ties need to be closely spaced, eg at reveals, it is acceptable to make a neat cut in the insulation to accept the
extra ties.
Rigid insulation boards should:
z be stored flat without bearers, otherwise they may distort, z be rejected where warped.
making them difficult to fix against the wall
Figure 7: Full fill insulation Figure 8: Insulation to combined lintel ends Figure 9: Cavity ties to rigid partial fill insulation
6.1
Rigid insulation should not be continuous across the end of a separating wall or floor. A flexible (mineral wool) cavity closer
should be used in line with these elements, and the rigid insulation butted up to these.
2024 I External masonry walls 12
Chapter 6.1
Injected and blown fill insulation systems should meet the requirements of the relevant standards and hold a satisfactory
assessment by an appropriate technical approvals authority acceptable to NHBC confirming suitability for use in a masonry
cavity wall and for the exposure rating of the site.
Separating wall and floor constructions and their associated flanking walls should be detailed correctly when using injected and
blown fill insulation. Cavity stops should be installed at the ends of separating walls and separating floors. Refer to the Robust
Details Handbook for the specification of materials and construction details.
Before installing injected or blown fill insulation materials the home should be in a condition ready to receive the insulation, this
will be defined in each systems instruction documents, but as a minimum would require that:
z the cavity wall is inspected by the installing team z all edges of cavities at window, door, and other
z the roof is in place, tops of the walls are protected from rain openings are closed with the permanent cavity closers,
as per the design.
6.1
Areas that cannot be accessed during the fill process by appropriate adaptation of the installation method (eg, below gas
membranes or low level continuous DPCs, where there is a cavity tray one course above a lintel, or where separate lintels are
used for each leaf) should be insulated with appropriate built-in materials.
On completion of the work, the Installer shall provide a declaration of compliance in accordance with the relevant standard for
the product.
Construction type
The following are recommendations and guidance according to construction type:
Partial fill cavity insulation
Where partial cavity insulation is installed:
z it should only be fixed against the cavity face of the z wall ties long enough to allow a minimum 50mm
inner leaf embedment in each masonry leaf should be used.
z a minimum 50mm clear cavity between the partial cavity
insulation and the outer leaf should be maintained
In areas of very severe exposure in England and Wales, a residual cavity of 75mm is required where the outer leaf is
fair faced masonry.
13 External masonry walls I 2024
Chapter 6.1
Table 2: Suitable wall constructions for use with full-fill cavity insulation
Exposure Suitable wall construction Minimum insulation thickness (mm)
category Built-in insulation Retro-fill (other than UF foam) UF foam
Very severe Any wall with impervious cladding 50 50 50
Fair faced masonry with impervious cladding 100 125 N/A
to all walls above ground storey
Any wall fully rendered(2) 75 75 N/A
Fair faced masonry (1)
150 150 N/A
Severe Any wall with impervious cladding or render(2) 50 50 50
Fair faced masonry with impervious cladding 50 75 50
or render(2) to all walls above ground storey
Fair faced masonry 75 75 N/A
Moderate Any wall with impervious cladding or render 50 50 50
Fair faced masonry with impervious cladding 50 50 50
or render to all walls above ground storey
Fair faced masonry 50 75 75
Sheltered Any wall with impervious cladding or render 50 50 50
6.1
1 In very severe exposure locations, fair faced masonry with full cavity insulation is not permitted in cavity widths of less than 150mm.
2 Render on an external leaf of clay bricks (F2,S1 or F1,S1 designation bricks to BS EN 771) in severe or very severe exposures is not permitted where the cavity
is to be fully filled with insulation.
3 This table covers walls where the external leaf does not exceed 12m in height.
4 The exposure category of the home is determined by its location on the map showing categories of exposure to wind-driven rain.
5 Fair faced masonry includes clay and concrete bricks and blocks and dressed natural stone laid in an appropriate mortar preferably with struck, weathered or
bucket handle joints. Cavity walls of random rubble or random natural stone should not be fully filled.
Multiple layers of insulation may be used where in accordance with manufacturer’s recommendations and within the scope of
satisfactory assessment by an independent technical approvals authority accepted by NHBC.
The thickness of materials should be as required in the design, and in accordance with Building Regulations.
Insulated dry linings
Where an insulated dry lining contains a combustible insulant, to prevent early collapse of the lining in a fire,
the plasterboard should be:
z a minimum of 12.5mm thick z mechanically fixed to the masonry inner leaf.
2024 I External masonry walls 14
Chapter 6.1
Intended loads
Concrete blocks should:
z comply with BS EN 771-3 & 4 and PD 6697 and be used in z be used in accordance with the
accordance with BS EN 1996-2 and PD6697 manufacturer’s recommendations.
z be of sufficient compressive strength for the application
The maximum load-bearing capacity of the wall should not be exceeded. Other factors may dictate the strength of blocks
required in certain circumstances, eg sulfate resistance may require blocks of greater strength.
For one and two storey homes, blocks with a minimum compressive strength of 2.9N/mm2 could be used.
For three storey homes or those with storey heights over 2.7m, 7.3N/mm2 blocks are required for certain parts of the structure,
unless structural design shows that strengths lower than 7.3N/mm2 are suitable.
Where the level of sulfates in the ground, at the level where blockwork is to used, is DS-2 or above their suitability for use should
be confirmed by the manufacturer. Where this is permissible, the mortar should be sulfate-resisting with a mix suitable for the
level of sulfates in the ground.
Other characteristics
6.1
Concrete blocks may have been specified according to their specific characteristics.
Tolerances
Tolerances should be declared in accordance with the relevant product standard.
6.1.9 Bricks
Bricks shall be capable of supporting intended loads and have appropriate resistance to the adverse effects
of freeze/thaw and sulfate attack.
The design strength of bricks should comply with:
z BS EN 1996-1 z the design.
Clay bricks
Table 3: Classification of clay bricks according to their freeze/thaw resistance and active soluble salt content in accordance
with BS EN 771-1
Durability Freeze/thaw resistance Active soluble salt content
F2,S2 Freeze-/thaw-resistant (F2), durable in all building situations (S2) low
F2,S1 Freeze-/thaw-resistant (F2), durable in all building situations (S1) normal
F1,S2 Moderately freeze-/thaw-resistant (F1), durable except when saturated and (S2) low
subject to repeated freezing and thawing
F1,S1 Moderately freeze-/thaw-resistant (F1), durable except when saturated and (S1) normal
subject to repeated freezing and thawing
F0,S2 Not freeze-/thaw-resistant (F0), liable to be damaged by freezing and thawing (S2) low
F0,S1 Not freeze-/thaw-resistant (F0), liable to be damaged by freezing and thawing (S1) normal
15 External masonry walls I 2024
Chapter 6.1
Bricks that are freeze-/thaw-resistant (F2,S2 or F2,S1 to BS EN 771) should be used where there is a high risk of prolonged
wetting and freezing including:
z external facing work in Scotland z areas of the country subject to exceptionally severe
z exposed parts, including copings, sills, parapets and freeze/thaw exposure. See Clause 6.1.6.
chimneys which have no overhang to provide protection
In areas of severe freeze/thaw exposure outside Scotland, bricks that are moderately freeze-/thaw-resistant (F1,S1 or F1,S2 to
BS EN 771) may be used for general wall areas, provided they are classified in the manufacturer’s published recommendations
as satisfactory for the exposure. Further guidance can also be found within the Brick Development Association “Severely
exposed brickwork” publication.
Bricks that are not freeze-/thaw-resistant (F0,S2 or F0,S1 to BS EN 771) are not acceptable for use externally, unless completely
protected by a cladding which can satisfactorily resist the passage of water.
Where brickwork may become saturated, moderately freeze-/thaw-resistant bricks (F1,S1 or F1,S2 to BS EN 771) are not
appropriate where there is a risk of vulnerability to frost. In saturated conditions, sulfate-resisting cement mortar is required for
S1 designation bricks.
For one and two storey homes, clay bricks to BS EN 771, with a minimum compressive strength of 9N/mm2 should be adequate.
For three storey homes; clay bricks to BS EN 771 with a minimum compressive strength of 13N/mm2 are acceptable.
z if the durability category cannot be determined may require z which have previously been used internally or which were
independent certification of suitability fully protected may be unsuitable in external situations.
z may require independent certification of suitability
It is advisable to know where reclaimed bricks came from, and if they were used internally or externally.
Special shaped bricks (only applicable to clay bricks and concrete bricks)
Special shaped bricks should conform to BS 4729.
Projecting brickwork
Where architectural detailing of brickwork is used to form decorative patterns that include projecting brickwork, exposing either
all or part of the width or length of the brick, consideration should be given to:
z perforations or frogs that may be exposed z suitable weathering of flat surfaces or ‘ledges’.
z visual appearance of exposed bed or differing face surfaces
Exposure of projecting bricks, particularly those with frogs or perforations may affect the durability and service life of the brick.
Written confirmation should be obtained from the brick manufacturer that the brick can achieve the required durability for the
proposed use.
2024 I External masonry walls 16
Chapter 6.1
Where squared or random rubble is used it is important that the stone masonry is “brought to course” at regular intervals of not
more than 450mm. Bed joints of up to 25mm wide can be acceptable, and the selection and installation of the correct wall ties
should be carefully considered.
6.1.11 Construction of masonry walls Also see: Chapter 7.1, 9.1 and PD 6697
Construction shall ensure a satisfactory standard of brickwork and blockwork. Issues to be taken into
account include:
a) finished appearance e) corbelling
b) bonding f) chasing for services
6.1
c) construction g) protection of ancillary components.
d) openings
Finished appearance
A site reference panel should be constructed to agree a benchmark for workmanship and products.
The appearance of a masonry wall depends upon the:
z materials used z workmanship.
z setting out
To keep courses to the correct height, use a gauge rod marked with the height of windows, doors and floors.
Where a number of openings of similar width are being formed, use a rod cut to the required size to check the width of openings
as the work rises.
Brickwork and blockwork should not be subjected to vibration until the mortar has set.
17 External masonry walls I 2024
Chapter 6.1
Bonding
A regular bonding pattern should be maintained. External walls should be bonded to partitions and party walls as required by
the design. Either:
z tooth every alternate course, or z tie with wall ties, expanded metal or equivalent at maximum
300mm vertical centres.
Figure 10: Internal to external wall bonded connection Figure 11: Internal to external wall tied connection
Where joist hangers are not used, joist filling should be brickwork or blockwork and without excessive mortar joints.
Joist filling should be:
z 12mm below the top of flat roof joists to allow for z checked to ensure the cold roof ventilation is not blocked.
timber shrinkage
z the recessed portion of timber joists should be treated
Clay bricks and concrete blocks should not be mixed. Figure 12: Dissimilar masonry types
6.1
Construction
The difference in heights between the two leaves of a cavity wall under construction can be up to six block courses, provided the
ties are sufficiently flexible to ensure coursing is achieved without breaking the bond. To keep the wall plumb, do not over-reach
at changes of lift; wait for the next scaffolding lift. With thin layer mortar construction having an assessment which complies with
Technical Requirement R3, it is normally permissible to build the inner leaf to storey height ahead of the outer leaf. In such cases
the recommendations of the assessment and the manufacturer’s recommendations should be followed.
Cavities should be constructed so that:
z they are uniform and in accordance with the design, z where partial cavity insulation is used, it is against the inner
including wall tie specification and cavity width leaf of the cavity
z mortar is struck from all joints as work proceeds z the thickness of the external leaf is consistent, any stone
z cavity trays and wall ties are clear of droppings and debris used should not project into the cavity
z mortar droppings are removed z cavity barriers are installed as the work progresses.
z where cavity insulation is used, mortar droppings are
removed from the top edge
2024 I External masonry walls 18
Chapter 6.1
Figure 13: Masonry cavity wall plumb level Figure 14: Striking of mortar
Laying bricks and blocks Figure 15: Rain penetration to mortar joints
6.1
z bricks should be cut cleanly and accurately
z cutting of facing brickwork with a trowel should be avoided.
Special bricks in accordance with BS 4729 should be used to form curves, features (eg plinths or cappings) or angles other than
90 degrees (eg bay windows), which cannot be satisfactorily formed with standard bricks. Cut and stuck specials may be used in
accordance with the design where a standard special is not available.
Openings
Masonry may be built around either: Figure 16: Squareness of window openings
6.1
Bed joint reinforcement R1 Austenitic stainless steel (molybdenum chrome nickel alloys)
conforming to BS EN R3 Austenitic stainless steel (chrome nickel alloys)
845-3
R23 Austenitic-ferritic stainless steel to EN 10088 (all parts)
Windpost (3)(4)
1 Austenitic stainless steel (molybdenum chrome nickel alloys)
3 Austenitic stainless steel (chrome nickel alloys)
Notes
1 Material/coating reference in accordance with the relevant part of BS EN 845.
2 These products are not suitable for use in contact with the outer leaf of an external cavity wall or a single leaf cavity wall.
3 Outside the scope of BS EN 845 but meets the specification requirements of BS EN 845-1 for the material/coating reference.
4 Alternative material/coating specification may be provided in accordance with Cl. 5.12 and Table 2 of PD 6697:2019 where windposts are not connected to or
embedded in an external cavity wall.
Components in contact with, or embedded in, an inner leaf which is damp or exposed to periodic wetting (eg below the DPC)
should be protected in the same way as components in contact with, or embedded in, an outer leaf.
21 External masonry walls I 2024
Chapter 6.1
Lintels, and supporting beams, shall be installed correctly, safely support the applied loads and be of
the type and dimensions appropriate to their position within the structure. Issues to be taken into
account include:
a) thermal insulation and condensation c) placing lintels.
b) durability and resistance to water entering the home
Concrete, steel and reinforced brickwork are acceptable Figure 19: Masonry overhang to openings
materials for use as lintels. Timber lintels should not be
used, unless:
z protected from weather
z they do not support masonry or other rigid or brittle materials.
Lintels should:
z comply with BS EN 845-2 ‘Specification for ancillary z not have brickwork or masonry which overhangs more
components for masonry’, where steel or concrete than 25mm
z be designed in accordance either with Technical z have cavity trays where they are specified in the design
Requirement R5 or the manufacturer’s recommendations z have padstones and spreaders provided under the
6.1
z be provided where frames are not designed to support bearings, where necessary
superimposed loads z not have concentrated loads applied before the
z be wide enough to provide adequate support to the manufacturer’s requirement of fully bedded brickwork is met
walling above (this is to avoid overstressing).
Lintels should extend beyond the opening (at each end) by the minimum lengths shown in Table 5.
Table 5: Lintel bearing
Minimum bearing length (mm)
Span (m) Simple lintel Lintel combined with cavity tray
Up to 1.2 100(1) 150
Over 1.2 150 150
Notes
1 Minimum bearing lengths should be in accordance with manufacturer’s recommendations.
Where separate lintels are used to support the inner and outer masonry leaves:
z the cavity, at the head of the opening, should be closed off z the cavity tray should be built into the inner leaf and taken
with an insulated cavity closer to the outer face of the external wall directly over the outer
z a cavity tray should be installed to protect the cavity closer lintel and not between the cavity closer and lintel.
from moisture in the cavity
Figure 21: Separate lintels - reconstituted stone or concrete Figure 22: Separate lintels - steel
structural lintel
(continuous reinforced
reconstituted stone or
concrete without joints)
separate lintel
(concrete or steel)
supporting inner leaf
insulated
cavity closer
insulated
cavity closer
6.1
Durability and resistance to water entering the homes
Cavity tray/damp proof protection should be provided:
z over all openings, either combined as part of the lintel z where the outer leaf is fair faced masonry or where full-fill
or separate insulation is used, all cavity trays (separate or combined)
should have stop ends.
Separate cavity tray protection should be provided when corrosion protection to the lintel is inadequate, or where required by the
manufacturer, or the shape of the lintel is unsuitable, such as when:
z the profile of the lintel does not form a cavity tray z steel lintels in external walls have material/coating in
accordance with L11, L14 and L16.1, see Table 4.
In Scotland, Northern Ireland, the Isle of Man and areas of severe or very severe exposure to driving rain, a separate cavity tray
should be provided over all lintels.
Lintels should be:
z austenitic stainless steel (molybdenum chrome nickel z located and sized so that the external edge of the lintel
alloys) where used in aggressive environments, projects beyond, and therefore offers protection to,
eg coastal locations the window head.
23 External masonry walls I 2024
Chapter 6.1
Mortar shall be of the mix proportions necessary to achieve adequate strength and durability and be
suitable for the type of masonry. Issues to be taken into account include:
a) sources of sulfate c) preparing mortar
b) admixtures and additives d) joints.
Unless recommended otherwise by the brick manufacturer, the mixes in Table 6 should be used for clay bricks. In the case of
concrete bricks, particular attention should be paid to the manufacturer’s recommendations.
Table 6: Mortar mixes using ordinary Portland or sulfate-resisting cements
Location Recommended Recommended Recommended Mortar Equivalent
cement:lime: cement:sand masonry designation Mortar Class to
sand mix mix cement: to BS EN 1996-1-1
sand mix BS EN 1996-1-1
General wall area In areas of severe 1:½:4½ 1:3½ 1:3 (ii) M6
above the DPC or very
severe exposure
– high durability
Other exposure 1:1:5½ 1:5½ 1:4½ (iii) M4
categories –
general use
Below DPC level High durability 1:½:4½ 1:3½ 1:3 (ii) M6
and in chimney
stacks
Cappings, Low permeability 1:0 to ¼:3 – – (i) M12
copings
and sills
2024 I External masonry walls 24
Chapter 6.1
Air-entraining plasticiser can be incorporated in the following general use and high durability mortars:
z 1:1:5½, cement:lime:sand, or z 1:1:4½, cement:lime:sand.
Retarded mortar
Retarded mortar and most premixed mortars can be used over a longer period of time than site-mixed, cement:lime:sand
mortars. When using retarded mortar:
z follow manufacturer’s recommendations and timescales z temporary bracing of larger walls, eg at gable peaks and
z do not use it beyond the time for which it is effective long walls, may be necessary due to delayed setting times.
z protect it against freezing prior to use
Sources of sulfate
Mortar is vulnerable to deterioration by sulfates, especially when masonry is saturated for long periods of time. Clay bricks
contain soluble sulfate (S1 designations have no limit on their sulfate content) and so a suitable mortar should be used.
To reduce risk, cement types listed in BS EN 998:2 NA1.2 with sulfate resisting properties or alternatively CEM II cements based
on blast-furnace slag are in widespread use where sulfate resistance is required, and should be used:
z below the DPC level when sulfates are present in z when there is a high saturation risk (examples below).
the ground
z when clay bricks (F2,S1 and F1,S1 to BS EN 771) are used
6.1
z only be used where agreed with the designer z be dosed and used in accordance with the
z not contain calcium chloride manufacturer’s recommendations.
Mortars containing an air-entraining plasticiser are more resistant to freeze and thaw damage when set, but do not prevent
freezing before the mortar is cured.
White cement to BS EN 197 and pigments to BS EN 12878 may be used, but pigments should not exceed 10% of the
cement weight, or 3% where carbon black is used.
Preparing mortar
When preparing mortar:
z ensure the mix is appropriate for the use and location z mixers should be kept clean to operate efficiently
z plant and banker boards should be kept clean z the colour should be consistent.
Joints
Jointing is preferable to pointing because it leaves the mortar undisturbed. Struck (or weathered) and bucket handle joints are
preferable for external walls. Unless the design states otherwise, only bucket handle or weathered joints should be used.
Recessed joints should not be used where:
z bricks are not frost-resistant, eg clay F1,S1 or F1,S2 to z bricks are perforated closer than 15mm to the face
BS EN 771, unless the brick manufacturer has confirmed z there is no reasonable shelter from driving rain, eg
their use for that particular location in writing from buildings or groups of trees within 50m and of
z the home is built on steep sloping ground, facing open similar height to the home
countryside or within 8km of a coast or large estuary z the cavity is to be fully filled with cavity insulation.
The surface to which render is applied, shall be appropriately constructed and satisfactorily resist the
passage of moisture.
Walls to be rendered should be constructed in accordance with the relevant parts of this chapter. For detailed guidance on
‘Render’, see Chapter 6.11.
Cladding shall satisfactorily resist the passage of moisture and be of the quality, type and dimensions
required by the design. Issues to be taken into account include:
a) masonry cladding to framed structures d) vertical tile or slate cladding
b) joints e) stone veneer cladding.
c) materials for cladding
This clause is for low rise applications where the masonry is used directly for weather tightness or used in conjunction with other
vertical cladding for weather tightness. Chapter 6.9 covers curtain walling and other structural cladding.
Refer to the Robust Details Handbook to check compatibility of lightweight external treatments.
6.1
z flexible movement joints should be provided at the z vertical movement joints should be provided at corners
underside of each horizontal support member z the inner leaf should be adequately tied to the
z the masonry outer leaf should have a minimum two-thirds structural frame.
of its width supported securely by the concrete frame or a
metal angle. See diagram (water exclusion detail not
included for clarity)
Where external claddings such as fibre cement, timber or tile hanging are installed on masonry walls, cavity barriers should
be provided:
z at the edges of cavities including eaves and verges, around z at the junction between an external cavity wall and every
openings such as windows and doors and entry/exit points compartment floor and compartment wall.
z flexible movement joints should be provided at the underside Figure 24: Masonry support
of each horizontal support member
z the masonry outer leaf should have a minimum two-thirds
of its width supported securely by the concrete frame or a
metal angle. See diagram (water exclusion detail not included
for clarity)
z appropriately detailed horizontal joint to be provided which can
accommodate all movements anticipated at the joint including
deflection of substrate and the angle support system, as well
as the limited compressibility of both the joint fillers & sealant
z additionally, horizontal movement joints should be capable of
accommodating at least 1mm movement per continuous meter
of vertical clay masonry
z vertical movement joints should be provided at corners,
where appropriate
z the inner leaf should be adequately tied to the structural frame.
Joints
Joints between claddings and adjacent materials should:
z be detailed to be watertight under the particular exposure z have provision for differential movement, where necessary.
conditions of the site
6.1
z be a naturally durable species or pre-treated
with preservative
Battens Battens should be: z of the size specified in the design
z pre-treated with preservative
Proprietary cladding systems Technical Requirement R3 Satisfactory assessment by an appropriate independent technical
approvals authority accepted by NHBC
Timber cladding should be in accordance with Chapter 3.3 ‘Timber preservation (natural solid timber)’.
z conform with Chapter 6.9 ‘Curtain walling and cladding’ z be fixed in accordance with manufacturer’s
recommendations.
27 External masonry walls I 2024
Chapter 6.1
DPCs and related components shall be provided to prevent moisture rising or entering the building. Issues
to be taken into account include:
a) provision of DPCs and cavity trays c) parapet details.
b) stepped cavity trays
Table 8: Positions where DPCs and cavity trays are generally required
Location Provision of DPCs and cavity trays
Base of walls, piers, etc A DPC should be provided a minimum 150mm above adjoining surfaces and linked with
the DPM in solid floors
Base of partitions built off oversite The DPC should be the full width of the partition
6.1
Figure 25: Low level DPC Figure 26: Cavity tray to air brick/meter box
6.1
Cavity trays
Cavity trays should be provided at all interruptions to the cavity (eg window and door openings and air bricks) unless otherwise
protected (eg by overhanging eaves). Cavity trays should:
z meet the requirements of BS EN 14909 and hold z have a 140mm minimum upstand from the inside face of the
certification from an appropriate independent technical outer leaf to the outside of the inner leaf
approvals authority accepted by NHBC confirming suitability z not be low-density polyethylene (LDPE) to BS 6515
for use as a cavity tray z be shaped to provide 100mm minimum vertical protection
z provide an impervious barrier and ensure that water above points where mortar droppings could collect
drains outwards z be provided where the cavity is bridged by air bricks,
z always be provided with stop ends where discontinuous etc and the DPC should extend 150mm beyond each
z project sufficiently beyond the lintel ends and cavity face of side of the bridge
the cavity closer or vertical DPC; forming a stop end in the z where not otherwise protected (eg by a roof at an
nearest naturally occurring perpend joint appropriate level), be provided over meter boxes
z be laid on a wet, even bed of mortar, free from projections z be in one continuous piece or where necessary have sealed
which could puncture or adversely affect the DPC material; or welded joints which are provided with rigid support and
with masonry above bedded on wet mortar to ensure the lapped at least 100mm
DPC material is ‘sandwiched’ z be preformed where used at complicated junctions
z provide drip protection to door and window heads z be used in accordance with the manufacturer’s
recommendation.
29 External masonry walls I 2024
Chapter 6.1
Figure 28: Cavity tray to openings Figure 29: Cavity tray stop ends and weepholes
3D
The upstand part of the cavity tray should be returned into the inner leaf unless it is stiff enough to stand against the inner leaf
without support. In Scotland, Northern Ireland, the Isle of Man and areas of very severe exposure to driving rain, the upstand part
of the damp proof protection should be returned into the inner leaf of masonry (this does not apply at sloping abutments).
Where fair faced masonry is supported by lintels:
z weepholes should be provided at a maximum of z each opening should have at least two weepholes
450mm intervals z cavity trays or combined lintels should have stop ends.
Where the cavity has full-fill insulation, a cavity tray should be used above the highest insulation level, unless the insulation is
taken to the top of the wall and is in accordance with the manufacturer’s recommendations.
6.1
Weepholes
Weepholes in cavity walls should be the equivalent of a full brick perpend joint, eg 65mm x 10mm where exposed within the
cavity. The size of the discharge opening in proprietary weepholes may be smaller, provided it is designed to discharge any
water collected, safely. The end of the weephole within the cavity should be kept clear of mortar droppings.
Weepholes to cavity walls should be provided:
z to cavity trays above openings and penetrations through the z on cavity trays in parapet walls or at horizontal roof
wall (such as sub-floor vents, ducts, or flues), at least two abutments at not more than 1m centres
per opening at not more than 450mm centres z to cavity trays above inset gas meter boxes, a minimum of
z at least one to the bottom tray in a series of stepped cavity 180mm from the edge of the meter box at not more than 1m
trays, eg at pitched roof abutments centres. See figure 30.
Horizontal DPCs
DPCs should:
z be the correct width z at ground level, generally be a minimum of 150mm above
z lap the DPM where appropriate finished ground or paving level
z be laid on a wet, even bed of mortar, free from projections z where intended to prevent rising damp, joints should have
which could puncture or adversely affect the DPC material; 100mm lapping, or be sealed or welded
with masonry above bedded on wet mortar to ensure the z be considered in the design of masonry wall panel
DPC material is ‘sandwiched’ z be used in accordance with the
manufacturer’s recommendations.
The concrete fill in a cavity wall should stop at least 225mm below the base DPC. This may be reduced to 150mm where special
foundations, such as rafts, are used.
Figure 31: Concrete cavity fill Figure 32: Stepped horizontal DPC
6.1
Vertical DPCs
A separate vertical DPC should be provided around openings, extend to the underside of the lintel, and:
z be of a proprietary material assessed in accordance with z 150mm wide DPC material, nailed to the full height of the
Technical Requirement R3, or frame and protrude 25mm into the cavity.
31 External masonry walls I 2024
Chapter 6.1
A fillet joint of sealant should not be considered a substitute for good workmanship or DPCs. However, a bead of mastic should
be used around openings.
Joints between the masonry and flashing should be pointed with cement mortar or suitable exterior grade sealant (polysulfide or
neutral-cured silicone) in accordance with the manufacturer’s recommendations.
Arches
At openings with an arched head or circular windows it is not practical to shape a flexible DPC and achieve the correct protection
and a preformed cavity tray should be used.
6.1
Preformed stepped cavity trays should be installed in accordance with the manufacturer’s recommendations and positioned:
z to suit the dimension of the flashing (which should be in z so that the stepped cavity tray cannot discharge behind
accordance with the manufacturer’s recommendations or a flashing (where it is necessary to cut bricks or blocks,
minimum width of 65mm) the bond should be maintained in the following joint).
2024 I External masonry walls 32
Chapter 6.1
Parapet details
Parapet walls should have:
z a DPC under the coping, and a DPC tray starting 150mm z coping throating which is 30mm clear of the brickwork
minimum above the roof z copings should comply with BS 5642 Parts 1 & 2.
6.1
33 External masonry walls I 2024
Chapter 6.1
Windposts should:
z be designed by an engineer in accordance with Technical z be austenitic stainless steel (chrome nickel alloys) or
Requirement R5 austenitic stainless steel (molybdenum chrome nickel
z comply with Cl. 5.12 and Table 2 of PD 6697:2019 alloys) where connected to or embedded in an external
‘Recommendations for the design of masonry structures to cavity wall
6.1
Water should be prevented from crossing the cavity. Care should be taken to avoid:
z ties sloping down to the inner leaf z ties having mortar droppings on them.
z drips being off-centre
Cavity walls should be coursed so that the wall tie is level or slopes outwards.
2024 I External masonry walls 34
Chapter 6.1
Figure 38: Wall tie locations Figure 39: Wall tie embedment Figure 40: Wall tie to partial fill insulation
Where 1,200mm boards are used with partial fill cavities, the wall ties should:
z be spaced closer to provide adequate support and restraint z be spaced at 600mm centres in rows, ie, not staggered.
6.1
Cavity widths of over 100mm
Where cavity to masonry walls is to be between 100-150mm, wall tie spacing in Table 9 above may still be used in dwelling
of up to three storeys high in sheltered and moderate exposure locations, provided they are of the right length with 50mm
minimum embedment in the masonry.
Where dwellings are exposed to severe and very severe winds including on exposed and elevated locations of over 150m
above sea level as well as coastal locations, site specific assessment of wall tie requirements should be undertaken. The wall tie
spacing in Table 9 above may still be acceptable, if used in conjunction with stiffer wall tie types – eg Type 1 or 2 in
accordance with PD 6697.
z deliveries should be undertaken safely to protect both the z cement should be stored off the ground and protected
operatives and materials only using pallets provided by from weather
the manufacturer z sand should be prevented from spreading and be protected
z stacks of bricks and blocks should be protected from rain so that it remains clean
and mud splashes, etc by covering them with z insulation materials should be handled and stored in
waterproof covers accordance with the manufacturer’s instructions. Normally
z a suitable level and safe place should be identified on each insulation materials should be protected from the weather.
site for the masonry deliveries
35 External masonry walls I 2024
Chapter 6.1
Materials should be handled with care during construction to avoid damage and staining. Chipped or fractured bricks are not
acceptable for facework.
Bricks that are tipped on delivery or moved about the site in dumper trucks often have a high degree of wastage.
The unloading of all bricks and blocks, especially facing bricks, should be:
z by mechanical means z directly onto a firm level surface.
Unless bricks have been blended by the manufacturer, bricks from different batches should be mixed to avoid colour patching.
To reduce the risk of efflorescence, newly erected masonry should be covered. This also prevents the mortar being washed out
of the joints by rain and stops masonry becoming saturated. Bricks and blocks that become excessively wet can suffer from:
z staining and efflorescence z lack of mortar adhesion to mud-stained surfaces.
z increased drying shrinkage, with a greater risk of cracking
The work place should be kept clean to reduce mortar splashes to a minimum. Any accidental mortar smears should be lightly
brushed off the face after the mortar has taken its first set.
6.1.20 Protection of the works during construction Also see: Chapter 3.2
Ensure the setting times of additives are checked and adhered to in accordance with the manufacturer’s recommendations.
Cold weather retarders increase setting times.
In cold weather:
z brickwork and blockwork should not be built when the air z covers should be provided to form a still air space to
temperature is below 3°C and falling insulate the wall
z work can resume when the temperature is 1°C and rising z walling damaged by frost will not regain strength and should
with the expectation the temperature will exceed 3°C be taken down and rebuilt when conditions improve.
z walls should be protected from frost until the mortar has set
sufficiently to resist frost damage
Note Thin joint mortars that can be shown to have been successfully tested for use down to 0°C are acceptable when the temperature is 0°C and rising. The mortar
should be used strictly in accordance with the manufacturer’s instructions and Chapter 3.2 ‘Cold weather working’.
In dry hot weather absorbent clay masonry units may be wetted by lightly spraying to reduce suction. Care should be taken not
to over wet units. Low absorption units such as engineering bricks should not be wetted.
Newly built masonry should be protected with suitable material ie, hessian or sheeting, to insulate and prevent drying out too
quickly. Hessian should not be wetted and laid dry.
6.1
Fig No Title/Description Clause Page
Figure 1 Lateral restraint by buttressing wall 6.1.3 3
Figure 2 Movement joint sealant 6.1.3 4
Figure 3 Lateral restraint and acoustics 6.1.5 6
Figure 4 Check reveal 6.1.6 7
Figure 5 Exposure zones 6.1.6 8
Figure 6 Frost exposure zones 6.1.6 9
Figure 7 Full fill insulation 6.1.7 11
Figure 8 Insulation to combined lintel ends 6.1.7 11
Figure 9 Cavity ties to rigid partial fill insulation 6.1.7 11
Figure 10 Internal to external wall bonded connection 6.1.11 17
Figure 11 Internal to external wall tied connection 6.1.11 17
Figure 12 Dissimilar masonry types 6.1.11 17
Figure 13 Masonry cavity wall plumb level 6.1.11 18
Figure 14 Striking of mortar 6.1.11 18
Figure 15 Rain penetration to mortar joints 6.1.11 18
Figure 16 Squareness of window openings 6.1.11 19
Figure 17 Masonry setting out at window openings 6.1.11 19
Figure 18 Corbelling 6.1.11 19
Figure 19 Masonry overhang to openings 6.1.12 21
Figure 20 Combined lintel 6.1.12 21
Figure 21 Separate lintels - reconstituted stone or concrete 6.1.12 22
Figure 22 Separate lintels - steel 6.1.12 22
Figure 23 Lintel end bearing 6.1.12 23
Figure 24 Masonry support 6.1.16 26
37 External masonry walls I 2024
Chapter 6.1
6.2
External timber
framed walls
This chapter gives guidance on meeting the Technical
Requirements for external walls of timber framed
homes up to seven storeys high, substantially timber
framed homes and timber wall panels.
6.2.1 Compliance 01
6.2.2 Provision of information 01
6.2.3 Design checking and certification 01
6.2.4 Load-bearing walls 02
6.2.5 Fixing the frame 04
6.2.6 Nails and staples 05
6.2.7 Sheathing 05
6.2.8 Differential movement 06
6.2.9 Fire resistance 11
6.2.10 Protection from moisture 12
6.2.11 Timber preservation 14
6.2.12 Air and vapour control layers 14
6.2.13 Breather membranes 15
6.2.14 Wall ties and fixings 15
6.2.15 Insulation 16
For figure reference tables in this chapter, please go to the end of the chapter
1 External timber framed walls I 2024
Chapter 6.2
External timber framed walls shall comply with the Technical Requirements.
External timber framed walls that comply with the guidance in this chapter will generally be acceptable. For guidance on internal
walls and floors within timber frame buildings, see Chapters 6.3 and 6.4.
Where the components of the timber frame cannot be inspected on site (eg closed panels or fully fitted out volumetric units)
the system should be subject to review by NHBC. Please refer to the NHBC Accepts website at www.nhbc.co.uk/builders/
products-and-services/techzone/accepts.
The fixing schedule should detail every connection which is to be made on site, including those for structural connections,
framing, wall ties, breather membranes, sheathing and vapour control layers, and should show as appropriate:
z number and spacing of fixings z method of fixing, eg skew nailing.
z size and type of fixing, including material and
corrosion protection
Further guidance on the contribution of plasterboard to racking resistance can be found in Clause 6.2.7. Where wall design relies
on plasterboard to take racking forces, the design should:
6.2
z clearly define those walls z include the type and spacing of fixings required.
Alternatively, timber frame superstructures from Gold level members of the Structural Timber Association’s Assure scheme, who
have engaged Silver/Gold level structural designers and engineers, are acceptable without additional certification.
The registered builder should ensure that a letter from the manufacturer is available on site for inspection by NHBC.
Designs should be submitted to NHBC when proposed buildings are four storeys or more and the floor joists are solid timber.
2024 I External timber framed walls 2
Chapter 6.2
Load-bearing timber framed walls shall be constructed to support and transfer loads to foundations safely
and without undue movement. Issues to be taken into account include:
a) timber elements e) fixing panels
b) joints between panels and other elements f) timber frame erection tolerances
c) positioning of sole plates g) support of prefabricated chimneys.
d) packing under sole plates
Timber elements
Load-bearing timber framed walls should be in accordance with BS EN 1995-1-1, and take into account:
z wind loads z floor loads
z roof loads z cladding loads.
Structural timber components should be of a suitable strength class as specified by the designer to BS EN 338. Solid structural
timber should be:
z machine graded to BS EN 14081, or visually graded to BS z dry graded
4978 for softwoods or BS 5756 for hardwoods z marked in accordance with BS EN 14081.
z assigned a strength class based on BS EN 1912 when
visually graded
Further guidance on strength classes for certain timber species can be found in PD 6693.
Engineered wood products such as I-section or metal-web studs should be assessed in accordance with Technical
Requirement R3.
Individual timber studs should have:
z a minimum width of 38mm z a maximum spacing of 600mm, unless other adequate
support is provided for wall boards and fixings.
Narrow or inaccessible gaps between studs which are difficult to insulate should be avoided.
6.2
Lintels and cripple studs should be provided at openings in Figure 1: Timber frame wall panel
load-bearing panels except where:
z the opening does not affect the stud spacing, or
lintel
z supported loads are carried by a ring beam or header joist.
Figure 2: Sole plate foundation overhang Figure 3: Sole plate foundation set back
12mm 12mm
the horizontal and vertical loads on the sole plate eg studs or posts.
Packing exceeding 20mm should be agreed between the timber frame manufacturer’s engineer and NHBC. The following
methods are generally acceptable to NHBC for packing up to 20mm.
Permanent structural packing under sole plate Figure 4: Permanent structural packing under each stud
The sole plate should be levelled on temporary spacers.
bottom member
of wall panel
When the first lift construction (including wall panels, first floor
structure, or roof structure in a single storey building) has been
erected, permanent packing should be placed under the sole
plate, which can be: permanent packing
under each stud
z free-flowing non-shrinkable grout for the full length and width sole plate
sole plate
Fixing panels
The wall panels should be adequately fixed to the sole plate so that the frame can resist both lateral and vertical forces.
When fixing panels:
z fixings, including nailed joints and sheathing, should be as z sole plates and head binders should be provided to bind the
scheduled in the design panels together.
z they should be securely fixed together, to the floor and to
the roof framing
6.2
Timber frame erection tolerances
Timber frame erection tolerances based on guidance from the Structural Timber Association will generally be acceptable.
Anchoring
When anchoring the frame:
z the sole plate should be adequately anchored to the z care should be taken to avoid splitting timber plates or
substructure so that the frame can resist both lateral and damaging the substructure.
vertical forces
5 External timber framed walls I 2024
Chapter 6.2
Figure 7: Sole plate anchor brackets Figure 8: Hold down straps built into masonry cladding
DPC
Fixing to plate
Fixing to stud
Holding-down devices should be durable, as detailed in the design and manufactured from:
z austenitic stainless steel to BS EN 10088-1, z galvanised mild steel with zinc coating to BS EN ISO 1461,
minimum grade 1.4301 minimum coating 940 g/m2 on each side.
Sole plate anchors within the internal envelope should be galvanised mild steel, minimum coating Z275.
z austenitic stainless steel, or z other material of similar strength and corrosion resistance.
6.2.7 Sheathing
Sheathing shall be durable and capable of providing structural resistance to racking.
The following materials are acceptable:
Plywood BS EN 636-2S or BS EN 636-3S
Oriented strand board BS EN 300 type OSB/3 or OSB/4
Moisture-resistant chipboard BS EN 312 type P5 or P7
Medium board BS EN 622-3 type MBH.HLS1 or MBH.HLS2
Impregnated soft board BS EN 622-4 type SB.HLS
Proprietary sheathing materials Technical Requirement R3 and used in accordance with the assessment
Plasterboard may contribute to racking resistance when used in accordance with PD 6693-1. Limitations or exclusions apply to
walls that are not separating walls comprising two or more built-up layers of plasterboard having a minimum thickness of 30mm,
and walls where plasterboard is combined with a wood-based sheathing on the same wall diaphragm.
2024 I External timber framed walls 6
Chapter 6.2
Timber structures shall account for differential movement between the timber frame wall and other
building elements.
As the timber frame dries out, it will shrink and the overall height will reduce. The extent of the differential movement
increases with the number of storeys, and will typically occur between the timber frame and other parts of the
construction, including:
z door and window openings with masonry cladding z staircases and lift shaft enclosures (where they are not
z eaves and verges with masonry cladding timber framed)
z openings for drive-throughs with masonry cladding z the interface of the timber frame with any other
z balconies (including Juliet balconies) construction at each floor level where cladding is fixed
z service entries
to the timber frame.
Where lightweight cladding is fixed to the timber frame, movement across floor zones should be allowed for in the cladding
system and its supporting structure.
Movement joints should be provided to accommodate the expected movement. Joints should be detailed to:
z accommodate the expected amount of shrinkage z provide a weather resistant and durable joint
or expansion safely z be protected by a cover strip where the movement gap/joint
z provide an additional allowance for the residual is expected to be more than 35mm.
thickness of any compressible filler materials after
movement has occurred
Where compressible filler materials are specified, they should be specified based on the anticipated residual gap size after
movement has occurred.
In the absence of project-specific calculations, gaps in accordance with Table 1 should be provided.
6.2
Solid timber (mm) Engineered I-joist (mm)
Eaves/verge Add 5mm to gap dimension at level below
Sixth floor Specialist calculations to be submitted to NHBC(2) 61
Fifth floor 53
Fourth floor 45
Third floor 45 35
Second floor 35 25
First floor 20 15
Ground floor (1)
5 5
Notes
1 Ground floor or lowest level of timber frame.
2 Calculations, where required, are to be based on BS EN 1995-1-1.
7 External timber framed walls I 2024
Chapter 6.2
Table 1 is based on the following: Figure 9: Platform timber frame floor zone
z the table allows for a 2mm thickness of compressible stud
material in closing gaps. Check the manufacturer’s bottom rail of panel
product details
sole plate
z timber components are not saturated and have normal
structural decking
moisture contents at the time of construction, eg less than
20% and tight-jointed construction
z the ground floor is concrete. For ground floors of timber
joist
joists, add 15mm for solid timber and 10mm for
engineered timber joists
z timber joist and ring beam/header joist have a maximum
depth of 240mm headbinder
z timber frame floor cross-section is as shown below, with
top rail of panel
maximum 45mm deep timber plates/binders
stud
z single head binder at the eaves. Maximum double
Timber frame construction on which Table 1 is based
sole plates
z outer leaf brickwork with expansion rates no greater than
Figure 10: Window head and sill with masonry cladding
2.5mm per storey
z brickwork up to five storeys, with lightweight cladding
above five storeys
z lightweight cladding – floor level joints must be 15mm for
solid timber joists and 10mm for engineered timber joists. opening
gap
Common details
The following sketches consider downward movement of the
6.2
Figure 11: Movement allowance at window sill with Figure 12: Movement allowance at window head with Figure 13: Movement allowance at window head with
masonry cladding masonry cladding masonry cladding
allow for
movement
sill not built
into masonry
allow for
movement
allow for
movement allow for
movement
2024 I External timber framed walls 8
Chapter 6.2
Figure 14: Lightweight cladding window head Figure 15: Lightweight cladding window sill
no differential movement
no differential movement
Figure 16: Movement allowance at roof to vertical abutment – before movement Figure 17: Movement allowance at roof to vertical abutment – after movement
allow for
movement
75mm min.
timber frame
movement
Figure 18: Timber frame interface with concrete or masonry communal areas – Figure 19: Timber frame interface with concrete or masonry communal areas –
6.2
before movement after movement
after movement
Figure 20: Movement allowance at roof eaves Figure 21: Movement allowance at roof verge
allow for
movement
allow for
movement
A
service passing B
through wall
allow for
movement A
6.2
Drive through
Figure 24: Drive through Section A-A Figure 25: Drive through Section B-B
timber frame
movement
timber floor
construction
allow for
movement
ceiling
lintel/beam ceiling
drive
Section A-A through
Section B-B
2024 I External timber framed walls 10
Chapter 6.2
Figure 26: Floor zone movement gap with lightweight cladding
15mm*
movement across
15mm* floor zone
15mm*
vertical batten
allow for
movement
allow for
allow for movement
movement decking
balcony structure
independent of
timber frame
opening gap
gap
6.2
Figure 30: Balcony abutment – Figure 31: Balcony abutment – masonry cladding Figure 32: Slotted holes in balcony support
masonry cladding brackets
allow for
slotted holes movement
Figure 33: Sliding movement joint in Figure 34: Juliette balcony support fixed Figure 35: Flat roof to masonry
balcony support bracket to masonry cladding abutment movement detail
after
movement
fix to masonry
cladding subject
to engineer’s
design
sliding joint
11 External timber framed walls I 2024
Chapter 6.2
Horizontal cavity barriers in lightweight cladding should be protected by cavity trays, DPCs or flashings as appropriate.
Figure 36: Fire-stopping and compartmentation at compartment Figure 37: Horizontal cavity barrier protected Figure 38: Vertical cavity barrier protected
wall/roof junction with DPC with DPC
breather membrane
lapped over
fire-stopping DPC tray
between batten
and above underlay
6.2
fire-stopping
below underlay
DPC
cavity closed
at eaves
DPC
fire-stopping within boxed eaves
Services
Only the services shown in the design should be installed in separating walls and:
z service outlets should not impair the fire resistance of floors z service mains should not pass through separating
and walls wall cavities.
Notching or drilling of structural timber members should be carried out as detailed in the design. If these details are not available,
the designer should be consulted before such operations are begun.
In Scotland, services are not permitted within a timber framed separating wall.
6.2.10 Protection from moisture Also see: Chapter 6.1 and 6.9
Timber structures and panels shall be adequately protected from the effects of moisture. Issues to be taken
in to account include:
a) cavity construction c) DPCs and cavity trays.
b) drainage and ventilation
Cavity construction
A drained and vented cavity should be provided to reduce the risk of rain penetrating the frame. Cavity widths, measured
between the cladding and sheathing, should be in accordance with Table 2.
In areas of very severe exposure to wind driven rain, wall construction should include a 50mm cavity between the sheathing and
the cladding and:
z a high performance breather membrane (see Clause z masonry cladding which is rendered or clad with an
6.2.13), or impervious material.
6.2
should be constructed in accordance with Chapter 6.11 ‘Render’. Vertical tile hanging and slating should be constructed
in accordance with Chapter 6.9 ‘Curtain walling and cladding’. Proprietary cladding should be fixed in accordance with the
manufacturer’s recommendations and Chapter 6.9 ‘Curtain walling and cladding’.
External wall cavities should not contain electricity cables other than meter tails.
Proprietary perpend ventilators should be used. Perpend ventilators should be installed to the base of external wall cavities
below the lowest timber sole plate and above finished ground level; if continuous cavity trays are installed at sole plate level,
perpend ventilators should be installed above and below the tray to provide drainage and ventilation to all areas of the timber
frame. Where wall areas are divided by horizontal cavity barriers and/or cavity trays, each individual cavity should be vented.
Weepholes should be provided at cavity trays over openings.
Cavities between lightweight external cladding and timber frame walls should be vented or ventilated depending on cladding
type. Cavity vents should be:
z installed to promote through ventilation where required z located to drain moisture from the cavity.
z protected to prevent the ingress of rain, insects, birds,
and vermin
Drainage and ventilation openings should be provided to the base of external lightweight cladding at/near ground level, above
horizontal cavity barriers and flashings, and above openings (such as windows and doors).
Horizontal battens used to support lightweight external cladding should be spaced off the frame using vertical counter battens to
provide a path for drainage and ventilation. Battens or carrier rail systems supporting lightweight cladding should be located over
and fixed to studs. Vertical battens and carrier rail systems should have joints at floor zones to accommodate differential movement.
13 External timber framed walls I 2024
Chapter 6.2
Clause 6.1.17 contains further guidance on the installation of cavity trays in masonry cladding.
In Northern Ireland, Scotland and the Isle of Man, and in areas of severe or very severe exposure to driving rain, masonry should
form a rebate at the reveals of openings to avoid a straight through joint where the frame abuts the masonry.
Figure 39: Window head detail with cavity tray and weepholes Figure 40: Rebate at window reveal in areas of severe
or very severe exposure
rain
sealant
DPC
any moisture
sealant to resist
driving rain
Cavities should:
z extend below DPC to allow drainage z be suitably drained to prevent water build-up.
z be kept clear and be vented
The lowest timber should be a minimum of 150mm above finished ground level. This may be reduced to 75mm in situations
where the site is not subject to a high water table or where the cavity will not have standing water.
Figure 41: Lowest timber at least 150mm above external Figure 42: Lowest timber at least 75mm above external ground level
ground level
perpend vents
DPC turned up
to lap with VCL
lowest
timber seal between
150mm min. wall and floor lowest timber
above barriers or 75mm min.
ground between skirting above ground level 225
level board and floor mm
drainage holes min.
perpend vents
drainage next to This detail is only acceptable in
masonry cladding situations where the site is not subject
to a high water table or where the
cavity will not have standing water
2024 I External timber framed walls 14
Chapter 6.2
6.2
z fixed at 250mm centres to the top and bottom of the
frame and at laps and around openings, vapour control
plasterboard should be fixed in accordance with
Clause 9.2.4
Where floor zone air tightness membranes are specified for enhanced air tightness, they should be of a breathable material with
a vapour resistance less than 0.6MNs/g (0.12 Sd) when tested in accordance with BS EN ISO 12572 using the set of conditions
C and using five test specimens.
15 External timber framed walls I 2024
Chapter 6.2
Figure 43: Breather membrane laps Figure 44: Breather membrane lapped over sole plate
150mm
6.2
100mm
membrane detailed
to protect the sole plate
staggered joints
membrane
protects lowest
timber
6.2.15 Insulation Also see: BRE Report ‘Thermal insulation: avoiding risks’
Water and heating services within walls should be on the warm side of the insulation.
Where insulation is to be installed to the external/cavity face of the frame:
z it should be assessed in accordance with Technical z wall ties should transfer loads directly to the timber frame
Requirement R3 as an integral part of the wall system studs and not via the insulation
z a clear cavity should be provided, based on the dimensions z the installation of lightweight cladding systems should be
set out in Table 2 in Clause 6.2.10, between the outer face designed by a structural engineer to ensure adequate load
of the insulation and the external cladding transfer to the structural frame
z a breather membrane should be installed to protect the z cavity barriers should be installed to fully close the
timber frame wall and sheathing. A secondary breather cavity, ensuring their performance is unlikely to be made
membrane to protect the external insulation may be ineffective by failure of the insulation.
necessary depending on insulation manufacturer’s
installation instructions and independent technical approval
6.2
z stud locator marks should be transferred onto the outer
face of insulation/external breather membrane (dependant
on wall tie type and order of works)
Where insulation, either in the form of insulated plasterboard or a separate continuous layer, is to be installed to the inside face
of the frame, the fire resistance of the wall should be in accordance with Clause 6.2.9 with appropriate supporting evidence.
Figure 42 Lowest timber at least 75mm above external ground level 6.2.10 13
Figure 43 Breather membrane laps 6.2.13 15
Figure 44 Breather membrane lapped over sole plate 6.2.13 15
Figure 45 Insulation between external wall studs 6.2.15 16
Chapter
6.3
Internal walls
This chapter gives guidance on meeting the
Technical Requirements for internal walls, including:
z separating and compartment walls
z internal partition walls.
6.3.1 Compliance 01
6.3.2 Provision of information 01
6.3.3 Supporting load-bearing
internal walls 01
6.3.4 Masonry walls 01
6.3.5 Load-bearing timber walls 04
6.3.6 Fire resistance 05
6.3.7 Sound insulation 06
6.3.8 Partitions: internal non load-bearing 08
6.3.9 Construction of timber partitions 08
6.3.10 Construction of steel
framed partitions 09
6.3.11 Construction of proprietary systems 10
6.3.12 Plasterboard 10
6.3.13 Damp proof courses 10
6.3.14 Components 11
1 Internal walls I 2024
Chapter 6.3
Foundations should be in accordance with Part 4 of these Standards, including, where applicable, Chapter 4.3 ‘Strip and trench
fill foundations’ and Chapter 4.4 ‘Raft, pile, beam and pier foundations’.
6.3.4 Masonry walls Also see: Chapters 6.1, 6.4, 6.8 and 9.2
6.3
Internal masonry walls shall be designed to support and transfer loads to foundations safely and without
undue movement. Issues to be taken into account include:
a) structural elements e) lateral restraint
b) mortar mix and jointing f) masonry separating walls
c) workmanship g) lintels and beams.
d) bonding and tying
Structural elements
Structural design of masonry walls should be in accordance with BS EN 1996-1-1.
Bricks and blocks should be selected in accordance with their intended use and as recommended in Table 1.
Table 1: Bricks and blocks in buildings up to three storeys high
Height of wall(1) Unit Minimum compressive strength(2)
One or two storey Blocks 2.9 N/mm2
Bricks 9.0 N/mm2
Lowest storey of a three storey wall, or Blocks 7.3 N/mm2
where individual storeys exceed 2.7m Bricks 13.0 N/mm2
Upper storeys of a three storey wall Blocks 2.9 N/mm2
Bricks 9.0 N/mm2
Notes
1. The compressive strengths shown are applicable where the floor to ceiling distance is not greater than 2.7m.
2. The compressive strengths shown are applicable where the roof is of timber construction.
Where buildings are more than three storeys high, masonry should be designed in accordance with Technical Requirement R5
and the block strength specified in the design.
2024 I Internal walls 2
Chapter 6.3
Bricks
Bricks should comply with the relevant British Standards:
Clay bricks BS EN 771-1
Calcium silicate bricks BS EN 771-2
Concrete bricks BS EN 771-3
Bricks and blocks should be laid on a full bed of mortar, with perpend joints solidly filled.
6.3
Where walls are to be finished with wet plaster, joints should be raked out to a shallow depth to provide a key, unless the units
have suitable texture or metal lathing is used, to ensure adequate bond strength is achieved. For dry lining, mortar joints should
be struck off flush. For further guidance see Clause 9.2.3 ‘Plastering’.
Workmanship
Internal masonry walls and associated works should be: Figure 1: Square and plumb walls
Lateral restraint
Load-bearing masonry walls, including separating walls, should be provided with lateral restraint at:
z each floor level z ceiling level below a roof.
Restraint straps should be provided to separating walls on each level, at a maximum of 2m centres, when the floor:
z is not on, or near, the same level z does not provide adequate restraint.
Lateral restraint should be provided in accordance with Chapter 6.4 ‘Timber and concrete upper floors’.
Timber floors
Adequate restraint can be provided by timber floors where joists have a minimum 90mm bearing. Alternatively, restraint should
be provided by:
z restraint straps with a minimum 30mm x 5mm z restraint type joist hangers to BS EN 845-1 with a
cross-section, or performance equivalent to restraint straps, or
z proprietary straps in accordance with Chapter 6.4.
Concrete floors Figure 5: Restraint straps to concrete floors
Adequate restraint can be provided by concrete floors that
6.3
6.3.5 Load-bearing timber walls Also see: Chapter 2.1, 6.2 and 9.2
Internal load-bearing timber walls shall be designed to support and transfer loads to foundations safely and
without undue movement. Issues to be taken into account include:
a) structural elements c) timber quality.
b) timber separating walls
Structural elements
Structural design of load-bearing timber walls should be in accordance with BS EN 1995-1-1.
When constructing structural elements: Figure 7: Load-bearing timber wall
continuous
z the underside of the lowest sole plate should be positioned at head binder
or above internal finished floor level, see Figure 8
z individual studs, rails and head binders should be
38mm x 75mm minimum, although larger sizes may be
required to achieve an adequate level of fire resistance cripple studs
support
z studs should be spaced at a maximum of 600mm centres
6.3
load-bearing lintels
z mid height noggings should be installed when required for
additional stiffness
z lintels and cripple studs should be provided to each opening,
DPC
except when the stud spacing is unaffected
z multiple studs should be included to support multiple joists,
beams, girder trusses and other point loads, unless otherwise
specified by the designer Figure 8: Ground floor - sole plate position
Timber Quality
Timber should be of the appropriate grade, moisture content and size to support the imposed loads.
Structural timber components should be of a suitable strength class, as specified by the designer to BS EN 338. Solid structural
timber should be:
z machine graded to BS EN 14081, or visually graded to BS z dry graded
4978 for softwoods or BS 5756 for hardwoods z marked in accordance with BS EN 14081.
z assigned a strength class based on BS EN 1912 when
visually graded
Further guidance on strength classes for certain timber species can be found in PD 6693.
Engineered wood products such as I-section or metal-web studs should be assessed in accordance with Technical
Requirement R3.
Timber should have a maximum moisture content of 20% at the time of dry lining to minimise shrinkage.
6.3.6 Fire resistance Also see: Chapter 6.2, 8.0 and 9.2
Internal walls shall have adequate resistance to the spread of fire. Issues to be taken into account include:
a) fire resistance c) services
b) typical construction d) materials.
The guidance below does not apply to Scotland, and reference should be made to the Technical Handbooks.
Fire resistance
Internal walls should provide fire resistance in accordance with Building Regulations.
Typical construction
Internal walls of hollow or cavity construction (fire-resisting or otherwise) should have cavity barriers installed at:
z the perimeter z junctions with fire-resisting floors and walls.
6.3
Fire-resisting walls should be fire stopped or constructed to resist fire spread at:
z their perimeter z openings for doors and pipes, etc.
z junctions with other fire-resisting walls, floors and roofs
At junctions between a separating or compartment wall and a pitched roof or flat roof:
z adequate precautions should be provided to prevent z soft fire-stopping material should be installed above and
fire spread below the roofing underlay to allow for movement in roof
z the separating wall should stop approximately 25mm below timbers to prevent ‘hogging’ of the tiles.
the top of adjacent roof trusses
Fire-stopping should be provided within the boxed eaves Figure 9: Junction of compartment wall and roof
and be:
z carefully cut to shape to seal the boxed eaves fully fire-stopping
between batten
z fixed in accordance with manufacturers recommendations. and above underlay
Services
Where services such as pipes, cables and ducting pass through fire-resisting walls, penetrations should be fire-stopped.
Fire-stopping should be:
z in accordance with Building Regulations and the z completed neatly.
design information
Materials
The selected fire-stopping material should be appropriate for the application. Suitable fire-stopping materials include:
z rock fibre quilt z intumescent mastic or preformed strip
z cement mortar z proprietary sealing systems assessed in accordance with
z gypsum plaster Technical Requirement R3.
Walls shall be insulated with materials of suitable thickness and density to provide adequate resistance to
the transmission of sound. Issues to be taken into account include:
a) sound-resisting construction b) rooms which contain a WC.
Sound-resisting construction
Masonry separating walls
In England, Scotland, Wales and Northern Ireland, separating walls may be registered and built in accordance with Robust
Details ‘Resistance to the passage of sound’ as an alternative to pre-completion sound testing.
To maintain sound insulation:
z the correct blocks should be used z close the junction between separating and external cavity
z fully fill joints, mortar beds and perpends walls with flexible cavity stops
z use only approved wall ties z care should be taken when specifying dry lining, as the
z space wall ties 900mm minimum horizontally and 450mm thickness of plasterboard layers, and the methods of sealing
and fixing, can affect the transmission of sound
6.3
minimum vertically
z avoid any reduction in the thickness of masonry z holes, voids and hairline cracks should be avoided or made
In masonry separating cavity walls, wall ties should be type A Figure 10: Separating wall junction
in accordance with Building Regulations. separating wall taken through
and tied to inner leaf
Solid separating walls can be taken through the inner leaf of
an external cavity wall and tied or bonded in accordance with
either Building Regulations or Robust Details guidance.
Chases can reduce the sound insulation value of a wall
and should:
z be cut only where specified in the design
z not be cut using impact power tools where there is a risk
of damage dense block lightweight block
z not exceed 1/6 of the thickness of the single leaf separating wall inner leaf
where horizontal
z not exceed 1/3 the thickness of the single leaf Figure 11: Vertical and horizontal chases
where vertical
z not be chased where hollow blocks are used, unless
specifically permitted by the manufacturer
z be fully filled with mortar
horizontal chase
z be staggered on each side of the wall to avoid them being no deeper than
1/6 block thickness
back to back.
vertical chase
no deeper than
1/3 block thickness
7 Internal walls I 2024
Chapter 6.3
Flanking walls
The construction of the flanking wall and the position of openings should comply with Building Regulations.
Rooms containing a WC
The construction should comply with Building Regulations, including the recommended sound reduction between rooms that
include a WC and adjacent:
z living rooms z studies
z dining rooms z bedrooms, except where the WC is ensuite.
Other forms of studwork construction may be acceptable where in accordance with the guidance in supporting documents to the
Building Regulations or where independent evidence of performance is available.
6.3
Blockwork partitions
Masonry partitions provide adequate sound insulation where:
z blocks have a minimum density of 600kg/m3 and are z blocks are tied at every course to adjoining walls, with joints
finished on both sides with 13mm of plaster or 12.5mm fully filled.
plasterboard, and
Further guidance can be found in the relevant Building Regulations.
Proprietary partitions
Independent test evidence of the system’s performance is required in accordance with Technical Requirement R3. Criteria for
testing is not provided in R3.
Sound insulation of soil pipes in floor voids Figure 13: Vertical S&VP boxing
and SVPs
All sections of soil and vent pipes including those in bathrooms
or ground floor stub stacks, should be fully soundproofed. timber framing
Where soil and vent pipes run horizontally through a floor void,
line the enclosure and
above or below a habitable room they should be: wrap the pipe with 25mm
unfaced mineral wool
z wrapped in at least 25mm of unfaced mineral wool (min. density of 10kg/m3)
(10kg/m3 min)
z adequately supported to avoid contact with the floor the material of the enclosure
should have a mass of
decking or ceiling. 15kg/m2
Sound insulation should be provided to soil pipes passing
through homes by:
z an encased boxing, using material (15kg/m²) and
z wrapping the pipe with a minimum 25mm of unfaced
mineral wool (10kg/m³ min). The insulation should be
continued through the thickness of each
sound-insulating floor.
2024 I Internal walls 8
Chapter 6.3
Soil and vent pipes which hold a satisfactory assessment by an appropriate independent technical approvals authority
acceptable to NHBC, maybe acceptable where the requirements of the Building Regulations are achieved.
Construction of timber stud internal walls shall ensure adequate stability, including:
6.3
a) setting out and workmanship c) fixing.
b) size of timber members
Fixing
Partitions should: Figure 15: Deflection head
Figure 16: Partition abutment Figure 17: Wall head fixing to joist Figure 18: Wall head fixing to nogging
extra stud
Figure 19: Partition fixing to joist Figure 20: Partition fixing to nogging Figure 21: Additional nogging support
6.3
nogging
supports
radiator
Noggings should be provided to support fittings, such as radiators, wall mounted boilers, sanitary fittings and kitchen units, etc.
6.3
Tapered edge boards should be used where the plasterboard is to be jointed before decoration.
For fire and sound-resisting walls (eg separating walls and walls to WCs), the correct thickness, number of layers and sealing
should be specified in the design information.
For guidance on the use of plasterboard in wet areas ie, bath and shower areas, please refer to Chapter 9.2 ‘Wall
and ceiling finishes’.
DPCs shall be installed where required to prevent moisture entering the building.
Load-bearing partition walls built on foundations should have a DPC. Where partitions which could be affected by residual damp
(eg timber or steel) are placed on concrete floors, a DPC should be provided directly below, even where there is a DPM beneath
the slab.
DPCs should be:
z at least the width of the wall or partition z continuous or lapped by a minimum of 100mm.
z linked with any adjoining DPM
Figure 24: DPC provision Figure 25: DPC provision
11 Internal walls I 2024
Chapter 6.3
Where steps are necessary in the ground floor slab, a DPC should be:
z incorporated as a continuous link between the upper and z protected from damage during construction.
lower DPM
Where steps are greater than 150mm, structural waterproofing should be provided in accordance with Chapter 5.4
‘Waterproofing of basements and other below ground structures’.
Materials acceptable for DPCs include:
Bitumen BS 6398, BS EN 14967
Polyethylene BS 6515, BS EN 14909
Proprietary materials Technical Requirement R3
6.3.14 Components
Walls ties and related items shall be of the appropriate type and strength and shall have adequate durability.
Joist hangers, restraint straps, bond ties, etc should be protected against corrosion. Ferrous metals with the following levels of
protection are acceptable:
z post-galvanizing to BS EN ISO 1461, or z pre-galvanizing to BS EN 10143.
6.4
Timber and concrete
upper floors
This chapter gives guidance on meeting the Technical
Requirements for timber and concrete upper floors.
6.4.1 Compliance 01
6.4.2 Provision of information 01
6.4.3 Upper floor design 01
6.4.4 Fire spread 02
6.4.5 Sound insulation 03
6.4.6 In-situ concrete floors
and concreting 03
6.4.7 Precast concrete 03
6.4.8 Timber joist spans 04
6.4.9 Timber joist performance 06
6.4.10 Construction of timber floors 06
6.4.11 Joists supported by
intermediate walls 08
6.4.12 Joists connected to steel 09
6.4.13 Joists into hangers 09
6.4.14 Timber joist and restraint straps 11
6.4.15 Strutting 13
6.4.16 Joists and openings 13
6.4.17 Multiple joists 14
6.4.18 Notching and drilling 15
6.4.19 Floor decking 16
6.4.20 Floating floors or floors
between homes 18
1 Timber and concrete upper floors I 2024
Chapter 6.4
Timber and concrete upper floors shall comply with the Technical Requirements.
Timber and concrete upper floors that comply with the guidance in this chapter will generally be acceptable.
Upper floors shall support and transmit loads safely to the supporting structure without undue deflection or
deformation. Issues to be taken into account include:
a) loads and support to partitions c) support of external envelope and projections.
b) steelwork
Structural design of timber and concrete upper floors should be in accordance with BS EN 1991-1-1.
The design of upper floors should account for dead loads, including:
z floor structure, decking and finishes z walls and partitions supported by the floor
z ceilings and applied finishes z permanent fixtures such as boilers, watertanks etc.
Imposed loads should be calculated in accordance with the relevant British Standards, including BS EN 1991-1-1
which recommends:
z 1.5kN/m2 for self-contained homes z values for communal areas serving flats or maisonettes.
Steelwork
Steelwork supporting upper floor should be:
z designed by an engineer in accordance with Technical z sized to allow an adequate bearing of the floor system.
Requirement R5 and comply with Chapter 6.5 ‘Steelwork’
Structural continuity of the floor should be provided by the use of continuous decking fixed to joists on both sides of a transverse
steel joist.
Steel beams should be protected by a suitably durable paint coating as detailed in Chapter 6.5 ‘Steelwork’.
6.4
and moisture movements of the envelope, in addition to any residual floor deflection that may be expected from the supporting
structure. The concrete floor together with any associated horizontal (eg masonry) movement joint it supports should be
appropriately designed taking into consideration the following:
z floor deflection behind the cladding/envelope/balcony z building elevation and load paths
z cladding (eg masonry) support system deflections z elastic shorting of structural columns and walls
z cladding (eg masonry) joint details z building sway.
Further guidance on horizontal movement joints in masonry can be found in Chapter 6.1 - External masonry walls.
structural
timber
separated
from
chimney wall
3 Timber and concrete upper floors I 2024
Chapter 6.4
Timber
To counteract fire spread:
z combustible material should be kept away from z structural timber should be separated from sources of heat
heat sources in accordance with Chapter 6.8 ‘Fireplaces, chimneys
and flues’.
Ancillary product
Where ceilings of intermediate floors in houses or compartment floors in flats/apartments are perforated or penetrated by
services such as recessed light fittings (downlighters); ceiling-mounted air valves, vents and extractor fans and pipes, the floor
construction should still achieve the required period of fire resistance.
When installing such ancillary products and/or services including their fire-stopping elements and intumescent seals used to
maintain the fire resistance of the floor, one of the following should be met:
z a satisfactory fire test evidence and/or extended field of z a proprietary floor system with satisfactory assessment by
application reports that support the use of such product/ an appropriate independent technical approvals authority
systems in the particular type of floor being considered, or accepted by NHBC which includes the use of specific floor
z products and systems with a satisfactory assessment by type and ancillary products which has been demonstrated
an appropriate independent technical approvals authority to be satisfactory through testing and assessment, and are
accepted by NHBC covering the particular type of floor to be used within the limitations of the certification.
being considered, or
z comply with BS EN 1992-1-1 and z be reasonably level and smooth, especially at doorways
Chapter 3.1 ‘Concrete and its reinforcement’ and junctions
z comply with the design z be in accordance with Technical Requirement R3 where
proprietary elements are used.
6.4
6.4.8 Timber joist spans
Timber floor joists shall be adequate for the spans and loads, and be correctly installed.
Solid timber joist sizes are provided in the BS 8103-3 span tables. Where the tables do not apply, or where there are
concentrated loads, floor joists should be designed by an engineer in accordance with Technical Requirement R5.
Span tables for solid timber joists
Tables 1 and 2 in this chapter are derived from the BM TRADA Technology Ltd. ‘Eurocode 5 span Tables for solid timber
members in floors, ceilings and roofs for dwellings (4th edition)’. Tables 1 and 2 give permissible clear spans of simply supported
domestic floor joists of solid timber for specified loadings, sizes and spacings calculated in accordance with EC5. The tables
make no allowance for concentrated or line loads applied by partitions, trimmers or other similar loads. The minimum bearing
length assumed for the tables is 40mm unless noted otherwise, and longer bearing lengths may be required for other practical
reasons. The section sizes are based on regularised ALS or CLS timber.
For timber floors between homes (compartment floors):
z to meet acoustic performance, the dead load of the z use the three right-hand columns from Tables 1 and 2.
construction of up to 1.25kN/m2 may be assumed
For upper floors with 22mm thick chipboard decking and a 12.5mm plasterboard ceiling:
z a dead load of up to 0.5kN/m2 may be assumed z use the centre three columns from Tables 1 and 2.
Where lightweight non load-bearing partitions weigh up to 1.0kN (101.9kg) per metre run and are parallel to the joists,
the following applies:
z partitions may be directly supported by one or two z where similar lightweight partitions run at right-angles to
additional joists the joists, the maximum spans in Tables 1 and 2 should be
z partitions should be fixed through the floor decking into the reduced by 10%
joist(s) beneath z for all other additional loads, joist sizes should be
designed by an engineer in accordance with
Technical Requirement R5.
5 Timber and concrete upper floors I 2024
Chapter 6.4
Table 1: Permissible clear spans for domestic floor joists. Table 2: Permissible clear spans for domestic floor joists.
Strength class C16 Strength class C24
Imposed load not exceeding qk = 1.5 kN/m2 or Qk = 2.0kN. Imposed load not exceeding qk = 1.5 kN/m2 or Qk = 2.0 kN.
Service class 1 or 2. Service class 1 or 2.
Dead load gk (kN/m2) excluding self-weight of joist Dead load gk (kN/m2) excluding self-weight of joist
Size of joist gk not more gk not more gk not more Size of joist gk not more gk not more gk not more
than 0.25 than 0.50 than 1.25 than 0.25 than 0.50 than 1.25
Joist spacing (mm) Joist spacing (mm)
400 450 600 400 450 600 400 450 600 400 450 600 400 450 600 400 450 600
Breadth Depth Maximum clear span (m) Breadth Depth Maximum clear span (m)
(mm) (mm) (mm) (mm)
38 95 1.71* 1.62 1.40 1.61 1.52 1.32 1.40 1.33 1.16 38 95 1.99* 1.89* 1.64 1.86* 1.76 1.54 1.61 1.53 1.34
38 120 2.37* 2.24* 1.95 2.19* 2.08* 1.82 1.87 1.78 1.56 38 120 2.64* 2.54* 2.27 2.49* 2.39* 2.11 2.14 2.03 1.80
38 145 2.86* 2.75* 2.49 2.69* 2.59* 2.33 2.35 2.23 1.97 38 145 3.18* 3.06* 2.78 3.00* 2.88* 2.61 2.62 2.52 2.26
38 170 3.34* 3.21* 2.91 3.15* 3.03* 2.74 2.75 2.64 2.39 38 170 3.72* 3.58* 3.25 3.51* 3.37* 3.06 3.07 2.95 2.67
38 195 3.83* 3.68* 3.34 3.61* 3.47* 3.14 3.15 3.03 2.73 38 195 4.26* 4.10* 3.72 4.02* 3.86* 3.51 3.52 3.38 3.06
38 220 4.31* 4.14* 3.76 4.06* 3.90* 3.54 3.55 3.41 3.08 38 220 4.79* 4.61* 4.19 4.52* 4.35* 3.95 3.96 3.81 3.45
44 95 1.84* 1.74 1.51 1.72 1.63 1.42 1.50 1.42 1.24 44 95 2.14* 2.02* 1.76 1.99* 1.89 1.65 1.71 1.63 1.44
44 120 2.49* 2.39* 2.09 2.33* 2.22* 1.95 1.99 1.89 1.67 44 120 2.77* 2.67* 2.42 2.61* 2.51* 2.25 2.27 2.16 1.92
44 145 3.00* 2.89* 2.62 2.83* 2.72* 2.46 2.47 2.37 2.10 44 145 3.34* 3.21* 2.92 3.15* 3.03* 2.75 2.76 2.65 2.40
44 170 3.51* 3.38* 3.06 3.31* 3.18* 2.88 2.89 2.78 2.51 44 170 3.90* 3.76* 3.42 3.69* 3.54* 3.22 3.23 3.10 2.81
44 195 4.02* 3.86* 3.51 3.79* 3.64* 3.30 3.32 3.18 2.88 44 195 4.47* 4.30* 3.91 4.22* 4.06* 3.68 3.70 3.55 3.22
44 220 4.52* 4.35* 3.95 4.26* 4.10* 3.72 3.73 3.59 3.25 44 220 5.02* 4.84* 4.40 4.75* 4.57* 4.15 4.16 4.00 3.63
47 95 1.90* 1.79 1.56 1.77 1.68 1.47 1.54 1.46 1.28 47 95 2.20* 2.08* 1.82 2.05* 1.94 1.70 1.76 1.68 1.48
47 120 2.55* 2.45* 2.16 2.40* 2.28* 2.01 2.05 1.95 1.72 47 120 2.83* 2.73* 2.48 2.67* 2.57* 2.32 2.33 2.22 1.97
47 145 3.07* 2.95* 2.68 2.89* 2.78* 2.52 2.53 2.43 2.16 47 145 3.41* 3.28* 2.98 3.22* 3.10* 2.81 2.82 2.71 2.45
47 170 3.59* 3.45* 3.13 3.38* 3.25* 2.95 2.96 2.84 2.57 47 170 3.99* 3.84* 3.49 3.77* 3.62* 3.29 3.30 3.17 2.87
47 195 4.10* 3.95* 3.59 3.87* 3.72* 3.38 3.39 3.26 2.95 47 195 4.56* 4.39* 4.00 4.31* 4.15* 3.77 3.78 3.63 3.29
47 220 4.62* 4.44* 4.04 4.36* 4.19* 3.81 3.82 3.67 3.32 47 220 5.13* 4.94* 4.50 4.85* 4.67* 4.24 4.26 4.09 3.71
6.4
63 95 2.17* 2.06* 1.80 2.02* 1.92 1.68 1.74 1.66 1.47 63 95 2.52* 2.43* 2.14 2.38* 2.26* 1.99 2.03 1.94 1.72
63 120 2.80* 2.70* 2.45 2.64* 2.54* 2.29 2.30 2.20 1.95 63 120 3.11* 2.99* 2.72 2.94* 2.83* 2.57 2.57 2.47 2.22
63 145 3.38* 3.25* 2.96 3.19* 3.07* 2.79 2.79 2.68 2.43 63 145 3.74* 3.60* 3.28 3.54* 3.40* 3.09 3.10 2.98 2.70
63 170 3.94* 3.80* 3.46 3.72* 3.58* 3.26 3.27 3.14 2.85 63 170 4.37* 4.21* 3.84 4.13* 3.98* 3.62 3.63 3.49 3.17
63 195 4.51* 4.34* 3.95 4.26* 4.10* 3.73 3.74 3.60 3.26 63 195 5.00* 4.81* 4.39 4.72* 4.55* 4.14 4.15 4.00 3.62
63 220 5.07* 4.88* 4.45 4.79* 4.61* 4.20 4.21 4.05 3.68 63 220 5.61* 5.41* 4.94 5.31* 5.12* 4.66 4.68 4.50 4.08
72 120 2.93* 2.82* 2.56 2.76* 2.66* 2.42 2.42 2.32 2.06 72 120 3.25* 3.13* 2.85 3.07* 2.96* 2.69 2.70 2.59 2.35
72 145 3.52* 3.39* 3.09 3.33* 3.20* 2.91 2.92 2.81 2.55 72 145 3.91* 3.77* 3.44 3.70* 3.56* 3.24 3.25 3.13 2.84
72 170 4.11* 3.96* 3.61 3.89* 3.74* 3.41 3.42 3.29 2.98 72 170 4.57* 4.40* 4.02 4.32* 4.16* 3.79 3.80 3.66 3.32
72 195 4.70* 4.53* 4.13 4.44* 4.28* 3.90 3.91 3.76 3.41 72 195 5.22* 5.03* 4.59 4.94* 4.76* 4.34 4.35 4.19 3.81
72 220 5.28* 5.09* 4.65 5.00* 4.82* 4.39 4.40 4.23 3.85 72 220 5.86* 5.65* 5.17 5.55* 5.35* 4.88 4.90 4.71 4.29
ALS/CLS ALS/CLS
38 89 1.56 1.47 1.27 1.47 1.39 1.21 1.29 1.22 1.07 38 89 1.82* 1.72 1.50 1.71 1.62 1.41 1.49 1.41 1.24
38 114 2.21* 2.09* 1.82 2.05* 1.94 1.70 1.76 1.67 1.47 38 114 2.51* 2.41* 2.12 2.36* 2.24* 1.97 2.01 1.91 1.69
38 140 2.76* 2.65* 2.40 2.60* 2.50* 2.23 2.25 2.14 1.89 38 140 3.07* 2.96* 2.68 2.90* 2.79* 2.53 2.53 2.43 2.17
38 184 3.61* 3.47* 3.15 3.41* 3.27* 2.97 2.98 2.86 2.58 38 184 4.02* 3.87* 3.52 3.79* 3.65* 3.31 3.32 3.19 2.89
38 235 4.60* 4.42* 4.01 4.33* 4.17* 3.78 3.79 3.64 3.29 38 235 5.11* 4.92* 4.47 4.83* 4.64* 4.22 4.23 4.06 3.68
89 184 4.74* 4.57* 4.18 4.49* 4.33* 3.95 3.96 3.81 3.46 89 184 5.26* 5.08* 4.64 4.98* 4.81* 4.39 4.40 4.24 3.86
89 235 6.00* 5.79* 5.30 5.69* 5.49* 5.01 5.03 4.84 4.41 89 235 6.65* 6.42* 5.88 6.31* 6.09* 5.57 5.58 5.38 4.90
Floor joists shall be of an appropriate size and quality, and be suitably durable.
I-joists and metal web joists should not be used in situations where any part of the joist is exposed to external conditions, and be:
z in accordance with Technical Requirement R3 z stored clear of the ground and stacked vertically
z used in accordance with the z not used where damaged
manufacturer’s recommendations z designed in accordance with BS EN 1995-1-1 and its UK
z protected from adverse weather conditions during transport National Annex.
and storage
Floors formed by the bottom chords of attic trusses are required to meet the above guidance.
Structural solid timber joists should be specified according to the strength classes in BS EN 338, eg C16 or C24 and
marked with:
z the strength class, or evidence of species and grade made z the identification of the company responsible for the grading
available so as to determine the strength class (when graded to BS 4978 or BS EN 14081).
When graded to BS 4978:
z the species should be included in accordance with z BS EN 338 can be used to determine strength class.
BS EN 1912 or the class strength specified
Regularised timber should be used for solid timber joists, and be:
z dry graded to BS 4978 or BS EN 14081 z marked ‘DRY’ or ‘KD’.
6.4
be protected.
Timber should not be used where:
z it is excessively bowed, twisted or cambered
z it has large edge knots or shakes
z it has a waney edge more than half the thickness
z it is damaged or has any sign of rot.
Upper floors shall be constructed in a workmanlike manner and provide satisfactory performance.
Issues to be taken into account include:
a) levelling c) support.
b) joist spacing and clearance
Levelling
Bearings for joists should be level. The floor should staircase
trimmer
be levelled:
z from the staircase trimmer and trimming joist
z in accordance with the manufacturer’s recommendations
z using hard packing; loose or soft packing should not
be used.
Support
The floor should have an adequate bearing on the supporting structure.
Timber joists should normally have a minimum bearing as shown in Table 3.
The figures in brackets should only be used when the joist is not providing restraint to the wall.
Joists may be:
z supported on joist hangers or on internal load-bearing walls z built into the inner leaf of an external cavity wall, with care
taken to ensure air-tightness.
Where joists are built into separating walls, fire-and sound-resisting performance, in accordance with Building Regulations,
should be taken into account.
I-joists and metal web joists should not be built into solid
external walls.
The support reaction, due to dead and imposed loads on the
floor, should not exceed the recommended value specified by
the manufacturer. metal web
uprights at uprights at
intermediate bearing end bearing
Where joists are supported on walls, noggings may be required at the top flange along the wall to support the floor decking,
and at the bottom flange to support the plasterboard ceiling. Where joists are not built into brickwork or blockwork, blocking
should be provided at the joist bearing. The blocking may be used for fixing plasterboard and floor decking.
6.4
Solid timber joists
Solid timber joists bearing onto intermediate load-bearing walls should:
z be nailed together where they overlap z not project more than 100mm.
I-joists
I-joists bearing onto intermediate load-bearing walls should have:
z blocking used to brace the butt joint z short sections of joist used to provide lateral support.
100mm max.
overhang
9 Timber and concrete upper floors I 2024
Chapter 6.4
I-joists
Where connected to steel beams, I-joists should not be notched at the flange, and should:
z bear directly into the steel beam where the bearing is more z have blocking fixed to the steel beam to enable the I-joists
than 45mm. Strutting, (noggings 38mm x thickness of to be face fixed using joist hangers. Strutting is not required
flange) should be provided at the top and bottom flanges, or when hangers the full depth of the joist are used to face fix
joists to the blocking.
Hangers should:
z be detailed in the design, including the type of support to
be used for joists, trimmers and trimming joists
z have a 75mm minimum bearing on masonry
z comply with BS EN 845-1 or another acceptable clause
described in Technical Requirement R3
z have performance equivalent to restraint straps at 2m
timber to timber to heavy duty
centres where required to provide restraint timber hanger masonry hanger hanger
z be the correct size for the joist or trimmer
z be nailed through each circular hole in the vertical sides gap between joist and
hanger is 6mm max.
z bear on level beds and be tight to the wall
z not be cut into the walling.
I-joists
Where connected to hangers, I-joists should not be notched at the flange, and should have:
z a minimum bearing of 45mm onto the hanger z the tabs of the hanger bent and nailed to the bottom flange.
6.4
(full depth) fixed to both sides of the web.
Hangers should be to the full depth of the joist and restrain the top flange, or another suitable means of restraining the top flange
should be provided.
joist hanger
tabs bent over
and nailed to flange
6.4.14 Timber joist and restraint straps Also see: Chapter 6.1 and BS 8103-1
restraint strap held tight top fixed strap strap centered on block
against blockwork and tight to wall
side fixed
strap
Restraint straps should be provided along the direction of the joists and spaced at a maximum of 2m centres. They are not
generally required at the ends of joists in buildings up to, and including, two storeys where:
z restraint type joist hangers in accordance with z joists are built into a wall and bear at least 90mm on
Technical Requirement R3 are used, or the wall.
6.4
Where joists run parallel to the wall, straps should be fitted along the joists with a maximum spacing of 2m, and:
z be supported on noggings and extend over at least z have noggings provided to receive two additional nails
three joists (for solid joists, two 4.76mm diameter x 50mm long wood
z be fixed with two screws or nails into each joist screws (No.10) or 4mm diameter x 75mm round nails
(8 SWG) can be used in each joist).
I-joist with
restraint strap max. 2m centres nogging
packing
2024 I Timber and concrete upper floors 12
Chapter 6.4
I-joists
I-joists should not be notched and have:
z solid timber noggings no less than 0.5 x the depth of the z noggings made from short lengths of I-joist, or solid timber
member and a maximum of 150mm fixed between the webs the full depth of the I-joists, or
and located beneath the top flange, with the straps installed z noggings half the depth of the member x depth of the flange
through small slots neatly cut through the top of the web of laid on their side between the flanges.
the joists
When nailing into laminated veneer lumber flanges:
z care should be taken to prevent splitting z nails should be driven in at an angle (not horizontally) and
should not protrude from the flanges.
noggings for small slots neatly
I-joists cut through the top
of the webs
6.4
Metal web joists should not be notched and should have:
z 35mm x 97mm solid timber noggings beneath the top flange z noggings nailed twice to each joist.
of the metal web joists, and
6.4.15 Strutting
Strutting shall be provided where required to distribute loads and ensure adequate rigidity of the
floor structure.
Strutting should: herringbone strutting blocking
Upper floors shall have adequately sized and properly supported trimmer joists around openings.
Trimmer, trimmed and trimming joists should be:
z detailed in the design z designed in accordance with Technical Requirement R5.
Connections between joists should be made with suitable ‘timber-to-timber’ hangers, and:
z where face fixing I-joists to another I-joist, be provided with z where metal web joists are used as a trimming joist to
backer blocks on both sides of the web of the trimmer support another metal web joist, have timber uprights
between the flanges of the trimmer.
void trimmer trimmed joists single or double trimmer in
accordance with the design
backer
blocks
Deflection
The following should be considered in the design and detailing around openings in floors:
z deflection of trimming joists to be similar and no worse than z where partition walls are built off trimmers and trimming
the adjacent floor joists joists, particularly fire compartment walls, additional care
z compound deflection of the floor including trimming and should be taken to ensure that the overall deflection of such
trimmed joists should be limited to the overall floor deflection, joists would not result in residual gaps at the heads of the
to ensure there is no differential movement or noticeable step walls or in distorted walls or openings within the walls.
in the floor level adjacent to the trimming joists
There should be no notching or drilling of trimmers or trimming joists unless proven by design calculations.
6.4
spacing shown in the table below may be used.
Fixing on centreline
S S
S
S 2S
S = spacing
Engineered joists should be secured together in accordance with the manufacturers recommendation.
15 Timber and concrete upper floors I 2024
Chapter 6.4
6.4
z adjacent boards should be square
min. 10mm
expansion gap
nogging
joist or nogging
When fixing:
z fixings should have a maximum spacing of 300mm along z where boards abut a rigid upstand, a minimum 10mm
continuously supported edges and intermediate supports expansion gap should be provided; for large areas of
boarded floor, a wider expansion gap may be required at
upstands and intermediate expansion gaps of 2mm per
linear metre of floor should be provided.
Oriented strand board flooring
When fixing oriented strand board flooring:
z boards should be laid over supports in the direction z where boards abut a rigid upstand, a minimum 10mm
indicated on the board, with the stronger axis at right angles expansion gap should be provided; for large areas of
to the supporting joists boarded floor, a wider expansion gap may be required at
z boards should be long enough to span two joists upstands and intermediate expansion gaps of 2mm per
z nails should be flat headed, annular grooved nails, linear metre of floor should be provided.
3mm in diameter
Plywood flooring
When fixing plywood flooring:
z boards should be laid with the face grain at right angles to z fixings should have a maximum spacing of 150mm around
6.4
Proprietary flooring
Proprietary flooring should be:
z certified in accordance with Technical Requirement R3 z installed in accordance with certification requirements.
Floor decking that are built in as the work proceeds and left exposed to the weather will be subjected to deterioration and
adverse effect of the weather, particularly when exposed to prolonged periods of rainfall. Such floor decking when used in
conjunction with engineered and traditional joists should:
z have a third-party approval certificate from a UKAS z be used strictly in accordance with the manufacturer’s
accredited body which covers weather resistance for the instruction and details.
period of time the boards are to be left exposed on site
Any floor decking that are left exposed beyond the period stated on the third-party approval certificate should be replaced.
Non-proprietary floor decking without third party certification should not be used on structural floors exposed to the weather for
any period of time under any circumstances.
Floors should not be overloaded, especially with materials during construction, and be protected against damp, plaster splashes
and other damage.
6.4
Chapter
6.5
Steelwork
This chapter gives guidance on meeting the Technical
Requirements for:
z steelwork which supports masonry partitions and
timber floors, including trimmed openings
z the protection of steelwork.
6.5.1 Compliance 01
6.5.2 Design guidance 01
6.5.3 Steel grade and coatings 03
6.5.4 Installation and support 05
6.5.5 Padstones 05
6.5.6 Connections 06
6.5.7 Examples 07
For figure reference tables in this chapter, please go to the end of the chapter
1 Steelwork I 2024
Chapter 6.5
6.5.2 Design guidance Also see: Chapters 6.1, 6.3 and 6.4
Steelwork shall be designed to support and transmit loads to the supporting structure without undue
movement or deflection. Issues to be taken into account include:
a) support of masonry partitions b) support of timber floors, including trimmed openings.
Where any of the conditions are not met, steelwork should be designed in accordance with Technical Requirement R5.
Method of applying tables:
z ensure that all conditions apply. z check the span of the beam(s)
z identify the masonry partition construction and thickness z use Table 2 to determine a suitable steel section size
z use Table 1 to establish the load per metre run z use Table 6 to determine if padstones are required.
3 to 5 Up to 3 127 x 76 x 13
3 to 3.5 152 x 89 x 16
3.5 to 4 178 x 102 x 19
Over 4 (2)
5 to 7 Up to 2.5 127 x 76 x 13
2.5 to 3 152 x 89 x 16
3 to 4 178 x 102 x 19
Over 4 (2)
Notes
1
For spans up to 4m, universal column 152mm x 152mm x 23kg/m (smallest size available) may be used.
2 For spans over 4m, beams should be designed by an engineer in accordance with Technical Requirement R5.
6.5
chipboard, oriented strand board or plywood) on timber studwork or proprietary product, is non load-bearing
joists and the ceiling is plasterboard with a plaster skim coat z padstones are provided where required in accordance
or a plastic finish (Artex or similar) with Table 6
z allowance has been made of 0.5kN/m2 for self-weight z clear span of beam does not exceed 4.4m
(floor and ceiling load) z connections between steelwork beams are in accordance
z the floor does not support masonry partitions with Clause 6.5.6, or are designed by an engineer
z the floor support is one of the methods shown in Figure 1.
Where any of the conditions are not met, steelwork should be designed by an engineer in accordance with Technical Requirement R5.
Method of applying tables:
z use Figure 1 to determine the area supported by z use Table 7 to determine if padstones are required
the beam(s) z where steel beam-to-steel connections are required,
z check the span of the beam(s) refer to the connections in Clause 6.5.6.
z use Table 3 to determine a suitable steel section size
A A
wall wall
under B under A A
A A B
void
B
B C B C
A A
B A A A A
void void void
B B C B C
Where any area shown as ‘void’ contains a staircase, add 2m2 to the effective area supported by any beam which fully or partially
supports that staircase.
Table 3: Size of steel beam supporting timber floor
Effective area Effective trimmer span Smallest suitable steel section size (mm x mm x kg/m)
supported (m2) = clear span + 100mm (m) Universal beam Universal column
0 to 20 0 to 2.0 127 x 76 x 13 152 x 152 x 23
0 to 20 2 to 2.5 127 x 76 x 13 152 x 152 x 23
20 to 30 152 x 89 x 16 152 x 152 x 23
0 to 10 2.5 to 3 127 x 76 x 13 152 x 152 x 23
10 to 20 152 x 89 x 16 152 x 152 x 23
20 to 30 178 x 102 x 19 152 x 152 x 23
0 to 10 3 to 3.5 127 x 76 x 13 152 x 152 x 23
10 to 30 178 x 102 x 19 152 x 152 x 23
30 to 40 203 x 133 x 25 152 x 152 x 30
0 to 10 3.5 to 4 152 x 89 x 16 152 x 152 x 23
10 to 20 178 x 102 x 19 152 x 152 x 23
20 to 30 203 x 102 x 23 152 x 152 x 23
6.5
Table 4: Environment categories for component groups in different locations and exposure conditions
Component group Location Description of exposure condition Environment categories
External Outside a home Above splash zone C4 or C5(1)
At ground level within splash zone C5(2)
(up to 150mm above ground)
Outside or basement Below ground level C5(2)
Internal Sub-floor void (3)
Unventilated C3
Ventilated C2
Internal Kitchen/bathroom, etc Moist humid conditions – protected against condensation C2
Kitchen/bathroom, etc Moist humid conditions – exposed to condensation C2
Rooms other than Warm dry C2
kitchen/bathroom, etc
In roof void Unheated dry C2
Internal/external Façade Embedded or partially embedded in building envelope C5(4)
Notes
1
For construction located within 500m of coastal shoreline.
2 Alternatively, steelwork may be encased in concrete.
3
For steelwork not in contact with the ground.
4 For steelwork in contact with, or embedded in an external masonry wall, for at the contact / embedment length.
Alternatively, guidance on suitable atmospheric corrosivity categories (C1 – C5) and appropriate protective coatings for domestic
construction may be based on the recommendations given on the website www.steelconstruction.info. A site specific
assessment is required in order to determine an appropriate classification level for the steelwork. A suitable protective coating
specification is to be determined by the designer in accordance with the coating manufacturer’s recommendations.
Table 5: Protective coatings for hot rolled structural steelwork for atmospheric corrosivity category (recommended for housing
applications only)
Atmospheric Surface Protective coating(1, 2, 3) Site or Making good of
corrosivity preparation(4) factory damaged areas of
Material Minimum coating thickness Number
and risk applied protective coating
(d.f.t.) / weight
(5) (6)
of coats
C1 N/A None required N/A N/A N/A N/A
6.5
Very low
C2 Thoroughly clean High build zinc 80 µm(8) 1 or 2 Factory Thoroughly wire brush
Low surface prior to phosphate epoxy damaged areas and
abrasive blast primer(7) build up coats using
cleaning to Sa 2½ the same materials
and to the same d.f.t.
C3 Thoroughly clean High build zinc 80 µm(8) 1 or 2 Factory Thoroughly wire brush
Medium surface prior to phosphate epoxy damaged areas and
abrasive blast (7)
primer, followed build up coats using
cleaning to by high build 120 µm 1 the same materials
Sa 2½ recoatable epoxy and to the same d.f.t.
micaceous iron
oxide (MIO) (200 µm in total)
C4 Hot dip 460 gms/m² 1 Factory To be determined
High galvanize to by the designer in
BS EN ISO 1461(9) accordance with
the manufacturer’s
recommendations
C5 Hot dip 710 gms/m² 1 Factory To be determined
Very high galvanize to by the designer in
BS EN ISO 1461(9) accordance with
the manufacturer’s
recommendations
Notes
here steelwork is to be given a decorative finish, the protective coat is to be compatible with the decorative finish.
1 W
Manufacturers’ recommendations should be followed.
2
Where steelwork is to be protected by intumescent paint for fire purposes, manufacturers’ recommendations should be followed.
3
All fixings and fittings to the structural steel elements are to be protected against corrosion in a manner that is both commensurate and compatible with the
protective coatings.
4
Surface preparation to BS EN ISO 12944-4.
5
Coating thicknesses given represent nominal dry film thickness (d.f.t.).
6
Thicknesses and weights shown represent the coating to be applied to each face of a steel section.
7
Epoxy primers have a limited time for over-coating. Manufacturers’ recommendations should be followed.
8
80 µm can be in one coat or as 20 µm pre-fabrication primer plus 60 µm post-fabrication primer.
9
Alternatively, use products manufactured from austenitic stainless steel in accordance with the recommendations of BS EN 1993-1-4:2006.
5 Steelwork I 2024
Chapter 6.5
Where shop-applied protective coatings have been damaged, the coatings should be made good on site prior to being built into
the works, as indicated in Table 5 ‘Making good of damaged areas’.
Where steelwork is to be welded, the protective coating system specified by the designer should be used.
Where steelwork is to be protected by intumescent paint for fire purposes, this should be in accordance with the
manufacturer’s recommendations.
Steelwork support
Beam supports should not occur above window or door openings. Bearings for steelwork supported on masonry should be:
z 100mm minimum z clean, dry and level.
6.5.5 Padstones
Steelwork shall be supported by padstones where required to distribute point loads safely to the supporting
structure without undue movement or deflection.
Where a steel beam is supported by masonry, a padstone may be required to spread the load over a larger area to
prevent overstressing. Padstones should be in accordance with:
z the engineer’s design, or z the guidance given in this chapter.
Where the inner leaf of the cavity wall contributes to the overall thermal performance of the wall, padstones should:
6.5
z have similar thermal properties to the masonry used for the z not create a cold bridge.
rest of the inner leaf, or
Padstones should be formed in one unit with a minimum compressive strength of 10 N/mm2 from:
z in-situ concrete z clay bricks, or
z precast concrete z engineering bricks (when less than 215mm x 100mm).
z concrete blocks
6.5.6 Connections
Connections shall be chosen and installed to achieve the required structural performance.
Steelwork connections should:
z be in accordance with the guidance in this chapter, or z where other forms of connection (eg high strength friction
grip bolts) are required, be designed by an engineer in
6.5
accordance with Technical Requirement R5.
Only weld, cut or drill steelwork where it is required by the design.
Bolts for connections should comply with the design information and relevant British Standards, including:
BS 4190 ‘Specification for ISO metric black hexagon bolts, screws and nuts’
BS EN 1011 ‘Welding. Recommendations for welding of metallic materials’
BS EN 14399 ‘High-strength structural bolting assemblies for preloading’
BS EN 1993-1-8 ‘Eurocode 3. Design of steel structures. Design of joints’
The connection methods detailed in this chapter are suitable for connecting steel beams used to support floor loads only, using
black bolts or welding.
Figure 3: Joints between beams of similar size Figure 4: Joints between beams of similar size
(beams 170mm to 230mm deep) (neither beam deeper than 170mm)
25mm 25mm
10mm max.
10mm max.
Connections between steel sections should be designed by an engineer in accordance with Technical Requirement R5,
where the above conditions are not met.
7 Steelwork I 2024
Chapter 6.5
6.5.7 Examples
1 Using information about the supported wall and Table 1: Figure 5: Example Wall supported by steel beam:
■ 75mm thick
z load per metre run = 4.2kN/m. ■ medium density (1200kg/m3)
■ plastered both sides
2 U
sing the load per metre run, the span of the beam ■ 2.6m high.
and Table 2:
z suitable section size = 178 x 102 x 19 UB.
inner
Steel beam: padstone
■ opening 3.8m 100mm
■ min 100mm bearing at each end.
6.6
Staircases
This chapter gives guidance on meeting the Technical
Requirements for staircases.
6.6.1 Compliance 01
6.6.2 Provision of information 01
6.6.3 Fire precautions 01
6.6.4 Lighting 02
6.6.5 Glazing 02
6.6.6 Structural design 02
6.6.7 Headroom and width 02
6.6.8 Design of steps 03
6.6.9 Landings 04
6.6.10 Guarding 04
6.6.11 Handrails 05
6.6.12 Staircases made from timber and
wood-based products 07
6.6.13 Concrete staircases 08
6.6.14 Steel staircases 08
6.6.15 Proprietary staircase units 08
6.6.16 Protection 08
For figure reference tables in this chapter, please go to the end of the chapter
1 Staircases I 2024
Chapter 6.6
Staircases which comply with the guidance in this chapter and relevant Building Regulations will generally be acceptable.
Further guidance can be found in BS 5395-1.
Staircases should be designed to meet relevant Building Regulations, taking into account the fire resistance of components and
smoke ventilation. Further guidance can be found in BS 9991 and BS 9999.
2024 I Staircases 2
Chapter 6.6
Artificial light sources should be provided to all staircases and landings within homes and common areas, and be controlled by
two-way switching. Alternatively automatic light-sensitive controls may be used.
6.6.5 Glazing Also see: GGF Safety and Security Glazing Good Practice Guide
Glazing near staircases (where contact could be made by someone using the stairs) shall be suitable for its
location.
Where staircases are located close to glazing, any glass below the minimum guarding height or within a zone where a user may
make impact, the glass should either not break or be designed to break safely. The glazing should be at least one of the following:
z protected by a balustrade or railing (balustrade spacing z toughened or laminated glass
should be a maximum of 75mm) z constructed using glass blocks.
6.6
See also Chapter 3.1 ‘Concrete and its reinforcement’
Steel staircases BS EN 1993-1-1 See also Chapter 6.5 ‘Steelwork’
Proprietary staircases Proprietary staircases should meet Technical
Requirement R3
Timber stud walls may require additional noggings to provide appropriate fixing locations, and block walls should be sufficiently
robust to support the required loads and to receive appropriate fixings. It should be noted that stairs generally are unable to be
secured to metal stud walls.
Differential movement
When considering differential movement in relation to setting out, levels and finishes, allowances should be made for:
z casting/fabrication tolerances z creep and thermal movement
z deflection under load z storey height.
z foundation settlement
Stairs should have a minimum of 2m clear head room (H) over the entire length and width of the stairway and landing, as
measured vertically from the pitch line or landing.
Staircases should have the minimum width as required by the relevant Building Regulations.
The overall floor opening should be checked off plan and on site prior to the stairs being installed:
z for size to accept the stairs, with sufficient clearance to z to allow for sufficient headroom.
enable installation
3 Staircases I 2024
Chapter 6.6
Where staircases form part of a means of escape, reference should be made to the relevant Building Regulations.
Figure 1: Minimum headroom
H
landing
pitch line
Pitch
The maximum angle of pitch of a stairway should not exceed: Figure 2: Pitch line
Stairs should be dimensioned so that the rise (R) and the going (G) is between
550mm and 700mm when using the equation:
2R + G.
Staircases should be accurately located and fixed with the string at the correct angle to ensure all treads are level.
Steps
In each flight:
z treads should be level z the treads should overlap by a minimum of 16mm (15mm in
z the rise and going of steps should be equal Scotland), where the riser is open
z account should be taken of the thicknesses of screeds. Floor z open risers should not permit a 100mm sphere to pass
finishes that reduce the bottom rise by a maximum of 12mm through and are not permitted for common stairs.
are acceptable
Where stairs are open to the weather, designers should consider that grip may be affected by inclement weather, and one of the
following should be specified:
z a non-slip finish z a non-slip insert to each tread.
6.6
400mm min.
6.6.10 Guarding
Staircases shall have adequate guarding and be constructed to reduce the risk of being climbed or
falling through.
Guarding:
z is required where the drop is more than 600mm at any point z may be required where a stair abuts an opening window,
along the open sides of stairs and landings to comply with relevant Building Regulations.
Guarding should be:
z provided along the full length of the flight, including landings z a solid wall or balustrading
z capable of resisting forces, in accordance with Table 2 and z positioned at a height, in accordance with Table 3.
BS 6180
5 Staircases I 2024
Chapter 6.6
Table 2: Minimum horizontal imposed loads for parapets, barriers and balustrades for residential usages
Type of Example use Horizontal uniformly Uniformly distributed load A point load applied
occupancy distributed line load (kN/m) applied to the infill (kN/m2) to part of the infill (kN)
Balustrading should:
Figure 7: Protective guarding
z be fixed securely
100mm diameter spheres cannot pass through
z not be climbed easily by children, eg have no horizontal foot
holds which would enable climbing
6.6
A handrail is required for flights of stairs that rise over 600mm. Figure 8: Minimum clearance gap
The handrail (throughout the full length) should:
z be securely fixed and located in accordance with the design
z be a vertical distance of 900mm–1000mm (or
840mm–1000mm in Scotland) above the pitch line
z have a 25mm minimum clearance from any surface
z ensure a firm handhold
z have rounded ends or be returned to the wall to reduce the 25mm
risk of clothing being caught min.
For tapered treads/winders, where handrails to the outside of the stairs are provided, they should provide a safe handhold for the
full rise of any stairs with a total rise greater than 600mm.
In England, Wales and Scotland, where the staircase has between one and four tapered treads/winders, the newel post may be
used to provide a safe handhold. In Northern Ireland, a handrail should be fitted to the outside of all tapered stairs.
handrail
handrail
additional handrail not needed additional handrail not needed
landing
6.6
In England, Wales and Scotland, a handrail is not required on the outside of the stairs if the newels provide a safe handhold.
There should be a minimum distance between newels of 100mm to provide a hand grip.
Figure 13: Handrail provision Figure 14: Handrail provision
additional handrail not needed handrail additional handrail not needed handrail
7 Staircases I 2024
Chapter 6.6
Nails should be punched below the surface of the wood and stopped. Further guidance can be found in BS 1186-2.
2024 I Staircases 8
Chapter 6.6
In-situ construction
Guidance for in-situ concrete can be found in Chapter 3.1 ‘Concrete and its reinforcement’.
Shuttering for concrete elements or connections should be constructed to ensure a consistent rise and going.
Chairs or spacing blocks should be used to provide cover to reinforcement in accordance with Chapter 3.1.
Formwork should be struck in accordance with the design information.
Design information on the spacing of bolt fixings for balustrades or handrails should be followed.
Balustrading for concrete staircases should be:
z grouted into the preformed holes or pockets z bolted to brackets cast into the concrete.
Care should be taken when using expanding fixings near the edges of concrete.
6.6
z the supporting structure should be constructed within relevant
tolerance limits set for the steel staircase
Proprietary staircases and associated components should comply with the Technical Requirements.
6.6.16 Protection
Stairs shall be free from damage and unsightly marks.
6.7
Doors, windows,
and glazing
This chapter gives guidance on meeting the Technical
Requirements for doors, windows, and glazing, including where
coupled door and window frame assemblies are contained within
a single storey. Coupled door and window frame assemblies
(including spandrel panels) which are:
z one storey or more in height, or
z not contained between a structural floor and ceiling
should be designed in accordance with Chapter 6.9 ‘Curtain
walling and cladding’.
This chapter does not provide guidance on compliance with
Building Regulations. Work shall comply with all relevant
Building Regulations covering:
z weathertightness z safety from impact
z thermal performance z ventilation
z fire safety z security.
6.7.1 Compliance 01
6.7.2 Provision of information 01
6.7.3 In-service performance 02
6.7.4 Coupled door and window
frame assemblies 04
6.7.5 Glazing 06
6.7.6 Security 08
6.7.7 Timber doors and windows 09
6.7.8 Non-timber doors and windows 10
6.7.9 Ironmongery 11
6.7.10 Material storage and protection 11
6.7.11 Installation 12
6.7.12 Completed work 13
For figure reference tables in this chapter, please go to the end of the chapter
1 Doors, windows and glazing I 2024
Chapter 6.7
For the purposes of this chapter the following terms and definitions apply:
Air and vapour Continuous layer of material with a high resistance to water vapour to control the movement of air and
control layer water vapour
Air barrier An air barrier controls air leakage into and out of the building envelope. For framed walls, this is usually in
the form of a membrane
Breather membrane Continuous layer of material with a low resistance to water vapour to allow vapour movement but
impermeable to water
Building envelope External wall or roof construction that separates the habitable parts of a building from the
external environment
Coupled door and A glazed wall formed by combining pre-assembled doors and (or) windows. The window frames may
window frame be supported directly by brackets fixed to the primary structure or may be supported by horizontal and
assemblies vertical framing members
Doors A complete door assembly, assembled on site or delivered as a complete assembly, consisting of the door
frame, door leaf or leaves, essential hardware and any integral side panel or fanlight
Fixings Component that is used to secure separate parts of a window or door to each other, to secure an item of
hardware to a window or door part, or to secure a completed window or door into the structure of
a building
Frames Outer frame, mullion, and transom components of doors and windows
Glazing Glass component of a door or window
Glazing material A material which provides a bedding for the glass and forms a joint between the glass and frame. The
term includes glazing compounds, sealants, putties, glazing strips and tapes, and gaskets
Impregnated foam Impregnated foam weatherproofing strip flexible, elastic, preformed material that constitutes a linear seal
tapes when compressed
Insulating glass unit Assembly consisting of at least two panes of glass, separated by one or more spacers, hermetically
IGU sealed along the periphery, mechanically stable and durable
Sealant Wet applied compound applied in an unformed state to a joint which seals it by adhering to appropriate
surfaces within the joint
Structural opening Opening in an external wall or roof into which a window or door is to be installed
System Company who designs, manufactures, and supplies a system
manufacturer
6.7
Thermal bridging Occurs when part of a thermal element has significantly higher heat transfer than the materials
surrounding it
Weathertightness Performance in respect of air permeability, watertightness, and resistance to windload
Window Building component or multiple components for closing an opening in a wall or roof that may admit light and/
or provide ventilation
Doors, windows and glazing shall comply with the Technical Requirements.
Doors, windows and glazing which comply with the guidance in this chapter will generally be acceptable.
Weathertightness
The following documents should show weathertightness performance classifications of doors and windows:
z CE/UKCA marking in accordance with BS EN 14351-1 z appropriate third-party product certification.
The performance classification levels should be appropriate for the site exposure conditions.
For doors and windows into low rise housing, the suitability of weathertightness performance classification levels for the site
exposure conditions may be determined according to the procedure in BS 6375-1.
Higher levels of performance should be specified for doors and windows into medium and high-rise buildings as remedial works
in the event of water leakage are likely to be more difficult. Windows in high rise buildings may also be exposed to higher levels
of wind driven rain.
The satisfactory weathertightness performance of doors and windows also depends on appropriate detailing of interfaces with
the surrounding building envelope. The interface between any window or door and its surround should be a robust detail that is
easy to understand at the construction stage. It should be evident how it should be constructed and should be easy to inspect
and/or test.
The head of frames should be set back from the edge of the lintel/cavity tray, and sills should project at least 25mm beyond the
wall face.
Where doors and windows are incorporated into structural openings of timber framed walls, breather membranes should be used
to provide a secondary water barrier to prevent entrapping water vapour and causing interstitial condensation within the wall.
Where accessible thresholds are required, the door should be protected from precipitation by a canopy, a drainage slot or
channel adjacent to the cill provided and a platform with a slope of between 1:60 and 1:40 to ensure water run-off.
6.7
In Scotland, Northern Ireland, and areas of very severe exposure, ‘check reveals’ should be used. The frame should be set back
behind the masonry outer leaf with a minimum 12mm overlap to the frame.
Notes
1. Many manufacturers supply doors and windows which exceed the recommended classifications in BS 6375-1, commonly class 9A (600Pa) for watertightness and
class 4 (600Pa) for air permeability. The use of doors and windows with higher levels of performance will reduce the risk of leakage.
2. Experience suggests that testing for watertightness at 25% of the design windload gives satisfactory performance provided that the installation is carried
out correctly.
Figure 1: Water bar and weatherboard to external doors Figure 2: Throating to window cill – cavity masonry wall
throating clear
wall face sealant
DPC turned up
at back and
ends of sill Sealant
Accommodating movement
Expansion and contraction of frames is to be expected due to temperature fluctuations. To prevent frames from distorting, a gap
around the perimeter of the frame and the structural opening should be provided.
The gap size depends on the frame material and the structural opening size and should be selected in accordance with Table 1.
The perimeter gap should be sealed with a suitable sealant which is able to resist water penetration and prevent air leakage
whilst accommodating differential movement between the structural opening and the frame.
For doors and windows incorporated into the structural openings of timber frame walls, opening, and closing gaps should
be provided around the frames in accordance with chapter 6.2 to allow for the thermal movement of frames and structural
movement of the timber frame.
Silicone sealants should be applied to a closed cell polyethylene foam backing strip to control the depth of the joint, force
the sealant against the sides of the joint during application and aid tooling of the sealant. The depth of sealant should be
at least 5mm.
For checked reveals, the sealant should form a fillet with an overlap of 6mm to the frame and 10mm to the brick outer leaf.
When impregnated foam tapes are used for perimeter sealing, over sealing with a wet sealant is not usually required.
Manufacturer instructions and product certifications should be followed.
Note
Further guidance on sealants is provided in the following standards:
z BS 6093 Design of joints and jointing in building construction - Guide
z BS 6213 Guide to selection of construction sealants
z BS EN ISO 11600 Building construction – jointing products – classification and requirements for sealants.
Durability
Subject to appropriate maintenance, doors and windows should have a minimum service life of 40 years. Component parts such
as operating handles, gaskets and locking mechanisms may need replacing within the service life.
6.7
a) system design d) movement accommodation
b) weathertightness e) thermal performance
c) structural integrity f) site testing for watertightness.
System design
Coupled door and window frame assemblies should be supplied as a standard system comprising only of components designed
and detailed by the system manufacturer.
Weathertightness
Jointing details should be designed on the principle of two lines of defence with flexible inner and outer seals. The cavity
between the seals should be drained to remove any water that bypasses the outer seals.
Weathertightness of coupling joints may be adversely affected by deflections under windload. Weathertightness of coupling joints
should be demonstrated by appropriate laboratory testing of an assembly.
Testing should be undertaken by a UKAS accredited test laboratory. During testing, there should be no leakage onto the internal
face of the system at any time.
On completion of the test there should be no standing water in locations intended to remain dry. Any remedial modifications to
the system that are made to pass the test should be reported and incorporated into the installed system.
To avoid difficulty in interpreting the results it is good practice to agree which materials and zones within the system may be
allowed to get wet.
Alternative jointing details should not be used unless they have been proven by testing. The interface between the assembly
and the surrounding building envelope should be a robust detail that is easy to understand at the construction stage. It should be
evident how the coupling and interface details are to be constructed and should be easy to inspect and/or test.
5 Doors, windows and glazing I 2024
Chapter 6.7
Structural integrity
Coupled door and window frame assemblies should be designed as an engineered system to support their self-weight, resist and
safely transfer imposed loads back to the supporting structure.
Windows tested and classified to BS EN 14351-1 are subjected to wind load tests, however, as the perimeter of the window is
supported by the test box, the response of the perimeter frame to wind load will not have been fully assessed.
The perimeter frame of the window used in an assembly needs to be able to resist the wind load in bending or the joining
component needs to provide support and contribute to the overall stiffness of the system in resisting deflection arising from wind
pressure and other loadings including accidental impact.
For window assemblies, it is recommended that the main structural members of the assembly satisfy class B for which the
allowable deflection is span/200 under the design wind load in both positive and negative directions. This is the limit which
applies for curtain wall mullions in BS EN 13830.
Movement accommodation
As window assemblies are larger than individual windows, the amount of movement to be accommodated is also likely to greater.
Coupling joints and interfaces with the surrounding construction should be designed to accommodate thermal expansion/
contraction of the frames and movement of the structure, whilst remaining weathertight.
Thermal bridging
Coupling joints, brackets, and fixings may create additional heat flow paths resulting in low surface temperatures, increasing the
risk of surface condensation.
Coupling joints and interfaces with the supporting structure should be designed to minimise the effects of thermal bridging and
risk of condensation including the appropriate use of thermal breaks.
The thermal assessments of linear coupling joints and interfaces with the supporting structure should be checked to assess the
risk of surface condensation.
The assessments should confirm that, under normal operating conditions, condensation does not form on the visible interior
surfaces of any framing members or glazing.
6.7
6.7.5 Glazing
The method of glazing shall ensure adequate in-service performance. Issues to be considered include:
a) standards d) glazing systems
b) performance requirements e) condition before installation
c) insulating glass units f) site glazing.
Standards
Glazing and materials should conform to relevant British Standards as shown in Table 2.
Performance requirements
Glazing should be selected to meet applicable design and performance requirements in accordance with BS 6262-1.
The type, thickness and size of glass should be selected to provide an appropriate degree of safety, considering the intended use.
Safety glass for use in critical locations (including glazed shower/bath screens) should be marked as follows:
6.7
Note
Further guidance on safety marking of glass is provided in technical guidance note TGN 6.7/17.
The design loads acting upon the glazed area should be determined in accordance with BS EN 1991-1-1, BS EN 1991-1-3 and
BS EN 1991-1-4. The type, thickness and size of glass should be specified to suit the design wind loads.
To improve thermal performance and minimise condensation formation around the perimeter zone of glass, glazed units with
spacer bars of low thermal conductivity should be specified.
Glazing systems
Drained and vented systems
Drained and vented systems should be used for site fixed insulating glass units (IGUs) and where units greater than 1m2 are
used. These systems allow moisture that enters the glazing channel between the frame and the edge seal of the insulating glass
unit to drain away and prevent long-term moisture contact with the edge seal.
To achieve the optimum service life of IGUs, the following basic principles should be adopted in the design of drained
and vented systems:
z Removal of moisture: Frames should have adequate drainage and ventilation through holes, slots, or channels for the rapid
removal of any water that may enter the glazing rebate
z Clearance: A minimum 5mm edge clearance should be provided between the glass edge and frame to prevent frame-to-
glass contact, ensure drainage, and allow for differential thermal expansion of the IGU and frame. For very well drained and
ventilated frames, the clearance can be reduced for the side and top rebates, to a minimum of 3mm in the case of glass
lengths up to 2m
z Edge cover: A minimum edge cover of 12mm should be provided to keep the spacer below the sight line and to protect the
edge seal from sunlight
z Rebates: The rebate height should allow for tolerances in both the frame size and IGU size to ensure the minimum edge
clearance and minimum edge cover requirements are met. The width of the rebate platform should provide the required
front, back clearances, and ensure sufficient contact of the glazing beads onto the platform. The width of the rebate platform
should be equal to the sum of the front and back clearances, the nominal thickness of the IGU, the width of the bead, and an
allowance for the tolerances on IGU and bead thicknesses
z Beads: Beads should have an installed height equal to the rebate height. Timber beads for timber frames should have a width
in contact with the rebate platform greater than the height, to enable firm fixing of the bead to be achieved. The bottom bead
should project slightly past the rebate edge. Screw fixings for timber beads should be located a minimum of 75mm from each
corner and spaced at no more than 200mm centres. If pins are used, they should be twice the height of the beads and located
a minimum of 50mm from each corner and spaced at no more than 150mm centres. Beads for metal and plastic frames
should be fixed in accordance with manufacturers recommendations to securely retain the IGU and the glazing seals
z Compatibility: Glazing material should be compatible with frame finishes and glazing unit seals in accordance with
manufacturers recommendations. Linseed oil-based putty should not be used in the installation of laminated glass or
insulating glass units.
6.7
A visual inspection of glass and insulating glass units should be undertaken for signs of defects which could lead to premature
failure. Signs of defects include.
z water accumulation between sheets z edge damage or scratching.
2024 I Doors, windows and glazing 8
Chapter 6.7
Site glazing
Site glazing should be in accordance with the frame design and undertaken by installers who are appropriately trained and
conversant with good glazing practice.
The following features should be checked before glazing:
z drainage and ventilation holes or slots are present, are z a minimum 5mm edge clearance is provided around the
of a suitable size, and are free from obstructions such as permitter of the insulating glass unit to prevent glass to
fabrication swarf, etc frame contact, to ensure drainage and allow for differential
z ventilation and the free flow of water to holes and slots are thermal expansion
not impeded by setting and location blocks, external bead z gaskets or strip materials supplied cut to size are the correct
retention lips, or glazing materials length to ensure that there are no gaps at the corners.
z as water can be present in the glazing rebate, screw fixing
holes and frame joints are adequately sealed against
water ingress
Note
Further guidance on system design and glazing considerations for insulating glass units is provided by the Glass and Glazing Federation.
6.7.6 Security
Doors, door frames, windows and locks shall be designed and specified to improve their resistance to
unauthorised entry. Issues to be considered include:
a) locking functionality of main entrance doors e) glazing
b) locking functionality of secondary access doors f) framed wall constructions
c) opening limitation device g) door and frame connections
d) view outside h) windows.
6.7
z has at least one thousand differs z has a hardened steel bolt, or inserts, to prevent sawing
z if burst open, would not pull out without breaking the door or z has a latch and deadlocking facility.
its frame
Locking devices fitted to main entrance doors should permit emergency egress without the use of a key when the home
is occupied.
Homes opening directly to the outside without an alternative means of escape via a door
z the door should be held closed on a latch z deadlocking should be operated by a key externally and
a handle or thumb turn internally (BS 8621 locks and PAS
8621 multi point locks meet these requirements).
View outside
There should be a means of giving a wide-angle view of the area immediately outside the main entrance door of individual
homes. Acceptable methods include:
z a through-door viewer z closed-circuit camera and displays (not connected to a TV).
z clear glazing either to part of the door or a
convenient window
6.7
Glazing
Any glazing which, if broken, would permit release of the internal handle or thumb turn by hand or arm entry should be laminated.
Windows
Opening lights on ground floor windows and others which are readily accessible from the outside may be fitted with lockable
devices which cannot be released without a key.
6.7.7 Timber doors and windows Also see: Chapter 3.3 and 9.5
Timber and wood-based materials shall be of suitable quality and be naturally durable or suitably treated.
Issues to be considered include:
a) quality assurance c) drying shrinkage
b) classification and use d) preparation and finish.
Quality assurance
Manufacturers of timber doors and windows should hold appropriate third-party certification to assure the fitness for purpose and
quality of their products.
2024 I Doors, windows and glazing 10
Chapter 6.7
In England, Wales, Northern Ireland, and the Isle of Man, planted stops are not permitted on frames to external doors.
External doors should be 42.5mm minimum (44mm nominal) in thickness.
Drying shrinkage
To minimise drying shrinkage, the moisture content of joinery, when fixed, should not exceed the value given in Table 4.
Note
On delivery, the moisture content should be within +/-2% of the values specified.
6.7
Preparation and finish
The following elements of timber doors and windows should be of naturally durable timber or timber pre-treated against fungal decay:
z external door frames z timber surrounds to metal windows
z windows z external doors, other than flush doors.
z to be painted, it should be primed before fixing z to be stained, it should have the first coat applied before
delivery to site.
Compatibility between preservative treatment or primer, with glazing compounds, sealants, and finishes, should be checked with
the relevant manufacturers.
Prefabricated items should conform with the relevant parts of BS 1186: Part 2, including:
z the fit and construction of joints and moving parts z gluing and laminating
z the construction of finger joints z surface finishes.
Quality assurance
Manufacturers of non-timber doors and windows should hold appropriate third-party certification to assure the fitness for purpose
and quality of their products.
11 Doors, windows and glazing I 2024
Chapter 6.7
Standards
Non-timber doors and windows should conform to relevant standards as shown in Table 5.
6.7.9 Ironmongery
Ironmongery shall be suitable for the intended use.
Ironmongery should be provided in accordance with the design. Materials used for critical functions should comply with the
appropriate standards given in Table 6:
Table 6: Relevant British standards for ironmongery
Standard/ Specification Number Standard/ Specification Name
BS EN 1935 Building hardware. Single-axis hinges. Requirements and test methods
BS 3621 Multipoint locking assemblies Keyed egress
BS 8621 Multipoint locking assemblies’ Keyless egress
BS 10621 Multipoint locking assemblies’ Dual mode egress
BS EN 1906 Building hardware. Lever handles and knob furniture. Requirements and test methods
6.7
BS EN 12209 Building hardware. Locks and latches. Mechanically operated locks, latches and locking
plates. Requirements and test methods
BS EN 1154 Building hardware. Controlled door closing devices. Requirements and test methods
Where doors to rooms containing a bath or WC have a securing device, it should be of a type capable of being opened from the
outside in an emergency.
In sheltered accommodation, additional special provisions may be needed for all door locks, limiters, and other fasteners, to
enable wardens to gain access when necessary.
Storage
Where joinery is stored on site, precautions should include:
z avoiding wetting during unloading z storing internal joinery in a weather protected condition.
z stacking external joinery on bearers off the ground and
covering with waterproof material
2024 I Doors, windows and glazing 12
Chapter 6.7
Cut ends
Where pre-treated joinery is cut or adjusted on site, Figure 5: Treatment of cut ends
the affected surfaces should be retreated with
appropriate preservative in accordance with the
manufacturer’s recommendations.
6.7.11 Installation
Doors and windows shall be correctly located and securely fixed. Issues to be considered include:
a) construction tolerances e) door hinges
b) workmanship and fixing f) window boards
c) hanging doors and opening lights g) bay windows.
d) general ironmongery
Construction tolerances
Construction tolerances for structural openings, doors, and windows should be in accordance with chapter 9.1 A consistent
approach to finishes.
6.7
z corner fixings should be between 150mm and 250mm from z there should be a minimum of two fixings on each jamb and
the external corner sill, with intermediate fixings at centres no greater than
z fixings should be a minimum of 150 mm from the centre line 600 mm.
of a mullion or transom
Notes
1. The number and spacing of fixings at the head depend upon the frame width and frame material.
2. The manufacturer’s instructions should be followed.
Where a standard flush door is reduced in height, the bottom rail should be replaced where necessary.
13 Doors, windows and glazing I 2024
Chapter 6.7
General ironmongery
Hinges and other ironmongery should be:
z housed neatly and flush with the surface z supplied with a full set of matching screws.
Locks should:
z turn easily z have keyholes which are properly aligned.
z not be fitted in mortises too tightly
Door hinges
To reduce twisting, doors should be hung on hinges in accordance with Table 7.
Window boards
Window boards should:
z have a flat and level top surface z be of a moisture resistant grade where MDF is used.
z be fixed close to the frame and adequately secured against
twisting and other movement, particularly any back slope
towards the frame
Bay windows
Bay windows should be:
6.7
z adequately supported and secured to the structure to z properly linked to DPCs at reveals.
prevent sagging or twisting
6.8
Fireplaces, chimneys
and flues
This chapter gives guidance on meeting the Technical
Requirements for fireplaces, chimneys and flues.
6.8.1 Compliance 01
6.8.2 Provision of information 02
6.8.3 Solid fuel – fireplaces and hearths 02
6.8.4 Solid fuel – combustion air 03
6.8.5 Solid fuel – flue pipes 03
6.8.6 Solid fuel – chimneys 04
6.8.7 Solid fuel – outlets and terminals 05
6.8.8 Gas – fireplaces and hearths 06
6.8.9 Gas – combustion air 07
6.8.10 Gas – flue pipes 07
6.8.11 Gas – chimneys 08
6.8.12 Gas – outlets and terminals 10
6.8.13 Oil – fireplaces and hearths 11
6.8.14 Oil – combustion air 12
6.8.15 Oil – flue pipes 12
6.8.16 Oil – chimneys 12
6.8.17 Oil – outlets and terminals 13
6.8.18 All – fireplaces and hearths 14
6.8.19 All – fireplace surrounds 14
6.8.20 All – flue pipes 15
6.8.21 All – flue liners 15
6.8.22 All – flues 16
6.8.23 All – chimneys 17
6.8.24 Masonry 19
6.8.25 Mortar 19
6.8.26 DPC 19
6.8.27 Flashings 19
6.8.28 Terminals 20
6.8.29 Flue testing 21
6.8.30 Further information 21
1 Fireplaces, chimneys and flues I 2024
Chapter 6.8
Introduction
In this chapter, the following terms are used:
ridge terminal flue and chimney terminal flue and chimney terminal
flue lining
roof space
first floor
gas appliance
flue pipe
free standing
solid fuel open hearth
appliance
6.8
party wall
Fireplaces, chimneys and flues shall comply with the Technical Requirements, working fireplaces shall
be designed to ensure efficient operation of the appliance, an adequate supply of combustion air and
protection for the building fabric. False chimneys ie, GRP shall comply with R3 and passed satisfactory
assessment by an appropriate independent technical approvals authority accepted by NHBC.
Fireplaces, chimneys and flues which comply with the guidance in this chapter will generally be acceptable.
Installations should be provided with an adequate supply of combustion air:
z as stipulated by statutory requirements and z where a fixed combustion appliance is provided, appropriate
building regulations provisions shall be made to detect and give warning to the
z to ensure satisfactory combustion of fuel and the efficient release of carbon monoxide.
working of flues and chimneys
Where a chimney or flue is provided:
z it should be continuous from the hearth or appliance to the z a notice plate containing safety information about any
outside air hearths and flues should be securely fixed in an unobtrusive
but obvious position within the home.
The design of homes which incorporate chimneys and flues should ensure that all details of the associated elements are
considered and appropriate provisions made. This should include the following:
z fire risk and separation z terminals and outlets
z hearths and the constructions adjacent to hearths z limitations on the appliance or open fire which can
and flues be installed, and fuel which can be used.
z chimneys and flues, including projections through
the building
2024 I Fireplaces, chimneys and flues 2
Chapter 6.8
Good workmanship and effective supervision during construction are essential to ensure that fireplaces, chimneys and flues
function correctly in use.
Fireplaces, chimneys and flues should be designed and installed to minimise the risk of the building catching fire. The design of
timber frame construction should ensure that combustible material is:
z suitably separated from heat sources, or z shielded, where permitted.
6.8
Constructional hearths should be: 150mm min.
plan view
z provided for open fires or closed combustion appliances in
150mm
accordance with Building Regulations and the min.
manufacturer’s recommendations
z a minimum of 840mm in any direction for
freestanding appliances
z the adjacent diagram shows the minimum dimensions from
the appliance to the edge of the hearth.
225mm min.
300mm for closed
min.* appliances
300mm
min.
1.2m
min
t
150mm 150mm
min. x
min.
hearth
appliance
75mm min. solid non-combustible material
t = thickness of solid non-combustible material as follows:
x less than 50mm = t (200mm min.)
x more than 50mm = t (75mm min.)
England, Wales and the Isle of 50% of throat area(1) If design air permeability is less than 5.0m3/h,
Man then 300mm2/kW for first 5kW of appliance is the
rated output and 850mm2/kW for the balance of
appliance rated output.
If design air permeability is greater than 5.0m3/h
then 850mm2/kW of appliance is the rated output
Scotland For fireplaces up to 450mm wide Above 5kW rating, 550mm2/kW
(measured between fire bricks), 1500mm2.
For fireplaces wider than 450mm,
manufacturer’s details should be followed
Northern Ireland 50% of throat area(1) Up to 6kW rating, 550mm2.
Over 6kW, add 550mm2 for each kW above 6kW
Notes
1 Where the fire has a canopy, the open air vents should be 50% of the flue area.
1.5xD
3xD
non-combustible
shield
non-combustible
1.5xD shield
D
min.
D 4xD
1.5xD
flue pipe
flue pipe
requirement in Northern Ireland
requirement elsewhere
(D = external diameter of the flue pipe)
6.8
b) flue liners d) resistance to weather.
Flue liners
Flue liners should:
z have rebated or socketed joints installed with the socket or z be reasonably smooth on the inside
internal rebate facing uppermost z be correctly jointed with mortar (the space between the
z be installed in accordance with the manufacturer’s liners and the brickwork should be filled with weak insulating
recommendations concrete unless the manufacturer recommends
z be non-combustible an alternative)
z be properly jointed at their junctions with the starter block, z have any changes in direction formed using purpose-made
or lintel, and the outlet terminal bends (cut pipes are not acceptable).
Where external chimneys built with clay bricks of F2,S1 designation are rendered, sulfate-resistant cement should be used.
In Scotland, external facing brickwork should be constructed using frost-resistant bricks.
Resistance to weather
In areas of severe or very severe exposure, cavities should be continuous up to roof level. This applies to:
z cavities below roof level where the stack forms part of an z the complete chimney structure, including the
external cavity wall fireplace recess.
In areas of severe or very severe exposure, and where the chimney breast is gathered in, the lower projecting masonry should
be protected against damp penetration with a suitable capping and cavity trays (see Clause 6.8.28b).
Above the roof:
z chimney DPCs should link with flashings; where the roof is z face brickwork should not have recessed joints
steeply pitched (where the difference in level between the z where lead trays are in contact with mortar, they should be
6.8
lower and higher intersection of the chimney with the roof protected with a thick coat of bitumen or bitumen paint
will be more than 450mm) two DPCs should be used at z where chimneys are to be rendered, render should be in
suitable levels accordance with Chapter 6.11 ‘Render’.
z plastic DPCs are not suitable
Outlet position
The flue will generally function more effectively where the A B C D
outlet is in a low pressure zone, taking account of
prevailing winds.
A low pressure zone generally occurs:
z on the lee side and at the ridge of a pitched roof
z close to the windward side of a flat roof.
Terminals
Terminals should be:
z purpose-made components z sealed to the flue liner.
z built into the top of the masonry to a minimum of 125mm or
0.25x the length of the terminal, whichever is the greater
An acceptable terminal can be achieved where the top flue liner projects a minimum of 20mm above the chimney capping.
Chimney cappings
Chimney cappings should:
z be weathered, monolithic slabs
z be designed to protect the masonry below purpose-made
chimney
z project a minimum of 50mm, and have a drip 30mm from cappings
6.8
the face to shed water clear of the masonry. min.
50mm
min.
30mm
flue outlet.
Brick chimneys which do not have this type of capping should
be constructed using frost-resistant masonry.
Back boilers
Hearths for back boilers should be constructed of solid non-combustible materials, a minimum of:
z 125mm thick, or z 25mm thick and placed on non-combustible supports which
are a minimum of 25mm high.
Other gas appliances plan view 150mm min.
Hearths for other types of appliance should be constructed of
non-combustible materials which: 150mm
min
z are a minimum of 12mm thick
z comply with the plan dimensions for back boilers.
appliance
In some cases, the provision of a hearth is not required,
eg where the flame or incandescent material is at least 225mm
above the floor.
For all forms of gas appliances the hearths should be marked
front of 225mm min.
at the edges to: appliance from front
of appliance
z provide a warning to the home owner
hearth for back boiler
z discourage combustible floor finishes, such as carpet,
from being laid too close to the appliance (this can be
achieved by introducing a change in level).
1.8m max.
6.8
Flues and flue liners
Flue blocks for use with gas appliances should comply with BS EN 1858 (Concrete) or BS EN 1806 (Clay).
Table 4: Gas flue sizes
Serving Minimum flue size
Non fan-assisted Gas fire Either:
individually flued gas z a circular flue with a minimum 12000mm2 cross-sectional area
burning appliances up (125mm diameter), or
to 70kW input, excluding z a rectangular flue with a minimum 16,500mm2 cross-sectional
balanced flue area and a minimum dimension of 90mm.
Any other z at least the cross-sectional area of the outlet from
the appliance.
Inset live or decorative Open fire within a fireplace z either a circular or rectangular flue with a minimum dimension
gas fuel effect appliances opening up to 500mm x 550mm of 175mm.
Rigid flue liners should comply with BS EN 1856 or be as described in Clause 6.8.6. Flexible flue liners are not acceptable in a
new build.
Chimneys
Chimneys for gas appliances must not incorporate an adjustable draught control.
Masonry chimneys
Flues within masonry chimneys should be in accordance with the requirements relevant to flues for solid fuel appliances
(see Clause 6.8.6b).
Brickwork or blockwork chimneys for gas appliances should, at minimum, have the same level of fire resistance as each
compartment wall or floor which it forms part of, or passes through. The compartment wall may form the chimney wall where it is
a masonry material.
9 Fireplaces, chimneys and flues I 2024
Chapter 6.8
Gas flue blocks are at least 140mm wide. Where this is wider
than the wall leaf: ridge tile adaptor
6.8
vertical DPM
6.8
D Below gutters, soil pipes or drain pipes 300 75 (3)
75
E Below eaves 300 200 (3)
200
F Below a balcony or car port roof 600 200 (3)
200
G From a vertical drainpipe or soil pipe 300 150 (4) (3)
150
H From an internal or external corner, or to a 600 300 (3)
200
boundary alongside the terminal(2)
I Above ground, roof or balcony level 300 300 (3)
300
J From a surface or a boundary facing the 600 600 (3)
600
terminal(2)
K From a terminal facing the terminal 600 1200 (3)
1200
L From an opening in the car port into the 1200 1200 (3)
1200
building
M Vertically from a terminal on the same wall 1500 1500 (3)
1500
N Horizontally from a terminal on the same wall 300 300 (3)
300
P From a structure on the roof N/A N/A 1500 (for a ridge terminal) N/A
2000 (for any other
terminal, as given in BS
5440-1)
Q Above the highest point of intersection with N/A Site in accordance Site in accordance with 150
the roof with manufacturer’s BS 5440-1
instructions
Notes
1 An opening here means an openable element, such as an openable window, or a fixed opening, such as an air vent. However, in addition, the outlet should not
be nearer than 150mm (fanned draught) or 300mm (natural draught) to an opening into the building fabric formed for the purpose of accommodating a built-in
element, such as a window frame.
2 Boundary as defined in paragraph 0.4. of Approved Document J: smaller separations to the boundary may be acceptable for appliances that have been shown to
operate safely with such separations from surfaces adjacent to, or opposite, the flue outlet.
3 Should not be used.
4 This dimension may be reduced to 75mm for appliances of up to 5kW input (net).
11 Fireplaces, chimneys and flues I 2024
Chapter 6.8
Where a flue outlet is not serving a balanced flue appliance, it should be:
z situated at roof level, so that air can pass freely across it z fitted with a flue terminal where the flue diameter is less
at all times than 170mm (larger diameter flues should be fitted with a
z a minimum of 600mm from openings terminal where required by Building Regulations).
600mm P
600mm
Q
Q
Q 2000mm
D,E
N
B
I
M
C
boundary
F A
J H H
K
H L I
G
Precautions should be taken, where appropriate, to prevent damp penetration in accordance with the requirements for resistance
to frost attack and weathering for solid fuel appliances (see Clause 6.8.6).
All flues which bridge the cavity of an external wall should have a means of preventing moisture crossing the cavity,
eg a moisture drip collar set in the centre of the cavity. For timber frame construction the guidance in IGE/UP/7 should be
adopted in relation to non combustible sleeving and to maintain the integrity of the vapour control layer.
6.8
Where cavity trays and weepholes are used they should be in line with chapter 6.1.
appliance appliance
6.8
z have a free area which is at least the same size as the z where possible, be vertical (where this cannot be achieved,
outlet of the appliance there should be no more than two bends, which should not
be more than 45° from vertical).
Factory-made insulated chimneys should:
z be designed in accordance with BS EN 1856 and BS EN z have a minimum operating life of 30 years
1859 and installed in accordance with BS EN 15287, or be z where they are part of a component system, comply with
assessed in accordance with Technical Requirement R3 BS EN 1856 and installed in accordance with BS 5440.
Flue liners
As for gas flue pipes where the flue gases are unlikely to exceed a temperature of 250°C (see Clause 6.8.10). As for solid fuel
flue pipes where the flue gases are likely to exceed a temperature of 250°C or the temperature is not known (see Clause 6.8.5).
Flexible flue liners are not acceptable for new build.
Resistance to weather
Resistance to weather as for solid fuel (see Clause 6.8.6).
100mm
min.
50mm min.
internal wall
external wall
6.8
vermiculite
concrete
approx.
1.1m
690mm-840mm 350mm
690mm-840mm 350mm
appliance recess with raft lintel: fire place recess for inset open fire (without boiler unit)
suitable for free-standing room heater
Fixings should be of durable material and be appropriate for the type of surround and the supporting wall or floor to which the
surround is to be fixed. Fixings should generally be of stainless steel to BS EN ISO 3506 ‘Mechanical properties of
corrosion-resistant stainless steel fasteners’ and be specified to provide suitable strength and durability. Materials that
comply with recognised standards which provide equal or better performance are also acceptable.
Methods that rely solely on adhesive for fixing fireplace surrounds to the structure are not acceptable.
More information on the installation of all types of natural and artificial stone fireplace surrounds can be found in the Stone
Federation Great Britain ‘Fireplace Surrounds’ data sheet (www.stonefed.org.uk).
reinforced concrete
raft lintel
non-combustible rope
fireplace surround
clamping ring
are specified, they should be fitted in accordance with the manufacturer’s instructions.
Flue pipes should be jointed in accordance with the manufacturer’s instructions, fixed socket up and correctly aligned.
Table 9: Acceptable standards for flue pipes
Flue material Guidance
Flue pipes for gas appliances BS EN 1856
Cast iron flue pipes BS EN 1856
Mild steel flue pipes BS 1449 (minimum 3mm wall thickness)
Stainless steel flue pipes BS EN 10088 (minimum 1mm thick) and be one of the
following grades: 1.4401, 1.4404, 1.4432 or 1.4436
Vitreous enamelled flue pipes BS EN 1856, low carbon steel coated internally and externally with acid-resisting enamel
bend
Liners suitable for solid fuel appliances, and generally suitable for other fuels, include liners whose performance is at least equal
to the designation T450 N2 S D 3, as described in BS EN 1443, such as:
z clay flue liners with rebates or sockets for jointing meeting z other products that are independently assessed in
the requirements for class A1 N2 or class A1 N1 as accordance with Technical Requirement R3.
described in BS EN 1457
z concrete flue liners meeting the requirements for the
classification type A1, type A2, type B1 or type B2 as
described in prEN 1857(e18) January 2001, or
Alternatively, imperforate clay pipes with sockets for jointing as described in BS 65:1991 are acceptable.
Joints should be made in accordance with the manufacturer’s recommendations, generally using:
z fire cement, or z refractory mortar.
Joints should be fully filled, and surplus material cleared from the inside of each joint as the flue is built.
Spaces between the lining and the surrounding masonry should be:
z filled with weak insulating concrete, or z in accordance with the manufacturer’s recommendations,
with the specified material providing adequate protection.
Ordinary concrete should not be used to fill the space between the lining and the surrounding masonry.
Suitable mixtures for weak insulating concrete include:
z one part ordinary Portland cement to 20 parts suitable z one part ordinary Portland cement to 10 parts perlite.
lightweight expanded clay aggregate, minimally wetted
6.8
z one part ordinary Portland cement to six parts
vermiculite, or
This does not apply to a floorboard, skirting, dado or picture rail, mantel shelf or architrave.
Twin wall flue systems should comply with:
z BS EN 1856, or z be assessed in accordance with
Technical Requirement R3.
17 Fireplaces, chimneys and flues I 2024
Chapter 6.8
Construction of chimneys
Masonry chimneys should be properly bonded to, or supported by, the adjoining walls of the building.
Foundations to a chimney should:
z be the same depth as adjacent wall foundations z where the chimney forms part of the wall, be a minimum of
z be designed to avoid uneven settlement 100mm wider than the chimney base.
W W
Chimneys which:
z are of block, brick or stone should have a minimum wall z form part of a compartment wall, and are not back to back
thickness of 100mm, excluding the lining thickness with an adjacent chimney, should have a minimum wall
z are built in a cavity separating wall should form two leaves, thickness of 200mm separating it from the other building
each a minimum of 100mm, between the flue and or home.
adjoining building
Factory-made insulated chimneys should be assembled, erected, anchored and protected in accordance with the
6.8
manufacturer’s instructions.
Masonry for chimneys:
z below roof level may be constructed using the same bricks z should be frost resistant above the roof unless protected
and mortar as used for the general brickwork by a capping projecting by a minimum of 50mm
z constructed with hollow or cellular blocks should be suitable (in Scotland, frost-resistant bricks should be used for all
for the construction of chimneys and filled with concrete as facing brickwork).
the work proceeds
Connections between flue blocks and ridge terminals should be made:
z as detailed in the design z using the correct fittings and supports as specified by
the manufacturers of the flue blocks, flue pipe and
ridge terminal.
100mm
min. plan of chimney at upper floor level
plan of recess
2024 I Fireplaces, chimneys and flues 18
Chapter 6.8
Timber chimney frame construction External chimney breast with masonry inner leaf
40mm min. air space where
chimney is less than 200mm
cavity maintained
around chimney
with cavity wall hearth min.
ties as required 125mm thick
joists on hangers
In Scotland, joists, etc. should be min. 200mm from the inner surface
of the flue; brickwork or blockwork in chimney construction should
be min. 100mm thick with a min. density of 1 600 kg/m3; for brick capping see Detail B
aircrete blocks should be min. 150mm thick.
6.8
cavity
cavity tray
prefabricated
throating
see Detail A
Other alternatives may be suitable, provided they meet the appropriate performance standards.
cover flashing
saddle overlapping back
flashing gutter flashing
stepped flashing
turned in at joints one-piece tray
(min. 25mm) turned down on
cover flashing DPC tray four sides
overlapping back turned up at stepped side
gutter flashing two sides flashing
DPC tray at front
apron level
turned up apron
at three sides flashing
chimney stack at ridge
6.8.24 Masonry
Masonry shall be capable of supporting intended loads and have appropriate resistance to the adverse
effects of frost and sulfates.
Masonry, including bricks, blocks, stone for masonry and reconstructed stone, should:
z be in accordance with BS 6461 or BS EN 15287-1 and z where blocks are used, have a minimum block density of
BS EN 771 1500 kg/m3 unless designed by an engineer in accordance
z where clay bricks are used in external chimney stacks, with Technical Requirement R5.
be of durability rating F2,S1 (as described in BS EN 771) or
6.8
In Scotland:
z frost-resistant bricks should be used for all external z where 100mm blocks are used for chimney construction,
facing brickwork they should have a minimum density of 1,500 kg/m3.
Mortar shall be batched and mixed to achieve adequate strength and durability.
Mortar should be in accordance with Chapter 6.1 ‘External masonry walls’, and include sulfate-resisting cement where flue gases
are liable to affect the masonry, eg above roof level.
6.8.26 DPC
Materials for damp proofing shall adequately resist the passage of moisture into the building.
The following are acceptable for use as DPCs:
z bitumen to BS 6398 z proprietary materials assessed in accordance with
z polyethylene to BS 6515 (not to be used in the chimney Technical Requirement R3.
stack above roof level)
6.8.27 Flashings
Flashings and trays shall be capable of adequately resisting the entry of moisture into the building.
Suitable materials for flashings and trays include:
z milled sheet lead (minimum code 4) to BS EN 12588 z proprietary materials assessed in accordance with Technical
z zinc alloy complying to BS EN 988 and 0.6mm thick Requirement R3.
2024 I Fireplaces, chimneys and flues 20
Chapter 6.8
6.8.28 Terminals
Flue terminals shall be suitable for their purpose and assist the functioning of the flue. Issues to be taken
into account include:
a) draught improvement b) chimney capping.
Relevant standards for flue terminals
BS EN 13502 ‘Chimneys. Requirements and test methods for clay/ceramic flue terminals’.
BS EN 1858 ‘Chimneys. Components. Concrete flue blocks.’
BS EN 1856 ‘Chimneys. Requirements for metal chimneys’.
flaunching
purpose-made
chimney cappings
freeze-/thaw-
min. min. resistant
50mm 30mm (F2,S1) bricks
chimney pot
chimney details with brick capping
6.8
The terminal of a masonry flue should be jointed to the flue lining with cement mortar to form a seal.
Draught improvement
Where downdraughts may occur, terminals designed to increase updraught should be fitted. However, a terminal will not
overcome problems caused by high pressure zones. Where relevant, the Solid Fuel Association or other authoritative body
should be consulted.
Chimney capping
Where a chimney is to be capped:
z a single unjointed concrete or stone capping should be used z the slab should project 50mm beyond the sides of the
z it should project and be throated to cast water away from chimney, and the withes between flues should be carried to
the face of the chimney the underside of the slab.
Decorative brick cappings should be carefully constructed to avoid rain penetration and frost damage. The use of frost-resistant
bricks may be required.
In Scotland, bricks used for facing brickwork should be frost-resistant.
21 Fireplaces, chimneys and flues I 2024
Chapter 6.8
6.9
Curtain walling
and cladding
This chapter gives guidance on meeting the Technical
Requirements for curtain walling and cladding.
6.9.1 Compliance 03
6.9.2 Provision of information 03
6.9.3 Certification 03
6.9.4 Loads 03
6.9.5 Support and fixings 04
6.9.6 Durability 05
6.9.7 Interfaces 05
6.9.8 Insulation 05
6.9.9 Damp proofing and vapour control 06
6.9.10 Installation and tolerances 07
6.9.11 Electrical continuity and
earth bonding 07
6.9.12 Maintenance 07
6.9.13 Glazing, gaskets and sealants 08
6.9.14 Cavity barriers and firestops 08
6.9.15 Ventilation screens 08
6.9.16 Handling and storage 08
6.9.17 Curtain walling 09
6.9.18 Rainscreen cladding 11
6.9.19 Insulated render and brick
slip cladding 13
1 Curtain walling and cladding I 2024
Chapter 6.9
Introduction
This chapter gives guidance on the forms of curtain walling and cladding acceptable to NHBC. Curtain walling and
cladding systems that do not conform to the descriptions in this chapter will not generally be acceptable.
Conservatories are not covered by this chapter.
Guidance on the use of other types of cladding, including brickwork, rendered masonry, vertical tile and slate cladding
and timber cladding, is given in Chapter 6.1 ‘External masonry walls’ and Chapter 6.2 ‘External timber framed walls’.
Curtain walling
Comprising a prefabricated or site assembled support 3D
framework with infill panels and/or wall sections with glazing
systems which include:
z structural silicone glazing
z mechanically fixed structural glazing
z slope glazing, excluding patent glazing
z coupled door and window frame assemblies
(including spandrel panels) which are one storey or more
in height, or not contained between a floor and ceiling.
Rainscreen cladding
Comprising: 3D
z an outer skin of panels which have unsealed, open, baffled
or labyrinth (rebated) joints
z a minimum 50mm pressure equalised air gap between the
insulation and the panels
z an insulated and airtight backing wall.
6.9
Insulated render
Comprising insulated render systems fixed to a backing wall. 3D
6.9
In-service The manner or quality of functioning of a material, product or system
performance
Insulated render A cladding system applied externally to an insulating layer which is fixed to a backing wall
system
Interstitial Condensation caused by vapour from within the building condensing on colder surfaces within the
condensation wall construction, often occurring due to a cold bridge
Negative pressure Where the air pressure on the internal face of the system is greater than that on the external face
Positive pressure Where the air pressure on the external face of the system is greater than that on the internal face
Primary components Components and parts of the system that are not easily replaceable. These may include:
z cladding panels z insulation
z fixings z vapour control layers
z framing z weathering components.
Pressure equalisation The creation of an air cushion within the cavity to reduce the amount of water passing through the
joints of a rainscreen. Compartmentation and adequately large joints are required to achieve
pressure equalisation
Rainscreen The part of the assembly, generally the outermost, that prevents the majority of rain from penetrating
the wall. Some water may pass through the joints of a rainscreen, but this should be limited by
appropriate detailing of open joints or the provision of baffled or labyrinth joints
Rainscreen cladding A façade that provides a barrier to wind and rain and which typically includes a vapour control layer,
system air barrier, supporting framework and fixings, insulation, breather membrane, cavity/air gap and
cladding panels. Traditional tile hanging and timber cladding are not classed as rainscreen cladding
systems under the definitions of this chapter
Replaceable Those which are readily replaceable without compromising the design and durability of the building
components or the need for progressive dismantling of the envelope. Where this cannot be achieved, components
should be designed as primary components. A method statement should be provided to demonstrate
how components will be replaced with specific reference to accessibility as detailed in this chapter
Secondary Components and parts of the system that are easily replaceable. These may include:
components z cladding panels z internal linings
z external finishes z seals and sealant
z glazing and gaskets z window and door furniture.
3 Curtain walling and cladding I 2024
Chapter 6.9
Separating floors Floors and walls designed to provide separation between homes.
and walls
Slope glazing A drained and ventilated sloped roofing system.
Systems For the purposes of this chapter, this term refers to acceptable forms of curtain walling,
rainscreen cladding, insulated render systems and brick slip cladding systems.
Spandrel panel A panel used in place of glazing units to hide the edges of floor slabs, ceiling details, insulation, and
other building elements.
Test pressure The pressure at which testing is conducted.
Vapour control layer A layer used to restrict the passage of water vapour into the construction to reduce the risk of
interstitial condensation.
Curtain walling and cladding systems shall comply with the Technical Requirements.
Curtain walling and cladding systems that comply with the guidance in this chapter will generally be acceptable.
6.9.3 Certification
6.9
Curtain walling and cladding systems shall be adequately tested, certified and designed in accordance with
appropriate standards.
Curtain walling and cladding systems should have certification confirming satisfactory assessment, undertaken by an
independent technical authority. Where applicable, certification should be in accordance with CWCT Standard for systemised
building envelopes (or a suitable alternative acceptable to NHBC). Independent technical approvals authorities acceptable to
NHBC include:
z British Board of Agrément (BBA) z certification bodies considered by NHBC to be a
z Building Research Establishment (BRE), or suitable alternative.
The use of the system should be within the scope of the certification and test documentation.
6.9.4 Loads
Curtain walling and cladding systems, including brackets and fixings, shall allow movement without
causing damage or deformation, and safely transfer loads to the building.
Dead loads and live loads should:
z be transferred safely to the building’s structure z be calculated in accordance with BS EN 1991-1-1 and
without undue permanent deformation or deflection of BS EN 1991-1-4, and take account of internal and external
any component pressures, the location, shape and size of the building.
2024 I Curtain walling and cladding 4
Chapter 6.9
6.9
Fixings should be manufactured from:
z phosphor bronze z BS EN 573 and BS EN 755 aluminium alloy
z silicon bronze z appropriate plastics
z BS EN ISO 3506 stainless steel z materials assessed in accordance with
z mild steel with coatings to BS EN ISO 2081, BS EN 1461, Technical Requirement R3.
or other appropriate treatment in accordance with
BS EN ISO 12944 or BS EN ISO 14713
Materials that comply with recognised standards and which provide equal or better performance to those above will generally be
acceptable to NHBC.
Pull-out or destructive testing of anchors and fixings should:
z comply with BS8539 and BS5080 z be carried out in accordance with the design
z comply with the Construction Fixings Association Guidance z carried out at a frequency agreed with NHBC.
Note ‘Procedure for Site Testing Construction Fixings’
Curtain walling and cladding systems shall provide satisfactory durability (subject to routine inspection
and maintenance). Timber shall be either naturally durable or preservative treated to provide adequate
protection against rot and insect attack.
The system should be designed to avoid the need for disproportionate work when repairing or replacing individual components.
In addition:
z primary components should provide satisfactory z secondary components should provide satisfactory
in-service performance for the design life of the building in-service performance for a minimum of 25 years.
The curtain walling system should be constructed with corrosion resistant or adequately protected materials. The risk of
bimetallic corrosion should be avoided by the isolation of dissimilar metals.
Systems should not include materials liable to infestation by micro-organisms, fungi, insects or vermin.
6.9.7 Interfaces
Curtain walling and cladding systems shall have suitable interfaces and resist the penetration of water
and wind.
The design should indicate the contractor responsible for constructing interfaces.
Interfaces, including those between curtain walling and cladding systems, and those between curtain walling and cladding
systems and other elements of the building (eg walls, roof, doors and windows), should be carefully designed and detailed to be
weather resistant, and prevent moisture reaching parts of the wall that it could adversely affect.
The design should take account of:
z differing profile characteristics z tolerances and deviation
z movement z the erection sequence
z continuity of insulation, vapour barriers and z planned maintenance.
breather membranes
6.9.8 Insulation
6.9
Reference should be made to BRE document BR135 – 2003 ‘Fire performance of external thermal insulation for walls of multi-
storey buildings’ when specifying the type of insulation system to be installed.
2024 I Curtain walling and cladding 6
Chapter 6.9
Rainscreen cladding
The backing wall should be adequately insulated, particularly at exposed areas. Where open joints are used, a continuous and
durable breather membrane should be provided over the outer face of the insulation.
Where the insulation is fixed to the backing wall, a minimum of one non-combustible fixing per 1m2 or per insulation batt,
whichever is the lesser, should be provided in addition to the other fixings.
Insulated render
A minimum of one non-combustible fixing per 1m2 or per
insulation batt, whichever provides the greater number,
should be provided in addition to the other fixings.
Non-combustible fixings should be fixed through the
mesh reinforcement. each layer cut
to fit neatly
around flue outlet
Insulation should be suitable to receive the
render finish, and keyed where appropriate.
6.9
Brick slip cladding
Where the insulation is fixed to the backing wall, a minimum
of one non-combustible fixing per 1m2 or per insulation batt,
whichever is the lesser, should be provided in addition to the
other fixings.
For curtain walling systems, the DPC/DPM should extend the full height of the system and have appropriate details at each
interface (including floors, walls, roofs, balconies and terraces).
7 Curtain walling and cladding I 2024
Chapter 6.9
Flashings
The following materials are acceptable as flashings:
z BS EN 12588 rolled lead sheet (minimum Code 4) z BS EN 988 zinc alloys
z BS EN 485 and BS EN 573 aluminium and aluminium alloys z stainless steel.
Breather membranes
Breather membranes should:
z comply with BS EN 13859-2: 2014 z be in accordance with Technical Requirement R3.
(Type 1 in areas of very severe exposure), or
Installation
Systems should be installed by operatives who:
z are competent z hold a certificate confirming that they have been trained by
z are familiar with the system being installed the system manufacturer, supplier or installer.
6.9
Tolerances
Systems should be completed, within reasonable tolerances, in accordance with the design, and allowing for the line, level,
plumb and plane of the completed wall to be within reasonable tolerances for the materials involved.
6.9.12 Maintenance
Curtain walling and cladding systems shall have appropriate access arrangements for the purposes
of cleaning, inspection, maintenance and repair.
Provision should be made for safe future access to the façade. Access should generally be provided from a safe working
platform, such as a cradle or mobile elevating platform.
Appropriate arrangements should be made for the replacement of failed insulating glass units without incurring excessive costs
for gaining access.
2024 I Curtain walling and cladding 8
Chapter 6.9
Sealant used in locations where differential movement may be expected, eg interfaces between the façade and the structure,
should be one of the following:
z one or two part polysulphide z one or two part polyurethane
z one part silicone z materials assessed in accordance with
Technical Requirement R3.
Systems incorporating proprietary intumescent materials should follow the guidance provided by:
z the Intumescent Fire Seals Association (IFSA) z the Association for Specialist Fire Protection (ASFP).
6.9
z in accordance with the design z at penetrations through the cladding.
z at the top and bottom of the rainscreen
Acoustic performance
Noise from the curtain walling system caused by loads, movements and changes in the environmental conditions should be
accommodated without being intrusive.
The curtain walling system should be designed to resist the passage of airborne and impact sound within the building. To reduce
flanking transmission, precautions may be required at the:
z edges of separating floors z outer ends of partition walls
z outer ends of separating walls z junctions with roof constructions and parapets.
Weather resistance
Curtain walling systems should have: Figure 1: Curtain walling to insulated render system:
z external and internal air and water seals with a drained horizontal section
and ventilated cavity at each interface 3D
internal DPC/DPM
z drained and ventilated glazing rebates including gaskets
and seals. internal seal
external seal
6.9
Figure 2: Curtain walling to balcony/terrace: vertical section Figure 3: Curtain walling to conventional brick and block
wall: horizontal section
internal seal
internal DPC/DPM
DPC/DPM external
DPC/DPM
linked to
roofing
membrane external
seal
roofing
membrane
2024 I Curtain walling and cladding 10
Chapter 6.9
Figure 4: Curtain walling to soffit: vertical section Figure 5: Curtain walling to roof, including coping detail:
vertical section
Air infiltration
Curtain walling systems should be sealed with preformed
factory-moulded ‘picture frame’ type vulcanised EPDM or
picture frame
silicone internal gaskets. Gaskets and sealants should: gasket
z be used to resist the flow of air from the outside to the interior
surface of the curtain walling system
6.9
z comply with BS 6213 and be used in accordance with
typical profile
manufacturer’s recommendations.
Particular attention should be given to the interfaces between
the curtain walling system and the walls, roof, doors,
windows and cladding system.
Off-site testing
Air and water testing of the ‘prototype’ curtain walling system should be carried out in accordance with, and pass, the CWCT
Standard (test sequence A or B), when tested at a test pressure of 600 pascals. Panels tested should be of a similar size and
configuration to those to be used on the building.
Where the maximum calculated design wind pressure is above 2400 pascals, the test pressure should be increased to 0.25 x the
design wind pressure.
The ‘prototype’ should remain watertight during and after the test.
At a test pressure of 600 pascals, an air infiltration rate no higher than 1.5m3/hr/m2 for fixed glazed panels is permissible,
provided there is no evidence of concentrated leakage.
Wind resistance, serviceability and safety testing should be carried out in accordance with the CWCT Standard.
11 Curtain walling and cladding I 2024
Chapter 6.9
Site testing
Site testing should:
z be conducted to determine resistance to water penetration, z ensure a minimum of 5% of the completed curtain walling
including joints and interfaces which are intended to be system is tested, especially in vulnerable areas such as
permanently closed and watertight joints and interfaces.
z ensure a representative sample of the finished installation is
hose tested in accordance with the current CWCT Standard
for curtain walling
Other testing may be acceptable where it is considered to be a suitable alternative by NHBC.
The results of the test should be made available to NHBC.
Acoustic performance
Noise from the rainscreen cladding system caused by rain striking the outer surface of panels should be accommodated without
being intrusive through the use of material that is:
z noise absorbing, or z anti-drumming.
Weather resistance
To ensure moisture is directed to the outside, DPC/DPM arrangements should be correctly formed with suitable upstands and
stop ends, including at the junction between the rainscreen cladding and any other component or system. External and internal
air and water seals and a drained cavity should be provided at all interfaces.
6.9
The air gap between the face of the insulation and the back of the panels should be of sufficient width and have suitably sized
drainage, allowing any water passing the joints to:
z run down the back of the rainscreen panels z be discharged externally without wetting the insulation or
the backing wall.
Free drainage
Air gaps should be adequately ventilated and the following
minimum widths maintained behind all rainscreen panels:
10mm
z 50mm for panels with open joints, or 10mm min. 10mm
min. min.
z 38mm for panels with baffled or labyrinth (rebated) joints.
Air infiltration
Before installation of the system, the backing wall should be reasonably airtight with:
z masonry walls jointed to a high standard, ie, each joint filled z framed walls, including a rigid sheathing on the cavity face,
with each joint taped or sealed.
Where reasonable airtightness cannot be achieved:
z a separate continuous vapour permeable air barrier should z joints should be taped or sealed.
be provided on the outer face of the backing wall
Compartmentation
Rainscreen cladding systems that have open joints between
1.5m max.
the panels should be designed to be pressure equalised. The
cavity should be compartmented by: 6.0m max.
The NHBC Standard for compartmentation is in addition to Building Regulations (to control the spread of smoke and fire), but
may be used for the same purpose.
Cavity closers should:
z be rigid and installed in accordance with the z enable ventilation and drainage to be maintained in
manufacturer’s recommendations accordance with the design.
Certification
Rainscreen cladding systems, including panels, should have current certification confirming satisfactory assessment by an
appropriate independent technical approvals authority accepted by NHBC.
6.9
Site testing
On-site hose or sparge bar testing should be carried out with emphasis on interfaces that are designed to be permanently closed
and watertight.
The building should remain watertight during and after the test.
13 Curtain walling and cladding I 2024
Chapter 6.9
6.9.19 Insulated render and brick slip cladding Also see: Chapter 6.2
Insulated render and brick slip cladding shall be designed and installed to ensure adequate
in-service performance. Issues to be taken into account include:
a) weather resistance d) insulated render: reinforcement and render
b) thermal bridging and condensation e) brick slip cladding: slips, carriers and joints.
c) air infiltration
Weather resistance
Timber and steel framed backing walls should have a cavity 15mm min. drained 15mm min.
and vented cavity drained cavity
between the wall and the insulation which is:
z a minimum of 15mm wide
z drained and vented (for timber frame)
z drained (for steel frame).
The following illustrations show typical interfaces and general design principles:
Figure 6: Insulated render system to Figure 7: Penetration of gas flue Figure 8: Brick slip cladding to
windows and doors: through insulated render insulated render system:
horizontal section system on horizontal section
light gauge steel frame:
horizontal section
6.9
internal seal
DPC/DPM external
seal
external
seal
external
seal
external seal
Air infiltration
Before installation of the system, the backing wall should be reasonably airtight with:
z masonry walls jointed to a high standard ie, each joint filled z each joint taped or sealed on framed walls, including a rigid
sheathing on the cavity face.
2024 I Curtain walling and cladding 14
Chapter 6.9
reinforcement continuous
across face of insulation
Render should:
z not be applied where the surface has contamination, z be mixed to ensure colour consistency where coloured
dust or loose particles pigments are specified
z have the appropriate number and thickness of coats in z be specified and used with the appropriate trims to form
accordance with the manufacturer’s recommendations corners, returns and features in accordance with the
manufacturer’s recommendations.
6.9
z be set out and designed to ensure that excessive cutting of
brick slips is avoided, ie, in the storey heights, at corners and
around openings
z have coursing arranged to suit lintel heights.
Mortars, proprietary mortars and grouts should be specified: insulation (carrier) neatly cut
around openings and positioned
z to enable each joint to be adequately filled and to avoid excess cutting of slips
appropriately struck
z in accordance with the system
manufacturer’s recommendations.
Chapter
6.10
Light steel framed walls
and floors
This chapter gives guidance on meeting the Technical
Requirements for light steel framed walls and floors and:
z applies specifically to ‘warm frame’ and ‘hybrid construction’
using 0.45-4.0mm thick framing
z does not apply to light steel framed walls used in basements.
6.10.1 Compliance 01
6.10.2 Provision of information 01
6.10.3 Structural certification 02
6.10.4 Structural design of load-bearing
floors and walls 03
6.10.5 Structural design of infill walls 06
6.10.6 Roofs 06
6.10.7 Steel and fixings 06
6.10.8 Detailing of steel joists 08
6.10.9 Restraint 09
6.10.10 Construction of load-bearing walls
and external infill walls 09
6.10.11 Interfaces with staircases 10
6.10.12 Fixing floor decking and ceilings 11
6.10.13 Other design issues 11
6.10.14 Behaviour in relation to fire 11
6.10.15 Acoustic performance 12
6.10.16 Moisture control 12
6.10.17 Insulation 13
6.10.18 Air and vapour control layers 14
6.10.19 Breather membranes 14
6.10.20 Cladding, lining and
sheathing boards 15
6.10.21 Wall ties 16
For figure reference tables in
6.10.22 Services 17 this chapter, please go to the
6.10.23 Further information 17 end of the chapter
1 Light steel framed walls and floors I 2024
Chapter 6.10
Stud partitions are considered in Chapter 6.3 ‘Internal walls’. LSF systems that do not comply with the principles of this chapter
should be assessed in accordance with Technical Requirement R3.
Where the components of the LSF cannot be inspected on site (eg closed panels or fitted out volumetric or modular units) the
system should be treated as a proprietary building system under Technical Requirement R3 and subject to assessment by an
appropriate independent technical approvals authority or be assessed under the NHBC Accepts service -
see www.nhbc.co.uk/accepts.
The LSF system shall be adequately tested and certified. The design of superstructures with primary
structural components formed from LSF shall be checked by an NHBC registered LSF certifier.
Primary structural components formed from LSF require two-stage certification confirming that both the system and the project
have been checked. External infill does not require Stage 1 and 2 certification (see Clause 6.10.5).
6.10
z holding down
z connections within the system
z connections with other building elements
z structural integrity
z positions and sizes of holes through members
Additional checks where LSF is z module-to-module connections (strength as well as accuracy)
used in volumetric construction z module-to-foundation connections
z rigidity in transportation
z lifting
Where there are various configurations (eg types of claddings), the manufacturer will need to specify which options SCI is to
consider in its assessment. Upon satisfactory completion, SCI will approve the manufacturer’s system manual and issue a
numbered ‘system certificate’ which includes:
z a detailed description of the system z information for reference by the designer and LSF
z details of usage limitations project certifier.
3 Light steel framed walls and floors I 2024
Chapter 6.10
Structural floors
Floors should:
z be of the correct type z have a typical maximum joist spacing of 600mm, although
z be fitted in the specified location greater spacings may be applied when designed by an
z have suitably sized trimmers around floor openings engineer in accordance with Technical Requirement R5 or
6.10
Static criteria for the maximum permissible deflection of a single joist due to:
z imposed load, limited to (span/450) z dead and imposed loads, limited to the lesser of (span/350)
or 15mm.
Dynamic criteria:
z the natural frequency of the floor should not be less than z the deflection of the floor (ie, a series of joists plus the floor
8Hz for dead load plus 0.2 x imposed load; this can be decking) when subject to a 1kN point load should be limited
achieved by limiting the deflection of a single joist to 5mm to the values in Table 2.
for the given loading.
Table 2: Deflection with point loads of 1kN
Span (m) Maximum deflection (mm)
3.5 1.7
3.8 1.6
4.2 1.5
4.6 1.4
5.3 1.3
6.2 1.2
The deflection of a single joist is dependent on the:
z overall floor construction z number of effective joists that are deemed to share the
applied 1kN point load (typical values are given in Table 3).
Table 3: Typical values
Floor configuration Number of effective joists
400mm joist centres 600mm joist centres
Chipboard, plywood or oriented strand board 2.5 2.35
Built-up acoustic floor 4 3.5
6.10
z 50mm oversite concrete or 50mm fine aggregate on 1200 z 100mm oversite concrete on a compacted clean, inert
gauge (0.3mm thick) polyethylene membrane laid on 50mm hardcore bed. Where necessary, this concrete should be
sand blinding, or protected against sulfate attack by the use of a lapped
polyethylene DPM, not less than 1200 gauge (0.3mm thick)
or 1000 gauge where assessed in accordance with Technical
Requirement R3.
Floors should have a 150mm minimum void below the floor which is ventilated by:
z openings on at least two opposite sides z 1500mm2 per metre run of external wall or 500mm2 per m2
of floor area (whichever provides the largest area).
Where there is shrinkable soil, heave can occur. The minimum underfloor void ventilation requirement should be increased
as follows:
z high potential – 150mm (300mm total) z low potential – 50mm (200mm total).
z medium potential – 100mm (250mm total)
See Chapter 4.2 ‘Building near trees’ for definitions of high, medium and low volume change potential.
For concrete ground floors refer to Chapters 5.1 ‘Substructure and ground-bearing floors’ and 5.2 ‘Suspended ground floors’.
Concrete upper floors
Concrete floors may be used with LSF and may be constructed using either thin precast units or in-situ concrete placed on steel
decking. The deflection of simply supported composite floors should be limited to take account of the long-term effects of creep
and shrinkage. Composite floors should be appropriately propped until the concrete reaches the required strength and should
not be overloaded during construction. Guidance can be found in Section 6.3 of SCI publication P402 ‘Light steel framing in
residential construction’.
5 Light steel framed walls and floors I 2024
Chapter 6.10
Structural walls
The structural design of the building should ensure adequate resistance to loadings including dead loads, imposed loads, wind
loads and snow loads, in accordance with:
z BS EN 1991-1-1 z BS EN 1991-1-4.
z BS EN 1991-1-3
Further guidance on deflection limits can be found in SCI guidance P402 ‘Light steel framing in residential construction’.
Individual studs should generally:
z be sized to meet structural requirements, allowing for board z consider deflection if not designed to carry vertical loading
fixings at joints and construction tolerances from the primary structure.
z have a maximum spacing of 600mm
Where panels are diagonally braced with a flat strip, the brace should be fixed to each stud at the intersection to minimise
bowing in the bracing member. Alternatively, bracing may be tensioned using alternative methods where included in the scope of
the Stage 1 certification.
6.10
Appropriate holding-down devices should be provided to resist uplift, where necessary. The anchorage for holding-down devices
should have sufficient mass to resist the uplift forces (See Clause 6.10.10).
Where roof trusses sit directly on a top track, the design should consider all loads, such as:
z wind uplift z vertical loading (assuming that trusses may be offset
z lateral support from studs).
Overall stability
Methods to provide overall stability should either:
z be designed to BS EN 1993-1-1, or z be tested to BS EN 594.
Wall panels may provide stability using one or more of the following techniques:
Internal lining boards can be used where demonstrated to be suitable for the purpose.
2024 I Light steel framed walls and floors 6
Chapter 6.10
6.10.5 Structural design of infill walls Also see: Chapters 7.1 and 7.2
Infill walls shall be designed to support and transfer loads to the structure safely and without undue
distortion or movement.
Infill panels should be designed to resist the expected wind loads, any loads transferred by the cladding system, and those
imposed by windows and doors within the panels. Load concentrations resulting from the presence of openings should also be
considered. The design should be in accordance with BS EN 1993-1-3. Additional information can be found in SCI publication
ED017 ‘Design and installation of light steel external wall systems’.
6.10.6 Roofs
Roofs supported by LSF constructions shall be designed to support the roof coverings and transfer loads
safely and without undue movement.
Connections between LSF walls and timber or LSF pitched roofs require careful consideration in the design.
LSF pitched or flat roofs should only be used in warm-roof or hybrid construction, ie, with insulation over rafters (or joists in
flat roofs).
Condensation risk should be considered in accordance with BS 5250.
Steel grade
Steel should be in accordance with BS EN 10346 and of any of the following grades:
z S280 z S390
6.10
z S320 z S420
z S350 z S450.
Holding-down devices
Holding-down devices should be suitable for the environment they will be exposed to, and manufactured from:
z mild steel with zinc coating to BS EN ISO 1461 z stainless steel to BS EN 10095 (suitable for
most environments).
unacceptable
notch
2024 I Light steel framed walls and floors 8
Chapter 6.10
Installation details
Joists or floor beams should be:
z spaced as shown in the design z joined with the correct type, size and number of fixings.
z accurately cut to length in accordance with the
manufacturer’s recommendations to ensure a tight fit
Where light steel joists are supported by steel joists, cleats or web stiffeners should be used in accordance with the design.
Joists may be doubled up to support partitions or to form trimmers.
Continuous joists on load-bearing intermediate walls should be reinforced as required by the design.
Figure 6: Web stiffeners for continuous joists over Figure 7: Joists overlapping on load-bearing
load-bearing intermediate wall intermediate wall
6.10
Where joists overlap on load-bearing intermediate walls, they should be fixed together with bolts or screws. This is to prevent the
floor decking being pushed up, or the ceiling being cracked, when the cantilevered part of the joist moves upwards.
Prevention of roll
Bridging and blocking should be provided in accordance with the design Figure 8: Floor bracing examples
to prevent roll.
Floors constructed using joists with an asymmetric web, eg of C or Sigma
profile, can cause the floor to roll. To avoid roll, unless otherwise specified
in the design, one of the following alternatives should be used where the
span exceeds 3.5m for C joists or 4.2m for Sigma joists:
z a continuous line, or lines, of proprietary steel herringbone
struts provided between the joists; the pairs of struts should
have a physical gap between them so that they do not rub
against each other at the cross-over point and create noise.
z solid blocking provided to every alternate pair of joists with
ties between them as shown.
z joists alternately reversed and tied together in pairs.
z joists alternately reversed and continuous ties
(eg resilient bar) fixed to the joist flanges.
Where joists bear onto steelwork or are supported by cleats, blocking is
not necessary adjacent to the supports.
9 Light steel framed walls and floors I 2024
Chapter 6.10
6.10.9 Restraint
Restraint strapping shall be provided in accordance with the design.
Where external walls, not constructed from LSF, are to be stabilised by a connection to the floor, straps may be required.
Straps will generally be fixed to the web of the joist, to suit the masonry courses.
Where joists run parallel to the wall, straps should be supported on noggings fixed between the joists. Straps should be placed
at a maximum of 2m apart and carried over three joists. Packing should be provided between the wall and the first joist.
Straps should be fixed with suitable bolts, screws or rivets and should bear on the centre of bricks or blocks, not across
mortar joints.
Preparation
The following should be in accordance with the design: Figure 9: Floor edges
Shims should be of pre-galvanised steel (the galvanised coating being at least equivalent to that of the member/s being packed)
or other suitable material, ie, not timber or plastic.
Wall frames should be checked to ensure that they are dimensionally accurate before erection commences.
2024 I Light steel framed walls and floors 10
Chapter 6.10
LSF should be correctly positioned, square and plumb, and within the Figure 10: Correct positioning
following tolerances: nominal line line of
of frame frame
z the vertical position of members should be within +/-5mm per
storey relative to the base 5mm max.
z the horizontal position of base rails should not vary in
alignment by more than 5mm in 10m.
10m
Anchoring
The frame should be anchored to resist both lateral movement and uplift in accordance with the design, including bolt-down
brackets where required.
Figure 11: Strap anchor example Figure 12: Bolt-down anchor example
anchor fixed
to studs
anchor in
accordance
with design
anchor built
into masonry
6.10
maintained, to avoid spalling of masonry or concrete positioned to receive fixings.
Where the design incorporates gas membranes (methane or radon), fixings should not puncture them, but where this is
unavoidable, the penetration should be sealed.
Accommodation of deflection
Infill walls should accommodate anticipated deflection within the primary frame in accordance with the structural design.
Floors and walls shall be designed to accommodate installation of any staircases without compromising
performance.
Wall linings should be continuous behind the string of staircases.
Fixing connections should be coordinated to ensure fire protection continuity and structural adequacy.
11 Light steel framed walls and floors I 2024
Chapter 6.10
Guidance for some of the performance issues listed in Table 7 may be included in the Stage 1 certificate.
Guidance within supporting documents to the Building Regulations should be fully considered in the design and construction of
LSF walls, floors and roofs.
Detailing and specification of components should be in accordance with the steel frame manufacturer’s recommendations and/
or guidance from SCI (see guidance in P424 ‘Light steel framing in fire’) and supported with representative test evidence to
appropriate standards such as BS 476:21 or BS EN 1365:1 for load-bearing walls, BS 476:22 or BS EN 1364:1 for infill walls and
BS EN 1365:2 for floors.
The performance of specific details should be taken into account, including:
z fire protection to the structure around openings z detailing around service penetrations
z detailing of cavity barriers, including moisture protection z compartmentation including interfaces with fire doors.
to the barrier
2024 I Light steel framed walls and floors 12
Chapter 6.10
Separating floors
The floating part of a floor should be separated from the main structure and surrounding walls by a resilient layer.
Where boards are laid loose over insulation without battens, joints should be glued.
6.10
Vertical tile hanging(1) where a breather membrane Dependent on batten support layout and spacing(1)
is provided and fixed to the sheathing
Other cladding(1) 15mm
Notes
1 See Chapter 6.9 ‘Curtain walling and cladding’.
Where levels are raised above the base rail or lowest steel:
z local areas of LSF walls (less than 15% of the external z in addition, where more than 15% of the external perimeter
perimeter) retaining up to a maximum of 600mm of has ground levels above the internal floor finish (up to a
ground can be acceptable, subject to appropriate maximum of 600mm), the structure should be designed by
waterproofing design an engineer in accordance with Technical Requirement R5.
Waterproofing should be designed by a waterproofing design specialist and be in accordance with Chapter 5.4 ‘Waterproofing of
basements and other below ground structures’.
The manufacturer of the waterproofing system should confirm compatibility between the waterproofing and sheathing board,
which should be supported by test evidence.
Insulation shall be correctly installed, be of a suitable material and thickness to comply with Building
Regulations and reduce the risk of interstitial condensation.
Insulation should:
z be inert, durable, rot and vermin proof, and should not be z extend 150mm below the base rail to minimise thermal
adversely affected by moisture or vapour bridging and maintain a warm frame
z cover the whole external face of the wall and be complete z be tightly butted with joints of rigid board insulation taped,
within the frame where required by the design.
Foil-faced insulation boards with an integral facing on one side only should be fixed with the foil face on the cavity side.
Split layers of AVCL-type material should be avoided, except where condensation risk analysis shows it to be acceptable.
Where they are provided, AVCLs should be:
z 500g polyethylene sheet, vapour control plasterboard, z placed to cover the external wall, including base rails,
or material assessed in accordance with head rails, studs, lintels and window reveals
Technical Requirement R3 z overlapping the base rail
z fixed on the warm side of the wall insulation and frame z fully sealed and punctures made good.
z in accordance with the design
6.10
Breather membranes should be:
z vapour resistant to less than 0.6MNs/g (0.12 Sd) when z At least Class W2 to BS EN 13859-2 with no water leakage
tested in accordance with BS EN ISO 12572 using the during testing. In areas of very severe exposure (see
set of conditions C and using five test specimens Clause 6.1.6 for classification of exposure zones) or where
z capable of resisting water penetration liquid water penetration of the cladding is anticipated,
z self-extinguishing for example open-jointed cladding, Class W1 should
z durable be used. When open-jointed claddings are used or the
membrane likely to be left exposed during construction
z installed so that each joint is protected and moisture
for a duration longer than normally to be expected (also
drains outwards
see the membrane manufacturers recommendations on
z lapped to a minimum of 100mm at horizontal joints and a
exposure times), performance should be based on artificial
minimum of 150mm at vertical joints
aged behaviour in accordance with BS EN 13859-2. Where
a vented and ventilated cavity with full rainscreen and no
gaps, for example masonry or rendered board claddings,
are used, performance should be based on artificial aged
behaviour in accordance with BS EN 13111.
Breathable membranes should be used to protect sheathing board and insulation. Breather membranes may be omitted
where water resistant insulation boards with taped joints are used. Tape should be of a type recommended by the insulation
manufacturer, breathable to allow water vapour to move freely and resist water penetration. Suitable taping should be applied at
the lintel interfaces and other penetrations to direct water outside.
15 Light steel framed walls and floors I 2024
Chapter 6.10
External cladding
The design and construction of the external walls should fully consider:
z cavity drainage z restraint
z differential movement z fire resistance.
In external walls, a clear cavity should be provided between the external insulation and the cladding. The cavity should:
z be drained z have drainage at its base, equivalent to 500mm2/m run,
z have cavity trays and weepholes installed where the cavity eg for masonry, one open perpend every 1.5m
is not fully maintained, eg at cavity barriers z have drainage openings placed to prevent the ingress
z be kept clean, free of obstructions and capable of of rain.
draining freely
Sheathing
Sheathing boards should be:
z of a suitable strength and quality z attached using suitable quality fixings.
z compatible with the steel frame
Sheathing boards contribute to meeting many of the critical performance issues described in Table 7 and cannot be easily
replaced, so they should be specified in accordance with the design life of the building.
Sheathing boards should be appropriate for the exposure of the building and suitable for use in humid conditions.
2024 I Light steel framed walls and floors 16
Chapter 6.10
Fixings used to apply sheathing boards should be selected in accordance with the board manufacturer’s instructions and be
suitably specified for strength and long-term durability in the anticipated exposure condition.
Sheathing boards should be adequately protected from weather during construction. This can be done through a combination of:
z the use of water resistant boards with accredited proof of z sequencing construction to minimise daily exposure with
performance in accordance with Technical Requirement R3 fully waterproof temporary coverings overnight and during
z the use of sealed jointed water resistant insulation to reduce inclement weather.
water penetration
z the application of a breathable membrane to the
sheathing board
For all sheathing board types, junctions between adjacent boards, and at interfaces with other building elements, should be
sealed and/or taped in accordance with the manufacturer’s recommendations.
A breather membrane should be used to provide protection to the building during and after construction in areas of very severe
exposure to wind-driven rain.
6.10
In addition to the general guidance for internal lining boards, plasterboard should:
z be shown to provide adequate fire resistance z be a minimum of 9.5mm for stud spacing up to 450mm
where required z be a minimum of 12.5mm for stud spacing up to 600mm.
z comply with BS EN 520 and be in accordance with
Chapter 9.2 ‘Wall and ceiling finishes’
Wall ties for masonry cladding should be according to the design and:
z installed at a minimum density of 3.7 ties/m2, eg spaced z spaced at jambs of openings, a maximum of 300mm
at a maximum of 600mm horizontally and 450mm vertically within 225mm of the masonry reveal
vertically (except where alternative densities have been (additional studs may be needed to achieve this)
demonstrated by building specific calculation and accepted z kept clean and free from mortar droppings.
under the Stage 2 certificate)
17 Light steel framed walls and floors I 2024
Chapter 6.10
6.10.22 Services
Services shall be adequately protected from damage.
Service mains and service outlets should be:
z designed to ensure the fire resistance of walls and floors is z installed in accordance with the design
not impaired z on the warm side of the insulation.
z designed to ensure that the required sound insulation of
walls and floors is maintained
Light steel joists or studs should not be notched to accommodate services. Holing of structural light steel members should be
carried out in accordance with this chapter and the manufacturer’s recommendations. On-site hole cutting should be avoided,
as badly cut edges can have an adverse effect on the durability of the frame and may cause damage to pipes and cables.
Where on-site adaptation of the frame is unavoidable, it should be undertaken by the manufacturer, with prior notification to
NHBC, and completed in line with the steel frame designer’s remedial details with all cut edges treated and badly cut edges
avoided. Significant adaptations should be overseen by the design engineer.
Grommets should be used around the edge of service holes to protect electrical cables and reduce the risk of bimetallic
corrosion between the LSF and copper pipes. Swaged holes for electric cables and plastic piping do not require grommets.
In Scotland, services are not permitted within:
z framed separating walls z separating wall cavities.
6.11
Render
This chapter gives guidance on meeting the
Technical Requirements for factory-made and
traditional render applied to external walls and
render onto board backgrounds.
Render intended for below ground waterproofing is
outside the scope of this chapter (see Chapter 5.4
‘Waterproofing of basements and other below ground
structures’). Chapter 6.9 ‘Curtain walling and cladding’
contains guidance for insulated render systems.
6.11.1 Compliance 01
6.11.2 Provision of information 01
6.11.3 Weather conditions 02
6.11.4 Backgrounds 03
6.11.5 Accommodation of movement 04
6.11.6 Mixes 05
6.11.7 Detailing 08
6.11.8 Render onto board backgrounds 10
6.11.9 Finishes 12
Introduction
This chapter is arranged in sections covering:
z site and factory-made render z detailing.
z render onto board backgrounds
Render, including site-made, factory-made and render onto board backgrounds shall comply with the
Technical Requirements.
Render that complies with the guidance in this chapter will generally be acceptable.
Table 1: Process chart for the application of site and factory-made render to masonry backgrounds
Process Steps See clause
Structure design Identify a suitable background material compatible with the intended render finish and 6.11.4
consider any preparation requirements
Consider how movement will be controlled, ie, are movement joints or bed joint 6.11.5
reinforcement needed?
Render design
Select an appropriate render strength that is compatible with the background 6.11.6
Determine the exposure zone which will influence the render's thickness 6.11.6
Construction Protect the background from adverse weather conditions at the earliest opportunity during 6.11.3
and following construction
Assess the likely weather conditions prior to and after rendering 6.11.3
Assess the background, eg suction and surface preparation, and apply a preparation coat 6.11.4
where necessary
6.11
Consideration should be given to likely weather conditions and, where required, measures taken to allow render to
cure satisfactorily.
When applying render in wet conditions:
z the background should not be saturated z curing render should be protected from heavy rainfall
z downpipes or temporary downpipes should be used to z specialist preparation coats should be used in accordance
prevent the background or completed render from with the manufacturer’s recommendations.
becoming saturated
When applying render in hot conditions the following precautions should be considered:
z avoid curing render from being directly exposed to z lightly spray the render with clean water to prevent
strong sunlight rapid drying.
When applying render in cold conditions:
z the air temperature should be at least 2°C and rising z the background should not be saturated.
z the background should be free from visual signs of frost
Where the air temperature is at, below or likely to fall below 5°C, appropriate precautions such as covering with a hessian sheet
should be used to protect curing render.
Factory-made render should be installed in accordance with the manufacturer’s recommendations for weather conditions.
Acrylic renders have different curing requirements which should be considered.
3 Render I 2024
Chapter 6.11
6.11.4 Backgrounds
Backgrounds shall be appropriate for their intended purpose and suitably prepared to receive render.
Issues to be considered include:
a) preparation of masonry backgrounds c) ribbed metal lath.
b) preparation of clay brick backgrounds
The suction of the block should be appropriate for rendering. High or low suction will generally require a preparatory coat. The
likely suction of the block can be gauged by applying a small quantity of water to the surface and observing the effects:
z water being absorbed instantly is an indication of z water running from the surface with little absorption
high suction suggests the background has low suction.
A spatterdash coat typically comprises cement and sand at a ratio of 1:3 mixed with water and often a bonding agent, such as
styrene butadiene rubber (SBR) or ethylene vinyl acetate (EVA). The mix should be applied by dashing onto the background to
give a rough texture approximately 3-7mm thick.
Generally, raking out mortar joints to blockwork will not sufficiently improve the key, and may extend the curing time of the
base coat.
To provide an appropriate bond, clay brick backgrounds with a water absorption rate of between 9% and 15% should generally
have sufficient suction to provide a mechanical key. Alternatively, when rendering onto bricks, one or more of the following
methods of improving the key can be adopted:
z keyed bricks used z mortar joints raked out to a depth of 10-12mm (although this
z a spatterdash coat applied may increase curing time).
Render on an external leaf of clay bricks (F2,S1 or F1,S1 designation bricks to BS EN 771) in severe or very severe exposures
is not permitted where the cavity is to be fully filled with insulation.
Render onto ribbed metal lath can be vulnerable to damage where impact is likely to occur, such as beside communal paths.
Appropriate reinforcement may be used to help improve the render’s impact resistance.
2024 I Render 4
Chapter 6.11
Rendered walls shall be detailed to reduce the risk of damage due to movement in the background. Issues
to be considered include:
a) movement in masonry background c) movement in ribbed metal lath render.
b) dissimilar materials
The construction should include appropriate measures to reduce the risk of damage to the render caused by movement in the
background, such as shrinkage, thermal or differential movement. The designer should follow the guidance in this chapter,
together with the render/background manufacturer’s recommendations. Alternatively, provision for movement should be designed
by an engineer in accordance with Technical Requirement R5.
Areas of the building to be rendered should be identified prior to construction, and movement control considered as part of
the design.
Where length/height ratios are greater than 3:1, consideration should be given to providing suitably designed:
z movement joints, or z bed joint reinforcement.
Where movement joints are provided, they should: Figure 1: Typical movement joint
compressible filler
6.11
z not align with openings such as windows, doors, or meter boxes.
external render
Austenitic stainless steel bed joint reinforcement conforming to BS
EN 845-3 should be provided in the first two courses of the external
masonry leaf above and below any opening to help distribute
tensile stress and avoid localised cracking. Where possible,
the reinforcement should project 600mm beyond the opening.
Notes:
1 The guidance in this table is generally acceptable for render coats in accordance with Table 5 and factory-made one-coat render based on 1:1:6 mix = 3.5N/mm².
2 Specialist advice from the block and render manufacturer should be sought.
3 Specialist advice should be sought where clay brick backgrounds are used.
5 Render I 2024
Chapter 6.11
Dissimilar materials
Backgrounds should not be constructed from materials of Figure 2: Metal lath reinforcement and separation strip (min. 300mm)
different densities. Where possible, render should not be
continuous across dissimilar materials. Where this cannot be
avoided the render should:
z be stopped at appropriately formed movement joints, or
z have austenitic stainless steel lath reinforcement carried
across the joint with a separation strip, such as building
min. 300mm metal lath reinforcement and separation strip
paper, behind.
Where significant differential movement is likely to occur, such as the junction between masonry and board backgrounds, render
should be stopped either side of an appropriately formed joint.
The render mix shall be appropriate for the intended purpose, be compatible with the background and be
designed to minimise the risk of de-bonding, cracking, and crazing. Issues to be considered include:
a) sand e) application of site-made render
b) mix design f) factory-made renders
c) admixtures and bonding agents g) lime.
d) coat thickness of site-made render
Render coats should not be stronger than the background or any previous coat to which they are applied. Weaker coats can be
achieved by reducing the cement content of each coat or by using the same mix but decreasing the coat thickness.
Potable water should be used for mixing render.
6.11
Sand
Sand for render should be well-graded category 2, in accordance with BS EN 13139. Sand with excessive fine material, clay or
silt can shrink and crack so should be avoided.
A sharp gritty or coarse sand is required for strength in the backing coats, but finer sand should be used for the finishing coat.
Typical sand grades should be:
z 5mm down to 0.075mm – undercoat(s) z 1.18mm down to 0.075mm – final coat.
Mix design
Designation ii, iii and iv (strength class M6, M4 and M2) mixes are generally used for rendering.
Stronger mixes are generally more moisture resistant; however, they are also more prone to shrinkage, which increases the
likelihood of the render cracking. Weaker mixes may be appropriate for weaker backgrounds in less exposed zones.
For exposure zone classification, see Clause 6.1.6.
2024 I Render 6
Chapter 6.11
Notes:
1 With fine or poorly graded sands, the lower volume of sand should be used.
2 Where soluble salts could be present in the background, mixes should have sulfate-resisting properties.
3 Where pigments are specified, batching should be undertaken with care to ensure colour consistency pigments to BS EN 12878 can be used but should not
exceed 10% of the cement weight, or 3% where carbon black is used (white Portland cement may be used).
6.11
Admixtures and bonding agents should:
z be assessed in accordance with Technical Requirement R3 z be compatible with the render
z be used in accordance with the z not be used with factory-made renders without the prior
manufacturer’s recommendations approval of the render manufacturer.
The effect on the adhesion of subsequent render coats should be considered when water-repelling agents are used.
Plasticisers and air entrainers should comply with BS EN 934 and not be used in mortars containing masonry cement.
Notes:
1 Designation iii (M4) should be used for the final coat in severe or very severe exposure zones.
2 For block classifications, see Table 2.
3 Specialist advice should be sought for low density aircrete backgrounds.
Where a three-coat render is used, this should include a second undercoat that is:
z the same thickness but a slightly weaker mix than the first z a slightly thinner coat of the same strength mix.
undercoat, or
Surfaces should be appropriately prepared to receive following coats. This can be achieved by either combing or scratching.
The final coat should be applied to an undercoat that is suitably keyed.
The size of the background to be rendered should be assessed to determine if it can be rendered in the time available.
This will help to establish the most suitable location for day joints.
The final coat should be of uniform thickness and not used to even out irregularities, which should be accommodated in
previous coats.
Factory-made renders
Factory-made renders should be applied in accordance with the manufacturer’s recommendations, including those for
ancillary components.
Factory-made renders with a declared mix in accordance with Table 4, applied to the thickness recommended in Table 6, and
that otherwise comply with the recommendations for site-made renders, will generally be acceptable to NHBC.
2024 I Render 8
Chapter 6.11
Lime
Render mixes containing hydrated lime can improve the ability of the render to accommodate movement, improving resistance to
cracking and crazing. The use of lime should be in accordance with BS EN 459.
Natural hydraulic lime (NHL) is used without cement, which can allow greater moisture vapour movement through the structure.
Specialist advice may be required for the use of NHL render.
6.11.7 Detailing
Rendering shall be detailed to ensure appropriate weathertightness and durability. Issues to be
considered include:
a) copings, cappings and sills e) exposed elements
b) abutments and interfaces f) ancillary items
c) weepholes g) render below the DPC
d) detailing at openings h) resistance to sulfate attack.
6.11
Extending sills or sub-sills beyond window reveals can help to disperse water and prevent staining.
Figure 3: Detailing of copings to protect render Figure 4: Detailing of capings to protect render
150mm 150mm
min. min.
weep holes weep holes
(max. spacing 1m) (max. spacing 1m)
render render
9 Render I 2024
Chapter 6.11
Weepholes
Weepholes should be provided: Figure 5: Provision of weepholes to window head
Detailing at openings
Design features around openings and at the head of the Figure 6: Check reveal detail
rendering should provide shelter and help shed water away
external min. 12mm overlap to frame
from the surface below.
window
In areas of very severe exposure, and in Scotland, a check sill
reveal should be provided at openings.
Proprietary render systems should be detailed at abutments in
sealant
accordance with the manufacturer’s recommendations.
sealant
internal
Exposed elements
Render to exposed masonry elements, such as parapets, freestanding walls, pillars, retaining walls or chimneys, should be of a
type appropriate for severe exposure conditions.
When rendering both sides of freestanding or parapet walls of single leaf construction, care should be taken to prevent damage
caused by moisture becoming trapped. For example:
z the detailing should prevent the masonry from z rendering both sides of single leaf walls in areas of very
becoming saturated severe exposure to frost attack should be avoided
z the wall should be protected from rain during construction (see Clause 6.1.6c).
Bricks with S1 or S0 designation are not recommended for exposed elements that are to be rendered.
2024 I Render 10
Chapter 6.11
Ancillary items
Stop beads and render stops should be austenitic stainless steel or PVC. Long runs of steel beads and stops should be avoided
due to their expansion potential.
Corner beads should have an appropriate projection to prevent thin tapering of the render which reduces its
overall thickness.
Beads should be:
z adhesive-fixed using a material appropriate for external z mechanically fixed using suitably durable fixings.
use and in accordance with the manufacturer’s
recommendations, or
Render below the DPC
To prevent damage caused by prolonged periods of wetting, it is preferable to stop the render at DPC level. Where rendering is
continued below the DPC, the following precautions should be taken:
z for site-made render, use a stronger mix (M4) that is sulfate z factory-made render used in accordance with the
resisting, or manufacturer’s recommendations.
6.11
6.11.8 Render onto board backgrounds
Render onto board backgrounds shall be suitable for the intended use and detailed to provide satisfactory
performance. Issues to be considered include:
a) provision of a system manual d) weather resistance
b) compatibility between the render and background e) movement joints
c) fixing back to the structure f) board backgrounds.
The system should be used in full accordance with the manufacturer’s guidance and third-party certification.
A suitably qualified and experienced chartered engineer should check that an adequate number of fixings are used to attach
the system.
Fixing battens and rails should be installed vertically and not block drainage paths. Timber battens should be suitably treated.
To reduce the risk of damage from impact, especially at low level, where people have access around balconies and where cradle
systems etc can meet the façade, appropriate precautions such as closer supports should be considered.
Cavity barriers should be appropriately detailed to ensure satisfactory performance and:
z be provided in accordance with Building Regulations z account for movement in the frame
z not block ventilation or drainage paths z be used in accordance with the
manufacturer’s recommendations.
Weather resistance
Timber and steel framed backing walls should be protected with breather membranes and have a minimum 25mm cavity.
Cavities to timber framed walls should be drained and vented, and cavities to steel framed walls should be drained.
Movement joints
Movement joints should be provided to accommodate movement in timber frame structures. Where board backgrounds are used,
movement joints should be:
z formed in accordance with the system z positioned to accommodate calculated deflection
manufacturer’s recommendations or movement
6.11
Board backgrounds
Board backgrounds to be rendered should be external grade and recommended for use in the render manufacturer’s
system manual and third-party certification.
Boards should be set out in accordance with the system manufacturer’s recommendations, taking account of possible
compression, deflection, and alignment of joints in relation to openings in the external wall, such as windows and doors.
The render should have alkali-resistant mesh embedded into the base coat across the whole surface.
Edges of boards should be suitably treated to provide protection from weather during construction and to maintain durability after
the render is completed.
2024 I Render 12
Chapter 6.11
6.11.9 Finishes
Finishes shall be to a satisfactory standard. Issues to be considered include:
a) decorative finishes b) appearance.
Decorative finishes
The choice of decorative finish should take account of:
z the exposure zone z background movement potential.
Scraped or textured finishes can reduce the risk of crazing and can break up the drainage path of rainwater as it runs down the
face of the wall.
Wet dash and dry dash finishes should have an aggregate size generally between 6mm and 14mm. Dry dash should be applied
to the final coat before it has fully cured.
Appearance
Render on external walls should be reasonably consistent in texture, finish, colour, and line. Clause 9.1.2b provides further
guidance on tolerances to render finishes.
Consideration should be given to detailing that will avoid obvious staining (eg the positioning of discharge pipes).
Completed render should be protected from damage that could be caused by construction activities.
Render may not be resistant to staining and may require periodic maintenance such as cleaning.
6.11
Figure 3 Detailing of copings to protect render 6.11.7 8
Figure 4 Detailing of capings to protect render 6.11.7 8
Figure 5 Provision of weepholes to window head 6.11.7 9
Figure 6 Check reveal detail 6.11.7 9
Effective from 01/24 V208b 01/24