Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                

NOV-23 - Sathya Ques Paper

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 5

Register Number

SATHYABAMA
INSTITUTE OF SCIENCE AND TECHNOLOGY
(Deemed to be University U/S 3 of UGC Act,1956)

Programme & Specialisation: B.E. / B.TECH. - CSE / Mechatronics /


IT Max. Marks: 100
Title of the Paper : Resource Management Techniques
Course Code : SMEA4001 (2019/2020) Time : 3 Hours
Date : 01/11/2023 Session : AN
________________________________________________________
(NOTE: Assume relevant data, if found missing)
PART - A (10 × 2 = 20)
Answer ALL the Questions
1. Summarize the Graphical method procedure. (CO1)
2. Give some example for usage of Surplus variable & Slack
Variable. (CO1)
3. Differentiate balanced transportation problem from unbalanced
transportation problem. (CO2)
4. Illustrate the traveling salesman problem. (CO2)
5. Define total elapsed time and idle time on machines. (CO3)
6. Distinguish CPM and PERT. (CO3)
7. Name the various costs involved in inventory problems. (CO4)
8. Contrast EOQ and EBQ. (CO4)
9. Give the formula for the problem for a customer to wait in the
system under (m/m/1 : N/FCFS)? (CO5)
10. When should the replacement be done?
(CO5)
PART - B (5 × 16 = 80)
Answer ALL the Questions
11. Solve LPP Problem by Graphical Method. (CO1)
Max Z = 4x1 + 3x2
Subject to 2x1 + x2 ≤ 1000
x1 + x2 ≤ 800 x1 ≤ 400, x2 ≤ 700, And x1,x2 ≥ 0
(or)
12. A company manufactures two types of products P1, P2.Each
product uses lathe and Milling machine. The processing time per
unit of P1 on the lathe is 5 hours and on the milling machine is 4
hours. The processing time per unit of P2 on the lathe is 10 hours
and on the milling machine, 4 hours. The maximum number of
hours available per week on the lathe and the milling machine
are 60 hours and 40 hours, respectively. Also, the profit per unit
of selling P1 and P2 are Rs.6.00 and Rs.8.00, respectively.
Create a linear programming model to determine the production
volume of each of the products such that the total profit is
maximized and also solved by simplex method. (CO1)
13. Determine Initial Basic Feasible Solution (IBFS) for the
following transportation problem by using Vogels Approximation
Method (VAM). (CO2)
Supply
11 13 17 14 250
16 18 14 10 300
21 24 13 10 400
Demand 200 225 275 250
(or)
14. Solve the assignment problem for the jobs (CO2)
Machines
M1 M2 M3 M4 M5 M6
J1 12 3 6 - 5 8
Jobs J2 4 11 - 5 - 3
J3 8 2 10 9 7 5
J4 - 7 8 6 12 10
J5 5 8 9 4 6 -
Find (a) Assignment Schedule (b) Assignment Cost
15. Solve the job sequencing problem for the jobs to be processed
through three machines. (CO3)
Jobs
A B C D E F G
M1 3 8 7 4 9 8 7
Machines M2 4 3 2 5 1 4 3
M3 6 7 5 11 5 6 12
Find (a) Optimum Sequence (b) Total Elapsed Time (c) Idle time
of each machines.
(or)
16. Construct the network for the project whose activities and the
three estimates of these activities (in weeks) are given below:
(CO3)
Activity to tm tp
1-2 3 4 5
2-3 1 2 3
2-4 2 3 4
3-5 3 4 5
4-5 1 3 5
4-6 3 5 7
5-7 4 5 6
6-7 6 7 8
7-8 2 4 6
7-9 1 2 3
8-10 4 6 8
9-10 3 5 7
Find (a) Expected Duration of each activity (b) Expected
variance (c) Critical Path of the project (d) Maximum duration of the
project.

17. The demand for an item is 18000 units per year. The holding
cost is Rs.1.20 per year and cost of shortage is Rs.5 per year and
the set up cost is Rs.400 per year. Determine (a) Economic order
quantity (b) Time between two consecutive orders (c) No of
orders (d) Min average cost (e) Max Inventory. (CO4)
(or)
18. Find the optimal order quantity for a product for which the price
break is as follows:
(CO4)
Quantity Unit Cost
0 ≤ Q1 ≤ 500 Rs.10
500 ≤ Q2 ≤ 750 Rs.9.25
750 ≤ Q3 Rs.8.75

The monthly demand for the product is 200 units, the cost of
storage is 2% of the unit cost and ordering cost is Rs.100 per
order.

19. In a railway Marshalling yard good train arrive at a rate of 30


trains per day. Assuming that inter arrival time follows an
exponential distribution and the service time distribution is also
exponential, with an average of 36 minutes. Calculate the
following: (a) the mean queue size (line length) (b) the
probability that queue size exceeds 10 (c) If the input of the train
increases to an average 33 per day. (CO5)
(or)
20. The cost of machine is Rs.6100 and its scrap value is Rs.100 for
entire year. The maintenance cost found from experience are as
follows: (CO5)
Year 1 2 3 4 5 6 7 8
Maintenance 100 250 400 600 900 1200 1600 2000
Cost

What should be the machine replacement year?

You might also like