Location via proxy:   [ UP ]  
[Report a bug]   [Manage cookies]                
0% found this document useful (0 votes)
18 views

Warringah Council: Development Engineering Minor Works Specification

Uploaded by

kjcivil01
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
18 views

Warringah Council: Development Engineering Minor Works Specification

Uploaded by

kjcivil01
Copyright
© © All Rights Reserved
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 42

Warringah Council

Development Engineering
Minor Works Specification

April 2010
MINOR WORKS SPECIFICATION

Table of Contents

Design and Construction Standards

1 General Requirements
1.1 Traffic Control
1.2 Testing
1.3 Working Hours
1.4 Insurance
1.5 Silt and Sediment Control
1.6 Occupational Health and Safety
1.7 Written Approval

2 Footpath Paving
2.1 Concrete Footpath Details
2.2 Concrete Footpath Requirements
2.3 Footpaths using Concrete Pavers
2.4 Tolerances

3 Kerb and Gutter


3.1 Kerb and Gutter Detail
3.2 Levels
3.3 Pedestrian Access Ramps
3.4 Excavation
3.5 Formwork
3.6 Material
3.7 Joints
3.8 Placing Concrete
3.9 Finish
3.10 Backfilling
3.11 Tolerances
3.12 Stormwater Drainage Outlets

4 Vehicular Access
4.1 Excavation
4.2 Formwork
4.3 Materials
4.4 Joints
4.5 Placing Concrete
5 Stormwater Drainage
5.1 Stormwater Pipes
5.2 Stormwater Pits
5.3 Trench Excavation
5.4 Bedding
5.5 Installation
5.6 Jointing
5.7 Backfilling
5.8 Concrete Works for Drainage Structures

6 Plan Submissions
6.1 Presentation of Plans
6.2 Plan Requirements for Road Design
6.3 Plan Requirements for Drainage
6.4 Work as Executed Drawings

7 Inspections
7.1 Footways
7.2 Footpath Paving
7.3 Kerb and Gutter
7.4 Road Pavement
7.5 Drainage Works

8 Works as Executed Plans

9 Maintenance Period

10 Standard Engineering Drawings


Normal Standard Vehicle Crossing Profile
Normal-High Standard Vehicle Crossing Profile
Normal-Low Standard Vehicle Crossing Profile
Extra High Standard Vehicle Crossing Profile
Extra Low Standard Vehicle Crossing Profile
Standard Kerb & Gutter Detail
Standard Gutter Crossing Detail
Standard Kerb Access Ramp Detail
Standard Concrete Footpath Detail
Standard Paving Details – Local Retail Centres
Typical Pipe Trench Detail (Roadway)
Standard Gully Pit Detail

Appendix A - Restoration Charges for Road Openings & Conditions to be


Observed
1. GENERAL REQUIREMENTS
This document is the specification defining construction details for minor works
undertaken by private contractors within the road reserve of Warringah Council, and the
requirements of both Council and the contractors who undertake the works.

1.1 Traffic Control

The contractor undertaking construction works on any public road within Warringah
Council shall be responsible for the safety of traffic both vehicular and pedestrian
during the works. The contractor must provide the provision of continuous access for
vehicles and pedestrians and provide all security, lights, barriers, signs and fences
necessary to prevent any accident or public or private damage or loss. The contractor
shall provide traffic control during the progress of the works in accordance with the
requirements of AS 1742.3 – 2009.

If it comes to the attention of Council that Traffic Control Devices are insufficient or
inoperational (particularly in an after-hours situation), then Council may arrange to
reinstate the Traffic Control Devices and recoup the costs from the contractor and or
applicant.

1.2 Testing

Where this document makes reference to compaction requirements it will be necessary


for the contractor to provide test results for the required compaction from a NATA
registered laboratory.

1.3 Working Hours

All construction works on any public road within Warringah Council shall be carried
out in daylight hours between 7.00am and 5.00pm Monday to Friday inclusive and
7.00am to 1.00pm on Saturdays. No construction work is to occur on Sundays and
public holidays.

1.4 Insurance

The contractor shall provide copies proving the currency of Public Liability Insurance
for $10 million and full Workers Compensation insurance on all construction works
undertaken on public roads within Warringah Council. Insurances must be kept current
for the duration of the works.

1.5 Silt and Sediment Control

All construction works on any public road within Warringah Council shall provide silt
and sediment control in accordance with Council’s Silt and Sediment Control Manual.
1.6 Occupational Health and Safety

Civil Contractors are to provide their employees and subcontractors with:

 safe plant and safe systems of work


 written procedures and instructions to ensure health, safety and welfare at work
 the necessary safety equipment required to do their work.
 health and safety information, instruction, training and supervision
 measures to ensure that they comply with all legislative requirements, standards
and Council policies and regulations.

Inspections undertaken by Council does not relieve the applicant/contractor of any


responsibility to comply with all OH & S responsibilities encumberant upon them by
such works.

1.7 Written Approval

The Applicant must not proceed with any part of the works until written approval has
been received from Council.
2. FOOTPATH PAVING
2.1 Footpath Details

Concrete footpaths are to be constructed in accordance with Council Drawing Number


A4 10536.

Footpaths using concrete pavers are to be constructed in accordance with Council


Drawing Number A4 10483.

2.2 Concrete Footpath Requirements

Where shown on the Drawings, concrete footpaths shall be constructed true to the line,
level and width as indicated and be in accordance with the following standards.

Ready Mixed Concrete shall conform to the provisions of AS 1379 – 2007


“Specification and Supply of Concrete”.

The minimum compressive strength Fc of the concrete shall be 20 MPa at 28 days in


accordance with AS 3600 – 2009 “Concrete Structures”.

Footpaths shall have a crossfall of 2% and be 1.5 metres wide if it is constructed


adjacent to the kerb, and 1.2 metres wide in all other locations.

The subgrade shall be excavated to a depth of 100mm and all soft and other unsuitable
material shall be removed and replaced with sand or road base (recycled road base is
acceptable) and shall be thoroughly compacted.

Timber pegs of 50mm x 50mm-dimension minimum must be provided for the support
of all formwork. The use of steel pegs for the support of formwork is prohibited.

The footpath shall be generally 75mm thick and increased at vehicular crossings to the
crossing thickness.

Expansion joints 10mm thick for the full depth of the slab using a preformed jointing
material, shall be provided at intervals not greater than 4.8 metres, at a junction with
other footpaths, kerbs or other concrete structures, on each side of vehicular crossings
and adjacent to all kerb ramps. Jointing material shall be flush with the surface of the
footpath.

Dummy joints shall be provided at intervals of 1.2 metres maximum or equidistant


between expansion joints and also being equalised between vehicular entrances. Joints
shall be at right angles to the outer edge of the path.

The surface finish of all concrete footpaths shall be light broom with all edges treated
with a 50mm wide edging tool.
Batters in cut and fill situations shall have slopes desirably not exceeding 1V: 5H and
up to 1V: 3H where so determined either by Council or an Accredited Certifier (Civil
Works). The top and lower edge of the cutting shall be neatly rounded. In any
circumstance where the batter slope will exceed that which can be maintained with a
domestic lawn mover, the batter shall be treated in a manner other than turf to the
satisfaction of Council.

On completion of works, grassed footways are to be restored to a condition at least


equivalent to that which existed prior to commencement. Any bare ground arising from
the construction works is to be returfed. Minor differences in levels, up to 20mm, may
be accommodated by top dressing where the existing turf is in good condition.

2.3 Footpaths using Concrete Pavers

Pavers will generally only be approved in commercial areas. Approved areas are to be
paved in “Boral Classic Pave 50” (200mm x 100mm x 50mm) concrete pavers.

Pavers shall be laid on 30mm bed of clean washed river sand over a 25Mpa concrete
base 75mm thick non-reinforced.

Double-header course banding will be provided along the kerb line and property
boundary and will comprise of two differing coloured header courses. The header
course adjacent to the kerb and boundary is to be the colour Saraha. The second header
course will provide the variation in banding colour and be in Charcoal.

The double-header course banding will be laid to flow as two continuous parallel
lines where angles or bends are required along kerb lines or boundaries. The double-
header course along kerb lines will flow in a continuous line around the perimeter of
kerb ramps.

Infill pavers between header course banding to be laid in Herringbone pattern in colour
Antique Copper.

Double-header course perpendicular to the kerb line is to be provided at 15m intervals


in colour Charcoal.

Paver type and layout for the footpath pavers in the Dee Why Town Centre are to be in
accordance with the Warringah Design Guidelines : STR-PR350, Part D –
Specifications, Dee Why Town Centre.

Driveways within areas to be paved must be constructed in plain concrete as per


Council Standard Crossing Profiles.

2.4 Tolerances

Tolerance on the level of footpaths both horizontal and vertical shall be plus or minus
10mm.
3. KERB AND GUTTER
The construction of concrete kerb and gutter is to be in accordance with AS 2876 –
2000 “ Concrete kerbs and channels (gutters) – manually or machine placed” unless
otherwise indicated below.

3.1 Kerb and Gutter Detail

Kerb and gutter shall be in accordance with Council Drawing Number A4 2267/A.

3.2 Levels

Design plans are to be prepared by the applicant and approved by Council prior to
construction.

Generally the following criteria should be met preparing a design for kerb and gutter.

 a minimum longitudinal grade of 1% is required

 the crossfall from the edge of the existing pavement should generally be
3%.

 reconstruction of existing kerb and gutter may be required to ensure that a


satisfactory connection is provided.

3.3 Kerb Access Ramps

Kerb access ramps are to be constructed in accordance with Council Drawing Number
A4 7284.

Kerb access ramps shall be constructed at the kerb return adjacent to the constructed
footpath and in the kerb return opposite the extension of the footpath construction.

Kerb access ramps are to be rough broom finished in an apricot coloured oxide at all
locations except where they abut Council approved concrete pavers where the finish
shall be rough broom in plain concrete.

3.4 Excavation

All soft, yielding and other unsuitable material shall be removed and replaced with an
approved road base (recycled road base is acceptable).

The base material shall be thoroughly compacted and finished to a smooth surface with
a uniform bearing value of minimum density of 95% Standard Compaction in
accordance with AS 1289.5.4.1 – 2007 “Methods of testing soils for engineering
purposes - Soil compaction and density tests - Compaction control test - Dry density
ratio, finished to a smooth surface moisture variation and moisture ratio”.
3.5 Formwork

The forms shall be aligned true to grade and without local irregularities. The tolerances
shall be + 15mm provided that variations in levels are not local and are over lengths of 3
metres or more.

Forms shall be constructed so that they can be removed without damaging the concrete
and shall be adequately braced. The inner surface of forms shall be adequately oiled to
ensure the non-adhesion of the concrete. The material used for forms for the exposed
surfaces shall be dressed soft woof timber.

Timber pegs of 50mm x 50mm-dimension minimum must be provided for the support
of all formwork. The use of steel pegs for the support of formwork is prohibited.

3.6 Materials

Ready Mixed Concrete shall conform to the provisions of AS 1379 – 2007 “Ready
Mixed Concrete”.

The minimum compressive strength Fc of the concrete shall be 25 MPa at 28 days in


accordance with AS 3600 - 2009 “Concrete Structures”.

3.7 Joints

For hand placed kerb and gutter expansion joints 10mm thick for the full depth of the
kerb and gutter shall be provided at intervals not exceeding 6m.

For machine placed kerb and gutter, expansion joints 6mm thick shall be provided at
intervals of 6m and contraction joints shall be formed every 3m for the full depth of the
kerb and gutter.

Joints are also required where the gutter abuts gully pits and gutter crossings. Expansion
joints shall consist of preformed jointing material bituminous fibreboard.

3.8 Placing Concrete

The concrete shall be placed so as to avoid segregation and shall be adequately


compacted. Care shall be taken to fill every part of the forms and to work the coarser
aggregate back from the face. Exposed surfaces shall be finished with a steel float, and
corners and edges shall be neatly rounded with a nosing tool. Concrete shall not be
disturbed after it has been in the forms for twenty (20) minutes.

3.9 Finish

After removal of the forms, minor or porous sections or holes shall be repaired with a 3
to 1 sand and cement mortar mix. The exposed surfaces shall then be rubbed with a
wooden float and clean water to leave the surfaces smooth and uniform in colour and
appearance.
3.10 Backfilling

After removal of formwork the footway behind the kerb shall be neatly trimmed, filled
and or turfed to make a smooth connection to the undisturbed nature strip.

3.11 Tolerances

Tolerance on the level of kerb and gutter construction both horizontal and vertical shall
be plus or minus 10mm.

3.12 Stormwater Drainage Outlets

Any existing stormwater drainage outlets located within the proposed kerb and gutter
construction works are to be reconstructed as part of the works.
4. VEHICULAR ACCESS
No construction is to commence until profiles have been determined and issued by
Council to ensure satisfactory vehicular access is provided.

4.1 Excavation

All soft, yielding and other unsuitable material shall be removed and replaced with an
approved road base, (recycled road base is acceptable) and shall be thoroughly
compacted and finished to a smooth surface. At filled locations a crushed sandstone
sub-base 100mm thick (minimum) shall be provided. Where laybacks are to be
constructed in existing kerbs as directed by Council, the gutter pad is to be neatly sawn.

4.2 Formwork

The forms shall be aligned true to grade and without local irregularities. Forms shall be
constructed so that they can be removed without damaging the concrete and shall be
adequately braced. The inner surface of forms shall be adequately oiled to ensure the
non-adhesion of the concrete. The material used for forms for the exposed surfaces shall
be dressed soft wood timber.

Timber pegs of 50mm x 50mm-dimension minimum must be provided for the support
of all formwork. The use of steel pegs for the support of formwork is prohibited.

4.3 Materials

Ready Mixed Concrete shall conform to the provisions of AS 1379 – 2007 “Ready
Mixed Concrete”. The minimum compressive strength Fc of the concrete shall be 25
MPa at 28 days in accordance with AS 3600 - 2009 “Concrete Structures”.

4.4 Joints

Expansion joints 10mm thick for the full depth of the slab shall be provided at intervals
not exceeding 6 metres. Joints are also required where the layback abuts gully pits and
kerb and gutter. Expansion joints shall consist of preformed jointing material
bituminous fibreboard.

4.5 Placing Concrete

The concrete shall be placed so as to avoid segregation and shall be adequately


compacted. Care shall be taken to fill every part of the forms and to work the coarser
aggregate back from the face. Exposed surfaces shall be finished with a wood float, and
corners and edges shall be neatly rounded with a nosing tool. Concrete shall not be
disturbed after it has been in the forms for twenty (20) minutes.
4.6 Tolerances

Tolerance on the level of vehicular access construction both horizontal and vertical shall
be plus or minus 10mm.

5. STORMWATER DRAINAGE
Stormwater systems are to be designed in accordance with Council’s Aus-spec Design
Manual.

5.1 Stormwater Pipes

Stormwater pipes shall be designed to cater for the flows determined by Council’s Aus-
spec Design Manual.

The minimum pipe size diameter for pipelines that will form part of Council’s
infrastructure is to be 375mm. The minimum box culvert size is to be 600mm wide x
300mm high.

The minimum pipe grade is to be 1.0%. The maximum pipe grade is to be in accordance
with AS 3500.3 – 2003 “Stormwater Drainage”, AS 3500.3:2003/Amdt 1:2006 and AS
3500.3:2003/Amdt 2:2010.

The minimum cover over pipes in Council roads is to be 600mm.

All pipes used shall be reinforced concrete pipes RCP minimum Class 2, spigot and
socket with rubber ring joints and conform to the test requirements of AS 4058 – 2007
“Precast concrete pipes (pressure and non-pressure)”. PVC and FRC pipes will
generally not be accepted as Council pipelines.

The location of any new stormwater lines in Council roads is to under the kerb and
gutter. The reconstruction of the kerb and gutter will form part of the works and must be
in accordance with Council’s standard kerb and gutter drawing number A4 2276/A.

5.2 Stormwater Pits

The location of gully pits in Council roads must not be on curves, kerb returns or in line
with normal pedestrian flows and clear of existing or future kerb access ramp locations.

Stormwater pits are to be cast in-situ in accordance with Council’s standard drawing
number A2 5476/A. Precast pits or combined lintel and pit units will not be accepted for
use in Council roads.

The minimum compressive strength Fc of the concrete shall be 25 MPa at 28 days in


accordance with AS 3600 – 2009 “Concrete Structures”.
The minimum size inlet or extended kerb inlet (E.K.I) length for gully pits is to be 1.8
metres.

All lintels in Council Roads are to be precast concrete.

Gully pit grates shall be hot dipped galvanised mild steel (MS) “Webforge” gully grate
and frame WG-5.

Step irons shall be provided in all pits 1.2 metres deep or greater. Steps shall be 325mm
apart vertically staggered one left and one right etc. with 75mm clear between step irons
when viewed from above and the first iron being 325mm from the top of the pit.

All pit bases shall be benched to ensure the pit is streamlined and any hydraulic losses
are reduced. This includes aligning the inlet and outlet pipes to ensure the inlet jets
directly into the outlet pipe. All inlet and outlet pipes are to be finished flush with the
pit walls.

5.3 Trench Excavation

Trenches shall be excavated to the required grade line to the base of the bedding level.
All soft, yielding and other unsuitable material shall be removed and the trench shall be
thoroughly compacted in sand or other granular material to a firm smooth surface of
uniform bearing value of minimum density of 95% Standard Compaction in accordance
with AS 1289.5.4.1 – 2007 “Methods of testing soils for engineering purposes - Soil
compaction and density tests - Compaction control test - Dry density ratio, moisture
variation and moisture ratio”.

The width of the trench shall be 1.4 times the external diameter of the pipe or culvert
plus 300mm and shall be parallel with the inverts of the pipes.

Where any section of pipe has an outlet to a pit, a length of subsoil drain, minimum 3
metres in length, shall be laid in the trench with the outlet to the pit and the upstream
end capped.

For pipes of 1200mm diameter or larger, two lengths of subsoil drain shall be laid, one
each side of the pipe.

It is the responsibility of the contractor to comply with the requirements of Workcover


and the NSW Department of Industrial Relations regarding the supporting of the sides
of trenches during excavation.

5.4 Bedding

The pipe shall be evenly bedded on a continuous layer of compacted sand with a
minimum depth of 200mm and a maximum of 325mm.

In wet trench conditions Council may specify 20mm blue metal or river gravel as
granular material to replace the sand.
5.5 Installation

Pipes, which have markings indicating the crown or invert of the pipes, shall be laid
strictly in accordance with the markings.

The space between the abutting ends of the pipes shall not exceed 0.5 % of the diameter
of the pipe. Spigot and socket joints shall have recesses left under the pipe joints to
permit jointing and to avoid bearing on the socket.

Pipes shall be uniformly supported over the entire length on the bedding layer and be
laid true to grade and line.

Where multiple pipes are laid side by side, the space between the line of pipes shall be
not less than one third (1/3) of the diameter of the pipes or 300mm whichever is the
greater.

5.6 Jointing

Rubber ring joints shall be fitted in accordance with the manufacturer’s specifications.

5.7 Backfilling

All pipes shall be backfilled with sand to a layer of 300mm above the pipe.

Pipes located outside the road pavement shall have the remainder of the trench to
natural surface level be backfilled with sand, placed in layers not exceeding 150mm
loose thickness, and compacted to a minimum density of 95% Standard Compaction in
accordance with AS 1289.5.4.1 – 2007 “Methods of testing soils for engineering
purposes - Soil compaction and density tests - Compaction control test - Dry density
ratio, moisture variation and moisture ratio”.

Pipes laid under a road pavement or under kerb and gutter shall have the sand backfill
taken to the underside of the selected subgrade layer only. The remainder of the trench
shall be backfilled with 150mm loose layers of fine crushed rock or DGB 20 road base
material and compacted to a minimum density of 100% Standard Compaction in
accordance with AS 1289.5.4.1 – 2007 “Methods of testing soils for engineering
purposes - Soil compaction and density tests - Compaction control test - Dry density
ratio, moisture variation and moisture ratio”.

5.8 Concrete Works for Drainage Structures

Ready Mixed Concrete shall conform to the provisions of AS 1379 - 2007 “Ready
Mixed Concrete”.

The minimum compressive strength Fc of the concrete shall be 25 MPa at 28 days in


accordance with AS 1480 - 2001 “Concrete Structures”.
Steel reinforcement shall conform to the provisions of AS/NZS 4671 – 2001 “Steel
Reinforcing Materials” and AS 4671:2001/Amdt 1:2003.

Formwork shall conform to the provisions of AS 3610 – 1995 “Formwork for Concrete”
and AS 3610-1995/Amdt 1-2003. It must be designed to ensure removal will not
damage the concrete. Oiling of the formwork is permitted to prevent adhesion of the
concrete.

Concrete shall be placed to avoid segregation and shall be adequately compacted. If a


mechanical vibrator is used to compact the concrete, care should be taken to ensure that
no segregation of the aggregate is caused by over vibration.

Exposed surfaces shall be struck off with a wooden float and neatly finished. Concrete
shall not be disturbed after it has been in the forms for 20 minutes.

Forms to concrete faces shall not be removed until at least 48 hours after the concrete
has been placed. At locations where the concrete will be under load and unsupported, a
period of 28 days will be required prior to removal of the forms.

Upon removal of the forms, any rough or porous surfaces or holes shall be thoroughly
scabbled, dressed and rubbed up with a 3 to 1 sand to cement mortar. Faulty and
honeycombed portions shall be taken down and rebuilt.
6. PLAN SUBMISSIONS
6.1 Presentation of Plans

Three copies of engineering plans are to be submitted to Council for approval. Unless
otherwise agreed all drawings shall be prepared on A1 sheets in accordance with
standard drawing practise.

Australian Height Datum shall be used for all levels and the consultant for each project
shall provide a permanent benchmark.

Scales shall be clearly indicated on all sheets and the following scales normally used.

 Plans 1:250 horizontal


 Long Sections 1:250 horizontal, 1: 100 vertical
 Cross Section 1:100 natural
 Special Structures 1:20

6.2 Plan Requirements for Road Design

The position of the road(s), and relation to other roads, road centreline with the bearings
of straight sections and the radius of the curves, all recovery pegs, benchmarks and
reduced levels including a schedule set out listing Easting, Northing peg levels and
finished surface levels, the road chainage, pits and pipe details. Horizontal curve
information should include, intersection angle, arc length, tangent length and secant.

Longitudinal section with levels showing road alignment, existing natural levels, grades
and vertical curves shall be provided.

Cross-sections are to detail the carriageway width, width and footpath slope, kerb and
gutter details. Spacing shall be at 10m intervals.

Kerb returns shall be designed using 1:100 horizontal and 1:10 vertical and shall detail
longitudinal profile of kerb levels.

6.3 Plan Requirements for Drainage

A catchment plan shall be included at a suitable scale with all existing Council and
private stormwater drainage lines shown.

Plans shall include details of hydraulic grade line calculations on all stormwater
drainage long sections.

The proposed drainage lines shall be shown on all road plans, together with the location
and type of all pits.
A long section of every stormwater drainage line shall be shown, detailing existing
ground levels, finished or proposed long sections, the pipe size and class, inverts and
grades, pit types, hydraulic grade line and flow rates.

Other drainage structures eg headwalls, scour protection, gross pollutant traps shall be
detailed.

6.4 Work as Executed Drawings

Upon completion of construction works on Council’s road reserve, work as executed


drawings by a registered surveyor are to be submitted to Council where directed. The
plans shall include details of all infrastructure demolished as part of the works and a
fully coordinated detail survey of the completed new works in hard copy and electronic
formats (preferably DXF Format) using MGA94 Coordinates and Australian Height
Datum (AHD).

Drainage asset infrastructure data (dimensions of pipes, pits, manholes etc.) shall be
provided in approved format available from Council’s Asset Management Section.
7. INSPECTIONS
7.1 Footpaths

A Compliance Certificate issued by an Accredited Certifier (Civil works) is to be


submitted if Council does not inspect the footpath works stating the works have been
completed in accordance with this specification. If Council inspects the footpath works
48 hours notice is to be given by the contractor. An inspection fee must be paid in
accordance with Councils fees and charges.

The Accredited Certifier must confirm:

 Thickness and alignment of the formwork


 Suitability of the subgrade including any required compaction testing.
 The formwork levels.
 Suitability of transitions to existing footpath levels and alterations to services.

Upon completion of works the contactor is to ensure that any laid turf is not below the
footpath or kerb, there are no localised depressions and no step-downs to any adjoining
vehicle crossings.

Engineering bonds and the Builders Kerb Security deposit will not be refunded until all
works have been completed to the satisfaction of Council and the 6-month maintenance
period has finished.

7.2 Kerb and Gutter

A Compliance Certificate issued by an Accredited Certifier (Civil works) is to be


submitted if Council does not inspect the Kerb and Gutter works stating the works have
been completed in accordance with this specification. If Council inspects the Kerb and
Gutter works 48 hours notice is to be given by the contractor. An inspection fee must be
paid in accordance with Councils fees and charges.

The Compliance Certificate is to be issued to Council following placement of


formwork, but prior to pouring of concrete. The Accredited Certifier (Civil works) is to
check.

 The finished surface levels


 The quality of finish.
 The restoration of the footpath area.
 A traffic control plan and traffic management is in place prior to and during all
construction works.

Any sections of kerb and gutter that do not met these specification standards will need
to be removed and reconstructed.
Engineering bonds and the Builders Kerb Security deposit will not be refunded until all
works have been completed to the satisfaction of Council and the 6-month maintenance
period has finished.

7.3 Road pavement

A Compliance Certificate(s) are to be issued by an Accredited Certifier (Civil works)


and submitted to Council for the Road pavement works stating the works have been
completed in accordance with this specification and prior to the following stages of
construction:

 Subgrade trimmed and compacted.


 Base course spread and compacted
 Intermediate course spread and compacted.
 Wearing course laid.

The subgrade and base course is to have compaction testing carried out by a licensed
NATA soil testing laboratory, in accordance with the requirements of Councils
Engineering Specification Auspec One.

7.4 Drainage works

A Compliance Certificate issued by an Accredited Certifier (Civil works) is to be


submitted if Council does not inspect the stormwater drainage works stating the works
have been completed in accordance with this specification. If Council inspects the
drainage works 48 hours notice is to be given by the contractor. An inspection fee must
be paid in accordance with Councils fees and charges.

Compliance Certificate(s) are to be issued to Council at the following stages:

 Following excavation and bedding of the pipe, but prior to backfilling.


 Following backfilling and restoration.
 Following erection of formwork and placement of reinforcement to any pits or
other concrete structures.
8. WORK AS EXECUTED PLANS
Following satisfactory completion of road and drainage works, “work as executed”
details are to be submitted in both hard copy and electronic formats as detailed below.

Hard Copy: A copy of the approved plans overdrawn in red

Electronic Copy:

9. MAINTENANCE PERIOD
A maintenance period of six (6) months shall apply to all footpath, kerb and gutter and
road works. Engineering bonds will not be refunded or released until the maintenance
period is completed and all compliance certificates issued to Council. Councils
Development Engineering section is required to complete a final inspection prior to
handover of any engineering works with contractor and Accredited Certifier (civil
works).
10. STANDARD ENGINEERING DRAWINGS
Appendix A
RESTORATION CHARGES FOR ROAD OPENINGS
& CONDITIONS TO BE OBSERVED

(Road openings include any opening of road pavement, road shoulder,


footpath, kerb & gutter, nature strip or other Council infrastructure)

Council has a responsibility to maintain its road pavement, road shoulder, footpath, nature
strip, kerb & gutter, etc. in the best possible condition. Therefore, strict compliance of the
following conditions and specifications are required to ensure a quality restoration.

Contractors and individuals engaged in trenching work within Warringah Council area are
required to obtain Council’s “Road Opening Permit’ and pay the associated Permit Fee and
Restoration Charges prior to commencing of works.

The permit fee and charges, required to cover the cost of restorations, are published in
Council’s book of Fees and Charges. These fees and charges will be used to cover the cost of
Council inspections, quality checking and checking of temporary coldmix asphalt wearing
course on trenches at the end of the maintenance period of six (6) months. The total charges
payable will be based initially on the road area to be affected by trenching works as
determined by Council and agreed by the Applicant. Upon completion of the works and
certification that all trenches have satisfied the specified backfilling and compaction
requirements, an actual measure of the areas to be restored (permanently) will be carried out
by Council’s Restoration Officer (with the applicant’s representative if required), and any
adjustment to the original restoration charges will be made on this basis. This may involve
additional charge if the restored area is larger than originally estimated.

Council recognises the need for these works and through mutual co-operation the work
should proceed smoothly for all parties concerned.

1. PERMITS

a) A Road Opening Permit must be obtained from Council’s customer service


centre, Civic Centre, Dee Why, before a road is opened by any plumber, drainer,
builder or any other person (Such contractors or individuals are referred to
hereunder as the Permit Holder).
b) The permit must be available at the work site whilst the opening is being carried
out.
c) Wherein the opinion of Council’s Restorations Officer a bona fide emergency
condition existed (eg. damaged sewer connection or burst water service) 24 hours
will be allowed for making an application for a Permit unless such a condition
existed during a weekend or a public holiday and in that case an application must
be made before the end of the next working day.
d) The Permit will be valid for six (6) months from the date of issue.
e) No main traffic route road pavement shall be opened without the permission of
the Restorations Officer.
f) A Permit Fee subject to Council’s Fees & Charges must be paid in addition to the
appropriate restoration charges.
2. RESTORATION CHARGES

In addition to the Permit Fee, a restoration charge shall be prepaid. This charge shall
be calculated in accordance with the schedule of Fees & Charges (refer to the Fees &
Charges hand book which is published by the Council annually) and the further
details set out hereunder.

3. LATE FEE

Where a Permit is not sought in accordance with (1) above, a late fee subject to
Council’s current Fees & Charges shall be charged and added to the restoration
charges. The late fee shall also apply where an inadequate Road Opening Permit has
been obtained and the charges are insufficient to cover the restoration costs, as
assessed in accordance with the actual field measurements of the opening and /or with
(4) hereunder.

4. AREA CALCULATED FOR RESTORATION CHARGES

a) Minimum width shall be 0.5 m for sewers and 0.3 m for other services.
b) Where the width is more than the minimum specified as above, it shall be
measured in steps of 0.1 m above the opening size.
c) Special conditions for concrete openings are to be observed as specified in Clause
5 hereunder.
d) In any case the actual area restored will be charged. Where this is greater than
that covered by the Permit, the extra charge will be payable by the applicant in
addition to the late fee as set out under (3) above.

5. CONCRETE OPENINGS

a) Under no circumstances a concrete road shall be opened without the express


permission of the Restorations Officer, in writing.
b) Longitudinal footpath openings and concrete road pavement openings shall be
saw cut along all edges.
c) The depth of saw cut shall be at least 50 mm for footpath and 75 mm for road
pavement and vehicular crossings.
d) Openings in concrete footpaths shall be charged on the basis of all full slabs
damaged.
e) Openings in concrete roads closer than 2 m to a longitudinal, or transverse joints
shall include the restoration of the area between the opening and the joint.

6. NATURE STRIP OPENING

No restoration will be charged on grassed nature strips provided the area is restored to
its original state. If unsatisfactory reinstatement occurs then the appropriate charge
will apply.

7. CONDITIONS TO BE OBSERVED BY THE PERMIT HOLDER

a) The Permit Holder shall provide adequate barriers and warning signs, and where
excavation is open overnight, adequate lighting with a minimum of three (3)
lamps.
b) Except under exceptional circumstances, all openings shall be carried out
between 7.00 am and 5.00 pm.
c) At the close of each day’s activity, the work site must be left in a safe condition,
having due regard to providing temporary access to private properties and public
thoroughfare.
d) Traffic control devices are to be provided for all works within the road reserve in
accordance with AS 1742.3-2009.
e) No more than half the width of a road pavement shall be opened at any one time.
On main traffic routes Police approval shall be obtained.
f) Any Utility Services damaged during the work are to be immediately reported to
the relevant Utility Authority.
g) Should Council receive complaints or be required to rectify an unsafe
condition outside normal work hours, the costs involved will be recouped
from the Permit Holder.
h) All excavated materials and surplus backfilling materials shall be removed from
the site of the work and the site must be left in a clean condition.
i) Upon completion of the opening, temporary restoration shall be carried out by the
Permit Holder as set out in the Specification for Trench Construction Within
Council Roads.
j) The permit holder must have a valid Public Liability Insurance Cover to a
value of minimum $10 million at the time of road opening.

8. GENERAL

a) Backfilling and compaction of road openings and trenches shall be carried out in
accordance with Council’s Specification for Trench Construction Within Council
Roads.
b) All work shall be carried out to the satisfaction of Council’s Restorations officer
and the applicant shall be liable for the cost of any extra restoration work, over
that paid for, where it is necessary to satisfy the above conditions or restore
adjacent failed sections of road subgrade or pavement.
c) A road-opening permit is also required for any boring work including the
payment of permit fee prior to the commencement of boring.
d) Where a road or path has not been constructed to its final levels, consideration
may be given to permitting the mains or services being laid at depths measured
from the existing surface, provided the owner or Utility Authority agrees to meet
all costs of adjustments that may be necessary when the road or path is finally
constructed, otherwise mains and services shall have the following minimum
cover below design levels:

Sewerage services 1m
Water 0.6 m
Other Services 0.45 m
SPECIFICATION FOR TRENCH CONSTRUCTION WITHIN COUNCIL ROADS

1. All trenches within the roadway, traversing pathways or driveways are to be backfilled to
within 250mm of the road surface with clean sand (not filling sand) as shown in Figure 1;

2. All sand backfilling shall be thoroughly compacted in layers not exceeding 250mm
thickness either by use of a “Wacker” type rammer or vibratory roller (where the width of
the trench permits);

3. Sand backfilling, to depths less than 1.5 metres, shall be compacted to 80% Relative
Density which is equivalent to a minimum of 10 blows per each 300mm penetration of a
Scala Penetrometer. Over 1.5 metres, the Scala blows are to be a minimum of 8;

4. The top layer of the trench shall comprise of a minimum of 200mm thick compacted
DGB 20 road base and a well compacted surface seal of 50mm thickness;

5. Compaction of DGB 20 roadbase shall be to a minimum of 98% modified compaction


ratio;

6. Concrete and asphaltic edges of trenches shall be saw cut after completion of the
trenching works on an alignment that includes all edge failures that have occurred during
the process;

7. The temporary coldmix-wearing course (surface seal), shall be maintained in a safe


condition by the permit holder until the permanent restoration is carried out by the
Council (but which shall not exceed a period of 6 months). Should failure occur within
the temporary coldmix surface during the maintenance period, the permit holder shall be
liable for the repairs;

8. The permit holder shall ensure that during the backfilling operation, specified materials
have been used, and specified layer thicknesses and densities have been achieved;
9. Council reserves the right to levy an additional charge for its testing and inspection
should a trench continually fail and becomes necessary to carry out repeated tests;

10. Where a work may be subject to erosion, appropriate erosion and sedimentation controls
shall be implemented in accordance with current standards and EPA requirements;

11. Bulkheads shall be drained in accordance with Council standards and all trenches shall be
dewatered at regular intervals into Council’s pipe stormwater system without
contravening to EPA regulations;

12. Build up of sub-surface water at manholes should be avoided and where possible to
redirect sub-surface drainage paths, including those through private property, should be
dewatered into Council’s stormwater system.
Existing asphalt/concrete pavement

50 mm thick coldmix layer well


compacted

200 mm thick (minimum) DGB20


roadbase
compacted to a
minimum of 98% modified
Saw cut edges

250 mm thick layers of clean sand


backfill
compacted to 80% Relative Density
Minimum cover
refer to 8 (d)

Affected service

FIGURE 1

TRENCH BACKFILLING - CROSS SECTION

CONTACT DETAILS

For any further details or assistance please do not hesitate to contact Council’s Roads and
Restorations Officer on 02-9942 2119.

You might also like