Republic of the Philippines


Department of Public Works And Highways
ALBAY 3RD DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE V
Paulog, Ligao City

Contract ID : 20FO0100
Contract Name : Construction of Water Supply System Level II, Brgy. Balanac, Cabarian,
Catburawan, Maonon, Palapas, San Vicente (Ligao City), Itaran (Polangui),
Karatagan (Pioduran), Burabod ES and Magallang ES (Libon) , Albay

BILL OF QUANTITIES
Part No. Part Description

(Columns (1), (2), (3), and (4) are to be filled up by the Procuring
(Columns (5) and (6) are to be filled up by the Bidder)
Entity)

(1) (2) (3) (4) (5) (6)

Pay Item Unit Price Amount


Description Unit Quantity (Pesos) (Pesos)
No.

ABC = PhP 29,700,000.00

Site No. 1 Construction of Water Supply System Level II, Brgy. Balanac, Ligao City, Albay

Sub-ABC (Site No. 1) = PhP 2,970,000.00


PART II OTHER GENERAL REQUIREMENTS
In Words : Pesos In Figures : Pesos

Project
B.5 each 1.00
Billboard/Signboard

In Figures : Pesos
In Words : Pesos In Figures : Pesos

Occupational Safety
B.7 (1) month 2.00
and Health Program

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Mobilization/
B.9 L.S. 1.00
Demobilization

In Figures : Pesos

Sub-Total (This Sheet)

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 1 of 26


Sheet 1

In Words : Pesos In Figures : Pesos


Additional
Geotechnical
Investigation (Geo-
B.13 L.M. 165.00
Resistivity Survey for
Groundwater
Exploration) In Figures : Pesos

PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS


DIVISION I - GENERAL
Part A EARTHWORKS
In Words : Pesos In Figures : Pesos

Structure Excavation
803 (1) a cu.m. 20.49
(Common Soil)

In Figures : Pesos

Part B PLAIN AND REINFORCED CONCRETE WORK


In Words : Pesos In Figures : Pesos

Structural Concrete
900 (1) b1 cu.m. 6.80
(Class A, 14 days)

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Reinforcing Steel
902 (1) a kg. 1,045.10
(Deformed), Grade 40

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Formworks and
903 (1) L.S. 1.00
Falseworks

In Figures : Pesos

DIVISION II - BUILDINGS
Part D ELECTRICAL
In Words : Pesos In Figures : Pesos

Solar Panel with


1102 (18) Inverter, Battery, and L.S. 1.00
Other Devices

In Figures : Pesos

Sub-Total (This Sheet)

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 2 of 26


Sheet 1

Part E MECHANICAL
In Words : Pesos In Figures : Pesos

Water Pumping
1201 (1) L.S. 1.00
System

In Figures : Pesos

In Words : Pesos In Figures : Pesos

1201 (8) Water Tank set 1.00

In Figures : Pesos

DIVISION IV - FLOOD CONTROL, DRAINAGE, AND WATER SUPPLY


Part I WATER SUPPLY
In Words : Pesos In Figures : Pesos

1602 (2) Cast Iron Water Pipe L.S. 1.00

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Polyethylene (PE)
1602 (5) L.S. 1.00
Plastic Pipe

In Figures : Pesos

In Words : Pesos In Figures : Pesos

1603 (1) Valve L.S. 1.00

In Figures : Pesos

Sub-Total (This Sheet)

Sub-Total (Site No. 1)

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 3 of 26


Sheet 1

Site No. 2 Construction of Water Supply System Level II, Brgy. Cabarian, Ligao City, Albay

Sub-ABC (Site No. 2) = PhP 2,970,000.00


PART II OTHER GENERAL REQUIREMENTS
In Words : Pesos In Figures : Pesos

Project
B.5 each 1.00
Billboard/Signboard

In Figures : Pesos
In Words : Pesos In Figures : Pesos

Occupational Safety
B.7 (1) month 2.00
and Health Program

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Mobilization/
B.9 L.S. 1.00
Demobilization

In Figures : Pesos

In Words : Pesos In Figures : Pesos


Additional
Geotechnical
Investigation (Geo-
B.13 L.M. 165.00
Resistivity Survey for
Groundwater
Exploration) In Figures : Pesos

PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS


DIVISION I - GENERAL
Part A EARTHWORKS
In Words : Pesos In Figures : Pesos

Structure Excavation
803 (1) a cu.m. 20.49
(Common Soil)

In Figures : Pesos

Part B PLAIN AND REINFORCED CONCRETE WORK


In Words : Pesos In Figures : Pesos

Structural Concrete
900 (1) b1 cu.m. 6.80
(Class A, 14 days)

In Figures : Pesos

Sub-Total (This Sheet)

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 4 of 26


Sheet 1

In Words : Pesos In Figures : Pesos

Reinforcing Steel
902 (1) a kg. 1,045.10
(Deformed), Grade 40

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Formworks and
903 (1) L.S. 1.00
Falseworks

In Figures : Pesos

DIVISION II - BUILDINGS
Part D ELECTRICAL
In Words : Pesos In Figures : Pesos

Solar Panel with


1102 (18) Inverter, Battery, and L.S. 1.00
Other Devices

In Figures : Pesos

Part E MECHANICAL
In Words : Pesos In Figures : Pesos

Water Pumping
1201 (1) L.S. 1.00
System

In Figures : Pesos

In Words : Pesos In Figures : Pesos

1201 (8) Water Tank set 1.00

In Figures : Pesos

DIVISION IV - FLOOD CONTROL, DRAINAGE, AND WATER SUPPLY


Part I WATER SUPPLY
In Words : Pesos In Figures : Pesos

1602 (2) Cast Iron Water Pipe L.S. 1.00

In Figures : Pesos

Sub-Total (This Sheet)

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 5 of 26


Sheet 1

In Words : Pesos In Figures : Pesos

Polyethylene (PE)
1602 (5) L.S. 1.00
Plastic Pipe

In Figures : Pesos

In Words : Pesos In Figures : Pesos

1603 (1) Valve L.S. 1.00

In Figures : Pesos

Sub-Total (This Sheet) Site No. 2

Sub-Total (Site No. 2)

Site No. 3 Construction of Water Supply System Level II, Brgy. Catburawan, Ligao City, Albay

Sub-ABC (Site No. 3) = PhP 2,970,000.00


PART II OTHER GENERAL REQUIREMENTS
In Words : Pesos In Figures : Pesos

Project
B.5 each 1.00
Billboard/Signboard

In Figures : Pesos
In Words : Pesos In Figures : Pesos

Occupational Safety
B.7 (1) month 2.00
and Health Program

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Mobilization/
B.9 L.S. 1.00
Demobilization

In Figures : Pesos

Sub-Total (This Sheet) Site No. 3

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 6 of 26


Sheet 1

In Words : Pesos In Figures : Pesos


Additional
Geotechnical
Investigation (Geo-
B.13 L.M. 165.00
Resistivity Survey for
Groundwater
Exploration) In Figures : Pesos

PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS


DIVISION I - GENERAL
Part A EARTHWORKS
In Words : Pesos In Figures : Pesos

Structure Excavation
803 (1) a cu.m. 20.49
(Common Soil)

In Figures : Pesos

Part B PLAIN AND REINFORCED CONCRETE WORK


In Words : Pesos In Figures : Pesos

Structural Concrete
900 (1) b1 cu.m. 6.80
(Class A, 14 days)

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Reinforcing Steel
902 (1) a kg. 1,045.10
(Deformed), Grade 40

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Formworks and
903 (1) L.S. 1.00
Falseworks

In Figures : Pesos

DIVISION II - BUILDINGS
Part D ELECTRICAL
In Words : Pesos In Figures : Pesos

Solar Panel with


1102 (18) Inverter, Battery, and L.S. 1.00
Other Devices

In Figures : Pesos

Sub-Total (This Sheet)

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 7 of 26


Sheet 1

Part E MECHANICAL
In Words : Pesos In Figures : Pesos

Water Pumping
1201 (1) L.S. 1.00
System

In Figures : Pesos

In Words : Pesos In Figures : Pesos

1201 (8) Water Tank set 1.00

In Figures : Pesos

DIVISION IV - FLOOD CONTROL, DRAINAGE, AND WATER SUPPLY


Part I WATER SUPPLY
In Words : Pesos In Figures : Pesos

1602 (2) Cast Iron Water Pipe L.S. 1.00

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Polyethylene (PE)
1602 (5) L.S. 1.00
Plastic Pipe

In Figures : Pesos

In Words : Pesos In Figures : Pesos

1603 (1) Valve L.S. 1.00

In Figures : Pesos

Sub-Total (This Sheet)

Sub-Total (Site No. 3)

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 8 of 26


Sheet 1

Site No. 4 Construction of Water Supply System Level II, Brgy. Maonon, Ligao City, Albay

Sub-ABC (Site No. 4) = PhP 2,970,000.00


PART II OTHER GENERAL REQUIREMENTS
In Words : Pesos In Figures : Pesos

Project
B.5 each 1.00
Billboard/Signboard

In Figures : Pesos
In Words : Pesos In Figures : Pesos

Occupational Safety
B.7 (1) month 2.00
and Health Program

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Mobilization/
B.9 L.S. 1.00
Demobilization

In Figures : Pesos

In Words : Pesos In Figures : Pesos


Additional
Geotechnical
Investigation (Geo-
B.13 L.M. 165.00
Resistivity Survey for
Groundwater
Exploration) In Figures : Pesos

PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS


DIVISION I - GENERAL
Part A EARTHWORKS
In Words : Pesos In Figures : Pesos

Structure Excavation
803 (1) a cu.m. 20.49
(Common Soil)

In Figures : Pesos

Part B PLAIN AND REINFORCED CONCRETE WORK


In Words : Pesos In Figures : Pesos

Structural Concrete
900 (1) b1 cu.m. 6.80
(Class A, 14 days)

In Figures : Pesos

Sub-Total (This Sheet)

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 9 of 26


Sheet 1

In Words : Pesos In Figures : Pesos

Reinforcing Steel
902 (1) a kg. 1,045.10
(Deformed), Grade 40

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Formworks and
903 (1) L.S. 1.00
Falseworks

In Figures : Pesos

DIVISION II - BUILDINGS
Part D ELECTRICAL
In Words : Pesos In Figures : Pesos

Solar Panel with


1102 (18) Inverter, Battery, and L.S. 1.00
Other Devices

In Figures : Pesos

Part E MECHANICAL
In Words : Pesos In Figures : Pesos

Water Pumping
1201 (1) L.S. 1.00
System

In Figures : Pesos

In Words : Pesos In Figures : Pesos

1201 (8) Water Tank set 1.00

In Figures : Pesos

DIVISION IV - FLOOD CONTROL, DRAINAGE, AND WATER SUPPLY


Part I WATER SUPPLY
In Words : Pesos In Figures : Pesos

1602 (2) Cast Iron Water Pipe L.S. 1.00

In Figures : Pesos

Sub-Total (This Sheet)

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 10 of 26


Sheet 1

In Words : Pesos In Figures : Pesos

Polyethylene (PE)
1602 (5) L.S. 1.00
Plastic Pipe

In Figures : Pesos

In Words : Pesos In Figures : Pesos

1603 (1) Valve L.S. 1.00

In Figures : Pesos

Sub-Total (This Sheet) Site No. 4

Sub-Total (Site No. 4)

Site No. 5 Construction of Water Supply System Level II, Brgy. Palapas, Ligao City, Albay

Sub-ABC (Site No. 5) = PhP 2,970,000.00


PART II OTHER GENERAL REQUIREMENTS
In Words : Pesos In Figures : Pesos

Project
B.5 each 1.00
Billboard/Signboard

In Figures : Pesos
In Words : Pesos In Figures : Pesos

Occupational Safety
B.7 (1) month 2.00
and Health Program

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Mobilization/
B.9 L.S. 1.00
Demobilization

In Figures : Pesos

Sub-Total (This Sheet)

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 11 of 26


Sheet 1

In Words : Pesos In Figures : Pesos


Additional
Geotechnical
Investigation (Geo-
B.13 L.M. 165.00
Resistivity Survey for
Groundwater
Exploration) In Figures : Pesos

PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS


DIVISION I - GENERAL
Part A EARTHWORKS
In Words : Pesos In Figures : Pesos

Structure Excavation
803 (1) a cu.m. 20.49
(Common Soil)

In Figures : Pesos

Part B PLAIN AND REINFORCED CONCRETE WORK


In Words : Pesos In Figures : Pesos

Structural Concrete
900 (1) b1 cu.m. 6.80
(Class A, 14 days)

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Reinforcing Steel
902 (1) a kg. 1,045.10
(Deformed), Grade 40

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Formworks and
903 (1) L.S. 1.00
Falseworks

In Figures : Pesos

DIVISION II - BUILDINGS
Part D ELECTRICAL
In Words : Pesos In Figures : Pesos

Solar Panel with


1102 (18) Inverter, Battery, and L.S. 1.00
Other Devices

In Figures : Pesos

Sub-Total (This Sheet)

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 12 of 26


Sheet 1

Part E MECHANICAL
In Words : Pesos In Figures : Pesos

Water Pumping
1201 (1) L.S. 1.00
System

In Figures : Pesos

In Words : Pesos In Figures : Pesos

1201 (8) Water Tank set 1.00

In Figures : Pesos

DIVISION IV - FLOOD CONTROL, DRAINAGE, AND WATER SUPPLY


Part I WATER SUPPLY
In Words : Pesos In Figures : Pesos

1602 (2) Cast Iron Water Pipe L.S. 1.00

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Polyethylene (PE)
1602 (5) L.S. 1.00
Plastic Pipe

In Figures : Pesos

In Words : Pesos In Figures : Pesos

1603 (1) Valve L.S. 1.00

In Figures : Pesos

Sub-Total (This Sheet)

Sub-Total (Site No. 5)

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 13 of 26


Sheet 1

Site No. 6 Construction of Water Supply System Level II, Brgy. San Vicente, Ligao City, Albay

Sub-ABC (Site No. 6) = PhP 2,970,000.00


PART II OTHER GENERAL REQUIREMENTS
In Words : Pesos In Figures : Pesos

Project
B.5 each 1.00
Billboard/Signboard

In Figures : Pesos
In Words : Pesos In Figures : Pesos

Occupational Safety
B.7 (1) month 2.00
and Health Program

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Mobilization/
B.9 L.S. 1.00
Demobilization

In Figures : Pesos

In Words : Pesos In Figures : Pesos


Additional
Geotechnical
Investigation (Geo-
B.13 L.M. 165.00
Resistivity Survey for
Groundwater
Exploration) In Figures : Pesos

PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS


DIVISION I - GENERAL
Part A EARTHWORKS
In Words : Pesos In Figures : Pesos

Structure Excavation
803 (1) a cu.m. 20.49
(Common Soil)

In Figures : Pesos

Part B PLAIN AND REINFORCED CONCRETE WORK


In Words : Pesos In Figures : Pesos

Structural Concrete
900 (1) b1 cu.m. 6.80
(Class A, 14 days)

In Figures : Pesos

Sub-Total (This Sheet)

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 14 of 26


Sheet 1

In Words : Pesos In Figures : Pesos

Reinforcing Steel
902 (1) a kg. 1,045.10
(Deformed), Grade 40

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Formworks and
903 (1) L.S. 1.00
Falseworks

In Figures : Pesos

DIVISION II - BUILDINGS
Part D ELECTRICAL
In Words : Pesos In Figures : Pesos

Solar Panel with


1102 (18) Inverter, Battery, and L.S. 1.00
Other Devices

In Figures : Pesos

Part E MECHANICAL
In Words : Pesos In Figures : Pesos

Water Pumping
1201 (1) L.S. 1.00
System

In Figures : Pesos

In Words : Pesos In Figures : Pesos

1201 (8) Water Tank set 1.00

In Figures : Pesos

DIVISION IV - FLOOD CONTROL, DRAINAGE, AND WATER SUPPLY


Part I WATER SUPPLY
In Words : Pesos In Figures : Pesos

1602 (2) Cast Iron Water Pipe L.S. 1.00

In Figures : Pesos

Sub-Total (This Sheet)

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 15 of 26


Sheet 1

In Words : Pesos In Figures : Pesos

Polyethylene (PE)
1602 (5) L.S. 1.00
Plastic Pipe

In Figures : Pesos

In Words : Pesos In Figures : Pesos

1603 (1) Valve L.S. 1.00

In Figures : Pesos

Sub-Total (This Sheet) Site No. 6

Sub-Total (Site No. 6)

Site No. 7 Construction of Water Supply System Level II, Brgy. Itaran, Polangui, Albay

Sub-ABC (Site No. 7) = PhP 2,970,000.00


PART II OTHER GENERAL REQUIREMENTS
In Words : Pesos In Figures : Pesos

Project
B.5 each 1.00
Billboard/Signboard

In Figures : Pesos
In Words : Pesos In Figures : Pesos

Occupational Safety
B.7 (1) month 2.00
and Health Program

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Mobilization/
B.9 L.S. 1.00
Demobilization

In Figures : Pesos

Sub-Total (This Sheet) Site No. 7

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 16 of 26


Sheet 1

In Words : Pesos In Figures : Pesos


Additional
Geotechnical
Investigation (Geo-
B.13 L.M. 165.00
Resistivity Survey for
Groundwater
Exploration) In Figures : Pesos

PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS


DIVISION I - GENERAL
Part A EARTHWORKS
In Words : Pesos In Figures : Pesos

Structure Excavation
803 (1) a cu.m. 20.49
(Common Soil)

In Figures : Pesos

Part B PLAIN AND REINFORCED CONCRETE WORK


In Words : Pesos In Figures : Pesos

Structural Concrete
900 (1) b1 cu.m. 6.80
(Class A, 14 days)

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Reinforcing Steel
902 (1) a kg. 1,045.10
(Deformed), Grade 40

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Formworks and
903 (1) L.S. 1.00
Falseworks

In Figures : Pesos

DIVISION II - BUILDINGS
Part D ELECTRICAL
In Words : Pesos In Figures : Pesos

Solar Panel with


1102 (18) Inverter, Battery, and L.S. 1.00
Other Devices

In Figures : Pesos

Sub-Total (This Sheet)

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 17 of 26


Sheet 1

Part E MECHANICAL
In Words : Pesos In Figures : Pesos

Water Pumping
1201 (1) L.S. 1.00
System

In Figures : Pesos

In Words : Pesos In Figures : Pesos

1201 (8) Water Tank set 1.00

In Figures : Pesos

DIVISION IV - FLOOD CONTROL, DRAINAGE, AND WATER SUPPLY


Part I WATER SUPPLY
In Words : Pesos In Figures : Pesos

1602 (2) Cast Iron Water Pipe L.S. 1.00

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Polyethylene (PE)
1602 (5) L.S. 1.00
Plastic Pipe

In Figures : Pesos

In Words : Pesos In Figures : Pesos

1603 (1) Valve L.S. 1.00

In Figures : Pesos

Sub-Total (This Sheet)

Sub-Total (Site No. 7)

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 18 of 26


Sheet 1

Site No. 8 Construction of Water Supply System Level II, Brgy. Karatagan, Pioduran, Albay

Sub-ABC (Site No. 8) = PhP 2,970,000.00


PART II OTHER GENERAL REQUIREMENTS
In Words : Pesos In Figures : Pesos

Project
B.5 each 1.00
Billboard/Signboard

In Figures : Pesos
In Words : Pesos In Figures : Pesos

Occupational Safety
B.7 (1) month 2.00
and Health Program

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Mobilization/
B.9 L.S. 1.00
Demobilization

In Figures : Pesos

In Words : Pesos In Figures : Pesos


Additional
Geotechnical
Investigation (Geo-
B.13 L.M. 165.00
Resistivity Survey for
Groundwater
Exploration) In Figures : Pesos

PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS


DIVISION I - GENERAL
Part A EARTHWORKS
In Words : Pesos In Figures : Pesos

Structure Excavation
803 (1) a cu.m. 20.49
(Common Soil)

In Figures : Pesos

Part B PLAIN AND REINFORCED CONCRETE WORK


In Words : Pesos In Figures : Pesos

Structural Concrete
900 (1) b1 cu.m. 6.80
(Class A, 14 days)

In Figures : Pesos

Sub-Total (This Sheet)

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 19 of 26


Sheet 1

In Words : Pesos In Figures : Pesos

Reinforcing Steel
902 (1) a kg. 1,045.10
(Deformed), Grade 40

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Formworks and
903 (1) L.S. 1.00
Falseworks

In Figures : Pesos

DIVISION II - BUILDINGS
Part D ELECTRICAL
In Words : Pesos In Figures : Pesos

Solar Panel with


1102 (18) Inverter, Battery, and L.S. 1.00
Other Devices

In Figures : Pesos

Part E MECHANICAL
In Words : Pesos In Figures : Pesos

Water Pumping
1201 (1) L.S. 1.00
System

In Figures : Pesos

In Words : Pesos In Figures : Pesos

1201 (8) Water Tank set 1.00

In Figures : Pesos

DIVISION IV - FLOOD CONTROL, DRAINAGE, AND WATER SUPPLY


Part I WATER SUPPLY
In Words : Pesos In Figures : Pesos

1602 (2) Cast Iron Water Pipe L.S. 1.00

In Figures : Pesos

Sub-Total (This Sheet)

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 20 of 26


Sheet 1

In Words : Pesos In Figures : Pesos

Polyethylene (PE)
1602 (5) L.S. 1.00
Plastic Pipe

In Figures : Pesos

In Words : Pesos In Figures : Pesos

1603 (1) Valve L.S. 1.00

In Figures : Pesos

Sub-Total (This Sheet) Site No. 8

Sub-Total (Site No. 8)

Site No. 9 Construction of Water Supply System Level II, Burabod Elementary School, Libon East, Albay

Sub-ABC (Site No. 9) = PhP 2,970,000.00


PART II OTHER GENERAL REQUIREMENTS
In Words : Pesos In Figures : Pesos

Project
B.5 each 1.00
Billboard/Signboard

In Figures : Pesos
In Words : Pesos In Figures : Pesos

Occupational Safety
B.7 (1) month 2.00
and Health Program

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Mobilization/
B.9 L.S. 1.00
Demobilization

In Figures : Pesos

Sub-Total (This Sheet) Site No. 9

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 21 of 26


Sheet 1

In Words : Pesos In Figures : Pesos


Additional
Geotechnical
Investigation (Geo-
B.13 L.M. 165.00
Resistivity Survey for
Groundwater
Exploration) In Figures : Pesos

PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS


DIVISION I - GENERAL
Part A EARTHWORKS
In Words : Pesos In Figures : Pesos

Structure Excavation
803 (1) a cu.m. 20.49
(Common Soil)

In Figures : Pesos

Part B PLAIN AND REINFORCED CONCRETE WORK


In Words : Pesos In Figures : Pesos

Structural Concrete
900 (1) b1 cu.m. 6.80
(Class A, 14 days)

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Reinforcing Steel
902 (1) a kg. 1,045.10
(Deformed), Grade 40

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Formworks and
903 (1) L.S. 1.00
Falseworks

In Figures : Pesos

DIVISION II - BUILDINGS
Part D ELECTRICAL
In Words : Pesos In Figures : Pesos

Solar Panel with


1102 (18) Inverter, Battery, and L.S. 1.00
Other Devices

In Figures : Pesos

Sub-Total (This Sheet)

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 22 of 26


Sheet 1

Part E MECHANICAL
In Words : Pesos In Figures : Pesos

Water Pumping
1201 (1) L.S. 1.00
System

In Figures : Pesos

In Words : Pesos In Figures : Pesos

1201 (8) Water Tank set 1.00

In Figures : Pesos

DIVISION IV - FLOOD CONTROL, DRAINAGE, AND WATER SUPPLY


Part I WATER SUPPLY
In Words : Pesos In Figures : Pesos

1602 (2) Cast Iron Water Pipe L.S. 1.00

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Polyethylene (PE)
1602 (5) L.S. 1.00
Plastic Pipe

In Figures : Pesos

In Words : Pesos In Figures : Pesos

1603 (1) Valve L.S. 1.00

In Figures : Pesos

Sub-Total (This Sheet) Site No. 9

Sub-Total (Site No. 9)

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 23 of 26


Sheet 1

Site No. 10 Construction of Water Supply System Level II, Magallang Elementary School, Libon East, Albay

Sub-ABC (Site No. 10) = PhP 2,970,000.00


PART II OTHER GENERAL REQUIREMENTS
In Words : Pesos In Figures : Pesos

Project
B.5 each 1.00
Billboard/Signboard

In Figures : Pesos
In Words : Pesos In Figures : Pesos

Occupational Safety
B.7 (1) month 2.00
and Health Program

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Mobilization/
B.9 L.S. 1.00
Demobilization

In Figures : Pesos

In Words : Pesos In Figures : Pesos


Additional
Geotechnical
Investigation (Geo-
B.13 L.M. 165.00
Resistivity Survey for
Groundwater
Exploration) In Figures : Pesos

PART III CIVIL, MECHANICAL, ELECTRICAL AND SANITARY/PLUMBING WORKS


DIVISION I - GENERAL
Part A EARTHWORKS
In Words : Pesos In Figures : Pesos

Structure Excavation
803 (1) a cu.m. 20.49
(Common Soil)

In Figures : Pesos

Part B PLAIN AND REINFORCED CONCRETE WORK


In Words : Pesos In Figures : Pesos

Structural Concrete
900 (1) b1 cu.m. 6.80
(Class A, 14 days)

In Figures : Pesos

Sub-Total (This Sheet)

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 24 of 26


Sheet 1

In Words : Pesos In Figures : Pesos

Reinforcing Steel
902 (1) a kg. 1,045.10
(Deformed), Grade 40

In Figures : Pesos

In Words : Pesos In Figures : Pesos

Formworks and
903 (1) L.S. 1.00
Falseworks

In Figures : Pesos

DIVISION II - BUILDINGS
Part D ELECTRICAL
In Words : Pesos In Figures : Pesos

Solar Panel with


1102 (18) Inverter, Battery, and L.S. 1.00
Other Devices

In Figures : Pesos

Part E MECHANICAL
In Words : Pesos In Figures : Pesos

Water Pumping
1201 (1) L.S. 1.00
System

In Figures : Pesos

In Words : Pesos In Figures : Pesos

1201 (8) Water Tank set 1.00

In Figures : Pesos

DIVISION IV - FLOOD CONTROL, DRAINAGE, AND WATER SUPPLY


Part I WATER SUPPLY
In Words : Pesos In Figures : Pesos

1602 (2) Cast Iron Water Pipe L.S. 1.00

In Figures : Pesos

Sub-Total (This Sheet)

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 25 of 26


Sheet 1

In Words : Pesos In Figures : Pesos

Polyethylene (PE)
1602 (5) L.S. 1.00
Plastic Pipe

In Figures : Pesos

In Words : Pesos In Figures : Pesos

1603 (1) Valve L.S. 1.00

In Figures : Pesos

Sub-Total (This Sheet)

Sub-Total (Site No. 10)

In Words : Pesos In Figures : Pesos

TOTAL
(10 sites)

Submitted by:

Date :
Name & Signature of the Representative of Bidder

Position

Name of Bidder

20FO0100 - Standard Bidding Document / BOQ (Rev 1) Page 26 of 26