International Delay Analysis Approaches
International Delay Analysis Approaches
International Delay Analysis Approaches
Approaches
Delay Analysis References, Categories and Perspectives
Mohamed Maged Hegazy
Associate Planning Director - Red Sea Global, LLM, MBA, BSc, MRICS, CCP, PMP
Project Planning and Scheduling Delay Analysis Contractual and Legal Aspects
Content
1) Introduction
Contractual Procedure
EOT Entitlement
Delay Analysis
EOT Claims
Key References
Additional References
2- Delay Analysis Categories
Types, timing and basis of delay analysis
Interim vs Final Extension of Time
Impact/Update – Timeslices
Driven by a delay schedule and subject to time slices within which the anticipated and
actual progress is analysed. Strong in addressing mitigation and concurrent delays.
Other Categories
Delay Analysis Approaches
Compensable Non-Compensable
Impact / Predict
Prompt Action – Prospective Analysis
4. Do not 'wait and see' regarding impact of
delay events (contemporaneous analysis)
Applications for an EOT should be made and dealt with as close in time as
possible to the delay event. A 'wait and see' approach to assessing EOT is
discouraged.
Where the Contractor has complied with its contractual obligations regarding
delay events and EOT applications, the Contractor should not be prejudiced in
any dispute with the Employer as a result of the CA failing to assess EOT
applications.
EOT entitlement should be assessed by the CA within a reasonable time (4.1:
not later than one month) after submission of an EOT application by the
Contractor.
The Contractor potentially will be entitled to an EOT only for those events or
causes of delay in respect of which the Employer has assumed risk and
responsibility (called in the Protocol Employer Risk Events) that impact the
critical path.
Contemporaneous analysis of delay
(Is it an ERE?)
Simply stating that Employer Risk Events have occurred and claiming the whole
of any delay apparent at the time of the events is not a proper demonstration of
entitlement.
4.4 These events vary between the different standard forms of contract, and care
is needed when reading them. When granting or refusing an EOT, the CA should
provide sufficient information to allow the Contractor to understand the reasons
for the CA’s decision.
Common Sense
4.14 Although the Updated Programme should be the primary tool for
guiding the CA in its determination of an EOT, it should be used in
conjunction with the contemporary evidence to ensure that any
resulting EOT is both reasonable and consistent with the factual
circumstances.
It will also be necessary for the parties to apply common sense and
experience to the process to ensure that all relevant factors are taken
into account, and that any anomalous results generated by the delay
analysis are properly managed. Any resulting EOT must be consistent
with the contractual requirements regarding entitlement.
7. Incremental review of extension of time
11.2 Irrespective of which method of delay analysis is deployed, this is particularly relevant where there is
a significant risk that the remaining duration projections, logic links, calendars and constraints within the
baseline programme (preferably the Accepted/Updated Programme) might produce anomalous results.
OTHER TECHNIQUES
11.4e Delay impact is determined in one of two different ways. A prospective delay analysis identifies the likely
impact of historical progress or delay events on a completion date. The conclusions of a prospective delay
analysis may not match the as-built programme because the Contractor's actual performance may well have
been influenced by the effects of attempted acceleration, re-sequencing or redeployment of resources in
order to try to avoid liability for liquidated damages or due to other Employer and Contractor Risk Events. A
retrospective delay analysis identifies the actual impact of the delay events on the identified actual or as-built
critical path.
11. 7 Other methods, which may be reasonably deployed in particular circumstances having considered the
criteria in paragraph 11.3 above, include: project wide retrospective as-planned versus as-built analysis (i.e.
not in windows), time chainage analysis, line of balance analysis, resource curve analysis, and earned value
analysis.
11.8 In order to avoid or at least minimise disputes over methodology, it is recommended that the parties
try to agree an appropriate method of delay analysis before each embarks upon significant work on or after the
event delay analysis.
Other Methods - Delay Quantification and Forecasting
5- Schedule Delay Analysis - American Society of
Civil Engineers, Construction Institute Standard
ANSI/ASCE/CI 67-17 Chronology, Responsibility & After the fact
ASCE – Schedule Delay Analysis
7 CHRONOLOGY OF DELAY
8.1 Concurrent Delay Can Be Described as a Situation Where Two or More Critical
Delays Are Occurring at the Same Time During All or a Portion of the Delay Time
Frame in Which the Delays Are Occurring
8.2 Concurrent Delay Typically Is Excusable but Noncompensable, Meaning a Time
Extension Is Given but No Costs Are Recovered by Either Party
8.3 Concurrent Delay Should Be Apportioned Where Possible
9 RESPONSIBILITY FOR DELAY
9.1 A Schedule Expert Typically Can Identify the Party Responsible for a Delay from the
Contemporaneous Records, Interviewing Project Personnel, and Reading Deposition
Testimony, and May Rely on Technical Experts or Fact Witnesses in Opining on Liability
9.2 During a Project, the Contractor Should Provide the Owner with a Notice of Delay for
Excusable Delays, Followed by a Request for a Change in Accordance with the Contract.
9.3 Responsibility Analysis Should Be Supported by a Factual Chronology Based on the
Contemporaneous Project Performance Records and Referencing the Remedy-Granting
Clause of the Contract
9.5 Schedule Experts Should Not Opine Beyond Their Expertise. If Necessary, a Technical
Expert Should Be Engaged on Whose Opinion the Schedule Expert Can Rely
9.6 Once a Technical Expert’s Finding as to Which Party Was Liable for the Delay Event Is
Formed, a Legal Review May Be Made with Counsel Consistent with Legal Precedent in the
Project Jurisdiction
10 CHANGING SCHEDULES AFTER THE FACT
10.1 The Schedules Should Be Presumed Correct as They Were Used During the
Project, Unless Otherwise Shown to Be Inaccurate
10.2 After-the-Fact Changes to Schedules Used During the Project Should Be
Minimized and Only Made Where Necessary
10.3 Any Changes Made to the Contemporaneous Record of Project Schedules
Should Be Carefully Identified and Documented
10.4 When Possible, the Preference for Dealing with Inaccurate Schedules After the
Fact Is to Make Corrections, Rather than Abandon the Schedules, Subject to the
Nature and Scope of the Corrections
10.5 Changes to Schedules Generally May Be Made to Correct Necessary Physical or
Contractual Constraints but Typically Not the Contractor’s Preferential Sequencing
12 References
6- AACE Recommended Practices RPs
RP 52R-06 TIA & RP 29R-03 Forensic Schedule Analysis
Delay Analysis Approaches - AACE
Prospective Retrospective
The appropriate 1. Classification and
update schedule is the Principles
most recently
reviewed schedule
update before the 2. Source Validation
event (unimpacted
schedule).
3. Method
Implementation
Insert a modeled
fragnet into the
schedule, then check 4. Analysis Evaluation
logic and duration,
and finally recalculate
the CPM to measure 5. CHOOSING A
the time impact. METHOD
AACE 52R-06 TIA Flowchart – 8 Steps
The MIP of the modeled additive method (3.6 MIP) can be also applied when
required as per AACE RP 29R-03 (Forensic Schedule Analysis).
I. Determination and Quantification of Excusable and Compensable Delay. An additive-modeled
schedule by itself does not account for concurrent delays and compensability. However, it is possible
to analyze for approximate concurrency by comparing two additive-modeled schedules (one by
inserting all owner-caused and force majeure-caused impact events into the baseline & another one
by inserting all contractor-caused impact events into the baseline).
K. Specific Implementation Procedures and Enhancements. Global Insertion (total impact)- Stepped
Insertion (in chronological order).
L. Considerations in Using Min Protocol. Suited primarily for the use in identifying and quantifying
potential delays rather than actual delays - Easy & doesn’t need as-built schedule - Does not account
for concurrent/pacing delays/acceleration .
Additional Validation –AACE 29R-03
Additional (SVPs)
The SVPs of the modeled additive method (3.6 MIP) can be also applied when required as per AACE
RP 29R-03.
Baseline
Enhancement: Each activity to be 0.5% to 5% of contract value - Separate as per responsible party -
Add activities to enhance the level of detail - Divide act.s based on progress records.
Update
Investigation: If update is the primary source, check: (Actual dates vs data date - Using the most
reliable source/ interviews if possible - Changes in IDs & scope) - Accuracy of dates of significant
activities to be 1 working day, and other activities to be 5 days - Consistency of dates along the
updates - Change in longest path/ controlling activities.
Enhancement: Tabulate all sources of data - Show discrete activities for delay events and influences -
Subdivide vague or general activities.
Evaluate Pacing or Acceleration (if exist).
Retrospective Delay Analysis (Foresnic)
Forensic Schedule Analysis:
A technical field of studying and investigating the schedule calculation using different methods (usually
requires many subjective decisions by professionals) to measure and quantify delay focusing on causation
to resolve EOT disputes.
Observational: Examining the schedule itself without changes. Modeled: Representing delay events in schedule.
Static: Same network - Dynamic: updates with variations. Additive: add to a base - Subtractive: from as-built.
2. Source Validation Protocols (SVP)
2.1. Baseline 2.2. As-built 2.3. Updates 2.4. Delay Events
3. Method Implementation
E F G,H,I,J
A&B Description & C&D K Specific L M
Min. Enhance Identification &
Common names SVP Procedures Cons Caveats
MIP ment Quantification
4. Analysis Evaluation
3. Critical Path 2. Concurrency 1. Excusability & 4. Mitigation &
and Float Quantification Compensability Acceleration
- Closing Notes
Data, EOT claim procedure, Standard forms, Law & Recap
Records / Source Data
No exact method
EOT Claims Procedure
-Contractual entitlement
Typically, construction contracts contain provisions entitling the contractor to an extension of time on the
occurrence of a particular event provided the progress of the works or time for completion is delayed as
a consequence.
-Contractual compliance
Generally within an extension of time clause, the contractor will be obligated to submit notice(s) and
detailed particulars within a specified time frame.
-Governing Law
AIA 2017 - Construction: § 13.1 Governing Law.
- US: “No harm, no foul” rule applies and neither party may
benefit monetarily from the delay (Time but no money).
- Australia: The current Australian authorities favour the “first
in time” approach considering the sequential delays.
- Scotland: City Inn found that it must firstly be considered
whether there was a “dominant” cause of delay.
- Germany: Concept of concurrent causality as parallel but
independent contributions to causation.
- Austria: Austrian courts use the so-called “theory of
spheres”, through which it can be determined whether any
particular cause of a delay falls into the employer’s or the
contractors’ sphere of responsibility.
EOT Sample – Table of Content
Choice of the Appropriate Method
Contractual
EOT Claims
Mechanisms
M.Maged Hegazy
mm.hegazy@ppmconference.net
Mobile : 00966 (0) 58 0264 968