I hereby declare that the Industrial Internship Report entitled "Suratgarh Super Thermal
Power Station Suratgarh, Rajasthan" is an authentic record of own work as requirements of
6 Weeks Industrial Internship for the award of Diploma in Mechanical Engineering, Government
Polytechnic College, Hanumangarh.
(Ajay)
(ME2023L003/117)
Date:__/__/_____
Certified that the above statement made by the student is correct to the best of our knowledge
and belief.
Examined by: 1.
2.
3.
4.
Certified that the above statement made by the student is correct to the best of my knowledge
and belief.
Head of Department
i
ACKNOWLEDGEMENT
I would like to thank Sh. Vikram Sharma, Head of Department of Mechanical Engineering for
his guidance and encouragement throughout my academic career and other faculties.
I express a deep sense of gratitude to Mr. Bhavdeep Assistant Engineer and other staff members
at “Suratgarh Super Thermal Power Station Suratgarh, Rajasthan” for their guidance and co-
operation during my training period.
I would also like to express my profound gratitude to Sh. Jaswant Kumawat (Training &
Placement Officer, III Cell, GPC Hanumangarh) for extending his support for training.
Finally, my heartfelt thanks to my family members for their unconditional love and support.
Words fail me to express my gratitude to my beloved parents and my sister, for their
encouragement, understanding, support and patience during my study.
ii
CONTENT
CERTIFICATE
CANDIDATE’S DECLARATION I
ACKNOWLEDGEMENTS II
1. Introduction
1.1 General 1
2.2 Construction 4
2.2.1 Coal Delivery 4
2.2.2 Coal Storage 4
2.2.3 Coal Crushing 5
2.2.4 Coal Conveying 5
2.3 Working 6
2.3.1 Coal Unloading and Storage 6
2.3.2 Coal Crushing and Screening 6
2.3.3 Coal Pulverization 6
2.4 Technical Considerations 6
2.4.1 Power Consumption 7
iii
3. Principles of Steam Generation
3.1 Steam Generation 8
3.2 Sensible Heat 8
3.3 Latent Heat 8
3.4 Critical Point 8
3.8 Circulation 11
3.9 Circulation Types 11
3.10 Boiler 12
3.11 Water Tube Boiler 13
3.12 Economiser 14
4.1 Introduction 16
iv
5.2.2 MEDIUM SPEED MILLS 19
5.2.3 High Speed Mills 19
5.3 RAW COAL FEEDERS 19
5.3.1 VOLUMETRIC FEEDER 20
5.3.2 GRAVIMETRIC FEEDERS 20
5.4 PULVERISERS 21
6. Electrostatic Precipitators (ESP)
6.1 Introduction 23
6.2 Construction of Electrostatic Precipitators 23
6.2.1 Inlet and Outlet Ducts 23
v
7. Turbine
7.1 Introduction 30
7.2 Construction of Turbines 30
7.3 Types of Turbine: 30
7.3.1 High-Pressure (HP) Turbine 30
REFERENCES