REPORT ON
GEOTECHNICAL INVESTIGATION
FOR CONSTRUCTION OF THE PROPOSED
HIGH LEVEL BRIDGE OVER FALGU RIVER
IN BETWEEN OLD GT ROAD TO VILLAGE CHANDA
VIA BABHAN DEV JUNGLE
BLOCK SHERGHATI, DISTRICT GAYA, BIHAR

Submitted To:

M/S. ACPL GLOBAL PVT. LTD.


KANPUR
UP

Executed By:

JFC LABORATORIES PRIVATE LIMITED


FOUNDATION ENGINEERS, GEOTECH EXPERTS & SOIL INVESTIGATION CONSULTANTS
AN ISO 9001:2015 & ISO/IEC 17025:2017 CERTIFIED
NABL ACCREDITED (TC-10129)
Regd Office: Plot no.-3429, Near Mecon Colony Gate, Kathalmore Chowk
Ranchi, Jharkhand 835303
a
b

)09334454475,*jfcpl.ranchi@gmail.com
8 a b 8
2621B_242060240B
Table of Contents

F Introduction………………………………………………………
1

F Project details…………………………………….. 2

F Laboratory Testings……………………………….. 4

F Subsoil formation & Recommendation……………………..


5

F Calculation of Pile Capacity………………………………………..………….


6-8

F Borelog data sheets…………………………………………..…………….


9

F Test Results……………………………………………..……………………
10

F Curves & Figs……………………………………………..……………………


11-12

F Site photograph……………………………………………..……………………
13
CHAPTER - I
1 INTRODUCTION:
1.1 In an attempt to facilitate the design of the proposed new
construction of the foundation structure of the :

HIGH LEVEL BRIDGE OVER FALGU RIVER IN BETWEEN OLD GT ROAD


TO VILLAGE CHANDA VIA BABHAN DEV JUNGLE BLOCK SHERGHATI,
DISTRICT GAYA, BIHAR
`
A subsoil investigation work was programmed by the authority and
for this work , the services of M/s. JFC Laboratories Private Limited
of Plot no.-3429, Near Mecon Colony Gate, Kathalmore Chowk,
Ranchi, Jharkhand-835303 was sought by :
M/S. ACPL GLOBAL PVT. LTD., KANPUR, UP

1.2 The scope of the soil investigation consisted of making one nos. of
bore hole at this site.
1.3 The formation at the site is to be reported for various layers presented

at their respective depth along with their thickness. This would also

include the subsoil properties for each stratum so as to come up with

the design parameters for designing foundations, the depth of

foundation and the selection of type of foundation. As the ground

water table location influences the bearing capacity of a foundation

and the method of construction of a foundation at the site, its location

has also to be found.

1.4 Soil samples both in disturbed and undisturbed condition wherever

possible are to be collected. These samples would be different

laboratory tests to obtain various properties of sub-soil formation.


1.5 The exploration of the sub-soil formation being limited to one no. of
bore hole it is suggested that due weighted is to be given to this
location only unexplored part (pires) of the area will not be considered
at the time of selecting design parameters.
CHAPTER - II
2 PROJECT DETAILS
2.1 The fieldwork consisted of one nos. of bore hole at pre-determined
location. The detail of fieldwork like depth of bore hole, date of the field
work of site are presented below in tabular form
Bore Hole / Depth of Bore Date of Date of Date of
Test No. Hole (m) Commencement Completion Completion

BH - 3 (P2) 17.00 23/05/2024 26/05/2024 12/06/2022

The fieldwork also included collection of disturbed and undisturbed


soil samples and conducting standard penetration tests at regular
intervals.

2.2 The bore holes of 150mm diameter (SX size) are initially sunk by hand
auger boring upto the water table and thereafter by rotary boring with
bentonite mud circulation.

In case rock encountered, bore holes of 150mm diameter (SX size) are
initially sunk by hand auger boring upto the refusal strata (N>100) in
line with specification. For further advancement of bore holes rotary
drilling technique is adopted upto the termination depth as directed by
the client. Drilling was done with standard G.O. type rotary drilling
machine as per IS: 6926. In this method the hole was advanced by

rotating a system, consisting of a series of hollow drill rods to the


bottom of which is attached a barrel with a TC/Diamond coring bit, by

means of a diesel operated engine.

High Level Bridge over Falgu River


2 at Old GT Road, Sherghati, Gaya
When the rod with the coring bit is rotated, downward pressure is

applied into the bottom of the hole through the hollow drill rods.

Water comes up through the annular space between the drill rods and

the bore hole and is collected in the water sump, from where it is re-

circulated. Water services the dual function of cooling the bit as it

enters the hole and carrying cutting from the bottom of the hole on its

return journey to the surface.

2.3 Ground water level in the bore holes within the explored depth below

the existing ground level was observed during boring work and also

after 24 hours of the completion of the field work.

High Level Bridge over Falgu River


3 at Old GT Road, Sherghati, Gaya
CHAPTER - III

3 LABORATORY TESTING:

The following tests were performed in the laboratory adopting


standard practice
1 Grain size analysis.

2 Bulk Density.

3 Specific Gravity.

4 Direct Shear test.

5 Crushing strength test.

The tests were conducted as per relevant IS Specifications

High Level Bridge over Falgu River


4 at Old GT Road, Sherghati, Gaya
CHAPTER - V
5 SOIL PROFILE AND & RECOMMENDATION
From the exploratory bore holes at the site it is observed that sub soil

formation at this site consists of cohesionless formation at surface

layer upto the depth of around 8.50m and fracture to fresh rock

observed below upto the explored depth of 17.0m. Details of the

formations along with the “N” values are shown in the field bore log

data sheets.

However, based on calculation the following Pile capacities are


suggested:
Sl. Founding Depth Pile capacity. (Ton)
No. from Scour level for 1500mm dia.
(m)
1 11.5 490.0
2 12.0 530.0
3 12.5 570.0
* Since the length of bridge is approximately 240.0m, single location's result may
not reflect for whole length of the bridge.
** Founding depth of the pile capacity should be considered from the scour depth
only, not from EGL
*** Detail calculations of pile capacities are shown in the subsequent pages.

(A Maiti)
(ME, Soil Mech. Fdn. Engg.)
(Chartered Engineer)

High Level Bridge over Falgu River


5 at Old GT Road, Sherghati, Gaya
Determination of pile capacity

Considering the nature of subsoil and type of foundation to be constructed at the site deep
foundation in the form of pile
EGL = 0.000 m
Such pile can be placed at = -11.500 m (Rl)
Cut off level = 4.00 m (bgl)
Effective length of the pile shaft = 7.50 m
Max. Scour level = = -4.00 m
(Rl)
The ultimate bearing capacity (Qu) of piles is given by the following formula:
D
Qu = Ap(0.5DgNg + PDNq) +SK PDitandAsi [ Cl. No 5.3.1.1
i =1 IS:2911(PartI/Sec2)-2010]
2
Where Ap = Cross sectional area of pile toe in cm
D = stem diameter in cm
g = effective unit weight of soil at pile toe in kg/cm3
Pd = Effective overburden pressure at pile toe kg/cm3
Nq, Ng = bearing capacity factors
K = coefficient of earth pressure
d = angle of wall friction between pile and soil
Asi = Surface area of pile stem in cm2

Sub-soil Properties
Effective Cohesion Angle of Sub.
From - To depth internal Density Nc Ng Nq
(m) 2 friction 3
t/m t/m
4.00 - 8.50 4.50 0 30 0.850

8.50 - 8.50 0.00 8.0 0 0.900

8.50 - 8.50 0.00 0 0 0.950

8.50 - 11.50 3.00 0 40 1.000 64.2 109.4


Tatal = 7.50
Dia of the pile = 1.50 m K = 1
2
Cross sectional area of pile 1.7671 m a = 0.5
Pile capacity
Clay ApNcCp aCAs
For
Sand Ap(0.5DgNg + PDNq) K PDitandAsi Total
End 4 - 8.5m 8.5 - 8.5m8.5 - 8.5m8.5 - 11.5m

Sand layer 1404.536 23.415 0.000 0.000 63.168 1491.119


For
Clay layer 0 0.000 0 0 0 0
Total 1491.12
Factor of safety = 3
Safe axial load carrying capacity of pile = 497.040 Ton
Based on the above calculation it is suggested that
safe axial load carring capacity may be taken as : 490.00 Ton
Lataral capacity of pile should be checked against as per Cl. No.- 5.5.2, IS:2911 (Part -1/Sec-2)-2010
High Level Bridge over Falgu River
JFC 6 at Old GT Road, Sherghati, Gaya
Determination of pile capacity

Considering the nature of subsoil and type of foundation to be constructed at the site deep
foundation in the form of pile
EGL = 0.000 m
Such pile can be placed at = -12.000 m (Rl)
Cut off level = 4.00 m (bgl)
Effective length of the pile shaft = 8.00 m
Max. Scour level = = -4.00 m
(Rl)
The ultimate bearing capacity (Qu) of piles is given by the following formula:
D
Qu = Ap(0.5DgNg + PDNq) +SK PDitandAsi [ Cl. No 5.3.1.1
i =1 IS:2911(PartI/Sec2)-2010]
2
Where Ap = Cross sectional area of pile toe in cm
D = stem diameter in cm
g = effective unit weight of soil at pile toe in kg/cm3
Pd = Effective overburden pressure at pile toe kg/cm3
Nq, Ng = bearing capacity factors
K = coefficient of earth pressure
d = angle of wall friction between pile and soil
Asi = Surface area of pile stem in cm2

Sub-soil Properties
Effective Cohesion Angle of Sub.
From - To depth internal Density Nc Ng Nq
(m) 2 friction 3
t/m t/m
4.00 - 8.50 4.50 0 30 0.850

8.50 - 8.50 0.00 8.0 0 0.900

8.50 - 8.50 0.00 0 0 0.950

8.50 - 12.00 3.50 0 40 1.000 64.2 109.4


Tatal = 8.00
Dia of the pile = 1.50 m K = 1
2
Cross sectional area of pile 1.7671 m a = 0.5
Pile capacity
Clay ApNcCp aCAs
For
Sand Ap(0.5DgNg + PDNq) K PDitandAsi Total
End 4 - 8.5m 8.5 - 8.5m8.5 - 8.5m 8.5 - 12m

Sand layer 1501.199 23.415 0.000 0.000 77.156 1601.770


For
Clay layer 0 0.000 0 0 0 0
Total 1601.77
Factor of safety = 3
Safe axial load carrying capacity of pile = 533.923 Ton
Based on the above calculation it is suggested that
safe axial load carring capacity may be taken as : 530.00 Ton
Lataral capacity of pile should be checked against as per Cl. No.- 5.5.2, IS:2911 (Part -1/Sec-2)-2010
High Level Bridge over Falgu River
JFC 7 at Old GT Road, Sherghati, Gaya
Determination of pile capacity

Considering the nature of subsoil and type of foundation to be constructed at the site deep
foundation in the form of pile
EGL = 0.000 m
Such pile can be placed at = -12.500 m (Rl)
Cut off level = 4.00 m (bgl)
Effective length of the pile shaft = 8.50 m
Max. Scour level = = -4.00 m
(Rl)
The ultimate bearing capacity (Qu) of piles is given by the following formula:
D
Qu = Ap(0.5DgNg + PDNq) +SK PDitandAsi [ Cl. No 5.3.1.1
i =1 IS:2911(PartI/Sec2)-2010]
2
Where Ap = Cross sectional area of pile toe in cm
D = stem diameter in cm
g = effective unit weight of soil at pile toe in kg/cm3
Pd = Effective overburden pressure at pile toe kg/cm3
Nq, Ng = bearing capacity factors
K = coefficient of earth pressure
d = angle of wall friction between pile and soil
Asi = Surface area of pile stem in cm2

Sub-soil Properties
Effective Cohesion Angle of Sub.
From - To depth internal Density Nc Ng Nq
(m) 2 friction 3
t/m t/m
4.00 - 8.50 4.50 0 30 0.850

8.50 - 8.50 0.00 8.0 0 0.900

8.50 - 8.50 0.00 0 0 0.950

8.50 - 12.50 4.00 0 40 1.000 64.2 109.4


Tatal = 8.50
Dia of the pile = 1.50 m K = 1
2
Cross sectional area of pile 1.7671 m a = 0.5
Pile capacity
Clay ApNcCp aCAs
For
Sand Ap(0.5DgNg + PDNq) K PDitandAsi Total
End 4 - 8.5m 8.5 - 8.5m8.5 - 8.5m8.5 - 12.5m

Sand layer 1597.862 23.415 0.000 0.000 92.132 1713.409


For
Clay layer 0 0.000 0 0 0 0
Total 1713.41
Factor of safety = 3
Safe axial load carrying capacity of pile = 571.136 Ton
Based on the above calculation it is suggested that
safe axial load carring capacity may be taken as : 570.00 Ton
Lataral capacity of pile should be checked against as per Cl. No.- 5.5.2, IS:2911 (Part -1/Sec-2)-2010
High Level Bridge over Falgu River
JFC 8 at Old GT Road, Sherghati, Gaya
GEOTECHNICAL INVESTIGATION FOR THE CONSTRUCTION OF THE PROPOSED
HIGH LEVEL BRIDGE OVER FALGU RIVER IN BETWEEN OLD GT ROAD TO VILLAGE CHANDA VIA BABHAN
DEV JUNGLE BLOCK SHERGHATI, DISTRICT GAYA, BIHAR
FIELD BORE / DRILL LOG DATA SHEET
Bore Hole No. : BH-03 (P2) : 99.760m
Chainage : 233.761 Water Level : 1.70 m bgl
Method of Boring : Auger and Rotary Dia. of the Bore Hole : 150 mm / 76mm
Date of Commencement: 23/05/2024 Date of Completion : 26/05/2024
Date DESCRIPTION Sample & In situ test Length No of blows (SPT)/ N-Value / Type of

Symbol
and DEPTH/RUN ( m) (m) Core recovered (m) Recovery sample/RQD Remarks
Depth
From To 0-15 15-30 30-45

0.00 0.50 - - - - - DS

1.50 1.95 0.45 2 2 3 5 SPT/DS


Coarse sand mix gravels and
boulder 3.00 3.45 0.45 3 4 4 8 SPT/DS

4.50 4.95 0.45 4 6 7 13 SPT/DS

6.00 6.45 0.45 5 7 9 16 SPT/DS

7.50 7.95 0.45 6 8 11 19 SPT/DS

8.50m
9.00 9.35 0.35 17, 35, 100 for 5cm N>100 SPT

Highly decomposed to
Drilling started from 9.00 m
decomposed product of
weathered rock
9.00 10.50 1.50 0.00 0% 0%-C

10.50 10.52 0.02 100 for 2cm N>100 SPT


10.50
10.50 12.00 1.50 0.80 53 % 34%-C

Fractured to hard rock


12.00 13.50 1.50 0.75 50 % 37%-C

13.50 15.00 1.50 0.85 56 % 50%-C


15.00
m
15.00 16.00 1.00 0.90 90 % 58%-C
Hard rock
16.00 17.00 1.00 0.95 95 % 95%-C

(Termination Depth = 17.00 m)

SPT - Standard Penetration Tests DS - Disturbed samples UDS - Undisturbed samples C - Core Samples

High Level Bridge over Falgu River


9 at Old GT Road, Sherghati, Gaya
LABORATORY TEST RESULTS FOR Table No. - 1
HIGH LEVEL BRIDGE OVER FALGU RIVER IN BETWEEN OLD GT ROAD TO VILLAGE CHANDA VIA BABHAN DEV JUNGLE
BLOCK SHERGHATI, DISTRICT GAYA, BIHAR
JFC

Type of sample

Depth (in m)

per IS:1498-
Type of soil as

Silt Factors

Rock (Kg/cm )
Test Particle Size Distribution Atterberg Limit NMC Shear Strength Consolidation

density(gm/cc

2
Bulk Density

Dry Density
No (%) (%) Parameter
Cohesion Charecteristic

Submersed

Strength of
Void ratio

Crushing
(in %) C

(gm/cc)

(gm/cc)
F

Specific
Gravity
Cc Cc/(1+e0)

Gravel
LL PL PI Kg/cm2 (degree)

Sand

Clay
Silt

)
SPT 1.50 SP 0.00 86.28 13.72 1.19 NON-PLASTIC - - - - 2.66 - 0 30 - - -

SPT 3.00 SP 0.00 88.91 11.09 1.07 NON-PLASTIC - - - - 2.64 - 0 30.5 - - -

SPT 4.50 SP 0.00 90.32 9.68 1.09 NON-PLASTIC - - - - 2.65 - 0 30 - - -


BH - 1

SPT 7.50 SP 0.00 95.37 4.63 1.12 NON-PLASTIC - - - - 2.66 - 0 31 - - -

C 12.00 - - - - - - - - - 0.98 2.698 2.672 - - - - - 174 - -

C 14.50 - - - - - - - - - 2.724 2.697 - - - - 297 - -


10

1.00 -

C 16.00 - - - - - - - - - 0.97 2.743 2.717 - - - - - 238 - -


High Level Bridge over Falgu River
at Old GT Road, Sherghati, Gaya
GRAIN SIZE DISTRIBUTION CURVES

100.00
90.00
80.00
70.00
Percentage finer

60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.002

0.075

0.425

4.75
0.00100 0.01000 0.10000 1.00000 10.00000 100.00000

Grain size (mm) 3.00m


1.50m

Grain size (mm) <0.002 0.002-0.075 0.075-0.425 0.425-2.0 2.0-4.75 >4.75


Clay Silt Fine sand Medium Coarse sand Gravel
Sample No.
(%) (%) (%) sand (%) (%) (%)
1.50m 0.00 13.72 50.18 36.10 0.00 0.00
3.00m 0.00 11.09 67.21 21.70 0.00 0.00

100.00
90.00
80.00
70.00
Percentage finer

60.00
50.00
40.00
30.00
20.00
10.00
0.00
0.002

0.075

0.425

4.75

0.00100 0.01000 0.10000 1.00000 10.00000 100.00000


Grain size (mm)
4.50m 7.50m

Grain size (mm) <0.002 0.002-0.075 0.075-0.425 0.425-2.0 2.0-4.75 >4.75


Clay Silt Fine sand Medium Coarse sand Gravel
Sample No.
(%) (%) (%) sand (%) (%) (%)
4.50m 0.00 9.68 71.22 19.10 0.00 0.00
7.50m 0.00 4.63 73.37 22.00 0.00 0.00
HIGH LEVEL BRIDGE OVER FALGU RIVER IN BETWEEN 1 Fig. No.
OLD GT ROAD TO VILLAGE CHANDA VIA BABHAN DEV
JUNGLE BLOCK SHERGHATI, DISTRICT GAYA, BIHAR
High Level Bridge over Falgu River
JFC 11 at Old GT Road, Sherghati, Gaya
DIRECT SHEAR TEST RESULTS

Location : FALGU RIVER Location : FALGU RIVER


BH No : 1 BH No : 1
Depth : 1.50 m Depth : 3.00 m
C = 0.00 Kg/cm2 C = 0.00 Kg/cm2
0 0
f = 30 f = 30.5

3.00
3.00
NORMAL SHEAR NORMAL SHEAR

2.50
2.50
0.50 0.28 0.50 0.40
Shear Stress (kg/cm 2)

Shear Stress (kg/cm2)


1.00 0.58 1.00 0.58
2.00 2.00
1.50 0.85 1.50 0.93
2.00 1.14 2.00
1.50 1.22
1.50

1.00 1.00

X Y X Y
0.50
0.0 0.00 0.50
0.0 0.00
2.75 1.59 2.75 1.62
0.00 0.00
0.00 0.50 1.00 1.50 2.00 2.50 3.00 0.00 0.50 1.00 1.50 2.00 2.50 3.00
2
Normal Stress (kg/cm )
Normal Stress (kg/cm2)

Location : FALGU RIVER Location : FALGU RIVER


BH No : 1 BH No : 1
Depth : 4.50 m Depth : 7.50 m
C = 0.00 Kg/cm2 C = 0.00 Kg/cm2
0 0
f = 30 f = 31

3.00
NORMAL SHEAR 3.00
NORMAL SHEAR

2.50
0.50 0.28 2.50
0.50 0.32
Shear Stress(kg/cm2)

1.00 0.66 1.00 0.50


Shear Stress(kg/cm2)

2.00 2.00
1.50 0.80 1.50 1.02
2.00 1.27 2.00 1.23
1.50 1.50

1.00 1.00
X Y X Y
0.50
0.0 0.00 0.0
0.50 0.00
2.75 1.59 2.75 1.65
0.00 0.00
0.00 0.50 1.00 1.50 2.00 2.50 3.00 0.00 0.50 1.00 1.50 2.00 2.50 3.00
2 2
Normal Stress(kg/cm ) Normal Stress(kg/cm )

JFC 12 a
GEOTECHNICAL INVESTIGATION FOR THE CONSTRUCTION OF THE PROPOSED
HIGH LEVEL BRIDGE OVER FALGU RIVER IN BETWEEN OLD GT ROAD TO VILLAGE CHANDA, VIA BABHAN
DEV JUNGLE BLOCK SHERGHATI, DISTRICT GAYA, BIHAR

SITE PHOTOGRAPH

High Level Bridge over Falgu River


13 at Old GT Road, Sherghati, Gaya