2_Design of Two Dimensional Well Profiles-2D_15!12!2021
2_Design of Two Dimensional Well Profiles-2D_15!12!2021
2_Design of Two Dimensional Well Profiles-2D_15!12!2021
Prepared by
Najah Saeed Abdulridha n.saeed@buog.edu.iq
Objectives
1. Draw the profile of a “S” well based on well plan inputs
2. Identify the expected outputs of planning a “S” well
3. Identify the max hold angle on a well plan
4. Calculate the max hold angle
5. Identify the EOB on a well plan
6. Calculate EOB TVD
7. Calculate EOB MD
8. Identify the EOB horizontal displacement on a well plan
9. Calculate EOB HD
10. Calculating Start of Drop (SOD) Measured Depth (TVD)
11. Calculating Start of Drop (SOD) Measured Depth (MD)
12. Calculate Target MD
13. Calculate the rectangular coordinates of the target location from well plan inputs
Well Plan Inputs
Typically, to plan a well, the planner starts with five basic inputs:
• Kickoff point (KOP)
The kickoff point (KOP) is the start of the build section. It is given as a certain vertical depth
below the surface location.
• Buildup rate (BUR)
The buildup rate defines the rate at which the well will be deviated from vertical from the KOP to the required
maximum inclination at the end of build (EOB) in order to hit the target. The optimum inclination of the well is
a function of the maximum permissible buildup rate and the location of the target. BUR is usually expressed in
degrees per 100 feet (English units) or in degrees per 30 meters (Metric units). A typical BUR is 3°/100 ft.
• Target True Vertical Depth (TVD)
The depth of the target measured vertically from the surface.
• Target distance
The total distance (vertical section) of the target from the surface location measured in the
plane of proposal.
• Target direction
The angle of direction of the target location. It is usually given in compass quadrant format
Design of Two Dimensional Well Profiles
Directional Patterns
Design of Two Dimensional Well Profiles
Type 2 ( Build , Hold &Drop) ( S Type Well).
6/9
Design of Two Dimensional Well Profiles
Type 1: Calculating Type 2 ( Build , Hold &Drop) ( S Type Well).
Design of Two Dimensional Well Profiles
Type 1: Calculating Type 2 ( Build , Hold &Drop) ( S Type Well).
S-Shaped (R1+R2) < Total Target Displacement
9/9
Design of Two Dimensional Well Profiles
Type 2 ( Build , Hold &Drop) ( S Type Well).
Example problem: With the given information below for a build-hold well, solve for the
following profile variables:
Solutions Steps
1. Profile drawing 8. Start of drop (SOD) MD
2. Well Coordinate 9. SOD TVD
3. Build and drop radius 10. SOD Displacement
4. MAX hold angle 11. Total MD to the target
5. EOB TVD
6. EOB MD
7. EOB displacement
Vertical Section and Plan View Drawings
Given Information:
• Target Location= 3500 ft at 235 azm
• Target’s TVD = 12,000 ft
• KOP = 6084 ft
• Build up rate (BUR) = 3 grd/100ft
• Drop off rate (DOR) = 2 grd/100ft
11/22
1.Profile Drawing
1.Profile Drawing
1.1 A plan View
A plan view drawing can easily represent the well
coordinate. Sometime referred to as a bird’s-eye
view ,the plan view is an overhead view of the
well path. The drawing should include the north,
south, east and west directions as well as the
coordinate given in the problem.
In this section you will perform the needed calculations to find the true
vertical depth of the end of build.
6.Calculating End of Build (EOB) Measured Depth (MD)
The end of build is the location where the wellbore has
finished increasing, point B on the drawing. The measured
depth of the end of build is the actual length of the
wellbore from its surface location to the end of build
The end of build (B) is the location where the wellbore has finished
increasing. The displacement of the end of build is the horizontal
distance between the surface location and the end of build (D1).
• Second, find SOD MD. To find the measured depth to the start of
drop, you must add the vertical section KOP (V1), the build
section [(θ / BUR) x 100 ft], and the tangent section (BC).
2) Given the following profile variables, choose the correct answer below after calculating the end of build
(EOB) true vertical depth of an "S"-type directional well:
Study Questions
3) Given the following profile variables, choose the correct answer below after calculating the target’s total
measured depth of an "S"-type directional well:
Impact of Kick off Depth on Well Trajectory
For the same target and BUR:
The shallower the kick off depth, the lower the tangent angle and the shorter is the well
length.
Target
Shallow Kick off Point
Shorter well length
Lower casing costs, smaller rig capacity
Lower tangent angles
Easier for hole cleaning
Maybe more difficult for directional work - holding low angle is not always easy
Essential for pad drilling or platforms to get away from other wells
Allows high displacement even if at a shallow TVD
ERD wells use very high kick off points and very high angle tangent section angles
Build up rate typically low to reduce overall torque and drag
Allowing high build up rates here will have large impact on torque values further down well
“J” Vs. “S” type Wells
To hit the same target for the same KOP, BUR and DOR, profiles would be as
follows:
J type Well MD INCL AZI TVD NORTHING EASTING DISPL DLS
feet deg deg feet N/-S feet E/-W feet feet deg
TIE 0 0 0 0 0 0 0
KOP 1000 0 0 1000 0 0 0 0.00
2000 30 90 1955 0 256 256 3.00
10712 30 90 9500 0 4612 4612 0.00
“S” type wells will tend to develop a lot more torque than an equivalent displacement “J” type, it also
depends on the DD work
Usually “S” shaped wells drilled for “production reasons” have a small tolerance on the angle across
reservoir (less than 5 or 10 degrees)
“S” type wells are unavoidable for low displacement wells or when directional drilling is complicated at
deeper sections
Directional drilling might be very difficult at the drop off curve due to high torque and BHA hanging
Summary
Every target potentially has 100’s of well plans to hit the centre.
Choose your plan based on reason – don’t just accept the 1st one you are given
Use geology to help with plans, if you know a formation naturally builds then
use this to your advantage
Also find out if formations are stable drilled in all directions
Make plans as simple as possible
Remember big bends at top sections cause major torque issues later
Know what the completion mechanism is during design stage e.g. ESP’s need
tangent sections, PCP’s have dogleg constraints