Method Statement for Substructure Waterproof
Method Statement for Substructure Waterproof
For
Substructure Waterproofing Work
EMPLOYER:
CONSULTANT:
MAIN CONTRACTOR:
Page 1 of 16
Method Statement for Substructure Waterproofing Works - Rev. 0
Contents
Description Page
2.0 Scope 4 of 16
3.0 Purpose 4 of 16
4.0 References 4 of 16
11.0 Attachments 16 of 16
11.1 Checklist
11.2 Safety Risk Assessment
11.3 ITP for Substructure Waterproofing Works
Page 2 of 16
Method Statement for Substructure Waterproofing Works - Rev. 0
1.0 Revisions Status
2.0Scope:
The scope of this method statement is to provide the controlled sequences of work
Methodology and safety precautions that will be used to execute the Substructure
Waterproofing works for the proposed G+19 (3P+16) STOREY, RESIDENTIAL
BUILDING ON PLOT NO. 3460558 AT BUSINESS BAY, DUBAI.
3.0Purpose:
The purpose of this method statement is to highlight the general measures and
precautions required during the waterproofing works on the substructure members.
Also to ensure that all information, materials, tools and equipment, manpower and
supervision are available for execution of the work.
4.0 References:
Page 3 of 16
Method Statement for Substructure Waterproofing Works - Rev. 0
5.0 Definitions / Abbreviations
Project Manager
Responsible for the successful execution of the contractual & statutory
requirements.
Ensuring that the day to day successful operation of quality & environmental
management system in accordance with company’s and the project’s
requirements.
Construction Manager
Ensuring that the project works are carried out in accordance with company
and Quality policies and in accordance with the requirements of this quality
plan.
Ensure area is ready and safe to start the works.
Liaise and coordinate with the project manager for the agreed sequence of
works with respect to the construction program.
Allocation of required manpower through coordination with the project
manager.
QA/QC Engineer
Perform all daily inspection and test of the scope and character necessary to
achieve the quality of construction required in the drawings and
specifications for all works under the contract performed ON or OFF site.
Cary out inspection and checking for all quality related procedures in the site
and ensures activity at site are as per approved method statement and
Page 4 of 16
Method Statement for Substructure Waterproofing Works - Rev. 0
inspection
test plan.
Coordinate with the consultant’s representative and Site In-charge for
inspection and meeting about quality problems including closure of Non-
Compliance Report.
Responsible in the quality and workmanship of every activities, thorough
knowledge of all phases of engineering construction relating to Civil,
Architectural and Structural discipline interfacing the multidisciplinary
operations.
Project Engineer
Execution of the project on time, within the approved budget and in accordance
with the contract quality specification for the project.
Ensuring that suitably qualified personnel required for the project are
mobilized on time to carry out specialized tasks.
Reviewing the manpower requirements for the project with the Project
Planning Engineer and then with the Administration Department.
Completion of all necessary Progress Reports (such as Weekly & Monthly
Reports) for the project.
Assist the Site Engineers in the preparation of all the Project Quality
Procedures.
Signing all site requisitions and following up with the purchasing department
to ensure that all information is available to procure.
Page 5 of 16
Method Statement for Substructure Waterproofing Works - Rev. 0
Site Engineer
Exercising full control of workforce on site.
Ensuring work is executed in accordance with the contract specifications,
agreed procedures and method statements.
Preparations of designated construction quality procedures.
Monitoring the work of sub-contractors.
Any other duties and responsible as designated by the Project Manager.
7.1.1 Ensure that the Material Submittals and Material Inspection have
been approved.
7.1.2 Ensure related details has been approved and properly coordinated
to the site engineer and all workers.
7.1.3 Ensure the Materials stored at the designated storage area.
7.1.4 All materials shall be delivered with a tag number
indicating manufactured date, off loaded as near as possible to the
point of use.
7.1.5 Ensure that the Inspection for Substrate/Blinding has been
approved.
7.1.6 All activities shall refer to this method statement in conjunction
with the manufacturer’s instructions/ procedural manuals.
7.1.7 Ensure that work area is with barricade & safety signages in place.
7.1.8 Ensure that work area is clear and safe.
7.1.9 Ensure that HSE & QAQC procedure are established.
Surface Preparation
Prior to installation, the areas to be covered with the membrane should
be carefully checked.
The surface where the primer to be applied should be clean
The substrate must be free from any sharp particles or edges.
Site inspection with the Consultant shall be arranged after the
preparation work has been completed prior to start waterproofing
work.
Fillets for internal corners and chamfer for external corner should be
according to manufacturer recommendations.
Page 6 of 16
Method Statement for Substructure Waterproofing Works - Rev. 0
Priming
Prior to commencement of waterproofing works, the substrate is to be
inspected and approved.
A primer is applied to horizontal & vertical surfaces where the
membrane is to be torch bonded.
Torch bonding can proceed 2~4 hours after the primer application.
Re-application of primer coat will be carried out again if the membrane
installation has been delayed for more than 24 hrs.
Horizontal Waterproofing
The membrane is torch bonded horizontally to the primed substrate.
The membrane rolls must be properly aligned observing at all times the
overlap dimensions which should be marked properly (10cms
longitudinal and 15cms transversal) in accordance with the
manufacturer’s recommendations.
Unrolling of the membrane can be done by hand
A cover strip of 200mm width should be torched over the overlapping
joints to ensure the perfect welding.
The membrane should be loosely laid over a slip sheet of non-woven
glass mat, to be seamed only at overlapping.
Ensure that an additional length of 250mm minimum horizontal
membrane is left all around for carrying an overlapping with the
membrane laid on vertical walls.
Torching can proceed only after the inspection of all overlaps and of
any accidental damage to the membrane itself.
The torch applicators will apply heat on both sides of the overlap and
press the overlaps immediately afterwards.
Proper checking of all welded overlaps will be done by a technician.
Membrane joints and protection board joints should be staggered.
Any gaps in overlaps will be re-torched.
Vertical Waterproofing
After casting the raft and the Basement walls, the membrane should be
overlapped and torch bonded to the existing membrane on the extended
PCC.
The membrane must be properly aligned observing at all times the
overlap dimensions which should be marked properly (10cms
longitudinal and 15cms transversal) in accordance with the
Page 7 of 16
Method Statement for Substructure Waterproofing Works - Rev. 0
manufacturer’s recommendations. Unrolling of the membrane can be
done by hand.
The torch applicators will apply heat on both sides of the overlap and
press the overlaps immediately afterwards.
Repairs
Accidental damages will be repaired as follows:
Clearing and cleaning the area concerned.
Marking specifically the areas to be repaired.
Seaming using the hot spatula over the damage area.
Torching a piece of membrane over the damaged area and at least
10cms around it.
Supervisor/Foreman
Safety Engineer/Safety Officer
QA/QC Engineer/Inspector
Approved Vendor/Subcontractor of Waterproofing Work
Labours / Helper
LPG Cylinder
Mixing Machine
Torch Machine
Tools & Power Tools
Scaffolding
Personal Protective Equipment (PPE)
Safety Helmet, Safety Gloves, Safety Shoes, Eye Protection or goggle,
approved respirator and Safety Jacket.
10.1 Health:
Page 9 of 16
Method Statement for Substructure Waterproofing Works - Rev. 0
Chemicals or dangerous goods shall not be brought to Site until a
material safety data sheet (MSDS) has been viewed and approved by the
Project manager.
Flammable and combustible liquids shall be stored and handled
according to all local regulatory standards in area of operation.
Hot work, hot processes and smoking shall be strictly prohibited within
a five meter radius of a flammable liquid storage area.
A suitable fire extinguisher shall be located in the nearest convenient
spot to any flammable liquid storage area.
MSDS shall be located in the work area for all chemicals used, and a
register of chemicals in use on the site shall be maintained, including
copies to First Aid personnel.
Assessments will be carried out on all chemical substances and
appropriate handling safeguards will be put in place prior to use.
Page 10 of 16
Method Statement for Substructure Waterproofing Works - Rev. 0
Drinking Water:
An adequate supply of potable water shall be provided at site.
The drinking water supplied during hot weather shall be cooled.
Toilets:
Shall be provided clean, well ventilated toilets.
Toilets shall be provided for employees according to the
following table.
10.1.6 Ventilation:
All work areas will be adequately ventilated and employee’s exposure to
atmospheric contamination shall be kept below the recommended levels
as per the applicable statutory requirements.
Areas in which there exists, or is likely to exist, the presence of
deleterious atmospheric contaminants they shall be identified and
appropriately sign-posted.
All employees working in areas that are likely to contain atmospheric
contaminants which cannot be adequately removed by ventilation shall
wear the appropriate respiratory protection devices.
Page 11 of 16
Method Statement for Substructure Waterproofing Works - Rev. 0
Wherever reasonably practicable, airborne contaminants will be kept to
the absolute minimum by way of engineering solutions as opposed to
use of personal protective equipment.
10.2 Safety:
Page 12 of 16
Method Statement for Substructure Waterproofing Works - Rev. 0
To review the implementation of the Health, Safety and Environment
Plan.
10.3 Environment:
Page 13 of 16
Method Statement for Substructure Waterproofing Works - Rev. 0
A skip will be maintained at site if found necessary to dispose all the
solid waste materials and it will be removed through authorized agencies
at regular intervals.
The Project Manager will allocate separate crew under a foreman for
scrap and waste removal if it is required.
11.0 Attachments:
11.1 Checklist.
11.2 Safety Risk Assessment.
11.3 ITP for Substructure Waterproofing Works.
Page 14 of 16
Method Statement for Substructure Waterproofing Works - Rev. 0