Project Management Networks
Project Management Networks
Project Management Networks
CPM/PERT
Project Scheduling Terms
A D E F
C
Project Scheduling
• Steps • Techniques
– Define activities – Gantt chart
– Sequence activities – CPM/PERT
– Estimate time – Microsoft Project
– Develop schedule
Network Diagrams
Show Help
interdependence schedule
resources
Show
Facilitate start &
communication finish
dates
Determine project Identify
completion critical
activities
Gantt Chart
Build house
Select paint
Select carpet
Finish work
1 3 5 7 9
Month
Project Control
• Time management
• Cost management
• Quality management
• Performance management
– Earned Value Analysis
• a standard procedure for numerically measuring a project’s
progress, forecasting its completion date and cost and
measuring schedule and budget variation
• Communication
• Enterprise project management
CPM/PERT
0 Hammock 18
0 18 18
• Activity-on-node (AON)
– nodes represent activities,
and arrows show Node
precedence relationships
• Event
– completion or beginning of 1 2 3
an activity in a project
• Dummy
– two or more activities Branch
cannot share same start and
end nodes
AON Network for House Building Project
2 4
Finish work
2 3
7
Start 1 1
3
Design house 6
and obtain
3
1 5 1
financing
1 Select carpet
Order and receive
materials Select paint
Critical Path
2 4
2 3
7
Start 1 1
3
3 6
1 5 1
1
Start at 5 months
2 4
Finish at 9 months
2 3
7 Finish
Start 1 1
3
3 6
1 5 1
1 Start at 6 months
Start at 3 months
Node Configuration
Earliest finish
1 0 3
3 0 3
Latest finish
Lay foundations
Build house
2 3 5
Start 4 5 8
2
3
1 0 3 7 8 9
3 1
Design house
and obtain 6 6 7 Finish work
financing 3 3 4
1
1 5 5 6
Select carpet
Order and receive 1
materials Select pain
Activity Scheduling (cont.)
1 0 3 7 8 9
3 0 3 1 8 9
1
Design house
and obtain 6 6 7 Finish work
financing 3 3 4
1 7 8
1 4 5 5 5 6
Select carpet
Order and receive 1 6 7
materials Select paint
Activity Slack
Activity LS ES LF EF Slack
*1 0 0 3 3 0
*2 3 3 5 5 0
3 4 3 5 4 1
*4 5 5 8 8 0
5 6 5 7 6 1
6 7 6 8 7 1
*7 8 8 9 9 0
* Critical Path
PERT—PROGRAM EVALUATION AND REVIEW
TECHNIQUE
22
Probability Considerations: The Beta Probability
Distribution
1
Activity Time Calculations
Orientation
7
2,2,2
Activity Time Estimates
1 6 8 10 8 0.44
2 3 6 9 6 1.00
3 1 3 5 3 0.44
4 2 4 12 5 2.78
5 2 3 4 3 0.11
6 3 4 5 4 0.11
7 2 2 2 2 0.00
8 3 7 11 7 1.78
9 2 4 6 4 0.44
10 1 4 7 4 1.00
11 1 10 13 9 4.00
Earliest, Latest, and Slack
Critical Path
1 0 8 4 8 13
8 1 9 5 16 21
10 13 17
16
4 21 25
8 9
Start 2 0 6 Finish
7 9 16
6 0 6 9
5 6 11 16 25
3 6 9 9 9 13
9 16 25
4 12 16
3 0 3 6 3 7
3 2 5 4 5 9
7 3 5
2 14 16
Activity Early, Late Times, and Slack
ACTIVITY t б ES EF LS LF S
1 8 0.44 0 8 1 9 1
2 6 1.00 0 6 0 6 0
3 3 0.44 0 3 2 5 2
4 5 2.78 8 13 16 21 8
5 3 0.11 6 9 6 9 0
6 4 0.11 3 7 5 9 2
7 2 0.00 3 5 14 16 11
8 7 1.78 9 16 9 16 0
9 4 0.44 9 13 12 16 3
10 4 1.00 13 17 21 25 8
11 9 4.00 16 25 16 25 0
Total project variance = sum of the
variances of all activities lying on
the critical path only
x-
Z=
where
= tp = project mean time (sum of
the weighted mean activity durations of all
activities lying on the critical path only)
= project standard deviation
(square root of project variance)
x = proposed project time
Z = number of standard deviations x
is from mean
Normal Distribution of Project Time
Probability
Z
= tp x Time
Southern Textile Example
What is the probability that the project is completed within 30 weeks?
x-
2 = 6.89 weeks Z =
P(x 30 weeks)
= 6.89 = 30 - 25
= 2.62 weeks 2.62
= 1.91
= 25 x = 30 Time (weeks)
• Activity a m b te Variance
• A 17 29 47 30 25
• B 6 12 24 13 9
• C 16 19 28 20 4
• D 13 16 19 16 1
• E 2 5 14 6 4
• F 2 5 8 5 1
Hypothetical Network
What is the probability that the
project would be completed on or
before 67 time units?
Possible Project Duration
TE = 64; TS = 67,
• Z = (67 – 64)/ sqrt (25+9+1+1)
• Z = 0.50
• P = 0.69
What is the probability that the
project would be completed on or
before 60 time units?
TE = 64; TS = 60,