305_judgment_02(f)-12-03-2016(w) (2)
305_judgment_02(f)-12-03-2016(w) (2)
305_judgment_02(f)-12-03-2016(w) (2)
BETWEEN
AND
Introduction
Background Facts
Phase 1 RM33,394,265.59
Phase 2 RM36,288,215.22
Phase 3 RM45,360,269.02
Total Contract Price RM115,042,749.83
8. Under the terms of the LOA the plaintiff was to pass a “Proof of
Concept Site Acceptance Test” [“POC SAT”]. The POC SAT was a
test aimed at determining whether the plaintiff’s proposal solutions
resolved the first defendant technical issues. Various drafts of the
test protocol were negotiated between the parties. There were twelve
(12) draft versions of the POC SAT. This culminated in the POC SAT
version 3.8(a).
10. The first defendant then deferred the test to the next day when
the first defendant alleged that the plaintiff’s representatives were told
that although version 3.8(a) would be used, that format changes
would have to be made in order to improve the presentation and
procedure of the test format to enable proper tracking of the test and
its results.
5
11. The defendants contended that the plaintiff was aware of the
changes and agreed to apply the changes to the the POC SAT.
Consequently the POC SAT was carried on 17.4.2008, 18.4.2008
and 21.04.2008 using reformatted version 3.8(a) which came to be
described as version 3.8(b). It was the defendants’ position that
versions 3.8(a) and 3.8(b) of the POC SAT were similar in substance.
The plaintiff however contended otherwise.
15. The plaintiff in its statement of claim sought the following reliefs:
(i) General damages for breach of contract in the sum of
RM21,278,498.10 comprising:
6
(a) amount due and owing for work done by the plaintiff
in the sum of RM11,217,797.84.
(b) amount due and owing to the plaintiff pursuant to
clause 15C(1) and 15C(II) of the LOA in the sum of
RM10,160,700.26;
alternatively, damages for breach of contract in a
sum to be assessed, by the first and second
defendants and/or each of them in such proportion
(if any) as may be determined by the court;
(ii) Special damages for storage and insurance costs of the
Transmitters in the sum of RM162,517.10 as of 23.6.2010
and still continuing;
(iii) Costs;
(iv) Interest on such amounts of special and/or general
damages as may be awarded by this Court; and
(v) Such further and other relief as deems fit.
17. The main issues for determination before the High Court as
found by the learned High Court Judge are as follows:
(1) Whether the POC SAT version 3.8(a) and 3.8(b) were the
same or were they different; and
(2) Whether the plaintiff had passed the POC SAT either
based on version 3.8(a) or 3.8(b).
18. The learned High Court Judge came to a finding that the
plaintiff had passed the POC SAT and hence allowed the plaintiff’s
claim and dismissed the defendants’ counterclaim for the following
reasons, amongst others:
19. The Court of Appeal affirmed the decision of the High Court and
dismissed the defendants’ appeal. The learned Judges of the Court
of Appeal in their Judgment stated that the crucial issue raised in the
case was, what was the correct test protocol to be used: version
3.8(a) or version 3.8(b). [See paragraph 53 of the Judgment of the
Court of Appeal].
20. The Court of Appeal took note of the learned High Court
Judge’s finding that the plaintiff’s witnesses, PW2 and PW3,
demonstrated that they had the technical expertise and knowhow of
the workings of the Project. This led the Court of Appeal to affirm the
decision of the High Court and to hold that the test protocol version
3.8(b) utilized was not mutually agreed to by the parties and that it
was substantially different from version 3.8(a) and that thus the
plaintiff was entitled to reject the test results of the test protocol of
version 3.8(b).
9
21. Learned Counsel for the defendants submitted that the plaintiff
was supposedly the expert who would solve the problems faced by
the first defendant in its digital broadcasting. The main point in the
case before the High Court was whether the plaintiff had solved the
problem that it was engaged to remedy. What this meant was
whether the POC SAT had been achieved.
22. It was the contention of the defendants that the issues raised
before the Court were admittedly of a technical nature. Learned
Counsel for the defendants submitted that the learned High Court
Judge did not direct parties to lead expert evidence on the technical
issues. Parties were left to determine the nature of their evidence
thought sufficient to establish their respective cases. Consequently,
no expert witness was called by either party at the trial.
(ii) the plaintiff was aware and accepted that whether the
system had “frozen” during the POC SAT was not the
only criteria for the plaintiff to pass;
(iii) the plaintiff recognized the first defendant’s desire to test
the system functionality and performance from end-to-
end;
(iv) the POC SAT conducted in April 2008 was not a trial run;
and
(v) there were no documents to show that the plaintiff had in
fact passed version 3.8(a).
24. The first defendant also contended that the test results
recorded failure of the plaintiff’s solutions at various stages, resulting
in the failed POC SAT. The plaintiff refused to accept the test results
and attempted to declare the test result as void, alleging the tests to
be merely a ‘trial run’.
26. It was the defendants’ case that the plaintiff’s failure to rectify
the failed POC SAT was a breach of the plaintiff’s obligations as a full
turnkey contractor under the terms of the LOA and of the
representations made by the plaintiff of its skills and expertise.
11
28. It was the submission of the plaintiff that the dispute between
the parties was essentially a contractual dispute over the agreed test
protocol version to be used for the tests conducted jointly between
representatives from both sides. In this regard the learned High
Court Judge was not called upon to decide on technical questions or
any mater involving scientific knowledge or knowhow.
29. It was the contention of the plaintiff, that there was concurrent
finding of fact by the Courts below that the first defendant deliberately
failed to use the test version designed by the plaintiff and effectively
prevented or hindered the plaintiff from completing the Project.
30. On the part of the plaintiff, its onus was to prove what was the
test protocol agreed by the parties under clause 15B of the LOA and
not the technical components of the same or how it worked. It was
submitted that expert evidence was neither relevant nor necessary
given what was agreed by the parties. If the first defendant thought
otherwise it could have called an independent technical witness to
prove the compatibility between versions 3.8(a) and 3.8(b).
12
Decision
33. The main issue for determination in the case before the High
Court was whether the POC SAT had been performed and the results
achieved. The plaintiff contended it met the test. The defendants
contended otherwise. Neither side called an expert to determine
whether the test had been met. Nevertheless, the learned High Court
Judge treated the two important witnesses of the plaintiff [PW2 and
PW3] as if they were experts.
34. It is our considered view that the fact that since both the Courts
below determined that there was a need for technical evidence for
parties to prove their respective case, the pertinent question to be
resolved in this case is whether the approach adopted by both the
High Court and the Court of Appeal was correct as regards the
discharge of the burden of proof by the plaintiff seeking judgment in
respect of matters of a technical nature.
13
37. In the present case the learned High Court Judge recognized
that the parties differed in their interpretation of the POC SAT. The
defendants understood it to be a model of the end-to-end broadcast
solution whereas the plaintiff viewed the POC SAT as a standalone
system. The learned High Court Judge further recognized that the
parties differed on the issue of whether POC SAT versions 3.8(a) and
3.8(b) were the same.
38. We are of the view the issues surrounding the POC SAT were
technical in nature and were pivotal in determining whether the first
defendant wrongfully prevented the plaintiff from performing the LOA
as contended by the plaintiff.
39. It is noted that the learned High Court Judge decided on the
burden of proof for the plaintiff to prove its case on this technical
15
40. The learned High Court Judge accepted PW2 and PW3 as
experts when in our view they did not satisfy the test under section 45
of the Act. Section 45 of the Act provides:
“45. (1) When the Court has to form an opinion upon a point of foreign
law or of science or art or as to identify or genuineness of handwriting or
finger impressions, the opinions upon that point of persons specially
skilled in that foreign law, science or art or in questions as to identity or
genuineness of handwriting or finger impressions, are relevant facts.
(2) Such persons are called experts.”
43. It is our finding that both the plaintiff’s witnesses, PW2 and
PW3, fell far short of the required standard of an expert witness under
section 45 of the Act. PW2 was the Senior Manager and PW3 the
plaintiff’s CEO and director. Both witnesses can hardly be described
as independent. As members of the plaintiff’s Senior Management
team they should have been treated as having an interest in the case.
This fact by itself should have disqualified them as truly independent
witnesses.
44. It is our considered view that the learned High Court Judge,
who formed the view that the issues required technical evidence, was
in no position to make a determination of those technical issues
without such expert evidence as the provision of section 45 of the Act
applied.
45. In the context of the present case we are of the view that expert
evidence was required. The plaintiff’s witnesses, namely PW2 and
PW3 were witnesses of facts and could not be characterized as
experts. It was not, but was found by the learned High Court Judge,
a question of accepting the testimony of plaintiff’s witnesses PW2 and
PW3 and disbelieving the testimony of the defendants’ witnesses,
17
“Our law is clear in that under section 45 of our Evidence Act 1950 it
is provided that…The scope of this section can be found in the
commentary in Sarkar on Evidence 12th ed. at page 488 where, while
recognizing that opinion in so far as it may be founded on legal
evidence shall be the function of the tribunal whose province alone it
is to draw conclusions of law or fact –
It is settled principle that while it is true that a Judge who sits alone is
entitled to weigh all the evidence, to put his own magnifying glass to
determine the probabilities so to speak and form his own opinion or
judgment, it would be erroneous for him to form a conclusion on a
matter which could only be properly concluded with the aid for expert
evidence.” [Emphasis added]
46. It is to be noted that the plaintiff did not lead their evidence on
the basis upon which its witnesses were experts and as such their
evidence were not scrutinized on that basis. On this point in PB
Malaysia Sdn Bhd v. Samudra (M) Sdn Bhd [2009] 7 MLJ 681 at
702, Ramli Ali J. (as he then was) held that:
48. It was submitted for the plaintiff that if the first defendant held
the view that expert evidence was relevant and necessary to prove
the compatibility between versions 3.8(a) and 3.8(b) it was for the first
defendant to call such independent technical witness. With respect
we could not agree with such a contention.
49. It must be borne in mind that the burden was on the plaintiff to
put sufficient material before the High Court to discharge its burden of
proof. It should also be noted that the defendants approached the
matter on the basis that the admissions of the plaintiff’s so-called
technical witnesses on essential points had wholly undermined the
plaintiff’s own case, which can be seen as follows:
(2) The plaintiff was also aware and accepted that whether
the system had “frozen” during the POC SAT was not the
only criteria for the plaintiff to pass. The plaintiff’s witness
PW4, one of the directors of the plaintiff in cross-
examination on this point had this to say:
“DC: Another words,….if you look at page 629 that is on the
Content Acquisition test stage and you look at page 639,
that is on the offline editing stage and finally you look at
page 650 that is on the Compression and Delivery test
stage. It does include a human perception element where
the testing the parameters is to check whether there is video
pixelization whether there is any video audio jerking and
freezing, video noise, video crackle, audio rumble so on and
so forth. So, therefore I said looking at all this, POC SAT is
21
(5) The plaintiff’s witness PW3 agreed that the onus was on
the plaintiff as the vendor to document and prepare the
test result.
“DC: Now, as a vendor, is it not in your interest to see that, you
passed the POC SAT, is it also not in your interest to make
recording of what was the results.
A: Yes, it is our interest.”
50. The High Court found that there was a need for technical
evidence but, however, it preferred the evidence of the plaintiff on the
basis of its so-called technical witnesses. It is our judgment, when it
was determined that there was a need for technical evidence, it was
incumbent on the plaintiff to lead evidence through experts. It did not
do so and by reason of that failure had failed to discharge its “burden
of proof” under sections 101 and 102 of the Act. Consequently the
23
53. Based on the facts and the circumstances of the case it is our
considered view that the plaintiff’s failure to rectify the failed POC
SAT was a breach of the plaintiff’s obligations as a full turnkey
contractor under the terms of the LOA and of the representations
made by the plaintiff of its skills and expertise. The failure of the POC
SAT effectively prevented the Project from moving forward as the
delivery of transmission sites and the testing and acceptance of the
redesigned Network Operation Centre were contingent on the plaintiff
having passed the POC SAT. In this regard, the plaintiff could not
contend that the first defendant wrongly prevented it from performing
the LOA.
54. It can be said in this case that the first defendant did not receive
what it contracted for. The turnkey contract required the plaintiff to
remove the technical faults faced by the defendant in the system.
Accordingly, we are of the view that there was a total failure of
consideration on the part of the plaintiff to perform its obligations
under the contract. [See the cases of Stocznia Gdanska SA v.
Latvian Shipping Co & Others [1998] 1 All ER 883 at 896 and
Damansara Realty v. Bangsar Hill Holdings Sdn Bhd & Others
[2011] 6 MLJ 464]. The act of termination of the contract by the
25
56. For the reasons above stated we would allow this appeal with
costs. The question of law posed is answered in the negative. The
orders of the High Court as affirmed by the Court of Appeal are
hereby set aside. As regards the counterclaim of the defendants
against the plaintiff, we would allow the counterclaim with costs to the
extent of only the recovery of the sum of RM20,833,053 already paid
to the plaintiff by the defendants under the contract sum for phase 1
of the Project with interest at the rate of 8% per annum, so as to put
26
Datuk Seri Gopal Seri Ram, Clinton Tan Kian Seng and David Yii.
Dato’ Cyrus Das, Nahendran Navaratnam, Wong Wye Wah and Tan
Min Lee.