9905_cons_en
9905_cons_en
9905_cons_en
AN/471
© ICAO 2009
AMENDMENTS CORRIGENDA
1 15/4/11 ICAO
(iii)
TABLE OF CONTENTS
Page
Chapter 1. Description of required navigation performance authorization required (RNP AR) ............ 1-1
(v)
(vi) RNP AR Procedure Design Manual
_____________________
FOREWORD
Required navigation performance (RNP) was initially envisaged by the International Civil Aviation Organization (ICAO)
as a means to facilitate change in airspace operation. ICAO recognized that global navigation satellite systems, the
navigation infrastructure, operations, and aircraft systems were undergoing change faster than could be supported by
their traditional technical standards processes. RNP was developed to allow the specification of airspace and operation
requirements without the constraints of the slow process for specifying equipment and systems.
Initially, in order to support RNP operations, RNP procedure design criteria were developed and incorporated in the
Procedures for Air Navigation Services — Aircraft Operations (PANS-OPS) (Doc 8168). However, lacking demand and
general familiarity with the change in operations and implementation paradigm possible with RNP, the initial criteria were
conservative in nature and specification. Consequently, as specific locations were identified where demanding RNP
solutions were needed, ICAO criteria were found to be insufficient and lacking in the necessary support guidance for
approving operations.
At the same time, one State in collaboration with industry and a key airline operator undertook the task to develop
criteria that permitted the usage of RNP-capable aircraft to address a significant problem with airport access in obstacle-
rich environments or terrain, under limiting weather conditions. These criteria for RNP procedures were documented in
regulatory guidance, as part of the United States Federal Aviation Administration (FAA) Advisory Circular (AC) 120-29A.
The AC 120-29A RNP criteria permit a significant degree of flexibility and customization in procedure design. It extends
beyond traditional procedure design guidance in its provision of criteria addressing relevant aspects of operational
requirements that must be considered in the implementation of such special flight operations e.g. visual segment
assessment, engine loss, extraction, tailored climb gradient and balked landing. However, such criteria can be very
demanding and time-consuming as it must be evaluated and approved for every application. As a result, it was
determined that a degree of standardization in lieu of maximum variability would facilitate not only procedure
development but implementation as well.
The same State, consistent with its aviation community, derived a separate set of procedure design criteria that retained
many key areas of flexibility but also set specific standards in others, so as to simplify the procedure design
implementation effort while retaining the means to achieve significant operational benefits. These criteria were
documented in United States FAA Order 8250.52, which was initially used in that State, but was also embraced by
others needing such criteria to address operational problems in their regions. ICAO has reviewed these criteria and
developed equivalent criteria contained herein that was harmonized with PANS-OPS with regard to terminology, units of
measurement and certain design parameters. As the concepts behind the criteria contained in this manual are relatively
new, it was decided not to include the criteria in PANS-OPS at this stage.
In order to rationalize and support the implementation of RNP operations, ICAO established the Required Navigation
Performance and Special Operational Requirements Study Group (RNPSORSG) which developed the Performance-
Based Navigation (PBN) Manual (Doc 9613). The PBN Manual provides two types of navigation specifications for
approach operations: RNP approach (RNP APCH) and RNP authorization required approach (RNP AR APCH). The
RNP APCH navigation specification is intended to satisfy general RNP operational requirements and permit participation
by aircraft with a basic level of RNP capability without a requirement for operational authorization. The other navigation
specification, RNP AR APCH, which enables a higher level of navigation performance better able to address issues of
airport access, such as obstacle-rich environments, and facilitate advances in air traffic management (ATM), requires
the operator to meet additional aircraft and aircrew requirements and obtain operational authorization from the State
regulatory authority.
(vii)
(viii) RNP AR Procedure Design Manual
RNP AR procedures can provide significant operational and safety advantages over other area navigation (RNAV)
procedures by incorporating additional navigational accuracy, integrity and functional capabilities to permit operations
using reduced obstacle clearance tolerances that enable approach and departure procedures to be implemented in
circumstances where other types of approach and departure procedures are not operationally possible or satisfactory.
Procedures implemented in accordance with this manual allow the exploitation of high-quality, managed lateral and
vertical navigation (VNAV) capabilities that provide improvements in operational safety and reduced controlled flight into
terrain (CFIT) risks.
This manual is intended for use by aircraft operators and procedure designers of instrument approaches based on RNP
using RNAV avionics systems, where authorization is required (AR).
The manual includes design criteria to aid States in the implementation of RNP AR approach procedures in accordance
with the PBN Manual, Volume II, Part C, Chapter 6, Implementing RNP AR APCH. Similar criteria for departure
procedures will be incorporated when developed.
_____________________
DEFINITIONS
Aircraft-based augmentation system (ABAS). An augmentation system that augments and/or integrates the
information obtained from the other GNSS elements with information available on board the aircraft.
Note.— The most common form of ABAS is receiver autonomous integrity monitoring (RAIM).
Airspace concept. An airspace concept provides the outline and intended framework of operations within an airspace.
An airspace concept is essentially a high-level statement of an airspace plan. Airspace concepts are developed to
satisfy explicit strategic objectives such as improved safety, increased air traffic capacity and mitigation of
environmental impact. Airspace concepts include details of the practical organization of the airspace and its users
based on particular communications, navigation and surveillance/air traffic management (CNS/ATM) assumptions,
e.g. air traffic services (ATS) route structure, separation minima, route spacing and obstacle clearance.
Approach procedure with vertical guidance (APV). An instrument procedure which utilizes lateral and vertical
guidance but does not meet the requirements established for precision approach and landing operations.
Area navigation (RNAV). A method of navigation which permits aircraft operation on any desired flight path within the
coverage of ground-based or spaced-based navigation aids or within the limits of the capability of self-contained
aids, or a combination of these.
Note.— Area navigation includes performance-based navigation as well as other operations that do not meet the
definition of performance-based navigation.
Area navigation route. An ATS route established for the use of aircraft capable of employing area navigation.
ATS surveillance service. Term used to indicate a service provided directly by means of an ATS surveillance system.
ATS surveillance system. A generic term meaning variously, ADS-B, PSR, SSR or any comparable ground-based
system that enables the identification of aircraft.
Note.— A comparable ground-based system is one that has been demonstrated, by comparative assessment or
other methodology, to have a level of safety and performance equal to or better than monopulse SSR.
Cyclic redundancy checking (CRC). A mathematical algorithm applied to the digital expression of data that provides a
level of assurance against loss or alteration of data.
Decision altitude (DA) or decision height (DH). A specified altitude or height in the precision approach or approach
with vertical guidance at which a missed approach must be initiated if the required visual reference to continue the
approach has not been established.
Note 1.— DA is referenced to mean sea level and DH is referenced to the threshold elevation.
Note 2.— The required visual reference means that section of the visual aids or of the approach area which should
have been in view for sufficient time for the pilot to have made an assessment of the aircraft position and rate of change
of position, in relation to the desired flight path. In Category III operations with a decision height the required visual
reference is that specified for the particular procedure and operation.
(ix)
(x) RNP AR Procedure Design Manual
Note 3.— For convenience where both expressions are used they may be written in the form “decision
altitude/height” and abbreviated “DA/H”.
Glide path. A flight path defined in the vertical axis that passes through the DCP/RDH on the final approach segment of
an APV or PA.
Mixed navigation environment. An environment where different navigation specifications may be applied within the
same airspace (e.g. RNP 10 routes and RNP 4 routes in the same airspace) or where operations using
conventional navigation are allowed together with RNAV or RNP applications.
Navigation aid (NAVAID) infrastructure. Navaid infrastructure refers to space-based and or ground-based navigation
aids available to meet the requirements in a navigation specification.
Navigation application. The application of a navigation specification and the supporting navaid infrastructure to routes,
procedures, and/or defined airspace volume, in accordance with the intended airspace concept.
Note.— The navigation application is one element, along with communication, surveillance and ATM procedures
meeting the strategic objectives in a defined airspace concept.
Navigation function. The detailed capability of the navigation system (such as the execution of leg transitions, parallel
offset capabilities, holding patterns, navigation databases) required to meet the airspace concept.
Note.— Navigational functional requirements are one of the drivers for selection of a particular navigation
specification. Navigation functionalities (functional requirements) for each navigation specification can be found in the
Performance-Based Navigation (PBN) Manual (Doc 9613), Volume II, Parts B and C.
Navigation specification. A set of aircraft and air crew requirements needed to support performance-based navigation
operations within a defined airspace. There are two kinds of navigation specifications:
RNP specification. A navigation specification based on area navigation that includes the requirement for
performance monitoring and alerting, designated by the prefix RNP, e.g. RNP 4, RNP APCH.
RNAV specification. A navigation specification based on area navigation that does not include the requirement for
performance monitoring and alerting, designated by the prefix RNAV, e.g. RNAV 5, RNAV 1.
Note.— The Performance-Based Navigation (PBN) Manual (Doc 9613), Volume II, contains detailed guidance on
navigation specifications.
Obstacle clearance surface (OCS). An obstacle evaluation surface used to determine the minimum obstacle clearance
altitude at any point.
Performance-based navigation (PBN). Area navigation based on performance requirements for aircraft operating
along an ATS route, on an instrument approach procedure or in a designated airspace.
Note.— Performance requirements are expressed in navigation specifications in terms of accuracy, integrity,
continuity, availability and functionality needed for the proposed operation in the context of a particular airspace concept.
Procedural control. Air traffic control service provided by using information derived from sources other than an ATS
surveillance system.
Definitions (xi)
RNAV operations. Aircraft operations using an area navigation system for RNAV applications. RNAV operations include
the use of area navigation for operations which are not developed in accordance with the Performance-Based
Navigation (PBN) Manual (Doc 9613).
RNAV system. A navigation system which permits aircraft operation on any desired flight path within the coverage of
station-referenced navigation aids or within the limits of the capability of self-contained aids, or a combination of
these. An RNAV system may be included as part of a flight management system (FMS).
RNP operations. Aircraft operations using an RNP system for RNP applications.
RNP route. An ATS route established for the use of aircraft adhering to a prescribed RNP specification.
RNP system. An area navigation system which supports on-board performance monitoring and alerting.
Satellite based augmentation system (SBAS). A wide coverage augmentation system in which the user receives
augmentation from a satellite-based transmitter.
Standard instrument arrival (STAR). A designated instrument flight rule (IFR) arrival route linking a significant point,
normally on an ATS route, with a point from which a published instrument approach procedure can be commenced.
Standard instrument departure (SID). A designated instrument flight rule (IFR) departure route linking the aerodrome
or a specified runway of the aerodrome with a specified significant point, normally on a designated ATS route, at
which the en-route phase of a flight commences.
_____________________
ABBREVIATIONS AND ACRONYMS
AC Advisory circular
ADS-B Automatic dependent surveillance broadcast
AGL Above ground level
anpe Actual navigation performance error
APCH Approach
APV Approach procedure with vertical guidance
AR Authorization required
*ase Altimetry system error
ASI Airspeed indicator
ATC Air traffic control
*atis Automatic terminal information service
ATM Air traffic management
ATS Air traffic services
ATT Along track tolerance
BARO-VNAV Barometric vertical navigation
BG Body geometry
CAT Category
CDA Continuous descent approach
CFIT Controlled flight into terrain
Cot Cotangent
CNS/ATM Communications, navigation and surveillance/air traffic management
DA/H Decision altitude/height
DER Departure end of runway
DFAP Distance from threshold to FAP
DFROP Distance to final approach roll-out point
DR Descent rate
DTA Distance of turn anticipation
FAA Federal Aviation Administration
FAF Final approach fix
FAP Final approach point
FAS Final approach segment
FCC Flight control computer
FOSA Flight operations safety assessment
FROP Final approach roll-out point
ft Feet
*fte Flight technical error
FTP Fictitious threshold point
GNSS Global navigation satellite system
GP Glide path
GPI Ground point of intercept
GPS Global positioning system
H Altitude
* Lower case is used for those abbreviations and acronyms that come from the Performance-Based Navigation (PBN) Manual
(Doc 9613).
(xiii)
(xiv) RNP AR Procedure Design Manual
_____________________
Chapter 1
1.1.1 This manual is intended for use by aircraft operators and procedure designers of instrument approaches
based on required navigation performance (RNP) using area navigation (RNAV) avionics systems, where authorization
is required (AR).
1.1.2 The manual includes design criteria to aid States in the implementation of RNP AR approach (APCH)
procedures in accordance with Performance-Based Navigation (PBN) Manual (Doc 9613) (hereafter referred to as the
PBN Manual), Volume II, Part C, Chapter 6, Implementing RNP AR APCH.
1.2 APPLICATION
1.2.1 Implementation of RNP AR procedures extends beyond procedure design in that an authorization process
for aircraft operators is necessary to ensure that other critical dependencies and associated airworthiness and
operational procedure approvals are complete prior to implementation. Guidance on implementation and operational
approval is provided in the PBN Manual.
1.2.2 The PBN Manual contains navigation specifications applicable to two RNP approach applications: RNP
APCH and RNP AR APCH.
1.2.3 RNP AR APCH operations are classified as approach procedures with vertical guidance (APVs) in
accordance with Annex 6 — Operation of Aircraft. This type of operation requires a positive vertical navigation (VNAV)
guidance system for the final approach segment (FAS). Current RNP AR APCH implementations utilize a barometric
vertical navigation system (BARO-VNAV) meeting specified airworthiness requirements. Obstacle clearance is based on
a statistical assessment of all the component errors referred to as a vertical error budget (VEB). Other suitably accurate
vertical guidance may be implemented provided equivalent accuracy, integrity and containment can be assured.
1.2.4 RNP AR APCH procedures may be designed to support multiple minima for various appropriate RNP, e.g.
RNP 0.3, RNP 0.2, down to RNP 0.1. However, designers should not promulgate procedures with RNP less than 0.3
unless there is an operational benefit. Reductions in RNP reduce the alert limits and increase the possibility of an alert
and a consequent go-around; therefore, the minimum RNP published should not be smaller than necessary to provide
the required operational capability.
1.2.5 The design criteria in this manual are applicable to a range of aircraft types and cannot; therefore, take into
account the full capability of some aircraft types. Consequently, procedures designed in accordance with this manual will
provide an acceptable operational solution in many but not all circumstances. Where an operationally acceptable
solution is not available through the application of these criteria, development of detailed procedures may be needed to
satisfy local conditions. Alternative design solutions may be derived which specify aircraft type or specific performance
parameters, special operating conditions or limitations, crew training, operational evaluation or other requirements that
1-1
1-2 RNP AR Procedure Design Manual
can be demonstrated to provide an equivalent level of safety. Such solutions are not the subject of this manual and
require a case-by-case flight operations safety assessment (FOSA) and operational approval.
1.2.6 RNP AR APCH operations utilize high levels of RNAV capability, and all aspects of the operation must
meet the relevant requirements specified in the PBN Manual.
1.2.7 The safety of RNP AR APCH procedures is dependent upon the proper inter-relationship between aircraft
capability, operating procedures and procedure design. Users of this manual should understand this critical difference in
the design of RNP AR procedures.
1.3.1 Aircraft qualification is integral to the process of authorization for RNP AR operations. For an RNP AR
instrument flight procedure, only aircraft that have demonstrated performance, capability and functionality can be
authorized to conduct RNP AR APCH operations.
1.3.2 Aircraft must meet the requirements of the RNP AR APCH navigation specification given in the PBN
Manual. Aircraft manufacturers must demonstrate and document aircraft performance and capability, and any special
procedures or limitations associated with the aircraft and systems as part of either an aircraft certification programme or
aircraft compliance assessment.
1.3.3 The demonstration of aircraft capability allows all qualified aircraft to use the instrument flight procedure,
relieving the designer of the need to consider individual aircraft types or performance capabilities.
1.3.4 As aircraft performance, integrity and functionality are demonstrated, documented and approved as part of
the demonstration of RNP AR capability, the conduct of special or extensive flight trials and simulations to gather
statistical evidence of the aircraft performance is not required to support the implementation of RNP AR operations.
1.4.1 The authorization process for RNP AR APCH operations includes the approval of operating procedures
and crew training in accordance with the RNP AR APCH navigation specification given in the PBN Manual.
1.4.2 Operating procedures must conform to any conditions in the aircraft RNP AR capability approval and any
additional requirement such as a minimum equipment list (MEL), flight crew operations manuals, aircraft flight manuals
and maintenance guidance.
1.4.3 Operating procedures must also take into account any limitations or requirements specified by the
procedure designer. Specified equipment or capabilities may be required to conduct an RNP AR APCH procedure in
certain cases.
1.4.4 Individual RNP AR APCH procedures are validated in accordance with the PBN Manual and other relevant
guidance prior to publication. However, as variations may occur in functionality, equipment and flyability, operators are
required to conduct an operational validation of each of the procedures applicable to the type of aircraft operated.
1.4.5 Prior to authorization for the conduct of RNP AR APCH operations, an operator must demonstrate to the
State regulator that all appropriate elements of the RNP AR APCH operations have been appropriately addressed
including:
Chapter 1. Description of RNP AR 1-3
e) dispatch procedures;
f) maintenance procedures;
i) conduct of a FOSA.
1.4.6 The specific considerations and issues for these areas are as described in detail in the PBN Manual.
1.5.1 The conduct of RNP AR instrument procedures requires that the aircraft operator examine its crew
information, flight procedures and training to ensure that they are sufficient to enable operator qualification and
operational approval.
1.5.2 Crew information, flight procedures and training must be suitable for the RNP AR APCH instrument
approach procedures, aircraft type(s) or variants, crew positions, airborne systems, navaids and ground systems to be
used. Training topics will be tailored to suit their application to initial qualification, recurrent qualification, requalification,
command training upgrade or differences qualification, as applicable. Crew training requirements are detailed in the PBN
Manual.
Users of this manual must be familiar with the following aspects associated with RNP AR APCH operations.
a) RNP capability. Crews must be aware of the aircraft RNP capability documented in the RNP AR
authorization appropriate to the aircraft configuration or operational procedures (e.g. global positioning
system (GPS) inoperative, use of flight director instead of autopilot).
b) RNP availability check. Prior to the commencement of an approach, the crew is responsible for
ensuring that the appropriate RNP is selected. The highest RNP consistent with the operating
conditions should be selected to reduce the possibility of alerts and consequent missed approaches.
Crews will ensure prior to commencement of a procedure that the required navigation system
performance is available and can be expected to be available through the conduct of the procedure.
RNP should not be changed after commencement of the procedure.
1-4 RNP AR Procedure Design Manual
c) Radius to fix (RF) legs. The use of RF legs provides more flexibility in the design of the procedure
track. RF legs may be present in all phases of the procedure including the final segment, and the
requirement for RF leg capability, if applicable, will be annotated on the approach chart. As the use of
RF legs in the design of procedures is optional, capability to fly procedures incorporating RF legs must
be specifically identified in the operator authorization.
d) Minimum equipment. Minimum equipment provisions are detailed in the PBN Manual. At some
locations, the airspace or obstacle environment will require RNP capability during a missed approach
from anywhere on the procedure. At these locations redundant equipment may be required.
e) Non-standard speeds or climb gradients. RNP AR approaches are developed based on standard
approach speeds and specified a nominal climb gradient in the missed approach. Any exceptions to
these standards must be indicated on the approach procedure, and the operator must ensure they can
comply with any published restrictions before conducting the operation.
f) Non-normal operations. Crews must be competent to contain the aircraft position within tracking
tolerances consistent with the selected RNP during all normal and non-normal operations. (Flight
technical tolerances are specified in the navigation specifications given in the PBN Manual, Volume II,
Chapter 6.)
g) Vertical flight path tolerances. In the FAS, crews will monitor any vertical deviation from the VNAV
path to ensure that the aircraft remains within the tolerances specified in the navigation specifications
given in the PBN Manual, Volume II, Chapter 6.
h) Coupled autopilot. Use of coupled autopilot is recommended. Operator procedures must specify the
conditions for operations without autopilot.
_____________________
Chapter 2
2.1.1 RNP APCH is defined as an RNP approach procedure that requires a lateral TSE of +/-1 NM in the initial,
intermediate and missed approach segments (MAS) and a lateral TSE of ±0.3 NM in the FAS. Guidance on
implementing RNP APCH operations can be found in the PBN Manual, Volume II, Chapter 5, Implementing RNP APCH.
2.1.2 RNP AR APCH is defined as an RNP approach procedure that requires a lateral TSE as low as ±0.1 NM
on any segment of the approach procedure. RNP AR APCH procedures also require that a specific vertical accuracy be
maintained as detailed in the PBN Manual, Volume II, Chapter 6. The vertical datum for RNP AR procedures is the
landing threshold point (LTP). The RNP AR APCH criteria apply only to those aircraft and operators complying with
specified additional certification, approval and training requirements. RNP AR APCH procedures are only published
where significant operational advantages can be achieved while preserving or improving safety of operation. The RNP
AR certification and approval requirements are contained in the PBN Manual. For the purposes of applying the criteria
contained in this manual, RNP levels address obstacle protection associated with RNP values. The RNP level is used to
determine the area semi-width value (in NM) of a protection area associated with a segment of an instrument procedure.
2.2.1 An OCA/H is published for RNP AR procedures on the chart; however, for procedures involving an MAS
with RNP values less than RNP 1.0, DA/H is published instead, and the appropriate notation is entered on the chart. In
this case, the approval process ensures that the missed approach is not executed before the along-track point where the
nominal DA/H occurs.
a) 75 m (246 ft) provided that the inner approach, inner transitional and balked landing surfaces of
Annex 14 — Aerodromes, Volume I, Chapter 4, have been assessed and have not been penetrated;
and
2-1 15/4/11
Corr.
2-2 RNP AR Procedure Design Manual
2.2.3 If an OCH of 75 m (246 ft) is obtained using a straight-in approach, the procedure should not be
further complicated by adding RF turns or reducing RNP solely to obtain lower OCH values.
OCA/H is promulgated for those categories of aircraft for which the procedure is designed. The OCH values shall be
based on the following standard conditions:
a) final approach vertical guidance and DA/H are based on pressure altimeter;
c) aircraft dimensions are considered in certification (no additional procedure design action is required);
d) early go-around or missed approach is safeguarded by the certification and approval process; and
e) aircraft are appropriately certificated and approved by the appropriate authority for RNP AR
operations.
The application of the VEB for obstacle protection relies on accurate altimetry. Rapidly rising terrain, significant
ridgelines or cliffs, steep valley walls and deep canyons may be associated with Bernoulli/Venturi/orographic lifting
effects that can impact vertical performance. Areas where significant variations in pressure may occur must be identified
during the design process, and their effect on the proposed procedure must be considered during the design process
and validated in the safety assessment.
For RNP AR procedures, the semi-width of the primary area is defined as 2 × RNP. There are no buffer or secondary
areas. Table 2-1 lists RNP values applicable to the specific instrument procedure segments.
15/4/11
Corr.
Chapter 2. RNP AR approach procedure design 2-3
RNP AR
Arrival 2 2 1.0
Initial 1 1 0.1
Intermediate 1 1 0.1
2.6.1 In the final approach and MAS, obstacle clearance is provided by two obstacle assessment surfaces
(OAS):
a) a final approach surface based on the VEB of the barometric altimeter system; and
b) a horizontal surface based on a transition distance (TrD) (see 4.6.9), and a missed approach (Z)
surface.
2.6.2 The certification, approval and training processes are designed to ensure barometric altimeter and crew
performance are adequate to remain within this vertical profile.
_____________________
Chapter 3
GENERAL CRITERIA
3.1.1 Aircraft performance differences have a direct effect on the airspace and visibility required for manoeuvres
such as circling approach, turning missed approach, final approach descent and manoeuvering to land (including base
and procedure turns). The most significant factor in performance is speed. Accordingly, five categories of typical aircraft
have been established to provide a standardized basis for relating aircraft manoeuvrability to specific instrument
approach procedures.
3.1.2 The landing configuration which is to be taken into consideration shall be defined by the operator or by the
airplane manufacturer.
3.1.3 Aircraft categories will be referred to throughout this document by their letter designations as follows:
• Category A — less than 169 km/h (91 kt) indicated airspeed (IAS)
• Category B — 169 km/h (91 kt) or more but less than 224 km/h (121 kt) IAS
• Category C — 224 km/h (121 kt) or more but less than 261 km/h (141 kt) IAS
• Category D — 261 km/h (141 kt) or more but less than 307 km/h (166 kt) IAS
• Category E — 307 km/h (166 kt) or more but less than 391 km/h (211 kt) IAS
3.1.4 The criterion taken into consideration for the classification of aeroplanes by categories is the IAS at
threshold (Vat) which is equal to the stall speed (Vso) multiplied by 1.3 or stall speed, in landing configuration at maximum
certificated landing mass (Vso) multiplied by 1.23. If both Vso and Vslg are available, the higher resulting speed at
threshold (Vat) is used. The ranges of speeds (IAS) in Tables 3-1 a) and 3-1 b) are to be used in calculating procedures.
For conversion of these speeds to TAS, see 3.1.7.
3.1.5 Where airspace requirements are critical for a specific category of aircraft, procedures may be based on
lower speed category aircraft, provided use of the procedure is restricted to those categories. Alternatively, the
procedure may be designated as limited to a specific maximum IAS for a particular segment without reference to
category. True airspeed (TAS) should be calculated using the procedure speeds given in Tables 3-1 a) and 3-1 b).
3.1.6 An operator may impose a permanent, lower landing mass, and use of this mass for determining Vat if
approved by the State of the Operator. The category defined for a given aeroplane shall be a permanent value and thus
independent of changing day-to-day operations.
3-1
3-2 RNP AR Procedure Design Manual
Note.— The speeds given in Table 3-1 b) are converted and rounded to the nearest multiple of five for
operational reasons and from the standpoint of operational safety are considered to be equivalent.
Calculating TAS
3.1.7 IAS to TAS conversion for RNP AR procedures uses the following standard equations:
Non-SI units:
TAS = IAS * 171233 * [(288 + VAR) – 0.00198 * H]0.5/(288 – 0.00198 * H)2.628
SI units:
TAS = IAS * 171233 * [(288 + VAR) – 0.006496 * H]0.5/(288 – 0.006496 * H)2.628
Chapter 3. General criteria 3-3
where
IAS = indicated airspeed (kt or km/h, as appropriate)
TAS = true airspeed (kt or km/h, as appropriate)
VAR = variation from international standard atmosphere (ISA) (standard value +15) or local data for
95 per cent high temperature, if available
H = altitude (ft or m, as appropriate)
The above equations are incorporated in a Microsoft Excel spreadsheet, which is available together with the electronic
version of the manual on the ICAO public website (www.icao.int) under “Publications”.
3.2.1 For RNP AR procedures, the turn radius for fly-by and RF turns is calculated using a speed V = TAS + an
assumed tailwind.
3.2.2 Determine the TAS for the turn using formulas in 3.1.7, and the airspeed for the highest aircraft category
from Table 3-1 a) or 3-1 b) for which the procedure is designed.
3.2.3 A speed restriction may be applied to reduce turn radius; however, the maximum speed must be
operationally acceptable for the aircraft intended for the operation. Only one speed restriction per approach segment is
permitted, and the fastest airspeed appropriate for the highest speed category of aircraft for which the procedure is
authorized shall be used to determine that speed.
3.2.4 The turn radius applied at fly-by fixes is based on a standard bank angle of 18 degrees at a TAS plus
assumed tailwind. Locate the highest speed aircraft category that will be published on the approach procedure and use
the appropriate IAS in Table 3-1 a) (international system of units (SI)) or Table 3-1 b) (non-SI units), using the highest
altitude allowed in the turn, calculate the TAS using the appropriate formulas in 3.1.7. For initial and intermediate
segments, use the minimum altitude for the fix prior to the turn fix. Use the tailwind component (TWC) from Table 3-2 a)
(SI units) or Table 3-2 b) (non-SI units) for the highest altitude within the turn. (For turns initiated at an altitude located
between values in the table, a new TWC may be interpolated for that turn. If an interpolated wind value is ever used
below 150 m (492 ft), then the 0 ft value for wind begins with 28 km/h (15 kt.))
3.2.5 For the MAS, use the altitude based on a seven per cent gradient with origin at OCA/H – HL (height loss:
nominally 15 m (49 ft)).
3.2.6 Other tailwind gradients, or specific values, may be used after a site-specific determination of wind has
been carried out based on that location’s meteorological history (using available information from other sources). The
source and values used should be documented.
15/4/11
Corr.
3-4 RNP AR Procedure Design Manual
100 40
500 92
1 000 100
1 500 130
2 000 157
2 500 185
3 000 220
≥3 500 242
3.2.7 Select the appropriate TWC from Table 3-2 a) or 3-2 b) for the highest altitude within the turn and add the
value to TAS. Determine the radius of turn (r).
where
V = (TAS + wind speed) in km/h;
α = bank angle
or
R = (3 431 tan α)/( π*V)
where
V = (TAS + wind speed) in kt;
α = bank angle
r = V/(20* π* R)
where
V = (TAS + wind speed)
15/4/11
Corr.
Chapter 3. General criteria 3-5
500 25
1 000 38
1 500 50
2 000 50
2 500 50
3 000 50
3 500 55
4 000 60
4 500 65
5 000 70
5 500 75
6 000 80
6 500 85
7 000 90
7 500 95
8 000 100
8 500 105
9 000 110
9 500 115
10 000 120
10 500 125
3.2.8 The standard design bank angle is 18 degrees. Lower or higher bank angles are allowed for smooth
transitions, maintaining stabilized approaches, lower minima or to achieve specific leg lengths. Non-standard bank
angles must fall in the window of values listed in Table 3-3.
3-6 RNP AR Procedure Design Manual
3.2.9 These criteria apply to construction at or below FL 190. Where turns above FL 190 are required, a bank
angle of five degrees should be used. If five degrees results in a distance of turn anticipation (DTA) value greater than
20 NM, then:
Note.— Aircraft using these procedures may be from States using SI units and with SI-unit airspeed
indicators (ASIs). However, the standard non-SI unit aircraft category speeds are not exact conversions, they are
rounded. The largest difference is for Category C, where the typical difference in turn radius can be 50 m. This is
significant at low values of RNP (RNP 0.1 with a semi-width of only 370 m) and should be considered in turn boundary
construction.
3.2.10 The DTA is the distance measured from the turn fix to the start and end points of a fly-by turn. The
minimum length of a segment cannot be less than the sum of the DTAs associated with the start and end fix of the
segment (see Figure 3-1).
DTA = r tan(A/2)
where
r = radius of turn for the TAS for the fastest aircraft speed category for which the procedure is designed,
calculated in accordance with 3.2.4
A = turn angle
Note 1.— These criteria differ from the formulas in Doc 8168 — Procedures for Air Navigation Services —
Aircraft Operations (PANS-OPS), Volume II, Tables III-2-1-1 through III-2-1-20, because the roll-in/ roll-out distance is
covered in RNP certification.
Note 2.— The nominal distances for calculations of descent gradients are measured along the arc from the
turn point to the bisector for the inbound leg component and along the arc length from the bisector to the roll-out point for
the outbound leg component.
15/4/11
Corr.
Chapter 3. General criteria 3-7
3.2.11 Where RF legs are necessary, the bank angle required for a given TAS, tailwind speed and turn radius is:
SI units:
Non-SI units:
where
W = tailwind speed
r = turn radius
3.2.12 To ensure that the maximum number of aircraft can fly the procedure, the required radius must result in a
bank angle requirement within the window specified in Table 3-3.
Roll-out
point
Turn
point
Flight DTA
______________________
15/4/11
Corr.
Chapter 4
PROCEDURE CONSTRUCTION
4.1.1 The arrival, initial and intermediate segments provide a smooth transition from the en-route environment to
the FAS. Descent to glide path (GP) intercept and configuring the aircraft for final approach must be accomplished in
these segments. RNP segments should be designed using the most appropriate leg type (track to fix (ARINC leg type)
(TF or RF)) to satisfy obstruction and operational requirements in initial, intermediate, final and MAS. Generally, TF legs
are considered first, but RF legs may be used in lieu of TF-TF turns for turn path control, procedure simplification, or
improved flyability.
Fixes
Fix identification
4.1.2 The fixes used are those in the general criteria. Each fix shall be identified as specified in Annex 15 —
Aeronautical Information Services.
Stepdown fixes
Restrictions on promulgation
of RNP AR procedures
Altimeter errors
4.1.4 Final approach vertical guidance is based on barometric altimeters, and therefore procedures shall not be
promulgated for use with remote altimeter setting sources.
4.1.5 The visual segment surface must be clear of obstacles in order to publish RNP AR procedures.
4-1
4-2 RNP AR Procedure Design Manual
Frame of reference
4.1.6 Positions of obstacles are related to a conventional x, y, z coordinate system with its origin at LTP and
parallel to the world geodetic system (WGS) WGS-84 ellipsoid (see Figure 4-1). The x-axis is parallel to the final
approach track: positive x is the distance before threshold and negative x is the distance after threshold. The y-axis is at
right angles to the x-axis. The z-axis is vertical, heights above threshold being positive.
4.1.7 RNP values are specified in increments of a hundredth (0.01) of a NM. Segment width is defined as
4 × RNP; segment half-width (semi-width) is defined as 2 × RNP (see Figure 4-2). Standard RNP values for instrument
procedures are listed in Table 4-1.
4.1.8 The standard RNP values listed in Table 4-1 should be applied unless a lower value is required to achieve
the required ground track or lowest OCA/H. The lowest RNP values are listed in the “Minimum” column of Table 4-1.
RDP
RDH
VPA
GPI Tangent plane
LTP
RDH
LTP orthometric
tan(VPA) x height
Parallel
Tangent point
Orthometric geoid
15/4/11
Corr.
Chapter 4. Procedure construction 4-3
Plan view
2 RNP 2 RNP
Course centreline
4 RNP
2 RNP 2 RNP
Cross-section view
2 × RNP 2 × RNP
MOC
RNP VALUES
Segment
Maximum Standard Minimum
Initial 1 1 0.1
Intermediate 1 1 0.1
* Used only with the provisions for minimum, straight final segment as specified in the
missed approach section. Refer to section 4.6.
4-4 RNP AR Procedure Design Manual
4.1.9 Segments should be designed with sufficient length to allow the required descent to be as close to the
optimum gradient as possible and to take account of DTA where turns are required. The minimum straight segment (any
segment) length is 2 × RNP (+DTA, as appropriate, for fly-by turn constructions). Paragraph 4.1.7 applies where RNP
changes occur (RNP value changes 1 × RNP prior to fix). For obstacle clearance calculations, the segment extends
1 × RNP before the first fix to 1 × RNP past the second fix.
4.1.10 Changes in RNP values must be completed upon the aircraft reaching the fix; therefore, the area within
±1 RNP of the fix must be evaluated for both segments. RNP reduction is illustrated in Figure 4-3, RNP increase is
illustrated in Figure 4-4, and RNP changes involving RF legs are illustrated in Figure 4-5.
TF leg segment
4.1.11 A TF leg is a geodesic flight path between two fixes and is the normal standard leg used in RNP AR
procedures. TF legs are normally linked by fly-by fixes.
4.1.12 This construction is specific to RNP AR procedures, and only primary areas are used: ½ AW = 2 × RNP;
buffer areas are not applied. Turn angles should be limited to a maximum of 70 degrees where aircraft are expected to
cross (fly-by) the fix at altitudes above FL 190, and to 90 degrees at and below FL 190. When obstructions prevent use
of this construction, use of an RF leg should be considered (see 4.1.13). The fly-by turn area is constructed using the
following steps:
STEP 1: Determine the required ground track. Calculate the turn radius (r) as described in 3.2.4. Construct the
turning flight path tangent to the inbound and outbound legs. The centre will be located on the bisector (see Figures 4-6
and 4-7).
STEP 2: Construct the outer boundary tangential to the inbound and outbound segment outer boundaries, with a
radius of 2 × RNP and centre located at the fix.
STEP 3: Construct the inner turn boundary tangential to the inbound and outbound segment inner boundaries, with
radius of (r + 1 RNP). The centre is located on the bisector (see Figure 4-7).
The evaluation for the succeeding segment begins at a distance of 1 RNP before the turn fix (see Figure 4-6) or at
1 RNP before the angle bisector line (see Figure 4-7), whichever is encountered first.
Chapter 4. Procedure construction 4-5
2 RNP
2 RNP
Fix identifying
1R
RNP change NP
1R
NP
1
RN
P
2 RNP
2 RNP
1 RNP inbound
segment
2
RN
P
2
RN
P
15/4/11
Corr.
4-6 RNP AR Procedure Design Manual
+1 RNP of
inbound segment Fix identifying
RNP change
2 RNP
2 RNP
2 RNP
2 RNP
Fix identifying
RNP change
+1
RN
P +1
R NP
+1
RN
2 RNP
P
α
2 RNP
2
RN
P
2
RN
P
15/4/11
Corr.
Chapter 4. Procedure construction 4-7
TF
RF
Tolerance for
south to north
RF
TF
STEP 2
Evaluate ±1 RNP
distance from bisector
or ATT, whichever
P
is reached first
2 RN
2 RNP
1 RNP ref.
4.1.12, STEP 3
P
STEP 3
RN
1
r+
Pr
ec ev a
ed l u
i n at i
g
s e on
gm
en
2R
t
NP
r
cto
e
2
bi s
RN
P
g le
An
P
2 RN
1 RNP
t reached first
en
g m
se
n g t ion
di lua
cee v a Bisector
u c e reached first
S
Pr
e c ev a
e d lu
P
RN
in a t
2
g io
se n
2
gm
RN
P
P
en
RN
t
2
STEP 1
2
RN
P
Angle bisect or
NP
1R
r+ STEP 3
15/4/11
Corr.
4-10 RNP AR Procedure Design Manual
RF turns
RF leg construction
4.1.13 An RF leg may be used to accommodate a track change where obstructions prevent the design of a fly-by
turn or to accommodate other operational requirements. RF legs provide a repeatable, fixed-radius ground track in a turn.
a) a beginning point at the path terminator fix of the inbound segment and an end point at the beginning
fix of the outbound segment; and
b) the centre of the turn located at the intersection of the bisector and any turn radius (or on the
intersection of the radius perpendicular to the inbound track at the initiation point and the radius
perpendicular to the outbound track at the termination point).
Parameters a) and b) must each specify the same turn arc that is tangent to the inbound leg at its termination fix and
tangent to the outbound leg at its originating fix. Taken together, they overspecify the turn. However, this is resolved by
the data coder selecting the parameters required for the specific navigation system. (See Figure 4-8.)
4.1.15 The turn area is bounded by concentric arcs. The minimum turn radius is 2 × RNP.
STEP 1: Determine the ground track necessary to avoid obstacles. Calculate the turn(s) and associated radii (r)
necessary to best achieve the ground track. Apply 3.2.8 to verify the bank angle associated with R is within the
Table 3-3 specified values.
STEP 2: Locate the turn centre at a perpendicular distance “r” from the inbound and outbound segments. This is the
common centre for the nominal turn track, outer boundary and inner boundary arcs.
STEP 3: Construct the flight path. Draw an arc of radius “r” from the tangent point on the inbound course to the
tangent point on the outbound track.
STEP 4: Construct the outer turn area boundary. Draw an arc of radius (r + 2 * RNP) from the tangent point on the
inbound segment outer boundary to the tangent point on the outbound track outer boundary.
STEP 5: Construct the inner turn area boundary. Draw an arc of radius (r – 2 * RNP) from the tangent point on the
inbound segment inner boundary to the tangent point on the inner boundary of the outbound track.
STEP 6: The height of the surface is constant along a radial line in a manner similar to a spiral stair case as
illustrated in Figure 4-9 a) for approach and Figure 4-9 b) for missed approach. To determine the height of the surface
for an RF leg in the approach, calculate the height based on the gradient along the nominal track and apply the height
across a radial line through the point. To determine the height of the surface for an RF leg in the missed approach, the
distance for the gradient is based on an arc length calculated using a radius of (r – 1 × RNP).
4.1.16 Descent gradients are calculated between the nominal fix positions. For RF segments, the distance used is
the arc distance between the nominal fix positions.
Chapter 4. Procedure construction 4-11
2 RNP
Evaluate ±1 RNP
distance from angle 2 RNP
bisector as both
segments
b
a STEP 4
a=r
b = r + (2 × RNP)
STEP 3 r c = r – (2 × RNP)
c
Segment STEP 5
initial
r STEP 2:
fix
Locate turn centre
Tangent points
2 RNP
2 RNP
15/4/11
Corr.
4-12 RNP AR Procedure Design Manual
Figure 4-9 a). Obstacle clearance surface (OCS) for RF approach segments
Chapter 4. Procedure construction 4-13
s = (r – 1 RNP) 2πθ
360°
h = climb gradient * s
h
r
s
)
(r – 1 RNP
θ
RNP)
(r – 1
15/4/11
Corr.
4-14 RNP AR Procedure Design Manual
Mountainous terrain
4.1.17 In mountainous terrain, minimum obstacle clearance (MOC) for the initial and intermediate and missed
approach segments should be increased by as much as 100 per cent.
4.2.1 In the initial approach segment the maximum and the optimum lateral accuracy value is 1.0 NM. The
minimum value is 0.1 NM.
Length
4.2.2 Segments should be designed with sufficient length to allow the required descent to be as close to the
optimum gradient as possible and to take account of DTA where fly-by turns are required.
4.2.3 Minimum straight segment (any segment) length is 2 × RNP (+DTA, as appropriate, for fly-by turn
construction). Paragraph 4.1.10 applies where the lateral accuracy value changes occur (changes 1 × RNP prior to the
fix).
4.2.4 The maximum initial segment length (total of all component segments) is 50 NM.
Alignment
4.2.5 The normal arrival for an RNP AR procedure will be via a direct RNP or RNAV route. However, RNP AR
procedures can also incorporate the normal RNP APCH T- or Y-bar arrangement. This is based on a runway-aligned
final segment preceded by an intermediate segment and up to three initial segments arranged either side of and along
the final approach track to form a T or a Y.
4.2.6 RNAV enables the geometry of approach procedure design to be very flexible. The “Y” configuration is
preferred where obstructions and air traffic flow allow. The approach design should provide the least complex
configuration possible to achieve the desired minimum OCA/H. See Figure 4-10 for examples.
4.2.7 Turns for connecting TF legs should normally be restricted to 90 degrees. For turns greater than this, RF
legs should be used and may be considered for all turns. For the T and Y configurations, offset initial approach fixes
(IAFs) are located such that a course change of 70 to 90 degrees is required at the IF. The capture region for tracks
inbound to the offset IAF extends 180 degrees about the IAFs, providing a direct entry when the course change at the
intermediate fix (IF) is 70 degrees or more.
4.2.8 The lateral initial segments are based on course differences of 70 to 90 degrees from the intermediate
segment track. This arrangement ensures that entry from within a capture region requires a change of course at the IAF
not greater than 110 degrees.
Chapter 4. Procedure construction 4-15
IAF IAF
IF
FAP
4.2.9 The central initial segment may commence at the IF. It is normally aligned with the intermediate segment.
Its capture region is 70 to 90 degrees either side of the initial segment track, the angle being identical to the course
change at the IF for the corresponding offset IAF. For turns greater than 110 degrees at the IAFs, sector 1 or 2 entries
should be used.
4.2.10 Where one or both offset IAFs are not provided, a direct entry will not be available from all directions. In
such cases a holding pattern may be provided at the IAF to enable entry to the procedure via a procedure turn.
4-16 RNP AR Procedure Design Manual
4.3 HOLDING
4.3.1 If holding patterns are to be provided, the preferred configuration is located at the IAF and aligned with the
initial segment.
Descent gradient
4.3.2 See Table 4-2 for standard and maximum descent values.
Minimum altitudes
4.3.3 Minimum altitudes in the initial approach segment shall be established in 50-m or 100-ft increments, as
appropriate. The altitude selected shall provide an MOC of 300 m (984 ft) above obstacles and must not be lower than
any altitude specified for any portion of the intermediate or final approach segments.
Procedure altitudes/heights
4.3.4 All initial approach segments shall have procedure altitudes/heights established and published. Procedure
altitudes/heights shall not be less than the OCA/H and shall be developed in coordination with air traffic control (ATC),
taking into account the aircraft requirements. The initial segment procedure altitude/height should be established to allow
the aircraft to intercept the FAS descent gradient/angle from within the intermediate segment.
4.4.1 The intermediate approach segment blends the initial approach segment into the FAS. It is the segment in
which aircraft configuration, speed and positioning adjustments are made for entry into the FAS.
Descent gradient
Segment
Standard Maximum
4.4.2 In the intermediate approach segment, the maximum and optimum lateral accuracy value is 1.0 NM. The
minimum value is 0.1 NM.
Length
4.4.3 Segments should be designed with sufficient length to allow the required descent to be as close to the
OPTIMUM gradient as possible and accommodate the DTA where fly-by turns are required. Minimum straight segment
(any segment) length is: 2 × RNP (+DTA, as appropriate, for fly-by turn constructions). Paragraph 4.1.10 applies where
the lateral accuracy value changes occur (RNP value changes 1 RNP prior to fix).
Alignment
4.4.4 The intermediate approach segment should be aligned with the FAS whenever possible. Fly-by turns at the
final approach point (FAP) are limited to a maximum of 15-degree track change at the fix. Turns of more than 15
degrees should employ an RF leg.
Descent gradient
4.4.5 The optimum descent gradient in the intermediate segment is 2.5 per cent (1.4 degrees). The maximum
descent gradient is the same as the maximum final approach gradient. If a descent angle higher than standard is used,
the evaluation should ensure that sufficient flexibility is provided for the continuous descent approach (CDA) technique.
4.4.6 If a higher than standard gradient is required, a prior segment must make provision for the aircraft to
configure for final segment descent.
4.4.7 Where a track change using a fly-by turn occurs at the FAP, the reduction in track distance may be ignored
as the difference is negligible (maximum 15-degree turn).
Minimum altitude/height
4.4.8 The minimum altitude/height is the height of the highest obstacle within the intermediate approach
segment area plus the MOC of 150 m (492 ft).
4.4.9 The minimum altitude/height in the intermediate approach segment shall be established in 50-m or 100-ft
increments, as appropriate.
Procedure altitudes/heights
4.4.10 Procedure altitudes/heights in the intermediate segment shall be established to allow the aircraft to
intercept a prescribed final approach descent.
4.4.11 When establishing the intermediate segment minimum altitude (vertical path angle (VPA) intercept altitude),
the difference between the 150 m (492 ft) intermediate MOC value and the MOC value provided by the VEB OAS where
it reaches the height of the intermediate segment controlling obstruction should be considered.
4.4.12 If the VEB MOC at the height of the controlling obstruction exceeds the intermediate segment MOC, then
the VEB MOC value should be applied (see Figures 4-11 and 4-12).
4.4.13 If the VEB is less than the MOC for the intermediate segment at the FAP, the intermediate MOC should be
extended into the final segment until intersecting the VEB surface.
Note.— If the minimum altitude has to be raised because of obstacles in the intermediate segment, the
FAP must be moved. The VEB must be recalculated and a new minimum altitude derived.
4.5 FAS
4.5.1 FAS lateral guidance is based on RNP. Vertical guidance is based on BARO-VNAV avionics. The FAS
OAS (VEB) is based on limiting the vertical error performance of BARO-VNAV avionic systems to stated limits.
4.5.2 In the FAS the maximum lateral accuracy value is 0.5 NM, the optimum value is 0.3 NM and the minimum
value 0.1 NM. The segment should be evaluated for 0.3 NM. A lower than optimum value should only be used if:
a) 0.3 NM results in a DA/H greater than 90 m (295 ft) above LTP; and
4.5.3 In these cases, the minimum that may be used is 0.1 NM. Where approaches with RNP values less than
0.3 are published, OCA/H should also be published for RNP 0.3.
15/4/11
Corr.
Chapter 4. Procedure construction 4-19
FAP
based on FAP
150 m (492 ft) based on
VPA
MOC VEB MOC
VEB MOC
OAS
VPA (θ)
Tangent
DVEB plane
15/4/11
Corr.
4-20 RNP AR Procedure Design Manual
Length
4.5.4 No maximum or minimum is specified. However, the length must accommodate the descent required and
must provide a stabilized segment prior to OCA/H.
Alignment
Straight-in approaches
4.5.5 The optimum final approach alignment is a TF segment straight in from FAP to LTP on the extended
runway centreline (see Figure 4-13). If necessary, the TF track may be offset by up to five degrees. Where the track is
offset, it must cross the extended runway centreline at least 450 m (1 476 ft) before the LTP.
Location of FAP
4.5.6 The FAP is a point on the reciprocal of the true final approach course where the VPA extending from RDH
above the LTP (fictitious threshold point (FTP) if offset) intersects the intermediate segment altitude.
VPA
4.5.7 In all cases, the FAP shall be identified as a named fix. The latitude and longitude of the FAP is calculated
geodetically from the LTP using:
a) the reciprocal of the true track of the final approach TF leg (true track – 180 degrees); and
4.5.8 Where the final approach consists of a single TF leg, a Microsoft Excel spreadsheet, which is available
together with the electronic version of the manual on the ICAO public website (www.icao.int) under “Publications”, is
provided to calculate DFAP (distance from LTP to FAP) and the WGS-84 latitude and longitude of the FAP
(see Figures 4-14 a) and 4-14 b)).
⎛ re + a ⎞
re * ln ⎜ ⎟
r
⎝ e + b + RDH ⎠
d=
tan ( VPA )
or
where
The calculations are geoidal (rather than ellipsoidal) since the VPA is a pressure gradient determined by the barometric
altimeter and is therefore relative to the geoid. The VPA maintains a gradient relative to the earth and follows an arcing
path as illustrated in Figure 4-13.
FAP calculator
4.5.10 An FAP calculator is available together with the electronic version of the manual on the ICAO public
website (www.icao.int) under “Publications”.
4.5.11 A final segment may be designed using an RF leg segment when obstacles or operational requirements
prevent a straight-in approach from the FAP to the LTP. Fly-by turns are not allowed. The along-track geodetic distance
from the LTP (FTP if offset) to the point the GP intercepts the intermediate segment minimum altitude (DFAP) should be
determined and DFAP calculated.
4-22 RNP AR Procedure Design Manual
FAP VEB
Calculations OAS Origin & Gradient
Min Intermediate Segment Altitude: 762.00 m
Min Intermediate Segment Alt (a): 500.00 m LTP Elevation: 16.00 m
LTP MSL Elevation (b): 20.00 m Vertical Path Angle: 3.00 °
RDH: 15.00 m -165.00 RDH: 17.00 m
Vertical Path Angle (VPA): 3.00° RNP Value: 0.30 NM
8 ISA: -12.44 °
Distance from LTP to FAP (D): 8,872.36 m
4.79 NM Straight In Segment
(Wingspan =<80 m ) LTPto Origin: 1042.86 m
LTP/FTP Latitude: 036° 30' 00.00" N
LTP/FTP Longitude: 095° 54' 00.00" W OAS Gradient : 0.049845
True RWY Bearing/True Course: 15.00
RF Turn Segment | Bank angle: 18.00°
FAP Latitude: 36° 25' 21.962'' N (Wingspan =<80 m ) LTP to Origin: 1138.37 m
FAP Longitude: 95° 55' 32.181'' W
Latitude/Longitude valid for OAS Gradient : 0.049845
straight segment only SI UNITS
V e r s I o n 2.2
VPA 3/17/09
VEB MOC
Temperature Limits
Vertical Path Angle: 3.00° Vertical Path Angle 3.00°
Max Vertical Path Angle: 3.50° LTP MSL Elevation 16.00 m
FAP Elevation: 762.00 m RDH 17.00 m
LTP Elevation: 400.00 m Tangent of VPA 0.052408
ACT: 2.44°C OAS Gradient 0.049845
OAS Origin Distance (measured 762.00 m
Min Vertical Path Angle 2.99°
along-track from LTP)
Obstacle Distance (measured
NA Below 2.44°C 36.39°F 3,048.00 m
along-track from LTP)
FAP VEB
Calculations OAS Origin & Gradient
4.5.12 The leg (TF or RF) on which the FAP is located is determined by comparing this distance with the total
length of the FAS.
4.5.13 Procedures that incorporate an RF leg in the final segment shall establish the aircraft at a final approach
roll-out point (FROP) aligned with the runway centreline prior to the greater of:
150 − RDH
SI units: D150 =
tan ( VPA )
492 − RDH
Non-SI units: D492 =
tan ( VPA )
b) a minimum distance before OCA/H is calculated as in 4.5.14 (see Figures 4-15 and 4-16).
4.5.14 TAS based on the IAS for the fastest aircraft category for which the procedure is designed at ISA + 15o C
at aerodrome elevation, plus a 15-kt tailwind for a time of:
HATh − RDH
SI units: D15sec = + ( VTAS + 27.78 ) * 4.167
tan ( VPA )
HATh − RDH
Non-SI units: D15sec = + ( VTAS +15 ) * 25.317
tan ( VPA )
b) 50 seconds where the missed approach RNP is less than 1.0 or where the missed approach is based
on RNP APCH:
HATh − RDH
SI units: D50sec = + ( VTAS + 27.78 ) * 13.89
tan ( VPA )
HATh − RDH
Non-SI units: D50sec = + ( VTAS +15 ) * 84.39
tan ( VPA )
Note.— The HATh is the height above threshold of the OCH or DH, as appropriate.
4.5.15 Where the FAP must be located within an RF segment, the segment must be broken into two segments,
each having the same radius and turn centre, with the FAP coincident with the initial fix of the second segment.
Determine the flight track distance (DFAP) from LTP to FAP under the formula in 4.5.9. The length of the RF leg
(LENGTHRF) from the FROP to FAP can be calculated by subtracting distance to the final approach roll-out point (DFROP)
from DFAP.
15/4/11
Corr.
Chapter 4. Procedure construction 4-25
LTP
Roll-out point
on final
centreline track
OCH 1 due
to obstacles
150 m
(492 ft)
FROP
RDH
4.5.16 The number of degrees of arc given a specific arc length may be calculated from:
Conversely, the length of an arc given a specific number of degrees of turn may be calculated from:
4.5.17 This method may be used for calculating WGS-84 latitude and longitude (see Figure 4-17). Several
software packages will calculate a geographical coordinate derived from Cartesian measurements from the LTP. Use
the following formulas and method to obtain the Cartesian values.
STEP 1: Determine the flight track distance (DFAP) from LTP to FAP using the formula in 4.5.9.
STEP 2: Determine the distance (DFROP) from LTP to the FROP (see Figure 4-17).
STEP 3: Subtract DFROP from DFAP to calculate the distance around the arc to the FAP from the FROP.
X = DFROP + r * sin A
Y = r – r * cos A
where
X and Y are measured on a conventional right-hand Cartesian coordinate system with a positive X-axis aligned with the
reciprocal of the runway azimuth.
r = radius of RF leg
A = turn angle
4.5.19 The turn altitude is determined by projecting the glide path from RDH out to the IAF along the fix-to-fix flight
track. The turn altitude is the altitude of the GP at the fix or the minimum fix altitude, whichever is higher.
4.5.20 The flight control computers (FCCs) in some aircraft limit bank angles when the aircraft is below 122 m
(400 ft) radio altitude. If an obstacle or terrain in any portion of the turn area is higher than the altitude of the nominal
approach track perpendicular to the obstacle or terrain minus 122 m (400 ft), (obstacle elevation greater than nominal
track altitude – 122 m (400 ft)), then the FCC bank angle limitation of five degrees should be used in the turn calculation.
Chapter 4. Procedure construction 4-27
r
r • cos(Φ) Φ
FAP
r r • sin(Φ)
r – r • cos(Φ)
LTP
FROP
DFROP
X = DFROP + r • sin(Φ)
Y = r – r • cos(Φ)
VPA requirements
4.5.21 The minimum standard design VPA is 3 degrees. VPAs higher than 3 degrees shall be used only:
b) when cold temperatures reduce the effective VPA below a minimum value of 2.75 degrees.
4.5.22 Table 4-3 lists the highest allowable VPA by aircraft category. If the required VPA is greater than the
maximum for an aircraft category, OCA/H for that category should not be published.
4.5.23 The GP angle should not result in a descent rate (DR) greater than a nominal 300 m/min (1 000 ft/min) for
aircraft served by the procedure.
4-28 RNP AR Procedure Design Manual
4.5.24 RDH values and recommended ranges of values appropriate for aircraft categories A to D. RNP AR
procedures serving the same runway should share common RDH and GP angle values. If an ILS serves the runway, the
ILS RDH and GP angle values should be used to define the VPA. If there is no ILS, but a visual glide slope indicator
(VGSI) system with a suitable RDH and GP angle serves the runway, the VGSI RDH and VPA equal to the GP angle
should be used. Otherwise, an appropriate RDH value from Table 4-4 should be selected, with a three-degree VPA.
Note.— A note must be published on the approach chart indicating when the VGSI angle is more than
0.2 degrees from the VPA or when the VGSI RDH differs from the procedure RDH by more than 1 m (3 ft), e.g. PAPI not
coincident with VPA.
4.5.25 RNP final segment OAS is based on vertical guidance provided by BARO-VNAV. The effective VPA
(actual angle flown) depends on the temperature deviation from standard ISA associated with airport elevation. The high
temperature limit attempts to prevent exceeding a DR of 300 m/min (1 000 ft/min). The low temperature limit assures
obstacle protection for the lowest expected temperature and prevents the effective VPA from going below 2.5 degrees.
ISA for the airport may be calculated using the following formulas.
Recommended
Aircraft Category RDH ±5 ft Remarks
The approach procedure should offer obstacle protection within a temperature range that can reasonably be expected to
exist at the airport. Establish the lower temperature limit from the five-year history (or longer). For each year, determine
the month with the lowest average temperature. Then within each month determine the coldest temperature. The
average of the five values is the average coldest temperature. Determine the difference (ΔISALOW) between this
temperature and the ISA temperature for the airport using the following formula:
Note.— Geopotential height includes a correction to account for the variation in acceleration of gravity (g)
(average 9.8067 m sec2) with heights. However, the effect is negligible at the minimum altitudes considered for
obstacle clearance: the difference between geometric height and geopotential height increases from zero at mean sea
level to –18 m (–59 ft) at 10 972 m (36 000 ft).
4.5.26 The minimum effective VPA is obtained by reducing the design VPA by deducting the cold temperature
altimeter error from the design altitude of VPA at the FAP and calculating the reduced angle from the origin of the VPA
at threshold level. (See Figure 4-18.)
FAP altitude
e
FAP altitude
PA at delta ISA low
nV
esig
D
PA a
tive V
Effec ISA low
lta
at de
LTP elevation
15/4/11
Corr.
4-30 RNP AR Procedure Design Manual
4.5.27 The effective VPA at the minimum promulgated temperature must not be less than 2.5 degrees. The
nominal VPA, in some cases may be raised above 3.0 degrees. However, consideration must be given to: aircraft
performance at the higher VPA; high temperature effects; and the regulatory constraints on the maximum GP for the
aircraft.
4.5.27.1 If the temperature history for the location indicates the low temperature limitation is frequently encountered
during established busy recovery times, consideration should be given to raising the GP angle to the lowest angle (within
the limits of Table 4-3) that will make the approach more frequently usable.
a+e
MinVPA = arctan( )
r
where
e (Si units) = ΔISALOW * [(0.19 * 0.3048) + (0.0038 * a)] + (0.032 * a) + (4.9 * 0.3048), or
4.5.27.1.2 If the effective VPA is less than 2.5 degrees, calculate the ΔISALOW to achieve an angle of 2.5 degrees
using one of the following formulas:
where
el = FAP altitude – b
a
r=
tan(VPA)
4.5.27.1.3 Determine the published low temperature limitation “NA below” for the procedure using the ΔISALOW
derived from the equation in 4.5.27.1.2 in the following formula:
Note.— If the temperature history for the location indicates the low temperature limitation is frequently
encountered during established busy recovery times, consider raising the VPA to the lowest angle that will make the
approach usable more often.
4.5.28 The maximum effective VPA is obtained by increasing the design VPA by adding the high temperature
altimeter error to the design altitude of VPA at the FAP and calculating the increased angle from the origin of the VPA at
threshold level (see Figure 4-19).
FAP altitude at
delta ISA high
eh
FAP altitude
A
VP
um
xim
Ma
c a
VPA
ign
Des
LTP elevation
4.5.28.1 To accomplish this, determine the maximum ΔISAHigh (above ISA) that will produce the maximum allowed
VPA using one of the following formulas:
eh − (0.032 * a) − 4.9
ΔISAHigh (non-SI units) =
0.19 + (0.0038 * a)
where
eh = c – FAP altitude
a
r=
tan(VPA)
4.5.28.2 The maximum effective VPA angle is 1.13 times the Table 4-3 maximum design value for the fastest
published approach category. If the calculated effective VPA exceeds this, then the published maximum temperature
must be restricted to a lower value. Determine NAabove with the following formula:
VEB
4.5.30 The distance of the final approach OAS origin from LTP (DVEB) and its slope are defined by the VEB. Two
Microsoft Excel spreadsheets (see Figures 4-20 a) and 4-20 b)) that perform VEB calculations are available together
with the electronic version of the manual on the ICAO public website (www.icao.int) under “Publications”.
Note.— In case of RNP reduction in segments where the VEB is applied, the maximum RNP value shall be
used in VEB calculation.
Chapter 4. Procedure construction 4-33
FAP VEB
Calculations OAS Origin & Gradient
Min Intermediate Segment Altitude: 762.00 m
Min Intermediate Segment Alt (a): 500.00 m LTP Elevation: 16.00 m
LTP MSL Elevation (b): 20.00 m Vertical Path Angle: 3.00 °
RDH: 15.00 m -165.00 RDH: 17.00 m
Vertical Path Angle (VPA): 3.00° RNP Value: 0.30 NM
Ξ ISA: -12.44 °
Distance from LTP to FAP (D): 8,872.36 m
4.79 NM Straight In Segment
(Wingspan =<80 m ) LTPto Origin: 1042.86 m
LTP/FTP Latitude: 036° 30' 00.00" N
LTP/FTP Longitude: 095° 54' 00.00" W OAS Gradient : 0.049845
True RWY Bearing/True Course: 15.00
RF Turn Segment | Bank angle: 18.00°
FAP Latitude: 36° 25' 21.962'' N (Wingspan =<80 m ) LTP to Origin: 1138.37 m
FAP Longitude: 95° 55' 32.181'' W
Latitude/Longitude valid for OAS Gradient : 0.049845
straight segment only SI UNITS
V e r s I o n 2.2
VPA 3/17/09
VEB MOC
Temperature Limits
Vertical Path Angle: 3.00° Vertical Path Angle 3.00°
Max Vertical Path Angle: 3.50° LTP MSL Elevation 16.00 m
FAP Elevation: 762.00 m RDH 17.00 m
LTP Elevation: 400.00 m Tangent of VPA 0.052408
ACT: 2.44°C OAS Gradient 0.049845
OAS Origin Distance (measured 762.00 m
Min Vertical Path Angle 2.99°
along-track from LTP)
Obstacle Distance (measured
NA Below 2.44°C 36.39°F 3,048.00 m
along-track from LTP)
FAP VEB
Calculations OAS Origin & Gradient
4.5.31 The height of the OAS at any distance “x” from the LTP can be calculated as follows:
where
( x − DVEB ) * OASgradient
f=
re
DVEB = distance from LTP to the LTP level intercept of the VEB OAS (m or ft, as appropriate)
Note.— DVEB and tan final approach OAS are both obtained from Appendix 1 (SI units) or Appendix 2
(non-SI units).
4.5.32 Where the final approach is a straight segment, the OAS gradient is the same for the straight and curved
path portions. However, the obstacle clearance margin is increased to account for the difference in the flight paths of the
navigation reference point on the aircraft and the wheels. For wings level, this is assumed to be 8 m (25 ft) for all aircraft.
Additional adjustment for bg during a bank is calculated as follows:
bg = 40 * sin(bank angle) m; or
The optimum bank angle equals 18 degrees; however, other bank angles may be applied for specific aircraft. The
adjustment obstacle clearance margin for the curved section of the final approach and the relative orientation of the VEB
OAS for the straight and curved sections are illustrated in Figure 4-21.
4.5.33 DVEB decreases slightly when the VPA is increased. Therefore, if the angle is increased to eliminate a
penetration, the VEB must be recalculated and the OAS re-evaluated. To determine the OAS height and VEB MOC (at
obstacle), use the following formulas:
where
OBS x − Dorigin
p=
⎛ 1 ⎞
re • ⎜ ⎟
⎝ OAS grad ⎠
OBS x • tan(VPA)
q=
re
4.6.1 The MAS begins at the point of the OCA/H on the VPA and terminates at the point at which a new
approach, holding or return to en-route flight is initiated.
General principles
4.6.2 The considerations of missed approach design options follow this order:
b) RNAV missed approach using RNP APCH. Reversion to RNP APCH is used only if a significant
operational advantage is achieved; and
4.6.3 The missed approach OAS (Z) is 2.5 per cent with provision for additional gradients of up to 5 per cent for
use by aircraft whose climb performance permits the operational advantage of the lower OCA/H associated with these
gradients, with the approval of the appropriate authority. In case of the application of a higher climb gradient, an OCH for
2.5 per cent or an alternate procedure with a gradient of 2.5 per cent must also be made available.
4.6.4 In a case where a 2.5 per cent gradient is not possible due to other constraints, the missed approach OAS
is the minimum practicable gradient.
Note.— A minimum gradient greater than 2.5 per cent may be required when an RF leg in the final
approach restricts the necessary increase in OCA/H.
Chapter 4. Procedure construction 4-37
AS
TF O
A
VP
AS OAS
RF
TF O
1 RNP
TF OAS RF OAS RF RF
origin origin FROP segment
initial fix
1 RNP
15°
FAS RNP RNP 0.5 RNP 1.0
1 RNP
Figure 4-22. Maximum extension of RNP < 1.0 in the missed approach
15/4/11
Corr.
4-38 RNP AR Procedure Design Manual
4.6.5 For missed approaches using levels less than RNP 1.0 (see Figure 4-22), the following constraints apply:
a) Aircraft are required to follow the designed missed approach track regardless of the point from which
the go-around is initiated;
b) Extension of final approach levels less than RNP 1.0 into the MAS is limited (see 4.6.17);
c) For RNP levels less than RNP 1, turns are not allowed below 150 m (492 ft) AGL;
d) Missed approach levels less than RNP 1.0 may limit the population of aircraft that can fly the
procedure and should be implemented only where necessary. If applied, a charting note is required;
and
e) A DA/H is specified and a note is added to the approach chart cautioning against early transition to a
missed approach RNP for guidance.
4.6.6 The standard MAS splays from the FAS width at OCA/H or DA/H, as appropriate, at 15 degrees relative to
course centreline, to a width of ±2 NM (RNP 1.0). (See Figure 4-23.)
4.6.7 Turns are not allowed until the splay is complete. If turns are required before Dsplay, consider another
construction technique, e.g. reducing the MAS lateral accuracy (RNP) values below 1.0.
2 NM
15°
15°
2 NM
DSPLAY
15/4/11
Corr.
Chapter 4. Procedure construction 4-39
4.6.8 See Figures 4-24, 4-25 and 4-26 for illustration of the following process.
4.6.9 The range of the start of climb (SOC) relative to LTP is:
where
XSOCCat = range of the SOC for the aircraft category, positive before threshold, negative after threshold.
OCHCat = OC H for the aircraft category (the minimum value is the pressure altimeter height loss for the
category)
and
×
3
6
0
0
where
t = 15 seconds
MaxGndSpeed = maximum final approach TAS for the aircraft category, calculated at aerodrome elevation
and ISA + 15 plus a 19 km/h (10 kt) tailwind
wpr = 18.3 m (60 ft) (99.7 per cent waypoint resolution error)
fte = 22.9/tan VPA m, (75/tan VPA ft) (99.7 per cent flight technical error)
Note.— The parameters listed above must be converted to units appropriate for the units used for
MaxGndSpeed for calculation of TrD in NM or km as desired.
OCHCat − HLCat
15/4/11
Corr.
4-40 RNP AR Procedure Design Manual
Note.— The actual navigation performance error (anpe), waypoint precision error (wpr) and fte are the 99.7
per cent probability factors from the VEB projected to the horizontal plane and factored by 4/3 to give a 10E–5 margin.
Gradient
4.6.11 A nominal missed approach climb surface gradient (tan Z) of 2.5 per cent is specified by the procedure.
Additional gradients of up to 5 per cent may also be specified as described in 4.6.2. These may be used by aircraft
whose climb performance permits the operational advantage of the lower OCA/H associated with these gradients, with
the approval of the appropriate authority.
4.6.12 The missed approach route is a series of segments. The following leg types are permitted: TF and RF.
4.6.13 Additionally, if the RF leg RNP value is <1.0, the RF leg length must comply with the requirements of
4.6.17 relating to “Missed approach RNP < 1.0 and promulgation of the maximum DA/H”.
OCHCat
VPA
RDH
LTP
TrD
VP
A′
VP
A
VE
B OCH Z
LTP
Height SOC
loss
2 2 2
T * MaxGndSpeed + 4/3 anpe + wpr + fte
4.6.14 The number and magnitude of turns add complexity to a procedure; therefore, their use should be limited.
Where turns are required in the missed approach, the FAS track should continue to be maintained to the departure end
of runway (DER) (or the equivalent in an offset procedure). The first turn must not occur before the DER unless the
missed approach RNP is less than RNP 1.0.
4.6.15 If the missed approach level is less than RNP 1.0, missed approach RF turns must limit bank angles to
15 degrees; maximum speed limits may be imposed to achieve a specific radius and, if possible, RF turns should not
start before DER.
4.6.16 In certain circumstances, neither a reduced RNP nor an RF turn can overcome a straight-ahead missed
approach obstacle. In these circumstances, the RNP procedure can be terminated and a standard global navigation
satellite system (GNSS) RNP APCH missed approach constructed. In this case, the area splay for the Z surface begins
1 RNP (final approach) prior to the longitudinal location of the OCA/H on the VPA, or 75 m (250 ft) on the VPA,
whichever is higher, and splays at 15 degrees on each side.
Note.— A heading to altitude (ARINC leg type) (VA) leg based on a GNSS missed approach (RNP APCH)
can provide better clearance margin from a straight ahead missed approach obstacle than either RF or fly-by turns.
15/4/11
Corr.
4-42 RNP AR Procedure Design Manual
Missed approach RNP < 1.0 and promulgation of the DA/H (see Figure 4-25)
4.6.17 Where the OCA/H is defined by missed approach obstacles, the missed approach RNP value may be
limited until past the obstruction. The largest RNP value (of FAS RNP or MAS RNP <1.0) that clears the obstruction
should be used. However, the DA/H is promulgated rather than OCA/H and is limited to 75 m (246 ft), (90 m (295 ft)) or
higher. The chart must be annotated that “Transition to missed approach RNP for lateral guidance must not be initiated
prior to the along-track position of the DA/H”.
4.6.18 The maximum distance (DMASRNP) that a lateral accuracy value <1.0 NM may be extended into the missed
approach measured from the point where the DA/H intersects the VPA is:
DMASRNP = (RNP missed approach – RNP final approach)*cot inertial reference unit (IRU) splay
where
TAS = initial missed approach speed for the aircraft category for the aerodrome elevation at ISA + 15
VP
A′
VP
A
OCH
Height SOC′
VE loss
B
LTP/FTP Z hma
ha SOC
15/4/11
Corr.
Chapter 4. Procedure construction 4-43
Note.— The specification of a DA/H and a distance ensures that an eight degrees per hour IRU drift rate
does not exceed the extended final approach RNP boundary.
4.6.19 Where turns are necessary, the turn initiation must occur after passing 150 m (492 ft) AGL and at least
DMASturn after DA/H. When possible, the turn should not occur until after DER.
4.7.1 OCA/H calculation involves a set of OAS. If the OAS is penetrated, the aircraft category-related height loss
allowance is added to the height of the highest approach obstacle or the equivalent height of the largest missed
approach OAS penetration, whichever is greater. This value becomes the OCA/H (see Figures 4-26 and 4-27).
VP
A′ Earliest
VP turn point
A
MOC
OCH
Height
loss
SOC′
VE
B
LTP/FTP Z
SOC
Approach obstacles
dz
15/4/11
Corr.
4-44 RNP AR Procedure Design Manual
Accountable obstacles
4.7.2 Accountable obstacles are those penetrating the OAS. They are divided into approach obstacles and
missed approach obstacles as follows (see Figure 4-26).
• Approach obstacles are those between the FAP and the SOC.
4.7.3 However, in some cases this categorization of obstacles may produce an excessive penalty for certain
missed approach obstacles. Where desired by the appropriate authority, missed approach obstacles may be defined as
those above a plane surface parallel to the plane of the VPA and with origin at the SOC, i.e., obstacle height greater
than (XSOC + x)tan VPA, where XSOC is the distance from LTP to the SOC.
OCH calculation
4.7.4 First, determine the height of the highest approach obstacle penetrating the final approach OAS or the
horizontal plane from Dveb to the origin of the Z surface.
4.7.5 Next, reduce the heights of all missed approach obstacles to the height of equivalent approach obstacles
by the formula given below:
where
X = distance of the obstacle from threshold (positive prior to the LTP threshold, negative after)
XZ = X coordinate of the point where ZX = ZLTP (origin of the missed approach surface).
4.7.6 MOC is 0 m/(0 ft) for a straight missed approach and RF turns; 30 m/(98 ft) for turns up to 15 degrees;
50 m/(164 ft) for turns greater than 15 degrees.
4.7.7 Determine OCH for the procedure by adding the height loss allowance defined in Table 4-5, to the height
of the highest approach obstacle (real or equivalent).
OCH = ha + HL margin
15/4/11
Corr.
Chapter 4. Procedure construction 4-45
where
do = shortest distance from the obstacle to the earliest turning point (TP) (see Figures 4-26 and 4-27)
50 m (164 ft) (Cat H, 40 m (132 ft)) for turns more than 15 degrees and 30 m (98 ft) for turns 15 degrees
or less.
4.7.9 If the obstacle elevation/height penetrates the Z surface, the OCA/H must be increased or the TP moved to
obtain the required clearance.
4.7.10 When an RF leg is used in a missed approach, the along-track distance during the RF turn for inclusion in
the track distance to calculate the gradient of the OAS is the arc length(s) based on a turn radius of: r – 1RNP. (See
Figures 4-9 b) and 4-28).
4.7.11 The height of the surface at any point on the track is constant radially across the surface. The slope is only
in the direction of the nominal flight vector tangent to the nominal track at any point and has a lateral slope of zero along
any radius.
where
do = is the distance measured along the arc(s), calculated for RF legs using a radius of (r – 1RNP),
4.7.13 If the obstacle elevation/height penetrates the Z surface, the OCA/H must be increased or the TP moved to
obtain the required clearance.
4-46 RNP AR Procedure Design Manual
4.7.14 The height loss margins in Table 4-5 shall be adjusted for airfield elevation higher than 900 m (2 953 ft).
The tabulated allowances shall be increased by two per cent of the RA margin per 300 m (984 ft) airfield elevation.
4.7.15 Procedures involving VPAs greater than 3.5 degrees or any angle when the nominal rate of descent (Vat
for the aircraft type x´ the sine of the VPA) exceeds 5 m/sec (1 000 ft/min) are nonstandard and require the following:
4.7.16 Such procedures are normally restricted to specifically approved operators and aircraft and are associated
with appropriate aircraft and crew restrictions. They are not to be used as a means to introduce noise abatement
procedures.
15/4/11
Corr.
Chapter 4. Procedure construction 4-47
2 RNP
1 RNP
r – 1 RNP
(Used to calculate
s = length for gradient)
4.7.17 Values in the height loss table are calculated to account for aircraft using normal manual overshoot
procedures from OCA/H on the nominal approach path. Values in the table may be adjusted for specific aircraft types
where adequate flight and theoretical evidence is available, i.e., the height loss value corresponding to a probability of
1 × 10–5 (based on a missed approach rate 10–2).
4.7.18 If a height loss/altimeter margin is required for a specific Vat, the following formulas apply (see also
PANS-OPS, Volume II, Part I, Section 4, Chapter 1, Tables I-4-1-1 and I-4-1-2):
where Vat is the speed at threshold based on 1.3 times stall speed in the landing configuration at maximum certificated
landing mass.
Note.— The equations assume the aerodynamic and dynamic characteristics of the aircraft are directly
related to the speed category. Thus, the calculated height loss/altimeter margins may not realistically represent small
aircraft with Vat at maximum landing mass exceeding 165 kt.
4.7.19 Where missed approach turns are necessary, the earliest point in the turn initiation area must be located
after a distance equivalent to 150 m (492 ft) AGL relative to a 2.5 per cent gradient or specified climb gradient, if higher,
with its origin at the SOC.
_____________________
15/4/11
Corr.
Chapter 5
5.1 INTRODUCTION
The general criteria in PANS-OPS, Volume II, Part I, Section 3, Chapter 5, Published Information for Departure
Procedures; Part I, Section 4, Chapter 9, Charting/AIP; and Part III, Section 5, Publication, apply as modified in this
chapter. See PANS-OPS, Volume II, Part III, Section 5, Chapter 2, for specific aeronautical database publication
requirements. The required navigation specification for any published procedure must be included in the State AIP on
the chart or in the GEN section.
5.3.1 The chart must be identified in accordance with Annex 4, 11.6, and must include the word RNAV.
5.3.2 RNP approach charts depicting procedures that meet the RNP AR APCH navigation specification criteria
must include the term RNAV (RNP) in the identification.
Note.— The text in parentheses (in 5.3.2) does not form part of the ATC clearance.
5.4.1 RNAV-related requirements concerning equipment, operation, or navigation functionality must be charted
as a note.
“RF required”.
5-1
5-2 RNP AR Procedure Design Manual
5.4.2 For RNP AR APCH procedures, the following specific notes may be required:
a) a note must be published on the chart that includes the specific authorization requirement; and
b) for RNP AR APCH procedures with missed approach RNP less than 1.0, the following note is
required: “Transition to missed approach RNP for lateral guidance must not be initiated prior to the
along-track position of DA/H”.
5.5 DEPICTION
RF legs
5.5.1 Any RF requirement must be charted. The RF requirement note may be charted with the applicable leg, or
as a specific note with reference to the applicable leg. If RF is a common requirement within a given chart, then a
general note should be used as indicated in 5.4.
5.5.2 Different required RNP levels on different initial segment legs must be charted with a note. The required
note may be charted with the applicable leg or as a procedure note with reference to the applicable leg. If the same RNP
value applies to all initial and intermediate segments, then a general note should be used as indicated in 5.4.
5.6 MINIMA
5.6.1 OCA/H is published an approach charts for all RNP AR APCH procedures with one exception: for RNP AR
APCH procedures involving a MAS with RNP values less than RNP 1.0, a DA/H shall be published. An example of
minima depiction is provided in PANS-OPS, Volume II, Part 1, Section 4, Chapter 9.
5.6.2 An OCA/H or DA/H for RNP 0.3 must be published for each RNP AR approach procedure. Additional
OCA/H or DA/H for values between RNP 0.1 and 0.3 may be published as applicable.
_____________________
Appendix 1
The minimum obstacle clearance (MOC) for the VEB is derived by combining three known standard deviation variations
by the root sum square method (RSS) and multiplying by four-thirds to determine a combined four-standard deviation
(4σ) value. Bias errors are then added to determine the total MOC.
MOC: 75 m when the approach surfaces are not penetrated (see Annex 14, Vol. I, Chapter 4)
90 m when the approach surfaces are penetrated (see Annex 14, Vol. I, Chapter 4)
The sources of variation included in the MOC for the VEB are:
a
n
p
e
w
p
r
f
t
e
a
s
e
v
a
e
a
t
i
s
2
= − + + + + + +
2
.
8
8
7
1
0
6
.
5
1
0
1
5
e
l
e
v
e
l
e
v
2
7
− −
The ase: =− ⋅ ⋅( ) + ⋅ ⋅( )+
⎛ elev − LTPelev ⎞
The vae: vae = ⎜ ⎡ tan ( VPA ) − tan ( VPA − 0.01° ) ⎤⎦
⎜ tan ( VPA ) ⎟⎟ ⎣
⎝ ⎠
APP 1-1
APP 1-2 RNP AR Procedure Design Manual
I
S 6
A 5
e
l
eI
vS
L
T0
Pe.
i
s
a
d
( )⋅Δ
l
e
v0
−
2
8
8
5
.
0
0
e
l
e
v
The isad: =
+Δ − ⋅ ⋅
SAMPLE CALCULATIONS
Design variables
Automatic terminal information service (atis) three-standard deviation altimeter setting vertical error is
assumed to 6 m: (atis = 6)
Calculations
4 3
M
O
C
b
g
i
s
a
d
a
n
p
e
w
p
r
f
t
e
a
s
e
v
a
e
a
t
i
s
2
= − + + + + + +
a
s
e
2
.
8
8
7
1
0
6
.
5
1
0
1
5
e
l
e
v
e
l
e
v
2
7
3
− −
The ase: =− ⋅ ⋅( ) + ⋅ ⋅( )+
a
s
e7
2
.
8
8
7
1
0
6
.
5 1
1 3
0
1
5
L 3
T 6
Pe 0
7 2
5
L 0
T
P 7
7 1
5 5
2 6
7
3 3
− −
=− ⋅ ⋅( ) + ⋅ ⋅( )+
l
e
v 7
e 5
l
e
v
+ +
5
2
.
8
8
7
1
0
.
5
0
5
6
7
− −
=− ⋅ ⋅( + ) + ⋅ ⋅( + )+
1
7
.
7
7
2
9
=
a
s
eF
2
.
8
8
7
1
0
6
.
5
1
0
1
5 1
F
A
P
F 1
A 4
P 0
2
7
3
− −
=− ⋅ ⋅( ) + ⋅ ⋅( )+
A
P
2
.
8
8
7
1
0
6
.
5
1
0
5
1
4
0
0
0
2
7
3
− −
=− ⋅ ⋅( ) + ⋅ ⋅( )+
2
3
.
5
3
4
1
⎛ elev − LTPelev ⎞
⎜ tan ( VPA ) ⎟⎟ [ tan(VPA) − tan(VPA − 0.01°)]
The vae: vae = ⎜
⎝ ⎠
⎛ 75 ⎞
⎜ tan ( VPA ) ⎟⎟ [ tan(VPA) − tan(VPA − 0.01°)]
vae75 = ⎜
⎝ ⎠
⎛ 75 ⎞
=⎜ ⎟ [ tan3° − tan(3° − 0.01°)]
⎝ tan3° ⎠
= .2505
⎛ FAP − LTPelev ⎞
⎜ tan ( VPA ) ⎟⎟ [ tan(VPA) − tan(VPA − 0.01°)]
vaeFAP = ⎜
⎝ ⎠
⎛ 1400 − 360 ⎞
=⎜ ⎟ [ tan 3° − tan(3° − 0.01°)]
⎝ tan 3° ⎠
= 3.4730
75 ⋅ ( ΔISA )
isad75 =
288 + ΔISA − 0.5 ⋅ 0.0065 ⋅ (LTPelev + 75 )
75 ⋅ ( −20 )
=
288 − 20 − 0.5 ⋅ 0.0065 ⋅ ( 360 + 75 )
= −5.6267
isadFAP =
( elev − LTPelev ) ⋅ ( ΔISA )
288 + ΔISA − 0.5 ⋅ 0.0065 ⋅ (FAP )
=
(1400 − 360 ) ⋅ ( −20 )
288 − 20 − 0.5 ⋅ 0.0065 ⋅ (1400 )
= −78.9524
APP 1-4 RNP AR Procedure Design Manual
4
MOC75 = bg − isad75 + anpe2 + wpr 2 + fte2 + ase76 2 + vae76 2 + atis2
3
4
= 12.6307 + 5.6267 + 16.64572 + 0.94332 + 232 + 17.77292 + 0.25052 + 6 2
3
= 63.3777
4
MOCfap = bg − isadfap + anpe2 + wpr 2 + fte2 + asefap 2 + vae fap 2 + atis2
3
4
= 12.6307 + 78.9524 + 16.6457 2 + 0.94332 + 232 + 23.53412 + 3.47302 + 62
3
= 141.3599
The OAS gradient is calculated by taking the difference in heights of the OAS surface at MOCfap and MOC75:
OASgradient =
( fap − ltpelev − MOCFAP ) − ( 75 − MOC75 )
FAP − LTPelev − 75
tan ( VPA )
The OAS origin is calculated by taking the distance from LTP of the 75-m point of the VPA and subtracting the distance
from the MOC75 point.
⎛ 75 − RDH ⎞ ⎛ 75 − MOC75 ⎞
OASorigin = ⎜ −
⎜ tan ( VPA ) ⎟⎟ ⎜⎝ OASgradient ⎟⎠
⎝ ⎠
OASgradient =
(1400 − 360 − 14.3599 ) − ( 75 − 63.3777 )
1400 − 360 − 75
tan 3°
= 0.0481726 (4.817%)
⎛ 75 − 17 ⎞ ⎛ 75 − 63.3777 ⎞
OASorigin = ⎜ ⎟−⎜ ⎟
⎝ tan 3° ⎠ ⎝ 0.0481726 ⎠
= 865.4422
_____________________
Appendix 2
The required minimum obstacle clearance (MOC) for the VEB is derived by combining known three standard deviation
variations by the RSS method and multiplying by four-thirds to determine a combined four standard deviation (4σ) value.
Bias errors are then added to determine the total MOC.
MOC: 250 ft when the approach surfaces are not penetrated (see Annex 14, Vol. I, Chapter 4)
300 ft when the approach surfaces are penetrated (see Annex 14, Vol. I, Chapter 4)
The sources of variation included in the MOC for the VEB are:
a
n
p
e
w
p
r
f
t
e
a
s
e
v
a
e
a
t
i
s
2
= − + + + + + +
t
a
n
V
P
A
.
The anpe: = ⋅ ⋅ ⋅
w
p
r
6
0
t
a
n
V
P
A
The wpr: = ⋅
8
.
8
1
0
6
.
5
1
0
5
0
e
l
e
v
e
l
e
v
2
8
− −
The ase: =− ⋅ ⋅( ) + ⋅ ⋅( )+
⎛ elev − LTPelev ⎞
The vae: vae = ⎜
tan θ ⎟ [ tan θ − tan( θ − 0.01°)]
⎝ ⎠
S 1
I
A 8
e
l
e
v
L
T
P
i
s
a
d
( )⋅Δ
e
l
e0
v
−
2
8
8
I
S
A
0
.
5
.
0
0
9
e
l
e
v
The isad: =
+Δ − ⋅ ⋅
SAMPLE CALCULATIONS
Design variables
Automatic terminal information service (atis) two standard deviation altimeter setting vertical error is
assumed to be 20 ft: (atis = 20)
Calculations
4 3
M
O
C
b
g
i
s
a
d
a
n
p
e
w
p
r
f
t
e
a
s
e
v
a
e
a
t
i
s
2
= − + + + + + +
1 0
8 3
5 0
2 4
a
n
p
e
1
.
2
2
5
r
n
p
t
a
n
V
P
A
.1 0
85
The anpe: = ⋅ ⋅ ⋅
8 3
2 4
1
.
2 4
2 .
5 6
0
.
1
4
t
a
n
3
.
0
8
= ⋅ ⋅ ⋅ °
5
1
1
7
=
w
p
r
6
0
t
a
n
V
P
A
The wpr: = ⋅
6
0
t
a
n
3
= ⋅ °
3
.
1
4
4
5
15/4/11
Corr.
Appendix 2. VEB MOC equation explanation (non-SI units) APP 2-3
a
s
e
8
.
8
1
0
6
.
5
1
0
5
0
e
l
e
v
e
l
e
v
2
8
3
− −
The ase: =− ⋅ ⋅( ) + ⋅ ⋅( )+
a
s
e2
8
.
8
1
0
6
.
5
1
0
5
0
L 1
T 2
Pe 0
2 5
5 0
0 2
L 2
T 0
Pe 0
2 0
5
0 5
2
8
3
− −
=− ⋅ ⋅( ) + ⋅ ⋅( )+
l
e
v
l
e 2
v
+ +
5
0
8
.
8
1
0
6
.
5
1
0
0
0
2
5
8
3
− −
=− ⋅ ⋅( + ) + ⋅ ⋅( + )+
5
9
.
2
4
0
0
a =
s
eF
8
.
8
1
0
6
.
5
1
0
5
0 5
F
A
P
F 4
A 5
P 0
2
8
3
− −
=− ⋅ ⋅( ) + ⋅ ⋅( )+
A
P
8
.
8
1
0
6
.
5
1
0
0
4
5
0
0
0
2
8
3
− −
=− 7
7 ⋅ ⋅( ) + ⋅ ⋅( )+
.
4
6
8
0
=
e
l
e t
v a
L V
T P
Pe A
v
a
e
t
a
n
V
P
A
t
a
n
V
P
A
0
.
0
1
l
e
v
⎛ − ⎞
⎟[ ° )]
n
The vae: =⎜ − ( −
⎝ ⎠
F
A
P
L
T
P
v
a
eF
t
a
n
V
P
A
t
a
n
V
P
A
0
.
0
1
e
l
e
v
−
= ⎛⎜ ⎞
⎟[ ° )]
t
a
n
V
P
A
− ( −
A
P
⎝ ⎠
4
5
0 t
0 a
1 3
2
0
0
t
a
n
3
t
a
n
3
0
.
0
1
−
= ⎜⎛ ⎞
⎟[ ° )]
n
°− ( °−
⎝ ° ⎠
1
1
.
0
2
0
0
=
2 n 5 n4
5 V 0 39
0 P
v
a
e2
t
a
n
V
P
A
t
a
n
V
P
A
0
.
0
1
= ⎜⎛ ⎞
⎟[ ° )]
t
a 2 t
A t
− ( −
5
0
⎝ ⎠
a
n
3
t
a
n
3
0
.
0
1
= ⎜⎛ ⎞
⎟[ ° )]
a3
°− ( °−
⎝ °⎠
.
8
=
S 1
I
A 8
e
l
e
v
L
T
P
i
s
a
d
( )⋅Δ
e
l
e
v
−
2
8
8
I
S
A
0
.
5
0
.
0
0
9
e
l
e
v
The isad: =
+Δ − ⋅ ⋅
isadFAP =
(FAP − LTPelev ) ⋅ ΔISA
288 + ΔISA − 0.5 ⋅ 0.00198 ⋅ (FAP )
=
( 4500 − 1200 ) ⋅ ( −20 )
288 − 20 − 0.5 ⋅ 0.00198 ⋅ ( 4500 )
= −250.432
250 ⋅ ΔISA
isad250 =
288 + ΔISA − 0.5 ⋅ 0.00198 ⋅ (LTPelev + 250 )
250 ⋅ ( −20 )
=
288 − 20 − 0.5 ⋅ 0.00198 ⋅ (1200 + 250 )
= −18.7572
15/4/11
Corr.
APP 2-4 RNP AR Procedure Design Manual
4
MOC250 = bg − isad250 + anpe2 + wpr 2 + fte2 + ase250 2 + vae250 2 + atis2
3
4
= 40.7902 + 18.7572 + 54.61172 + 3.14452 + 752 + 59.24002 + 0.83492 + 202
3
= 208.782
4
MOCFAP = bg − isadFAP + anpe2 + wpr 2 + fte2 + aseFAP 2 + vaeFAP 2 + atis2
3
4
= 40.7902 + 250.432 + 54.61172 + 31445
. 2
+ 752 + 77.46802 + 11.0202 + 202
3
= 455.282
The OAS gradient is calculated by taking the difference in heights of the OAS surface at MOCfap and MOC250:
OAS gradient =
( fap − ltpelev − MOCFAP ) − ( 250 − MOC250 )
FAP − LTPelev − 250
tan VPA
=
( 4500 − 1200 − 455.282 ) − ( 250 − 208.782 )
4500 − 1200 − 250
tan ( 3 )
= 0.04817 (4.817%)
The OAS origin is calculated by taking the distance from the LTP of the 250-ft point of the VPA and subtracting the
distance from the MOC250 point.
= 2865.179
— END —