Lecture 1 - Introduction to Project Management
Lecture 1 - Introduction to Project Management
Management
Project?
EXAMPLES:
Delivery of requirements spec;
Delivery of alpha tested code.
Work Breakdown
For each work package & task, it is usual to document:
1. Brief description;
2. Earliest start date;
3. Earliest end date;
4. Total person months effort;
5. Pre-requisite WPs or tasks;
6. Dependent WPs or tasks;
7. Who is responsible.
Critical paths
The pre-requisites and dependencies of WPs and tasks determine
a critical path: the sequence of dependencies in the project.
The critical path is the sequence of activities that takes the longest
time to complete.
Any delay to an activity in the critical path will cause delays to the
overall project.
Delays to activities not on the critical path need not necessarily
cause overall delays.
Risks
When planning a project, it is critically important to know what the
key risks are, and is possible plan for them:
http://www.microsoft.com/en-us/evalcenter/evaluate-project-
professional-2013
Class After Next!
https://basecamp.com/