MAINTENANCE GUIDE FOR FENDERING SYSTEM Super Cone Fenders with Frontal Frames & ANP Fenders.
1|Page
Trelleborg Marine Systems India Pvt Ltd 801, 8th Floor, Parshwanath E-Square, Corporate Road, Opp. Prahladnagar Garden, Satellite, Ahmedabad, Gujarat - 380015, India. Website: www.trelleborg.com/marine
page 3 page 3
Chain System Inspection procedure Rubber Element Inspection procedure Inspection Schedule
2|Page
Trelleborg Marine Systems India Pvt Ltd 801, 8th Floor, Parshwanath E-Square, Corporate Road, Opp. Prahladnagar Garden, Satellite, Ahmedabad, Gujarat - 380015, India. Website: www.trelleborg.com/marine
Introduction
The following procedures and inspection schedules are provided as a guide only. Inspection intervals and subsequent repair procedures vary & greatly dependent on : Local Climate. System type and frequency of usage. Type resources and equipment. Local resources and equipment. Owner philosophy to acceptable system life cycle. Initial system design.
The following recommendations are focused on providing the maximum life cycle for the system installed. Inspection intervals should be adjusted to suit local conditions and feedback from maintenance personnel.
4 5
Inspect the areas surrounding the bolt head for wear. Check the tightness of ten facia pad fasteners in various locations on the frontal frame.
Notes : Damage paintwork should be treated in accordance with the paint manufacturers instructions.
3|Page
Trelleborg Marine Systems India Pvt Ltd 801, 8th Floor, Parshwanath E-Square, Corporate Road, Opp. Prahladnagar Garden, Satellite, Ahmedabad, Gujarat - 380015, India. Website: www.trelleborg.com/marine
12 13
Check for missing shackle locking nuts or split pins. Check threads on all shackles pins for rust or physical damage. Check all shackles for wear or corrosion. Inspect chain tensioning devices, if fitted, for corrosion or wear. Check to ensure all chains are firmly tensioned.
14 15 16
17
TABLE A
Original chain diameter Minimum chain diameter 22 16 24 17 26 19 28 20 30 22 32 23 34 24 36 25 38 26 40 28 42 30 46 32 48 34 50 35
4|Page
Trelleborg Marine Systems India Pvt Ltd 801, 8th Floor, Parshwanath E-Square, Corporate Road, Opp. Prahladnagar Garden, Satellite, Ahmedabad, Gujarat - 380015, India. Website: www.trelleborg.com/marine
If corrosion is apparent remove corrosion from bolt and treat with rust inhibitor or replace bolt. Ensure that a non soluble vegetable grease is applied to the bolt and the ferrule before refitting. If unacceptable deterioration is apparent on one bolt sequentially remove, inspect and treat remaining bolts.
22 23
Remove one fender to frontal frame attachment bolt. Ensure that the fender is sitting symmetrically on the face of the wharf.
See above. If not symmetrical the weight and tension chains will require adjustment.
5|Page
Trelleborg Marine Systems India Pvt Ltd 801, 8th Floor, Parshwanath E-Square, Corporate Road, Opp. Prahladnagar Garden, Satellite, Ahmedabad, Gujarat - 380015, India. Website: www.trelleborg.com/marine
INSPECTION SCHEDULE
INTERVALS 6 MONTHS 12 MONTHS
ITEM No. Frontal Frame Facing Panels 1 2 3 4 5 Paint and Steel Work 6 7 8 9 10 Chain Systems& Components 11 12 13 14 15 16 17 Rubber Element 18 29 20 21 22 23
3MONTHS
6|Page
Trelleborg Marine Systems India Pvt Ltd 801, 8th Floor, Parshwanath E-Square, Corporate Road, Opp. Prahladnagar Garden, Satellite, Ahmedabad, Gujarat - 380015, India. Website: www.trelleborg.com/marine