SPM lecture 25 -
SPM lecture 25 -
Project Tracking and Control and Earned Value Analysis (EVA) are crucial
concepts in project management used to ensure that a project is on track, within
scope, and meeting its objectives.
For example:
This requires:
Planned Value (PV): The value of the work that was planned to be completed
by a specific time. It represents the budgeted amount for the work that was
scheduled to be done up to a certain point in the project.
Earned Value (EV): The value of the work actually completed by a specific
time. It reflects the value of the work that has been completed in terms of the
original budget and scope.
Actual Cost (AC): The actual cost incurred for the work completed by a
specific time. This includes all expenses incurred for the work performed.
Cost Variance (CV): Measures the difference between the earned value (EV)
and the actual cost (AC). It tells whether the project is under or over budget.
CV=EV−AC
SV=EV−PV
3|Page
CPI=EV/AC
SPI=EV/PV
Estimate at Completion (EAC): The expected total cost of the project based
on the current performance. It can be calculated in several ways, with the
simplest being:
EAC=BAC/CPI
ETC=EAC−AC
Planned Value (PV): $100,000 (this is the value of the work planned to be
completed by a certain time)
Earned Value (EV): $90,000 (this is the value of the work actually completed
by that time)
Actual Cost (AC): $95,000 (this is the cost incurred for the work completed)
In conclusion, Project Tracking and Control and Earned Value Analysis (EVA)
are vital for managing project performance, ensuring that any issues are identified
early and that resources are used efficiently to meet the project’s goals.