Investment Appraisal: Important Formulas For The PMP® Exam
Investment Appraisal: Important Formulas For The PMP® Exam
Investment Appraisal: Important Formulas For The PMP® Exam
Investment Appraisal
Payback Period: Payback Period is achieved when the cumulative cash flow becomes equal to the initial investment. Shorter the payback period, better the project. Net Present Value (NPV) NPV = Initial Investment less cumulative PV of all cash flows for n years n Present Value (PV) = FV / (1 + r) r = discount rate n = valuation period in years FV = Future Value A higher NPV is better. Higher the Discount rate, lower the NPV IRR The discount rate at which NPV is zero Benefit Cost Ratio (BCR) BCR < 1 : reject project BCR > 1: accept the project PERT / SD. (PERT can be used for both Time and Cost dimensions) Formula PERT Duration Activity Variance 2 Activity Standard Deviation SD () PERT (BETA Distribution) O + 4(ML) + P 6 {(P O) /6}2 (Standard Deviation squared) (P O) / 6 Triangular Distribution O + ML + P 3 ((P - O)2 + (ML O)*(ML P))/18
Note: Default for PERT calculations is the BETA distribution formulas Confidence levels (Mean n ) 1 Sigma () 2 3 6
To find range of estimate for Individual Activities: PERT duration for the activity SD To find range of estimate at Project Level: Step 1: Add all the PERT durations in the critical path. Step 2: Calculate the Variance for each activity in the critical path. Step 3: Add all the Variances. Step 4: Take square root of the sum of all the Variances which gives the SD. Step 5: Project duration range estimate is total project PERT duration (step 1) SD (step 4). Page 1
Earned Value Formulas SV = EV-PV CV = EV-AC SPI = EV/PV CPI = EV/AC Forecasting EAC EAC = BAC/ CPI cumulative EAC = AC + (BAC-EV) CPI new EAC = AC + (BAC-EV) EAC = AC + ETC new TCPI = BAC-EV BAC-AC
- To forecast EAC when ETC will be performed at the cumulative CPI - To forecast EAC when a different / assumed CPI will be used for ETC - To forecast EAC when ETC will be performed as per the original budget (BAC) - To forecast EAC when totally new estimates are developed for ETC
Earned Value Acronyms & formulas Acronym PV EV AC BAC SV Term Planned Value Earned Value Actual Cost Budget At Completion Schedule Variance Definition Planned cost or value of the work to be done till this point in time. The value of the work accomplished till this point in time. Cost is as per the original budget. The costs actually incurred to complete the work till this point in time. The total planned value or budget for completing the entire project. Difference between the scheduled completion and actual completion of an activity or group of activities. Negative SV - is behind schedule. Positive SV- is ahead of schedule. Difference between the budgeted cost of completing an activity/group of activities and the actual budget spent for it. Negative CV: is over budget. Positive CV - is under budget. The measure of efficiency in managing the projects schedule. SPI > 1 is good (ahead of schedule) = 1 on target < 1 poor (behind schedule) The measure of efficiency in managing the projects budget. CPI > 1 is good (under budget) = 1 is on target <1 is poor (over budget) Prediction of what project will cost when completed. EAC is calculated using different formulas for different possible conditions. How much more we expect project to cost from this point in time. How much under budget or over budget we expect the project to be once it is completed. The remaining cost performance needed in project to stay within the planned budget (BAC).
CV
Cost Variance
SPI
CPI
Page 2
Some Contractual Terms Arbitration Breach of contract Contract Condition Design specifications Force Majeure Settling a dispute out of court using an independent third party. The arbitrator must be agreed upon and accepted by both parties. Violating or breaking of a legal obligation. Is a serious condition. Buyer should always issue letter to contractor notifying the breach. A written or oral agreement made by one party to another that has legal obligations on both parties. A term of fundamental importance in the contract. Breach of this condition can cause the contract to be terminated. A detailed description of the physical characteristics describing and specifying what is to be done. Used in contracts to free both parties from liabilities arising from events beyond their control e. g. strikes, war, floods, earthquake etc. Common response is for buyer to extend the time. Transparency and fair dealing between all parties. Violation of a legally recognized right. A payment or compensation as protection against any future loss. It is an obligation made by one party to reimburse another party for losses that have occurred or that may occur in future. Reasonable damages to be paid by the contractor to the owner due to failure to complete the specified work as per the contract terms. Not acting in a reasonably accepted manner. The contractor is not allowed to work for a competitor for a given time. A restriction on the contractor from disclosing some proprietary knowledge gained in doing the work. An agreement made in financial terms to be paid by the contractor for not performing as per the contract terms. The measurable capabilities that the product should achieve in terms of operational characteristics. They must be met by the contractor. A mutual relationship that exists between a buyer and seller. The contract cannot give rights or impose obligation on any person / party / sub-contractor except the parties that have signed the contract. A process used to determine if a contractor has the minimum qualifications to bid. The seller is the only available source for the procurement. Giving up of a legal right or privilege voluntarily A written, verbal or implied promise assuring that a specified provision in the contract is true. Provides protection to the buyer against breakdowns and major repairs.
Liquidation damages Negligence Non-compete clause Non-disclosure / confidentiality clause Penalty clause Performance specifications Privity of contract
Page 3
Types of Estimates Rough Order of Magnitude (ROM) estimate - Initiating phase: +/- 50% Budget Estimate - early Planning phase: -15% to +25% Definitive or detailed estimate - Planning phase: +10% to -10% Communication channels Communication channels between people = {n(n-1) } / 2 n = total number of persons Procurement Fixed Price Incentive Fee (FPIF) contract Point of Total Assumption (PTA): The point at which additional cost overruns have to be fully borne by contractor. Costs above PTA are assumed to be the result of mismanagement. PTA is only applicable in FPIF contracts. PTA = { (Ceiling price - Target price) /Buyers share ratio} + Target cost Price: The amount charged to buyer by seller (contractor) Target cost: Expected cost for doing the work at time of signing the contract Target fee: Sellers planned profit margin or fee for doing the work. Will be increased / decreased using the Share ration based on performance Target Price: Target cost + target fee Share ratio: Ratio by which Buyer/Seller will share cost savings and cost overruns Ceiling Price: The maximum amount the buyer will pay for the contract irrespective of the costs. Actual Cost: Costs that actually incurred at end of contract
Cost Plus Incentive Fee (CPIF) contract: CPIF includes all of the above terms except Ceiling Price and Point of Total Assumption (PTA) . Instead CPIF has a Minimum fee and a Maximum fee: Minimum Fee: Minimum assured fee buyer will pay to contractor Maximum Fee: Maximum fee that buyer will pay to contractor
Quality the degree to which a set of inherent characteristics fulfils (project) requirements Quality Tools Pareto Chart - 80/20 rule. Is a histogram ranking no. of defects in order of frequency or importance - 80% quality problems due to 20% causes
Page 4
Control chart - Used to decide whether the product or service is in control or out of control - Identifies special or assignable causes - Has a mean or center line, an upper control limit (UCL) and a lower control limit (LCL) - Does not show causes for deviation or provide solutions Cause-and-Effect diagram (Fishbone or Ishikawa diagram) - Graphical technique that helps team to group ideas and identify the causes of a problem - Breaks down problem for analysis - Shows how different variables may be linked to the effect (problem) Sampling Attribute sampling: checks that the result either conforms or does not conform pass or fail Variable sampling: checks the degree to which the result conforms acceptable within a tolerance level
Effect of Response Remove root cause. Project management plan changed to completely remove threat e.g. extend schedule, reduce scope by removing work package or activity, remove a team member, etc. Third party made financially responsible for negative impact and ownership of response. e.g. insurance, contracts, warranties etc. Transfer does not eliminate the risk. Probability or Impact or both to acceptable threshold limits e.g. make a prototype, improve skills through training No change made in the project management plan to deal with risk or unable to select suitable response. Passive acceptance no action taken Active acceptance - Contingency reserve commonly kept time, money or resources to deal with the risk Change plans to remove uncertainty to ensure the opportunity occurs Allocate some or all ownership of opportunity to third party as they are better equipped e.g. joint ventures, teams, partnerships Increase positive Impact or Probability or both of opportunity e.g. add more resources to finish early Accept the risk if it occurs. Not actively pursued
Transfer
Mitigate
Accept
Exploit
Share
Enhance Accept
Page 5