Piping and Equipment Insulation
Piping and Equipment Insulation
Piping and Equipment Insulation
Rev 02
Location of Change
General (Any changes on future issues will be Indicated with a ?)
02
General
Reformatted to comply with current document standard format. Revised where indicated thus:
Page 2 of 22
Rev 02
1 1.2 1.4 2 2.2 3 4 4.1 4.2 4.3 4.4 4.5 4.6 4.7 4.8 4.9 4.10 4.11 4.12 4.13 4.14 5 6 6.1 6.2 6.3 7 7.1 7.2 7.3 7.4 7.5 8 8.1 9 9.1 10 10.1 11 11.1 11.2 TABLE 1 TABLE 2 TABLE 3 TABLE 4 TABLE 5 TABLE 6 TABLE 7 TABLE 8 TABLE 9
Page 3 of 22
Rev 02
1 1.1
INTRODUCTION PURPOSE This document defines the minimum technical requirements for the design, supply, storage, application and inspection of thermal and acoustic insulation of pipe work and equipment for onshore and offshore oil and gas exploration and production facilities to be operated by Sakhalin Energy Investment Company, Ltd (SEIC).
1.2
SYSTEMS EXCLUDED All HVAC and architectural services Risers and sub sea pipe work Proprietary mechanical packages Accommodation areas
1.3
DISTRIBUTION, INTENDED USE AND REGULATORY CONSIDERATIONS Unless otherwise authorised by SEIC, the distribution of this document is confined to the nominated Contractors and Suppliers.
1.4 1.4.1
DEFINITIONS General definitions The standard general definitions below shall be included if the words defined are used in the particular document: The Contractor is the party, which carries out all or part of the design, engineering, procurement, construction, commissioning or management of a project or operation/maintenance of a facility. The Principal may undertake all or part of the duties of the Contractor. The Supplier/Manufacturer is the party, which manufactures or supplies equipment and services to perform the duties specified by the Contractor. The Principal is Sakhalin Energy Investment Company, Ltd. (SEIC) - the party, which initiates the project and ultimately pays for its design and construction. The Principal will generally specify the technical requirements. The Principal may also include an agent or consultant authorised to act for, and on behalf of, the Principal. The word shall indicates a requirement. The word should indicates a recommendation.
1.4
ABBREVIATIONS ASME BS CINI ISO NDE SEIC American Society of Mechanical Engineers British Standard Stichting Isolatie Nederlandse Industrie International Organization for Standardization Non-Destructive Examination Sakhalin Energy Investment Company, Ltd.
Page 4 of 22
Rev 02
Definitions of terms relating to thermal insulating materials Stainless and heat-resisting chromium steel plate, sheet and strip Test for density of preformed pipe-covering type thermal insulation Test for density of preformed block type thermal insulation Sampling and acceptance of preformed thermal insulation Mineral fibre preformed pipe insulation Mineral fibre blanket insulation and blanket type pipe insulation Mineral fibre block and board thermal insulation Surface burning characteristics Insulation for industries Acoustics; materials for acoustical applications; determinations of airflow resistance
ASTM C168 ASTM C176 ASTM C302 ASTM C303 ASTM C390 ASTM C547 ASTM C592 ASTM C612 ASTM E84 CINI ISO 9053
Standards equivalent to those listed above may be substituted upon specific approval by the Principal. Approval of equivalent standards shall not relieve the Supplier or Contractor from compliance with specific codes and standards applicable to materials offered. 2.2 ORDER OF PRECEDENCE The order of precedence shall be as follows: Material requisition (where applicable) Data sheets This specification SEIC specifications referenced herein Industry codes and standards referenced herein.
In case of any conflict between specifications, data sheets, enquiry documents, scope of work or drawings, or any lack of clear definition as to the applicability of any specification or standard, Supplier shall obtain a written clarification from Purchaser. Purchaser 's approval of Supplier's drawings/specifications in no case absolves Supplier for deviations contained therein, unless such deviations are clearly brought to Purchaser 's attention, and Purchaser s written approval is received. In case of conflict between the English and Russian versions of this specification, the English version shall take precedence. 3 3.1 SCOPE OF WORK The Project facilities design shall include piping and equipment drawings together with the line list, equipment list and other documents deemed necessary to enable the Contractor to measure, plan, organise and install the required insulation. Pipe work and equipment shall be insulated where stated on the line list and isometric for pipe work, and on the equipment data sheet for equipment. Operating temperatures shall be used as the basis for the selection of insulation thickness, as defined on the line lists, or equipment data sheets. Temperature used for the selection of materials shall be the design temperature. This Specification shall not be applied to compressors, pumps and other rotating equipment, including exhausts for turbines. The Contractor shall supply, store and install the insulation in accordance with this specification and the specifications/standards referred within.
3.2 3.3
3.4 3.5
Page 5 of 22
Rev 02
3.9
4 4.1 4.1.1
MINERAL WOOL Rigid mineral wool pre formed sections and slabs, having a minimum density 125 kg/m 3 3 (Density range 125 150 kg/m ) For acoustic insulation, only flexible or semi-rigid mineral wool complying with the requirements of Section 11.0 shall be used. CELLULAR GLASS Rigid pre-formed cellular glass shall have a minimum density of 120 kg/m 3, compressive strength of 7 kg/cm and nil vapour permeability. To be a minimum of two coat system. FLEXIBLE ELASTOMERIC FOAM Pre-formed pipe sections shall have a minimum density of 50 kg/m 3 , be closed cell and have nil vapour permeability. To be applied in a single layer
Page 6 of 22
Rev 02
4.5.4 4.5.5
Page 7 of 22
Rev 02
CLASSIFICATION AND DESIGNATION INSULATION SELECTION The classification and thickness shall be shown on isometrics, line lists P&IDs etc., where applicable. On P&IDs the basic classification shall be added to the line definition number. Example: 8 PL 12135 11490 H, where H denoted Class H heat conversion
Page 8 of 22
Rev 02
DESIGNATION OF SYSTEMS Class H Heat conservation For lines 2 and below, operating from 0C to 115C, select system 6, thickness to table 9. For all other applications select system 1, thickness to Table 2 for Offshore or Table 3 for Onshore.
6.3.2
Class PP/PG Personnel Protection Personnel protection is to be provided for piping (including flanges and valves) and equipment that is operating at temperatures in excess of 65 deg C, and is within 2m vertically and 1 metre horizontally of the deck, platform, ladders, or normal path of travel by personnel. For protection from hot surfaces operating above 65 deg C, use guards as System 2, set at a distance of 75 mm from the surface. For protection from hot surfaces operating above 205 deg C, which are hazardous areas, and, in places where guards are impractical, use System 1 with thickness as in table 5.
6.3.3
Class EP Electrical tracing on Process lines. For lines 2 and below, operating from 0C to 115C, select system 6, thickness to table 9.For all other applications select system 3, thickness to table 2 for Offshore or table 3 for Onshore.
6.3.4
Class EW Winterisation plus electric tracing For lines 2 and below, maintaining a temperature above 0C, select system 6, thickness to table 9.For lines 3 and above select system 3, thickness to table 2 for Offshore or table 3 for Onshore. Note The isometric will show the extent of the insulation for classes EP and EW.
6.3.5
Class A Acoustic Insulation This class has three levels of noise protection that are defined in section 11.0 Class A = AA Class B = AB Class C = AC System 4 to be used in accordance with section 11.0
Page 9 of 22
Rev 02
7.1.4
7.1.5 7.1.6
7.1.7 7.1.8
7.1.9 7.1.10
Page 10 of 22
Rev 02
7.1.14 7.2 7.2.1 7.2.2 7.2.3 7.2.4 7.2.5 7.3 7.3.1 7.3.2
Page 11 of 22
Rev 02
11 11.1 11.1.1
11.2 11.2.1
11.2.2
11.2.3
Page 12 of 22
Rev 02
11.2.6
11.2.7
11.2.8
11.2.9
11.2.10 Resilient elements shall not be loaded to such an extent that their operational range of deflections is exceeded. 11.2.11 For Class C insulation, there shall be vibration isolation between the pipe support and the base in order to achieve the specified acoustic performance. The vibration isolating materials shall be selected for the required mechanical properties as well as the acoustic properties.
Page 13 of 22
Rev 02
TABLE 1 WINTERISATION
The thicknesses stated are insulation only and exclude any finishing material In accordance with BS 5422
Page 14 of 22
Rev 02
TABLE 2 INSULATION THICKNESS - FOR HEAT CONSERVATION OFFSHORE INCLUDING ELECTRICALLY TRACED PIPING AND EQUIPMENT FOR USE ON OFFSHORE FACILITIES ONLY. ECONOMIC THICKNESS OF MINERAL FIBRE (mm)
50 & BELOW 25 25 25 25 25 30 30 30 30 30 30 50 50 50 50 50 50
201 250
251 - 300
25 25 30 30 30 30 30 40 40 40 40 50 50 50 50 80 80
30 30 30 30 30 30 40 50 50 60 60 60 60 70 70 100 100
30 30 30 30 40 40 50 50 60 70 70 70 70 70 80 110 110
30 30 30 40 40 50 50 60 70 80 80 80 80 90 90 130 130
Page 15 of 22
Rev 02
TABLE 3 - INSULATION THICKNESS - FOR HEAT CONSERVATION ONSHORE INCL. ELECTRICALLY TRACED PIPING AND EQUIPMENT FOR USE ON SAKHALIN II PROJECT ONSHORE PROCESSING FACILITY
100
40 40 40 40 50 50 50 60 60 60 90
150 40 40 40 50 60 60 70 70 80 80 110
200 40 50 50 60 60 70 80 80 80 90 120
Insulation material mineral wool pipe sections and slab, weather covering is mastic. Thicknesses greater than 50mm are to be applied in multiple layers. For temperatures outside the range given use the next highest temperature to determine the required insulation thickness.
Page 16 of 22
Rev 02
Number of Layers
1 1 1 1 2 2 2 2 2 3 3
30 30 40 40 50 40 50
40 50
25 30 40 50 30 40 40 40 50 40 50
Page 17 of 22
Rev 02
Notes: 1. Insulation only to be applied on lines/equipment, which are in hazardous areas, operating within this
temperature range.
Page 18 of 22
Rev 02
40 50 50 50 50 60 60 60 60 60 60 60 60 60 60
50 50 50 60 60 70 70 70 70 70 70 80 80 80 90
80 80 80 100 100 100 110 110 120 120 120 120 130 130 150
Page 19 of 22
Rev 02
-20
38 38 50 50 50 50 50 65 65 65 65
-40 50 50 65 65 65 65 80 80 80 90 115
Insulation material cellular glass pipe sections and slabs. Thicknesses greater than 40mm are to be applied in multiple layers. For temperatures outside the range given use the next highest temperature to determine the required insulation thickness.
Page 20 of 22
Rev 02
-20
25 25 40 40 40 40 40 50 50 50 50
-40 40 40 50 50 50 50 65 65 65 65 75
-60 40 50 65 65 65 65 75 75 90 90 90
Notes: 1) 2) 3) Insulation material wool pipe sections and slab, weather covering is mastic. Thicknesses greater than 40mm are to be applied in multiple layers. For temperatures outside the range given use the next highest temperature to determine the required insulation thickness.
Page 21 of 22
Rev 02
0 50 25 25 25 25 25
51 100 25 25 30 30 30
101 - 115 30 30 30 30 30
1 1 2
Page 22 of 22