06 PPC
06 PPC
06 PPC
Introduction
Production
planning and control (PPC) is concerned with the logistics problems that are encountered in manufacturing, that is, managing the details of what and how many products to produce and when, and obtaining the raw materials, parts, and resources to produce those products.
Introduction...
PPC
solves these logistics problems by managing information are essential for processing the tremendous amounts of data involved to define the products and the manufacturing resources to produce them
Computers
Introduction...
Planning
and control in PPC must themselves be integrated functions It is insufficient to plan production if there is no control of factory resources to achieve the plan It is ineffective to control production if there is no plan with which to compare factory progress Both planning and control must be accomplished, and they must be coordinated with each other and with other functions in the manufacturing firm
6
Production Planning
Consists of
1. Deciding which products to make, in what quantities, and when they should be completed; 2. Scheduling the delivery of the parts and products; and 3. Planning the manpower and equipment resources needed to accomplish the production plan.
7
Production Planning
Aggregate planning (1 & 2) involves planning six months or more into the future, whereas detailed planning (3 & 4) is concerned with the shorter term (weeks to months)
8
Production Control
It consists of determining whether the necessary resources to implement the production plan have been provided If not, take corrective actions to address the deficiencies
It includes various systems and techniques for controlling production and inventory in the factory; including
Shop floor control Inventory control Manufacturing execution systems (MES) Manufacturing resource planning Enterprise resource planning
9
Establish a company wide game plan for allocating resources Develop an economic strategy for meeting demand
The production quantities of the major product lines listed in the aggregate plan are converted into a very specific schedule of individual products known as master production schedule (MPS) This is a list of the products to be manufactured, when they should be completed and delivered, and in what quantities
10
11
inventory control and production planning system Calculates the demand for components items, when they are needed and lead time to make or buy them MRP translates a master schedule for end items into time-phased requirements for sub-assemblies, components and raw materials MRP plans
Purchasing activities Manufacturing activities Delivery schedules
12
Demand Characteristics
Independent Demand (Finished product) A Dependent Demand (Component parts) C(2)
B(4)
D(2)
E(1)
D(3)
F(2)
13
Work orders
Purchase orders
Rescheduling notices
14
Master production schedule Product structure file Item master file Outputs Planned order releases Work orders Purchase orders Rescheduling notices
15
Once MPS is set, MRP system accesses the product structure file to determine which component items need to be scheduled Product structure file contains a bill of material (BOM) for every item produced The BOM for a product lists
the items that go into the product, their brief description, and when and in what quantity each item is needed in the assembly process
16
Product Structure
Clipboard
Pivot (1)
Spring (1)
17
Pressboard (1)
Rivets (2)
Level 1
Pivot (1)
Spring (1)
Level 2
18
an extensive amount of information on every item that is produced, ordered, or inventoried in the system Includes data such as on-hand quantities, onorder quantities, lot sizes, safety stocks, lead times, past usage figures The item master file is updated whenever items are withdrawn from or added to the inventory or whenever order is released, revised or completed
19
MRP Matrix
22
MRP: Example
School Mate offers a number of standard products to encourage writing outside of the class room, including clipboards, lapdesks, lapboards, and pencil boxes. Rising costs and inventory level have prompted the company to install a computerized planning and control system called MRP. The MPS and bill of material modules are up and running. Sample output is shown previously. Before going live with the MRP module, School Mate has asked for a manual demonstration. Since manual calculations can be quite tedious, you are asked to prepare MRP matrices for only three items the clipboard and lapdesk, and a common component, pressboard. The MPS, inventory information, and abbreviated product structure diagram are given below: 23
MRP: Example
Master Production Schedule 1 Clipboard Lapdesk 85 0 2 95 60 3 120 0 4 100 60 5 100 0
MRP: Example
Product Structure Record
Clipboard
Level 0
Pressboard (1)
Rivets (2)
Level 1
Lapdesk
Level 0
Pressboard (2)
Trim (3)
Beanbag (1)
Glue (4 oz)
Level 1
25
MRP: Example
ITEM: CLIPBOARD LOT SIZE: L4L Gross Requirements Scheduled Receipts Projected on Hand 25 LLC: 0 LT: 1 1 85 175 2 95 PERIOD 3 120 4 100 5 100
Net Requirements
Planned Order Receipts Planned Order Releases
26
MRP: Example
ITEM: CLIPBOARD LOT SIZE: L4L Gross Requirements Scheduled Receipts Projected on Hand 25 LLC: 0 LT: 1 1 85 175 115 2 95 PERIOD 3 120 4 100 5 100
Net Requirements
Planned Order Receipts Planned Order Releases
(25 + 175) = 200 units available (200 - 85) = 115 on hand at the end of Period 1
27
MRP: Example
ITEM: CLIPBOARD LOT SIZE: L4L Gross Requirements Scheduled Receipts Projected on Hand 25 LLC: 0 LT: 1 1 85 175 115 20 2 95 PERIOD 3 120 4 100 5 100
Net Requirements
Planned Order Receipts Planned Order Releases
MRP: Example
ITEM: CLIPBOARD LOT SIZE: L4L Gross Requirements Scheduled Receipts Projected on Hand 25 LLC: 0 LT: 1 1 85 175 115 20 0 2 95 PERIOD 3 120 4 100 5 100
Net Requirements
Planned Order Receipts Planned Order Releases
0
100
100
100
20 units available (20 - 120) = -100 100 additional Clipboards are required Order must be placed in Period 2 to be received in Period 3
29
MRP: Example
ITEM: CLIPBOARD LOT SIZE: L4L Gross Requirements Scheduled Receipts Projected on Hand 25 LLC: 0 LT: 1 1 85 175 115 20 0 0 0 2 95 PERIOD 3 120 4 100 5 100
Net Requirements
Planned Order Receipts Planned Order Releases
0
100
100
100 100
100
100 100
100
100
Following the same logic Gross Requirements in Periods 4 and 5 develop Net Requirements, Planned Order Receipts, and Planned Order Releases
30
MRP: Example
ITEM: LAPDESK LOT SIZE: MULT 50 Gross Requirements Scheduled Receipts Projected on Hand 20 LLC: 0 LT: 1 1 0 2 60 PERIOD 3 0 4 60 5 0
Net Requirements
Planned Order Receipts Planned Order Releases
31
MRP: Example
ITEM: LAPDESK LOT SIZE: MULT 50 Gross Requirements Scheduled Receipts Projected on Hand 20 20 10 10 0 0 LLC: 0 LT: 1 1 0 2 60 PERIOD 3 0 4 60 5 0
Net Requirements
Planned Order Receipts Planned Order Releases
0
50
40
50 50
50
50
Following the same logic, the Lapdesk MRP matrix is completed as shown
32
MRP: Example
ITEM: CLIPBOARD LOT SIZE: L4L LLC: 0 LT: 1 1 2 100 1 50 1 2 2 PERIOD 3 4 5 Planned Order Releases ITEM: LAPDESK LLC: 0 LOT SIZE: MULT 50 LT: 1 Planned Order Releases ITEM: PRESSBOARD LLC: 0 LOT SIZE: MIN 100 LT: 1 Gross Requirements Scheduled Receipts Projected on Hand 150 Net Requirements Planned Order Receipts Planned Order Releases 100 100 PERIOD 3 4 50 PERIOD 3
33
MRP: Example
ITEM: CLIPBOARD LOT SIZE: L4L LLC: 0 LT: 1 1 2 100 PERIOD 3 4 5
Planned Order Releases ITEM: LAPDESK LLC: 0 LOT SIZE: MULT 50 LT: 1 Planned Order Releases ITEM: PRESSBOARD LLC: 1 LOT SIZE: MIN 100 LT: 1 Gross Requirements Scheduled Receipts Projected on Hand 150 Net Requirements Planned Order Receipts Planned Order Releases
x1
1 2
x1
5
x2
50
1 100
5 0
34
MRP: Example
ITEM: CLIPBOARD LOT SIZE: L4L LLC: 0 LT: 1 1 2 100 1 50 1 100 50 2 PERIOD 3 4 5 Planned Order Releases ITEM: LAPDESK LLC: 0 LOT SIZE: MULT 50 LT: 1 Planned Order Releases ITEM: PRESSBOARD LLC: 0 LOT SIZE: MIN 100 LT: 1 Gross Requirements Scheduled Receipts Projected on Hand 150 Net Requirements Planned Order Receipts Planned Order Releases 100 100 PERIOD 3 4
50 PERIOD 2 3 4 100 200 100 50 50 100 150 0 150 150 100 0 100 100
5 0 0
100
35
MRP: Example
Planned Order Report PERIOD ITEM Clipboard Lapdesk Pressboard 1 2 100 50 100 150 3 100 50 100 4 100 5
36
MRP Example 2
37
MRP ensures that material requirements are met Material is not the only resource necessary to produce goods
machines or workers are required Order of operations to be conducted Length of time each operation should take
of jobs that have already been released but have not yet been completed
39
CRP
MRP planned order releases
Routing file
Load percent =
Copy Courier is a fledgling copy center in downtown Richmond run by two college students. Currently, the equipment consists of two high-speed copiers that can be operated by one operator. If the students work alone, it is conceivable that two shifts per day can be staffed. The students each work 8 hours a day, 5 days a week. They do not take breaks during the day, but they do allow themselves 30 minutes for lunch or dinner. In addition, they service the machines for about 30 minutes at the beginning of each shift. The time required to set up for each order varies by the type of paper, use of color, number of copies, and so on. Estimates of setup time are kept with each order. Since the machines are new, their efficiency is estimated at 100 percent
42
20
30 40 50
1000
5000 10000 2000
10.6
3.4 11.2 15.3
0.10
0.12 0.14 0.10
43
50
2385.7 minutes
44
Capacity Adjustments
Short-term
adjustments
Employment levels Number of temporary workers Number of work shifts Number of labor hours Inventory stockpiling Order backlogs
46
Capacity Adjustments
Long-term
adjustments
Investing in new equipment Constructing new plants Purchasing existing plants Acquiring existing companies Closing plants
47
These phases are executed by a combination of computer and human resources The term manufacturing execution system (MES) is used to denote the computer software that supports SFC Other functions included in an MES are
Generation of process instructions Real-time inventory control Machine and tool status monitoring Labor tracking
48
Order Release
Consists of
These paper documents move with production order in the operation of a conventional factory AIDC in modern factory
1. The route sheet, which documents the process plan for the item to be produced, 2. Material requisitions to draw the necessary raw materials from inventory, 3. Job cards to report direct labor time devoted to the order and to indicate progress of the order through the factory, 4. To authorize the material handling personnel to transport parts between work centers 5. The parts list for assembly jobs
49
Order Scheduling
Assigns the production orders to the various work centers in the plant It is intended to solve two problems in production control
Allocating orders to work centers is referred to as machine loading Job sequencing involves determining the sequence in which the jobs will be processed Priorities are established among the jobs in the queue
50
Order Scheduling
Dispatching
First come first served Earliest due date Shortest processing time Least slack time (the difference between the time remaining until the due date and the process time remaining) Lowest Critical ratio (the ratio of the time remaining until the due date divided by the process time remaining)
51
Order Progress
Work order status reports: Current work center where each job is located Processing hours remaining Job is on time or behind schedule Progress reports: Used to report the performance of the shop during a certain time period Exception reports: Provides exception information such as deviations from the production schedule
52
Inventory Control
Stock
Types of inventory: Raw materials Purchased parts and supplies Work-in-process (partially completed) products (WIP)
53
Inventory Costs
1. Carrying costs Cost of holding an item in inventory Vary with the level of inventory and the length of time an item is held Carrying costs include Rent Heating, cooling, lighting Security Record keeping Depreciation Obsolescence Product deterioration, spoilage, breakage
54
Inventory Costs
2.
Ordering costs Cost of replenishing inventory Expressed as a dollar amount per order Independent of the order size Vary with the number of orders made As the order size increases, ordering costs decrease and carrying costs increase Ordering costs include Purchase orders Transportation and shipping Receiving Inspection Accounting and auditing
55
Inventory Costs
3.
Shortage costs Temporary or permanent loss of sales when demand cannot be met because of insufficient inventory Customer dissatisfaction and loss of goodwill Price discounts or rebates For internal demand, shortage can cause work stoppage or create delays Costs resulting from lost sales because demand cannot me met are difficult to determine Shortage costs have an inverse relationship to carrying costs
56
57
a fixed-order-quantity system when inventory reaches a specific level, referred to as the reorder point, a fixed amount is ordered To determine how much to order in a continuous system the economic order quantity (EOQ) model is used The function of EOQ model is to determine the optimal order quantity that will minimize total inventory costs
58
Demand rate
Reorder point, R
Time
60
Also known as fixed-time-period system Order placed for variable amount after fixed passage of time Advantage: Inventory level is not monitored at all during time intervals between orders Disadvantages: Less direct control Larger inventory levels Determine a new order quantity each time a periodic order is made
61
inventory classification system in which a small percentage of (A) items account for most of the inventory value In ABC analysis each class of inventory requires different levels of inventory control The higher the value of inventory, the tighter the control
62
5 15 % of units 70 80 % of value
Class
30 % of units 15 % of value
Class
50 60 % of units 5 10 % of value
63
1. 2. 3.
Material requirements planning, or MRP, Capacity planning, and Shop floor control
64
software system that organizes and integrates all of the data and business functions of an organization through a single, central database ERP commonly runs as a client-server system Operates on a company-wide basis, not on plantbasis like MRP Modules in an ERP system include
Production and materials management Sales and marketing What is ERP II? Finance and accounting Human resources
65
66
Engineering Faculty wants to buy a new Printer this reason Secretary gives a purchasing order by filling purchasing order forms
For
Next
slide shows how this purchasing request process flow was working before ERP systems
67
Example IE Faculty
Industrial
Engineering Faculty wants to buy a new HP Printer this reason Secretary gives a purchasing order using Online ERP systems
For
Next
slide shows the purchasing order process flow with ERP Systems
70
CONFIRMATION
FINANCIAL ACCOUNTING
CONFIRMATION
CONFIRMATION
72
Data Flow decreases the process time Fast & Online Confirmation Less Paperwork No need for folder storage Database Security Less Employee needed Easy Financial Management Better Inventory Management
73
Material Management
Better
Procurement Handling Orginized Inventory Management Easy Purchase Organization Faster Storage Location
PM
Plant Maintenance
Maintenance
Order Management Equipment and Technical Objects Coordination Preventive Maintenance Workflow Scenarios Work Clearance Management
74
The End
75