Project Management
Project Management
Project Management
An Insight into
By
JANAK V. SHELAT
1
Suppose one of you wants to build a tower. Will he not first sit down and estimate the cost to see if he has enough money to complete it? For if he lays the foundation and is not able to finish it, everyone who sees it will ridicule him"
A project is a set of related tasks that are coordinated to achieve a specific objective in a given time limits. It is one shot, time limited, goal directed, major undertaking, requiring the commitment of varied skills and resources both human and nonhuman pooled together in a temporary organisation to achieve a specific purpose. Project is a temporary endeavor undertaken to create a unique product, service or result. It is a complex effort, usually less than three years in duration, made up of interrelated tasks performed by various organizations, with a well-defined objective, schedule and budget Key words Achieve a specific objective normally unique and "novel" Time limit often other constraints too Coordinated projects typically involve many people - a team this will be assumed from now on
PROJECT CHARACTERISTICS
It has objectives. It has life span. It is single entity. It is team work. It has life cycle. Every project is unique. It is synonymous to change. It pursues Successive principle. It is made to order. It is Unity in diversity. It has high level of sub contracting. It is Risk and uncertainty. It has missionary Zeal. It has long term effect. It is irreversible. It has substantial out lay. It has measurement problems. It has temporal spread. The cost benefit received is different at different point of time.
Projects
One-off task
Specific deliverables Time restrictions Many tasks Multi-function teams
Process work
Varies little day-to-day
Measured by quantity produced On-going work Tasks fit within functional boundaries Interfaces between
6
CONCEPT PHASE
CLASSIFICATION OF PROJECTS
NATIONAL
INTERNATIONAL
NON INDUSTRIAL
INDUSTRIAL
HIGH TECH
CONVENTIONAL TECH
LOW TECH
MEGA
MAJOR
MEDIUM
MINI
OTHER CLASSIFICATION
New ventures Expansion Diversification Modernisation Technology Up gradation Replacement Renewal/ Reconstruction/ Revamping Addition/ Modification Maintenance Research and development Automation/ Computerisation Energy Conservation Quality Improvement Spare/ Reserve/ Standby facilities Infrastructure Projects.
Launching of Advertising Campaign New product introduction New market development Acquisition/ Take over Government projects Social Projects EOU Projects Joint Venture Projects Other Private participation projects 1. Build, own & Transfer (BOT) 2. Build, Own. Operate, & Transfer (BOOT) 3. Build, Own, Lease & Transfer (BOLT)
10
Projects
1
A People B C D E / /
2
/ /
/ /
11
12
CONCEPTUALISATION
TECHNICAL
TECHNICAL SPECIFICATION
FINANCIAL CLOSURE
FORMULATION
EVALUATION
COMMERCIAL
PROJECT COMMISSIONING
PERFORM. GUARANTEE TEST
POST PROJECT EVAL. & REPORT
13
Describes how the organization's project portfolios are related to the organization's growth strategies, Identifies the basic types or categories of projects that exist or are planned, Defines the project life cycle for each project category, Defines, for each project category, the corporate guidelines for project risk analysis and planning and control, with provision for appropriate adaptation for specific situations, Specifies the documents and related levels of approval authority for initiating and authorizing new projects and major changes to authorized projects, Identifies the key roles and defines their responsibilities and authority as related to project and functional management, and Specifies the procedures for escalating the inevitable conflicts (for scarce resources, priorities between projects and others) to the appropriate level for their prompt resolution.
14
15
Define the project portfolios required within the organization. Define the project categories within each portfolio based on uniform criteria for the entire organization. Identify and group all projects within categories and programs. Validate projects with the organization's strategic objectives. Prioritize projects within programs and portfolios. Develop the Project Portfolio Master Schedule. Establish and maintain the key resources data bank. Allocate available key resources to programs and projects. Compare financial needs with availability. Decide how to respond to shortfalls in money or other key resources and approve the list of funded projects. Plan, authorize and manage each program and project using the Project Management Process and supporting systems and tools. Periodically re-prioritize, re-allocate resources and re-schedule all programs and projects as required.
16
17
18
19
20
Define and control systematically the project's objectives and scope. Evaluate and proactively manage individual project risks together with the aggregate project portfolio risks. Define and control the specification, quality, configuration and quantity of intermediate and final products (or deliverables) of the project. Systematically define and control the work to be carried out using the project/work breakdown structure (P/WBS) approach. Estimate the labor, material and others costs associated with the project's deliverable products and related work elements, and each summary element in the P/WBS. Plan and control the sequence and timing of the project deliverables and related work elements using a top level project master schedule plus an appropriate hierarchy of schedules. Authorize and control the expenditure of funds and work hours required to execute the project. Provide the information regarding both a) actual progress and expenditures and b) forecasts in the future required by project managers, department managers, functional task leaders and work package leaders on a timely and reasonably accurate basis. Continually evaluate progress and predict and mitigate problems with quality, cost, schedule and risk using earned value project management methods. Report to management and customers on the current status and future outlook for project quality, cost and schedule completion, including post-completion reports.
21
Feasibility study:
A feasibility study may be carried out before a project commences Its purpose to establish an outline of what users require to ensure it is feasible to meet their needs
to record initial impressions of how to meet the requirements (options?) to give management a feel for costs and timescales of project to provide as much information as possible to project manager for to help management decide whether to proceed with the project Financial Feasibility Technical Feasibility Economic Feasibility Market Feasibility Social Feasibility
entirely in part
22
(1)Investment per annual tonne capacity New Installed Capacity Cost R2= R1 xC2/C1 (2)Turn Over ratio and Capital ration: The ratio between annual sales and investment expressed in rupees is known as turn over ratio. Inverse of this is known as Capital Ratio. New Installed Cost R2 = C x V1 x P1 ( V1 projected volume, C capital ratio, P1 price per unit of sales volume) (3)Six tenth factor: If C be annual capacity and R be the investment cost logR2 = logR1 + 0.6 {logC1 - logC2} (4)Inflation Index : can be used with above methods Installed Cost (now) = Installed cost (past) x Cost Index (new) / Cost index (past) (5) Location Index: Ratio between the cost in two countries.
(6)
(7)
Pay Back Period method (PBP) Return on investment (ROI) Net present Value (NPV) Internal Rate of return (IRR) Benefit Cost Ratio (BCR) Urgency method Social profitability Analysis
24
Planning
Project Summary Plan Project/Work Breakdown Structure (P/WBS) Task Responsibility Matrix Project Master Schedule
Authorizing
Master Contract Release Project Release Subcontracts and Purchase Orders
Controlling
Management Reserve Transaction Register Cost Expenditure Reports Updated planning and authorizing documents, comparing actuals with budgets and schedules - Project Master Schedule - Milestone Charts - Other Cost Performance Reports Schedule Variance Reports Earned Value and Cost Variance Reports
Reporting
Monthly Progress Reports - Narrative - Project Master Schedule - Cost Performance Reports - Risk Tracking Reports
Project Interface and Milestone Event List Project Budget Project Funding Plan Project Chart of Accounts Task Statements of Work Task Schedules Task Budgets Detailed Network Plans Task Work Orders ["Task: A short-term effort performed by one organization... ."[May be synonymous with "work package"; usually comprised of more detailed activities.]
Management Reviews of Critical Projects: - Major Project Identification Data - Summary Status Reports - Above Reports as required
Technical Perf. Measurement Reports Risk & Issue Tracking Reports Milestone Slip Charts Trend Analysis Charts Task Estimates to Complete (ETC) and Estimates at Completion (EAC)
25
Table 4. Summary of documents for project planning, authorizing, controlling and reporting.
26
The main problems are: over-optimism, especially if estimators are involved in justifying the project costs an expectation that estimates will be wrong, because we've always accepted it in the past forgetting major activities e.g.. installing software at many sites, data set up, user training Question: How can we ensure that all activities have been included?
Product Breakdown Structure Product Flow Diagram Product Descriptions Critical Path etc can be derived
The Work Breakdown Structure is the traditional tool for devising lists of tasks The WBS can be conceived as a tree, with the project as the root node, major components of the project as the main branches, and tasks/subtasks branch off from these. A WBS may be a diagram or a text list. It is up to the project manager to ensure that all the tasks are included. TYPES OF WBS: AGENCY BASED, FUNCTION BASE, HARDWARE, SOFT WARE 27
PROJECT
DESIGN
PROCUREMENT
CONSTRUCTION
COMMISSIONING
CIVIL
MECHANICAL
ELECTRICAL
CONTRACTOR -1
CONTRACTOR -2
CONTRACTOR - 3
Township
28
NETWORK TOOLS
ACTIVITY BASE
EVENT BASE
30
SCHEDULE PERFORMANCE
ACTUAL PERFORMANCE
31
Global and macro level government policies influenced by macro factors Indian government policies. Import regulations. Panic taxations Resource constraints. Defence expenditure Political situation Inflation Non developmental expenditure. Budgetary deficits Economic stagnation Natural disaster, like earthquakes, floods. etc Labour unrest Law and order situation Social turmoil, like terrorist menace, communal vandalism, etc Un schedule mid term election Global recession, or unrest Interference from unexpected quarter. (INTERNAL FACTORS/ ACTORS IN NEXT SLIDE)
32
In appropriate choice of site. Dispute with local agencies. Inadequacy of foreign collaboration agreement. Monopoly of technology. Technical incompetence. Lack of skilled workers. Inadequate project planning preparations or over ambitious project target dates.. Frequent changes in design and technology up gradation, change of scope because of government regulations. Alteration because of demand fluctuation. Resources constraints because of limitation of funds. Vendor delivery problems. Foreign exchange curbs. Labour unrest Low motivation of project team for want of job guarantee after project completion. Zero date not being specified. Lack of coordination / cohesion between team members. Late clearance of project schedule by different agencies. Price escalation because of change in exchange rates. Delay in obtaining import licences. Inadequate and improper liaison with Custom, Excise, Sales Tax, police, octroi, and other authorities. Poor monitoring and control. Unavoidable statutory controls. Not equipped with force majeur to operate in contingencies.
33
THANK YOU
Any Question?
34