The document discusses various aspects of construction contracts, including:
1) It outlines the key components of a construction contract such as the agreement between client and contractor, general conditions, specifications, drawings and bill of quantities.
2) It describes different types of contracts like lump sum, measure and pay, and cost reimbursable contracts. Cost reimbursable contracts further include cost plus fixed fee, cost plus percentage of cost, and target estimate contracts.
3) It discusses important aspects of bidding and tendering processes for construction projects including open competition bidding, limited competition bidding, and negotiated bidding. Evaluation criteria for bids and different bidding processes are also summarized.
The document discusses various aspects of construction contracts, including:
1) It outlines the key components of a construction contract such as the agreement between client and contractor, general conditions, specifications, drawings and bill of quantities.
2) It describes different types of contracts like lump sum, measure and pay, and cost reimbursable contracts. Cost reimbursable contracts further include cost plus fixed fee, cost plus percentage of cost, and target estimate contracts.
3) It discusses important aspects of bidding and tendering processes for construction projects including open competition bidding, limited competition bidding, and negotiated bidding. Evaluation criteria for bids and different bidding processes are also summarized.
The document discusses various aspects of construction contracts, including:
1) It outlines the key components of a construction contract such as the agreement between client and contractor, general conditions, specifications, drawings and bill of quantities.
2) It describes different types of contracts like lump sum, measure and pay, and cost reimbursable contracts. Cost reimbursable contracts further include cost plus fixed fee, cost plus percentage of cost, and target estimate contracts.
3) It discusses important aspects of bidding and tendering processes for construction projects including open competition bidding, limited competition bidding, and negotiated bidding. Evaluation criteria for bids and different bidding processes are also summarized.
The document discusses various aspects of construction contracts, including:
1) It outlines the key components of a construction contract such as the agreement between client and contractor, general conditions, specifications, drawings and bill of quantities.
2) It describes different types of contracts like lump sum, measure and pay, and cost reimbursable contracts. Cost reimbursable contracts further include cost plus fixed fee, cost plus percentage of cost, and target estimate contracts.
3) It discusses important aspects of bidding and tendering processes for construction projects including open competition bidding, limited competition bidding, and negotiated bidding. Evaluation criteria for bids and different bidding processes are also summarized.
Download as PPTX, PDF, TXT or read online from Scribd
Download as pptx, pdf, or txt
You are on page 1of 41
At a glance
Powered by AI
The key takeaways are that all construction work is done through contracts, and construction contracts define the agreement between the client and contractor. Standard forms of contracts are commonly used for their practicality.
The main components of a construction contract are the agreement, general conditions, supplementary conditions, drawings, specifications, bill of quantities, addenda, and bonds.
Some standard contract documents used locally include ICTAD SBD forms, while internationally FIDIC and JCT forms are common. Funding organizations like the World Bank also have their own standard forms.
HASITHA GUNASEKARA
M.Sc in PM, B.Sc (Hons.) QS, Dip. Arbitration,
AIQS (SL), ACIArb (UK), MCIOB (UK)
1 CONSRUCTION CONTRACT All construction is done within a contract except that done by a person for himself. A contract determines the actions of the parties in their dealings with each other. The construction contract documents define the agreement between the Client and the Contractor. It is a two-party agreement that does not include the designer 2 CONTRACTS REQUIREMENTS Mutual Agreement Offer and Acceptance (Form of Bid and Letter of Acceptance) Capacity to Contract Consideration in a Contract Lawful Object of a Contract Contract Time 3 WRITTEN CONTRACTS Contracts usually need not be in writing to be valid, but they may need to be in writing to be enforceable. Usually a contract must be in writing. Therefore, most major construction projects require a written contract An oral contract is unsubstantial and difficult to prove, and because it cannot be demonstrated by tangible. 4 WRITTEN CONTRACTS (Contd) The written instrument of most ordinary contracts is a printed standard form. The majority of building construction jobs have a lot in common and the use of standard forms of construction contracts is both economical and practical.
5 INDUSTRY STANDARD CONTRACT DOCUMENTS (LOCAL) ICTAD/SBD/01 Standard Bidding Document - Procurement of Works ICTAD/SBD/02 Standard Bidding Document - Major Contracts ICTAD/SBD/03 Standard Bidding Document - Minor Contracts ICTAD/SBD/04 Standard Bidding Document - Design & Build Contracts 6 INDUSTRY STANDARD CONTRACT DOCUMENTS (FUNDED) World Bank Asian Development Bank UNOPS JAICA etc 7 INDUSTRY STANDARD CONTRACT DOCUMENTS (INTERNATIONAL) International construction documents are also often based on industry-prepared standard forms. A number of organizations prepare recommended standard general conditions and associated forms. Such as: FIDIC (International Federation of Consulting Engineers) ICE (Institute of Civil Engineers, United Kingdom) JCT (Joint Contracts Tribunal) 8 CONSTRUCTION CONTRACT DOCUMENTATION Construction contract documents generally include: The agreement General conditions Supplementary conditions Drawings Specifications BOQ Addenda issued before submittal Bonds 9 TERMS AND CONDITIONS OF CONTRACTS In some construction contracts, the order of superiority of the several parts of a written contract is as follows: Agreement General conditions Supplementary conditions Specifications Drawings All the several parts go together as one (complementary); In a discrepancies the contract may say that a stipulated order of superiority determines which part governs.
10 TERMS AND CONDITIONS OF CONTRACTS (cont.) The agreement should contain: The names of contracting parties A brief description of the work A list of contract documents, including agreement, general conditions, drawings, and specifications. The contract sum, or amount The procedures for payment The contract time, or dates for start and completion The signatures of contracting parties and witnesses 11 12 Award of Competitive-Bid Contract Award contract to the lowest responsive bidder Tender/ Bidding Procedure Bids can be either:
Negotiated Bid Limited competition /selective Bid Open competition Bid 13 Negotiated Construction Bid The Engineer on behalf of the owner, invites a contractor to submit a bid. The initial invitation includes information regarding the proposed contract procedure, a brief description of the work etc. Prepare the priced bill of quantities. The priced bills are then handed over to the other party for consideration. Rates in dispute are compared with current rates for similar work and negotiate for finalization When the Engineer and the Contractor reach agreement, the agreed schedule of prices is sent to the Owner for his approval and assent.
Limited Competition Construction Bids Calls for bids from a few contractors who are known to have specialized in the special type of work and from whom he has, in the past, experienced excellent results. This procedure is usually adopted for private works, where the owner has the right to negotiate directly and to enter into agreement with whomsoever he chooses. Open Competition Construction Bids The method is usually adopted for public works, as the rules generally require that government and other public contracts be advertised publicly, to obtain the most advantageous terms.
Any contractor who is willing to undertake a work and who has the requisite finance and construction equipments to complete it satisfactorily is allowed to submit a bid. Advantages of Open Tender
1. Give high level of competition and contractors tend to give best prices as compare to other tendering method 2. There is no list of restrictive tenderer, which does not allow favoritism 3. It is very transparent process which ensures that only the contractor with the best price and meeting all the technical requirements will win the tender. Disadvantages of Open Tender
1. The low price usually detriment of quality and often result in the client obtaining poor quality job and late completion of work.
2. There are no restrictions on the number of contractor who can bid and become bulky and lengthy job for tender analyses which often result in delays and high cost.
Method of Pricing Fixed-price 1. Lump sum Traditional, single fixed price Predetermined price that includes profit, overhead, and all other costs Greatest risk to contractor resulting in a higher markup (the greater the risk, the higher required rate of return ) Most common contract form
TYPES OF CONTRACTS Measure & Pay Lump sum Cost reimbursable contracts 20 21 Reimbursable Costs Definitions of what types of costs can be reimbursed Payments to Subcontractor per subcontract Contractors field labor, material and equipment costs Definitions of what types of cost that will NOT be reimbursed Contractors main office overhead and staff Salaries of contractors officers Cost Reimbursable Contracts 1. CostPlus-Fee as a Percentage-of-Cost Fee may be on a sliding 22 Cost Reimbursable Contracts (cont.) 2. Cost-Plus-Fixed-Fee Contracts 3. Incentive contracts Share of the cost savings up to a maximum Bonus for each day finished early, or penalty for each day finished late 4. Guaranteed Maximum Cost
23 Fixed-price 2. Measure and pay Prices of specified units of work are fixed or predetermined Actual cost to the owner will vary with actual quantities placed Best used when details and general character of the work are known, but quantities are subject to variation Risk of unbalanced bids
Cost-plus Contractor agrees to perform the work for a fixed or variable fee covering profit and home office costs (general overhead) Field costs are reimbursable at actual cost Used when: nature of the work or physical conditions are unpredictable scope is unknown or difficult to define
Cost-plus All cost-plus contracts depend on cooperation among A/E, owner, and contractor Record keeping and timely evaluation are extremely critical Detail record of labor hours and salaries, material and equipment must be maintained
Types of Cost-plus Contracts Cost plus fixed % Fixed % based on portion or all of reimbursable costs Used in construction involving new technology or extremely pressing needs Owner assumes risk Contractor cooperation very high Little or no incentive for cost savings
Types of Cost-plus Contracts
Cost plus fixed fee More incentive for cost savings Incentive for timely completion Risk shared by owner and contractor
Cost plus variable % Also called sliding scale % Keeps fee in line with type & volume of work Fee becomes progressively smaller on work that is repetitive, requires little or no re-engineering, re- planning, or additional layout
Types of Cost-plus Contracts
Target estimate
May be based on cost, man-hours, schedule, or
combination
Cost savings or overrun shared by owner and
contractor at predetermined split
Cost under run increases contractor profit, overrun
decreases profit
Selection Criteria In this following section look at the ways to choose between different bidders, reviewing the specific Criteria for bid evaluation:
Technical evaluation Financial Evaluation Relationship between Technical and Financial
Finally review possible Bidding processes: Prequalification, 2 Envelope 2 Stage Bid Process
Content of Bidding Documents Invitation to Bid Volume 1: Section 1 Instructions to Bidders Section 2 Standard Forms [Contract] Section 3 Conditions of Contract Volume 2: Section 4 Form of Bid and Qualification Information Section 5 Bidding Data and Contract Data Section 6 Specifications Section 7 Bills of Quantities Section 8 Drawings Section 9 Standard Form [ Bid] Invitation for Bids (IFB)
[name of Procuring Entity]
1. The Chairman [insert MPC/DPC/PPC/RPC as appropriate] on behalf of the [insert name of Procuring Entity] now invites sealed bids from eligible and qualified bidders for construction/renovation/rehabilitation/refurbishment/repair * of [insert the title of the Works to be procured] as described below and estimated to cost [insert relevant cost of construction in the latest TCE (Total Cost Estimate)] [Insert a brief description of the Works including major quantities, location of project, and other information necessary to enable potential bidders to decide whether or not to respond to the Invitation. The construction period is [insert no. of Days]. 2. Bidding will be conducted through National Competitive Bidding Procedure. 3. To be eligible for contract award, the successful bidder shall not have been blacklisted and shall meet the following requirements [list the required ICTAD registration] 4. Qualifications requirements to qualify for contract award include: [insert key technical, financial, legal and other requirements]. 5. Interested bidders may obtain further information from [insert name of Procuring Entity; insert name, address and e-mail of officer in charge] and inspect the bidding documents at the address given below [state address at end of this IFB] from [insert office hours].
6. A complete set of Bidding Documents in English language may be purchased by interested bidders on the submission of a written application to the [state addressee] from [state date of commencement of issuing document] until [state date] from 0900 hrs to 1500 hrs. upon payment of a non refundable fee of [insert amount in Rupees]. The method of payment will be [insert method of payment].
7. Bids shall be delivered to the address below [state address] at or before [insert time and date]. Late bids will be rejected. Bids will be opened soon after closing in the presence of the bidders representatives who choose to attend.
8. All bids shall be accompanied by a [insert as appropriate, either Bid Securing Declaration/ Bid-Security, of (insert amount in Rupees)] The address(es) referred to above is(are):
Name Designation, Address, fax number etc of the Procuring Entity
INSTRUCTIONS TO BIDDERS A. General, 9 1. Scope of Bid, 9 2. Source of Funds, 9 3. Ethics, Fraud and Corruption, 9 4. Eligibility and Qualification of the Bidder, 9 5. One Bid per Bidder, 9 6. Cost of Bidding, 10 7. Site Visit, 10 -------------------------------------------------------- A. Bidding Documents, 10 1. Content of Bidding Documents, 10 2. Clarification of Bidding Documents, 10 3. Amendment of Bidding Documents, 11 -------------------------------------------------------- A. Preparation of Bids, 11 1. Language of Bid, 11 2. Documents Comprising the Bid, 11 3. Bid Prices, 11 4. Currencies of Bid, 12 5. Bid Validity, 12 6. Bid Security and Bid-Securing Declaration, 12 7. Pre-BID Meeting, 13 8. Format and Signing of Bid, 13
A. Submission of Bids, 13 1. Sealing and Making of Bids, 13 2. Deadline for submission of Bids, 14 3. Late Bids, 14 4. Modification and Withdrawal of Bids, 14 ----------------------------------------------------------------------------- A. Bid Opening and Evaluation, 15 1. Bid Opening, 15 2. Process to be Confidential, 15 3. Clarification of Bids, 15 4. Examination of Bids and Determination of Responsiveness, 15 5. Correction of Errors, 16 6. Currency for Bid Evaluation, 16 7. Evaluation and Comparison of Bids, 16 8. Preference for Domestic Bidders, 17 ----------------------------------------------------------------------------- A. Award of Contract, 17
1. Award of Contract, 17 2. Employers Right to Accept any Bid and to Reject any or all Bids, 18 3. Notification of Award and Signing of Agreement, 18 4. Performance Security, 18 5. Advance Payment and Security, 19 6. Adjudicator, 19
Form of Bid
Note: Prior to issue of the bidding documents, the Employer should insert relevant data for all items marked with an asterisk (*). Name of Contract:*
To:* [insert name of Employer 6 ]
Gentleman, 1. Having examined the Standard Bidding Document - Procurement of Works [ICTAD/SBD/01 - Second Edition, January 2007], Specifications, Drawings and Bills of Quantities and Addenda for the execution of the above-named Works, we the undersigned, offer to execute and complete such Works and remedy any defect therein in conformity with the aforesaid Conditions of Contract, Specifications, Drawings, Bills of Quantities and addenda for the sum of Sri Lankan Rupees ....................................... (LKR ...................) or such other sums as may be ascertained in accordance with the said Conditions. 2. We acknowledge that the Contract Data forms part of our Bid. 3. We undertake, if our Bid is accepted, to commence the Works as stipulated in the Contract Data, and to complete the whole of the Works comprised in the Contract within the time stated in the Contract Data. 4. We agree to abide by this Bid for the period of* ........................... ................ (insert number of Days in accordance with Sub-Clause 15.1 of Instructions to Bidders) Days from the date fixed for receiving or any extended period and it shall remain binding upon us and may be accepted at any time before the expiration of that period. 5. Unless and until a formal agreement is prepared and executed this Bid, together with your written acceptance thereof, shall constitute a binding contract between us. 6. We accept / we do not accept the Adjudicator. 7. We understand that you are not bound to accept the lowest or any Bid you may receive.
Dated this ............. day of ............ 20... in the capacity of .............. duly authorized to sign tenders for and on behalf of ............................................................................ (IN BLOCK CAPITALS)
Witness : ................................................... DATA FOR BIDDING DOCUMENT EV = Estimated Value( Initial Contract Price) = 100 M Rs. 73,000,000.00 Duratiion in months 4 Clause No Footer Note Description Equation Value (4.2)b 20 Average annual volume of construction work performed in any of the last five years 1.5 x (EV x 12) /(Duration in Months) 328,500,000.00
Experience in the construction of at least one contract of a nature and complexity equivalent to the Works over the last 10 years (to comply with this requirement, works sited should be at least 70 percent complete) EV+EVx70%+ect. 73,000,000.00 (4.2)f 22 The minimum amount of liquid assets and/or credit facilities net of other contractual commitments and exclusive of any advance payments which may be made under the contract shall be not less than EV/ (Duration in Month) x 3 45,625,000.00 17.1 27 The amount of bid security EV x 2% 1,460,000.00 13.1 41 Minimum cover for Insurance of Works & of Plant & Materials EV x 110% 80,300,000.00
42 Minimum deductible for insurance of Works & of Plant & Materials EV x 5%
3,650,000.00 14.5 46 Minimum amount of Interim Payment Certificates 50% of the average monthly value of the contract
9,125,000.00 27.4 48 The Amount to be withheld for late submission of a Programme is EV x 2%
1,460,000.00 39.2 49 Engineer may order variation up to a total cumulative value of not exceeding EV x 10%
7,300,000.00 48.1 53 The retention of from each payment shall be 10% 54 The limit of retention shall be 5% 49.1 55 The liquided damages for the whole of the Works shall be per day EV x 0.002%
36,500.00 50.1 56 The maximum amount of liquidate damagges for the whole of the work shall be EV x 10%
7,300,000.00 52.1 57 The perfomance Security shall be EV x 5%
3,650,000.00 60.1 58 The percentage to apply to the value of the work not completed, representing the Employer's additional cost for completing the works, is EV x 25%
18,250,000.00 Lowest responsive bidder Lowest bidder whose offer best responds in quality, fitness and capacity to fulfill the particular requirements of the proposed work and with the necessary qualifications to complete the job in accordance with the terms of the contract. 37 Retention A percentage of the payment to the contractor that is withheld each month Usually is 10% Owner may reduce below 10% after SUBSTANTIAL COMPLETION Paid by owner to contractor after FINAL COMPLETION of the project Serves as an incentive for contractor to complete ALL work per contract
38 Other Contractual Terms Substantial Completion Beneficial Occupancy of the project Warranty Period Contact time Calendar days vs. working days 39 Other Contractual Terms Liquidated Damages Used as a PENALTY for late completion Must be a REASONABLE penalty based on a forecast of actual damages the owner would suffer if the contractor is in breach of contract by finishing late 40 THANK YOU 41