Project Management: Asit Kumar Singh
Project Management: Asit Kumar Singh
Project Management: Asit Kumar Singh
management
ASIT KUMAR SINGH
What is project?
An interrelated statement set of
activities that have a definite starting
and ending point and the result in a
unique outcome for a specific allocation
of resources.
Selecting project manager
Should be good motivator,teachers,and
communicators.
Able to organize a set of disparate
activities and work with personnel from
a variety of disciplines.
Should be responsible for the whole
team.
Scope and activities
A thorough statement of project scope,
Program evaluation and review
technique(PERT)
Development of PERT In the U.S.Navy
4
2
1 5
3 6
Activity description
immediate predecessors
A select administrative and medical staff -
B select site and site survey -
C select equipment A
D prepare final construction plan and
layout
B
K
A F
C G
START
FINISH
B D H
E
J
?