Eocp (Ptws Training)
Eocp (Ptws Training)
Eocp (Ptws Training)
Familiarization
End-of-day TARGET
BE ABLE TO :1) Carry-out hazardous work activities in a safe manner
2) Interpret effective PTW System form-filling
3) Clarify responsibilities of personnel involved
4) Co-ordinate non-routine activities via work planning
5) Specify isolations preventing potential hazards
6) Control activities as not to create harmful results
7) Determine non-conflict work activities
8) Comply with statutory provisions wrt worksite safety
9) Improve confidence in the safety standards
10) Be a reliable team member contributing to Zero Incident
Introduction of PTWS
The Petroleum industry handles large quantities of flammable & toxic
materials, so the potential of serious accident is clear.
When incidents occur, human factor is often a root cause. This is so
due to lack of training, instruction or understanding of either the purpose
or practical application of a Permit-To-Work (PTW) Systems.
However, a permit should not be regarded as a statement that all hazards
& risks have been eliminated from the work area. It ensures that those
authorized & trained have thought about the foreseeable risks being
avoided using suitable precautions.
Those carrying out the job should think about and understand what they
are doing & how their work may interface with that of others i.w.o. work
incompatibility and handing over without acknowledging safety
concerns towards oneself & others.
ref: OGP (Intl Assoc of Oil & Gas Producers
Functions of PTWS
1.
2.
3.
4.
5.
6.
7.
Establish conditions to enable requested work be undertaken without danger to personnel or facility
8.
9.
Ensure all personnel including sub-contractors & visitors receive training on effective use of the PTW System
10.
Comply with statutory provisions/legislatives with regards to work-site safety & well-being
PTWS Training
Reflect different responsibilities of: person issuing the permit
person-In-Charge of the work
workforce
Understandings in: legislation & industry guidance
company policy, local rules & procedures
responsibilities
case histories of accident &/or near-misses involving failure of PTWS
Demonstrate knowledge & competence in: potential hazards existing
means of mitigating the hazards before issuing a permit
use of different forms & records
communication skills
shift handover requirements
auditing & monitoring requirements
PTWS Training
Communication (discuss/state clearly): exact scope pf work, number of personnel & special tools involved
potential hazards, precautions taken wrt informing others involved
actions required in event of emergency, also wrt changes in work
environment
Monitoring of PTW System (spot-checkings): Is the permit displayed at the worksite?
Has the permit been properly completed?
Is specified safety equipment in place?
Are specified precautions adequate & being implemented?
Has the personnel been briefed, & are the conditions of the permit &
nature of work to be performed understood?
ref: OGP (Intl Assoc of Oil & Gas Producers
ORGANISATION
CHART
Authorization
Authority
CHSELS
Storeman
(x2)
OIM
Production
Superintendent
Lead
Cargo
Operator
Bosun
Cargo
Operator
GPO /
ABs
Technical
Administrator
Maintenance
Supervisor
Performing
Authority
Production
Supervisor
Senior
DCS
Operators
Lead
Mechanical
Technician
Laboratory
Technician
Lead
Instrument
& Electical
Technician
Campboss
Chief
Cook
2nd
Cook
Mechanical
Technician
Instrument
& Electrical
Technician
MessLaundry
Man
Production
Operators
Fitter
Utility
Operator
Room
Steward
Medic
Radio Operator
Isolation Authority : responsible for application & removal of isolations (Preparation & Re
Instatement Form)
under instructions of the Production Supervisor (PS)
advises the PS on the isolations required for PTWS and also for
Sanction to Test requirements
Safety Requirements
Safety Requirements
Management Statement
a) formal written statement (PTWS) to control hazardous operations
b) positive communications between installation management,
supervisors & technicians
c) personnel to receive training in PTW System and demonstrates an
acceptable level of competency
d) all to understand individuals roles & responsibilities
Supervision of Operations
a) all operations & non-routine maintenance on facility to be supervised by OIM (or delegate) in accordance with PTW System
Safety Requirements
Number of Permits in Operation
1) total number of permits in operation at one time is at the discretion of
the OIM
2) Hotwork Permits running simultaneously are limited to 3 only
Emergency Situation
1)
Work may proceed (without permit endorsement) during emergencies, but prior to verbal agreement being noted inside the
CCR logbook at the time it is made
2)
Permit issue shall follow as soon as possible after the log entry
3)
It is in NO WAY relieves the PS/Area Authority off the responsibility to control work effectively
Safety Requirements
Emergency Alarms
1) at the sound of Emergency Alarm, ALL permits shall be automatically
suspended (regardless of drill or actual emergency)
2) ALL shall STOP WORK, make the work area safe, report to Muster
Station and bringing the permit along
3) after emergency is called-off, earlier works via permits shall not
commence until suspended permits are re-issued (ALL permits are to
return to CCR for re-issue and re-validation)
(ZONE)
FPSO is divided in 3 groups of hazardous area zone classifications
ZONE 0
Part of a hazardous area in which a flammable atmosphere is
continuously present for long periods
ZONE 1
Part of a hazardous area in which a flammable atmosphere is likely to
occur in normal operation
ZONE 2
Part of a hazardous area in which flammable atmosphere is not likely to
occur in normal operation
(CLASS)
Class defines the flammable material that is being evaluated
(DIVISION)
Division defines the work area that is being evaluated & the
probability of presence of flammable materials
DIVISION 1
Substance referred is present during NORMAL Conditions
DIVISION 2
Substance referred is present only in ABNORMAL Conditions,
such
as container failure or system breakdown
Validation
- maximum 24hrs (with endorsement after first 12hrs)
tasks involves source of ignition, examples like:(grit blasting, needle gunning, opening live junction boxes, electrical
switchgear, heat shrink blowers, steel wire powerbrushes, pneumatic/
hydraulic chipping, non-IS cameras, voltage checks, etc.)
Validation
- maximum 7days (re-endorsement every 12hr shift)
Site Gas-Test (conducted by Authorized Gas Tester)
- before Hotwork Permit is issued, results recorded inside Gas Test
Certificate and number entered on the Permit To Work
- repeated test during Work Permit re-validation and site re-occupied
after work break (tea/lunch breaks or Emergency Muster)
- continuous testing using a multi-gas detector by work group
Hotwork Permit is not required for operations involving Gas Flaring
spray painting
heavy lifting
specialized rigging operations
erect/dismantle scaffoldings
work on isolated electrical
equipment
install pipe works
handling hazardous substances
(eg. radioactive sources, toxic /
corrosive chemicals, asbestos)
Validation
- maximum 7days (re-endorsement every 12hr shift)
Sanction to Test
Allows AMENDMENTS to isolations on Hot, Cold & Electrical Work Permits.
Some works may need test-runs to ensure faults, defects & maladjustments
be rectified, at which may require isolations applied under the Electrical
Work Permits
To permit these isolations, Section 7 (under Hot & Cold Work Permit) must be completed in order to make Section 9 (under Electrical Work
Permit) to be actioned.
The only permit being valid at that time is the Electrical Work Permit
The re-isolation must be completed before the permit is returned to the PA for normal work to resume.
Workshop Operations
Memorandum (standing order) issued by OIM covering works that may be done
in designated workshops
Memorandum must be prominently displayed inside referred workshops specifying precautions & conditions to be observed
Memorandum indicates that only identified qualified personnel should use the workshop equipment
Fumes-released activities, like soldering, need to apply the Inhibit Protection Certificate to inhibit workshops smoke detectors.
Form can then be cancelled only after the PA has signed the work completion section in the permit to work, and therefore this then allows the
PS/Area Authority to clear the isolations. After this, then form is cancelled
An Approved Gas Tester (AGT) initiate the very initial inspection. A Gas-Test Certificate is required before entry
Gas-Testing Certificates
Purpose is to register the results of all the gas-tests carried out, and to certify the atmospheric conditions within the area concerned
Certificate does not permit any work to be carried out. An appropriate Hot or Cold Work Permit must be raised before any tasks can be
undertaken
Isolations
When isolations is required, the Preparation & Re-instatement Form has to be
attached to the Hot or Cold Work Permit to work
Preparation & Re-instatement Form ensures that equipment, plant, machineries and process systems have be made/rendered safe for the work to be
performed
Mechanical isolation uses the Preparation & Re-instatement Form, via the tagging system (isolation, de-isolation register form with lock-open and
lock-closed checklists)
Electrical isolation uses Electrical Work Permit, via the Key Safe System controlled by the Electrical / Operation Supervisor (removal of the fusible
electrical links). Listing will be done also inside the Preparation & Re-instatement Form
Safety Checklist
Toolbox Meeting
PICWS will conduct an on-site safety (toolbox) meeting attended by all
those involved in carrying out the work
Purpose is to discuss the plan, identify individual responsibilities, review
procedures, and to identify & discuss the hazards
Topics that may be covered involved:- plan & methods
- precautions
- responsibilities
- PPE
- material handling
- emergency equipment/system
- work scope
- conflicting activities
- equipment
- isolations
- earthing
- questions for work party
2.
3.
4.
5.
6.
7.
8.
9.
PTW REGISTER
10.
11.
9. PTW REGISTER
PTW AUDIT
PTW Audit
Permit System Audit
Ensures that the PTW Systems remains within the spirit of Company regulations
and complies with formally approved rules & regulations
Audit Checklist
Allows auditor to consider various aspects of the PTW System, via assessing the degree to which the work is carried out, and determining its
effectiveness
Audit Register
The facility will register every findings of permits audited and improvements targeted via each identified critical findings
Auditors
OIM &/or CHSEL shall carry-out internal audits at regular intervals. External Audits will be conducted in accordance with the annual HSE Audit
Program
PTW Audit
PTW Audit
PTW Audit
ISOLATION
(LOTO)
ELECTRICAL Isolation
ENSURE ALL POWER
SOURCES ARE DECLARED
AS SAFE
LOCKOUT/
TAGOUT
A device that positively :Prevents a machine from being started up or turned on,
Prevents a machinery part from moving,
Prevents electrical energizing,
Blocks a pipeline, steam line or air line
What is a Tag-out?
Tag warnings are devices only, and :They dont provide the same level of protection as lockout devices
They can only be removed by an authorized personnel
They must be legible, securely attached and resistant to degradation
6. PRAPARATION &
INSTATEMENT Form
RE-
8. INHIBIT PROTECTION
Certificate
9. PTW REGISTER
Risk Assessment
HSE RISKS
ENTERPRISE RISKS
?
Customer
HSE
Regulatory
non-compliance
Financial
Env.
pollution
Property
Damage
Personal
Injury
Management
Operational
People
Market
Falling
from height
Struck
against
Struck by
Contact
with
Caught in
between
PROCESS RISKS
Slip
&
Fall
Risk Categories
RISKS identified ..
1
2
3
5
6
7
Pollution of Environment
Spillage, Emission. Leak and Contamination to land, water and air
Property Damage
Any accident which results in damage to company property
workshop
pumproom
fwd windlass
module
OLD Rating
Probability x Severity
Control Measures
to Minimise Risk
Toolbox Meeting
- miss-communication
- interpreter/Translator
- local language
- slip/trip/fall
- isolation
- barrier
- lighting
- instruction
- buddy-system
Isolation
- electrical
- mechanical
- instrumentation
- pneumatic
- pinch-point injury
- electrocution
- engulfment
- struck by moving object
- equipment failure
- miss-communication
- miss-reading on gadgets
- maintenance log
- competent personnel
- training (trained
personnel)
- equipment checklists
Tank opening
- trapped gases
- slip/trip/fall
- oil spillage
- SOP
- PTWS
Purging
- miss-communication on
LOTO valves
New Rating
Probability x Severity
Task Description
OLD Rating
Probability x Severity
Control Measures
to Minimise Risk
Donning of breathing
apparatus (BA)
- height
- pinch-point
- falling objects
- wet & slippery
(slip/trip/fall)
- heat (humidity)
- dehydration heat
stress/strain)
- manhole cover (broken
hinge/arm)
- slip/trip/fall
- panic / phobia
- toxic / LEL
- equipment failure
- sparks from steel toecaps
- biological
- noise
- tiredness
- pinch-point
- personnel left inside tank
- body posture (ergonomic
positioning)
- manhole cover hinge
broken
New Rating
Probability x Severity
OK-Let'scallitaDAY!!
ThankYou